Hamilton County Facilities

Archived Projects

Archived Projects

JC – Parking Lot EV Charging Station Study

05/29/19 – Hamilton County requests SOSS for the project.

06/26/19 – TEI submits SOSS for approval. Project pending approval of SOSS and PO.

07/24/19- Project pending approval of SOSS and PO.

08/27/19 – Project pending approval of SOSS and PO.

09/25/19 – Project pending approval of SOSS and PO.

10/30/19 – Project pending approval of SOSS and PO.

12/11/19 – Project pending approval of SOSS and PO.

01/28/20 – Project pending approval of SOSS and PO.

02/26/20 – Project pending approval of SOSS and PO.

03/26/20 – Project pending approval of SOSS and PO.

04/30/20 – Project pending approval of SOSS and PO.

05/27/20 – Project pending approval of SOSS and PO.

06/23/20 – Project pending approval of SOSS and PO.

07/29/20 – Project pending approval of SOSS and PO.

08/21/20 – Project pending approval of SOSS and PO.

 

JC – Parking Lot EV Charging Station Study Read More »

800 – 4th and 5th Floor Security

05/29/19 – Hamilton County requests SOSS for the Project.
06/26/19 – TEI submits SOSS to facilities. Project pending approval of SOSS and PO.
07/24/19 – Project pending SOSS approval and PO.
08/27/19 – Project Pending SOSS approval and PO.
09/25/19 – Project Pending SOSS approval and PO.
10/30/19 – Project Pending SOSS approval and PO.
12/11/19 – Project Pending SOSS approval and PO.
01/28/20 – Project Pending SOSS approval and PO.
02/26/20 – Project Pending SOSS approval and PO.
03/26/20 – Project Pending SOSS approval and PO.
04/30/20 – Project pending approval of SOSS and PO.
05/27/20 – Project pending approval of SOSS and PO.
06/23/20 – Project pending approval of SOSS and PO.
07/29/20 – Project pending approval of SOSS and PO.
08/21/20 – Project pending approval of SOSS and PO.
10/28/20 – Okay to Archive.

800 – 4th and 5th Floor Security Read More »

2020 – Arc Flash Modeling and Labeling

05/29/19 – Hamilton County requests SOSS for project.

06/26/19 – TEI submits SOSS to facilities. Project Pending SOSS approval and PO.

07/24/19 – Project pending SOSS approval and PO.

08/27/19 – Project pending SOSS approval and PO.

09/25/19 – Project Pending SOSS approval and PO.

10/30/19 – Project Pending SOSS approval and PO.

12/11/19 – Project Pending SOSS approval and PO.

01/28/20 – Project Pending SOSS approval and PO.

02/26/20 – TEI receives signed SOSS and PO for project. TEI contacts Jessica Powell and requests project kickoff with 2020 staff. Kickoff meeting to occur ASAP and project to commence thereafter.

03/26/20 – TEI, County Facilities, and building manager meet to kick off the project. Due to the COVID-19 restrictions, design meetings and field work at this facility have been placed on hold until all restrictions are lifted.

04/30/20 – Project Pending COVID-19 restrictions.

05/27/20 – Project pending COVID-19 restrictions.

06/23/20 – Project pending COVID-19 restrictions.

07/29/20 – TEI meets with Bryan Collins to re-kickoff project. TEI contacts sub contractor to schedule field investigation to incorporate into the SKM model. field investigations to be coordinated with building manager.

08/21/20 – TEI has Phasor Electric perform field investigation of all of the gear and feeders at the building. Field work notes were sent to TEI on 08/20/20, and the data will now be entered into the model for running calculations.

09/23/20 – TEI processing data from Phasor – and will complete the modeling upon receipt of follow up data requested from Phasor.

10/27/20 – Phasor scheduling back visit to the building to get missed information and then the model will be completed and sent to Hamilton County Safety Consultant for review.

12/09/20 – Phasor returned to site to gather missed information. Finalizing model, and will send through internal review, and then forward to Charlie for his review.

01/26/21 – Model to be sent to Charlie at CMI for review by 01/29/21.

02/23/21 – Model completed and sent to Charlie at CMI for review and comments. Upon receipt of review comments from Charlie, labels will be printed and applied at the building.

03/24/21 – ThermalTech receives comments from CMI and incorporates into the model. Labels printed and building manager contacted to schedule installation of labels – proposed to be installed week of 03/29/21.

04/28/21 – Labels installed on all equipment. TEI to over report to HCFD and project complete.

05/26/21 – Project Complete.

 

2020 – Arc Flash Modeling and Labeling Read More »

CH – CMSnet AD Migration

PM: Terry Cannon, Bert Watts
03/08/19 – TEI met with CMSnet for a scoping meeting on the AD Migration Project and submitted an SOSS for the project.
03/20/19 – SOSS approved by County.
04/15/19 – Coordinating design meeting times with CMSnet.
05/15/19 – Attended CMSnet quarterly PM meeting and kicked off project with departments.
05/20/19 – Sent Purchasing a review set of documents and front end with dates which they approved in general. Need to finalize bidding schedule with CMSnet.
05/21/19 – Met with Conexio after 5/15 and discussed scope, schedule and work required for bid.
05/22/19 – Found two additional Novell to AD migration experts, invited them into ThermalTech to discuss means and methods of project.
05/23/19 – Internal meeting at ThermalTech to convert this job to a perform.
05/24/19 – ThermalTech forwarded review meeting books to Stephanie because Shannon is out.
05/28/19 – ThermalTech rewrote the specs as performance specs after meeting with CMSnet. TEI setup meeting to meet with specialist on Monday June 3.
06/20/19 – Met with specialist earlier this month and asked for some bidding data from them. Did not receive anything back. Circled back and checked with them again today.
06/27/19 – As of today nothing back from any third party vendors in the way of helping the bid but companies are interested in bidding the work. TTC will have final review specs next week for CMS review.
07/24/19 – Final RFP sent to Purchasing and CMSNet for approval.
07/25/19 – CMSNet sent back comments this morning. TTE will pick these up with the hopes of releasing this document on 7/31 as scheduled.
08/28/19 – CMSNet review book sent back with new dates and schedule. We are awaiting new comments from the department heads and approval of the new bidding schedule form CMSNet.
09/03/19 – Received email and comments back from CMSnet on the RFP document.
09/24/19 – Made comments and submitted back to CMSnet for approval.
09/25/19 – Talked to Shannon Supe to setup a meeting for final schedule on Friday for bidding out this project.
10/04/19 – Project Issued for Bidding. Bid Opening scheduled for Nov 7, 2019.
10/24/19 – Add01 Issued.
10/30/19 – Add02 Issued.
12/12/19 – One bid was received and eventually rejected by the County. We have submitted a small SOSS to cover the time to solicit State Term of GSA type contracts for mid January 2020.
01/24/19 – ThermalTech making final edits for rebidding through STS currently, will send to Shannon for final review this week.
02/20/20 – Met at CMSNet PM Mgr meeting and discussed final review of revised GSA STS bidding. Ready to bid after final remarks are picked up on bid documents.
03/23/20 – Final review document sent to CMS, checked back 2 or 3 times for final comments.
04/29/20 – Final review document sent to CMS, checked back 2 or 3 times for final comments.
05/25/20 – Talked to CMSNet this month and the releasing of this proposal is on hold pending funding for the project. ThermalTech is holding the project manual for bidding for the time being.
06/23/20 – CMS contacted TEI today for a refresh of this job. We sent a review set back to CMS and contacted the vendors about bidding the work. There is still interest in this job so this is good news.
07/29/20 – TTE followed up with CMSnet several times this month for progress update. We await the comments and dates on our final package submission.
08/26/20 – TTC checked back with CMSNet for updates.
09/18/20 – TTE wrapped up final markups on specs and will send for bidding next week.
10/28/20 – Bid packets sent out through ThermalTech for GSA pricing only. ThermalTech is managing the bid for the County. Three vendors are interested in giving us a price for this work. CMSnet currently reviewing the packet for current submitted questions. There was a misunderstanding on the timing of the bid which ThermalTech and CMS are working out currently. Addendum sent to extend the bid to the end of November and installation in mid to late 2021.
12/10/20 – We extended bid out to after the first of the year. No other updates.
01/26/21 – TTE suspended bid with vendors, contacted CMS and said that we are ready when they are ready. Until then on hold.
03/25/21 – No updates.
04/29/21 – No updates.
05/26/21 – No updates.
06/25/21 – No updates.
07/21/21 – Shannon said the contract is at Prosecutor for review, just waiting on feedback.
08/25/21 – No updates.
10/28/21 – No updates.
12/03/21 – No updates.
01/22/22 – No updates.
02/22/22 – No updates.
07/27/22 – Shannon emailed this month. We will work with Jeff Roy to update this bid packet for bidding. CMS may run the bid this time.
09/22/22 – Ready to Archive.

CH – CMSnet AD Migration Read More »

CH – West Entry Security Screening Renovations

04/24/19 – HCFD requests SOSS from TEI for the project. TEI submits SOSS and receives signed SOSS and PO. TEI requests kickoff meeting the HCFD and all parties . Project start pending project kickoff meeting.

05/29/19 – Design progressing and TEI anticipates that 100% documents will be issued to HamCo no later than mid week (week of June 3).

06/26/19 – Drawing submitted to HamCo for review and no comments received. TEI submits to IBI for plan review and permit on 06/28/19.

07/24/19 – TEI receives plan review approval from IBI, and secures the electrical permit for trades to work on the project. Core drills complete and trades working on electrical modifications for the project. Hamilton County trades to notify ThermalTech when they are ready for the rough in inspection.

08/27/19 – work completed , inspections passed, and the security scanners have been relocated.

CH – West Entry Security Screening Renovations Read More »

230 – 2019 Façade Critical Façade Repairs

12/20/18 – THP submitted SOSS.
01/14/19 – County approved SOSS.
03/28/19 – THP anticipated Owner review by 4/2/18 and Final by 4/8/19.
04/04/19 – THP met BW to discuss questions about documents issued for Owner Review.
04/10/19 – THP finalized estimated budget and emailed to BW.
04/12/19 – THP issued documents for bid.
04/15/19 – Project advertised to bidders.
04/23/19 – Pre-bid meeting.
04/25/19 – THP issued Addendum No. 1.
05/07/19 – THP attended Bid Opening.
05/07/19 – THP received Bid tabulation from Purchasing and reviewed.
05/07/19 – THP had telephone conversation with American Façade Restoration to qualify bid.
05/07/19 – THP developed bid summary letter recommending American Façade Restoration and emailed to BW.
05/14/19 – THP finalized draft of Owner-Contractor agreement and emailed to BW.
08/29/19 – Work scheduled to start after F117 complete.
09/16/19 – Work scheduled to start after F117 complete.
10/31/19- See F117 for project status.
01/30/20 – See F117 for project status. Construction work complete. Final closeout paper work in progress.
02/27/20 – Refer to F117 for project status.

230 – 2019 Façade Critical Façade Repairs Read More »

CAB – 2019 Critical Façade Repairs (F118)

12/20/18 – THP submitted SOSS.
01/14/19 – County approved SOSS.
03/28/19 – THP anticipated Owner review by 4/2/18 and Final by 4/8/19.
04/04/19 – THP met BW to discuss questions about documents issued for Owner Review.
04/10/19 – THP finalized estimated budget and emailed to BW.
04/12/19 – THP issued documents for bid.
04/15/19 – Project advertised to bidders.
04/23/19 – Pre-bid meeting.
04/25/19 – THP issued Addendum No. 1.
05/07/19 – THP attended Bid Opening.
05/07/19 – THP received Bid tabulation from Purchasing and reviewed.
05/07/19 – THP had telephone conversation with American Façade Restoration to qualify bid.
05/07/19 – THP developed bid summary letter recommending American Façade Restoration and emailed to BW.
05/14/19 – THP finalized draft of Owner-Contractor agreement and emailed to BW.
08/29/19 – Work scheduled to start after F117 complete.
09/16/19 – Work scheduled to start after F117 complete.
10/31/19- See F117 for project status.
01/07/20 – THP finalized and emailed letters to city about completion of façade repairs.
01/30/20 – See F117 for project status. Construction work complete. Final paper work closeout in process.
02/27/20 – Refer to F117 for project status.
09/22/20 – THP emailed City of Cincinnati to ask about status of closing out façade inspection case for 2020 Auburn and 230 E. 9th St.
09/30/20 – THP visited site to document completed TPC letter installation, and issued field report 26.
10/06/20 – THP sent follow-up email and had conversation with contact at City of Cincinnati about open inspection cases at 2020 Auburn and 230 E. 9th.
10/22/20 – THP received, reviewed, and approved AFR’s 10th application for payment reflecting completion of all work. AFR to submit remaining closeout documents before submitting final application for payment for retainage.
11/06/2020 – THP reviewed AFR’s closeout binders, identified and requested missing information.
11/10/2020 – THP finalized closeout binders, reviewed and approved final application for payment, and delivered to Hamilton County.

CAB – 2019 Critical Façade Repairs (F118) Read More »

800 – 2019 Façade Stabilization (F117)

12/20/18 – THP submitted SOSS.
01/14/19 – County approved SOSS.
03/28/19 – THP anticipated Owner review by 4/2/18 and Final by 4/8/19.
04/04/19 – THP met BW to discuss questions about documents issued for Owner Review.
04/10/19 – THP finalized estimated budget and emailed to BW.
04/12/19 – THP issued documents for bid.
04/15/19 – Project advertised to bidders.
04/23/19 – Pre-bid meeting.
04/25/19 – THP issued Addendum No. 1.
05/07/19 – THP attended Bid Opening.
05/07/19 – THP received Bid tabulation from Purchasing and reviewed.
05/07/19 – THP had telephone conversation with American Façade Restoration to qualify bid.
05/07/19 – THP developed bid summary letter recommending American Façade Restoration and emailed to BW.
05/14/19 – THP finalized draft of Owner-Contractor agreement and emailed to BW.
08/01/19 – THP met with Owner and Contractor for preconstruction meeting and issued meeting notes.
08/12/19 – THP reviewed and returned submittals received 8/7/19 from Contractor.
08/14/19 – THP reviewed and returned revised submittals from Contractor.
08/19/19 – THP met with Owner and Contractor for first progress meeting and issued meeting notes.
08/20/19 – THP met with Darnell at 800 Broadway to review additional façade issues to be reviewed for repair.
08/22/19 – THP met Contractor at 800 Broadway to review and document completed stone patch preparation progress and stone patch mockups.
08/23/19 – THP issued field report 1.
08/23/19 – THP had telephone conversations with Owner and Contractor to discuss status of mortar joint tuckpointing quantities relative to unit cost allowance amounts.
08/26/19 – THP met with Owner and Contractor for weekly progress meeting and issued meeting notes.
08/26/19 – THP reviewed pencil copy of Contractor’s first application for payment.
08/28/19 – THP visited 800 Broadway to meet Contractor, review progress, and do close-up inspection of south elevation in the area of the façade near the office where leaks have been an ongoing issue.
08/29/19 – THP directed Contractor to install two additional stone patch samples at 800 Broadway west elevation.
08/29/19 – THP reviewed and approved Contractor’s first application for payment.
08/30/19 – THP delivered application for Payment to HC.
08/30/19 – THP visited 800 Broadway to observe and document additional stone patch samples.
09/03/19 – THP issued field reports 2 & 3 from 8/28 & 8/30 site visits.
09/06/19 – THP visited 800 Broadway to meet Contractor and review progress.
09/09/19 – THP developed Change Order 1.
09/09/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
09/09/19 – THP met Contactor and American Scaffolding at 800 Broadway to review access for pricing repairs at southwest corner of tower.
09/09/19 – Change Order #1 for survey of A&D façade was approved and signed by Owner and Contractor.
09/09/19 – THP issued field report 4 from 9/6 site visit.
09/10/19 – THP issued notes from 9/9 progress meeting.
09/16/19 – THP developed Change Orders 2 & 3.
09/16/19 – THP met Owner and Contractor at CAB for progress meeting.
09/16/19 – Change Orders #2 for Justice Center façade repairs and #3 for 800 Broadway tower spall repair were approved and signed by Owner and Contractor.
09/17/19 – THP visited CAB to meet Contractor, review progress of concrete repairs, and identify additional repair areas.
09/18/19 – THP issued notes from 9/16 progress meeting.
09/20/19 – THP reviewed pencil copy of Contractor’s second application for payment and had conversation with Owner about use of unit cost allowances to cover additional façade repairs requested by HC at CAB.
09/20/19 – THP issued field report 5 from 9/16 site visit.
09/23/19 – THP met Owner and Contractor at CAB for progress meeting and issued meeting notes.
09/23/19 – THP reviewed and approved Contractor’s second application for payment.
09/23/19 – THP visited CAB to meet Contractor, review progress of concrete repairs, and document conditions at terra cotta excavation.
09/24/19 – THP issued field report 6 from 9/23 site visit.
09/28/19 – THP visited site at 800 Broadway to document progress of limestone removal at west elevation.
09/30/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
09/30/19 – THP visited site at 800 Broadway to document conditions of masonry backup wall at west elevation.
10/01/19 – THP issued notes from 9/30 progress meeting.
10/02/19 – THP met Contractor at THP to review conditions of backup wall at 800 Broadway and discuss details for installation of wall ties.
10/02/19 – THP had telephone conversation with Owner to discuss recommendation to demolish and rebuild a portion of the backup wall at the west elevation at 800 Broadway.
10/02/19 – THP issued field report 7 from 9/30 site visit.
10/02/19 – THP developed letter outlining effect of additional work at backup wall on overall schedule at 800 Broadway.
10/07/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
10/07/19 – THP issued notes from progress meeting.
10/07/19 – THP developed Cash Allowance Usage 1 and emailed to Owner and Contractor for review and approval.
10/07/19 – THP visited site at 800 Broadway to review and document progress of backup wall modifications at 800 Broadway.
10/08/19 – THP issued field report 8 from 10/7 site visit.
10/14/19 – THP met Owner and Contractor at WH Taft Center for progress meeting.
10/15/19 – THP issued notes from 10/14 progress meeting.
10/16/19 – THP met Contractor at WH Taft Center to review and document progress, then visited 800 Broadway and CAB to document completed work.
10/19/19 – THP visited site to document progress of limestone re-installation at west elevation.
10/20/19 – THP visited site to document progress of limestone re-installation at west elevation.
10/21/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
10/21/19 – THP issued field report 9 from 10/16 site visit.
10/21/19 – THP issued notes from progress meeting.
10/25/19 – THP reviewed and approved Contractor’s third application for payment.
10/25/19 – THP issued field report 10 from 10/19 & 10/20 site visits.
10/28/19 – THP met Owner and Contractor at 800 Broadway for progress meeting.
10/29/19 – THP met Contractor at CAB to document progress of GFRC installation, then visited 800 Broadway and WH Taft Center to document completed work.
10/29/19 – THP issued noted from 10/28 progress meeting.
12/31/19 – THP reviewed and approved AFR’s fifth application for payment.
01/03/20 – THP issued field report #19 for 2020 Auburn Ave. façade repairs.
01/07/20 – THP delivered AFR’s fifth application for payment to BW.
01/07/20 – THP finalized and emailed letters to city about completion of façade repairs at CAB, 800 Broadway, and WHT Center.
01/13/20 – THP reviewed AFR closeout documents and discussed requirements with BW and AFR.
01/21/20 – THP developed and issued change order #5 for trench drain repairs at 250 WHT.
01/21/20 – THP finalized and emailed letters to city about completion of façade repairs at Justice Center and 2020 Auburn Ave.
01/24/20 – THP finalized Alms & Doepke window sill repair details and emailed to AFR proposal for change order #6.
01/24/20 – THP received and reviewed AFR’s revised closeout documents and forwarded to BW for approval.
01/28/20 – THP reviewed and approved AFR’s sixth application for payment.
01/30/20 – THP delivered AFR’s sixth application for payment to BW.
02/04/20 – THP received Champlain Architecture drawing for CAB signage change and forwarded to AFR for change order proposal.
02/10/20 – THP received and reviewed change order proposal from AFR for CAB signage change, and forwarded to BW for review and approval.
02/12/20 – THP developed AIA G701 Change Order #6 for 250 WHT plumbing repairs and emailed to AFR for review and signature.
02/18/20 – Change Order #6 signed by AFR and BW.
02/20/20 – THP visited site at 250 WHT to observe and document progress of trench drain replacement at Bellevue Ave. entrance.
02/21/20 – THP developed AIA G701 Change Order #7 for CAB signage change and emailed to AFR for review and signature.
02/24/20 – Change Order #6 signed by AFR.
04/06/20 – THP visited 250 WHT to observe and document prep of south trench drain prior to concrete pour.
04/09/20 – THP issued Field Report #24 documenting 250 WHT trench drain repairs.
04/22/20 – THP visited Todd A. Portune Center, Alms & Doepke, and 250 WHT to document repairs.
04/24/20 – THP issued Field Report #25 documenting completion of repairs at Alms & Doepke and 250 WHT, and completion of coating at removed CAB letters.
04/28/20 – THP reviewed pencil copy of AFR’s 9th application for payment, and replied with markups about revisions for line items related to change order #8.
04/28/20 – THP had conversation with BW about signage company’s request for payment on new signage letters.
04/29/20 – THP requested and received photographs of letters in storage at signage subcontractor’s warehouse.
04/30/20 – THP signed AFR’s 9th application for payment and forwarded to BW.
06/25/20 – 2020 Auburn, and 230 E 9th/WH Taft Center are still waiting for final approval of completed façade repairs by city.
06/25/20 – Justice Center is closed as of 3/27/20. A&D sill repairs and 250 WHT trench drains are complete. CAB signage removed and repairs are complete, but the installation of the new Todd B. Portune Center for County Government letters has been put on hold.
07/30/20 – Portune letters still on hold.

800 – 2019 Façade Stabilization (F117) Read More »

DDS – Security Upgrades

11/28/19 – DDS contacts GBBN by telephone to discuss project and Architectural involvement.
11/29/19 – DDS forwards the four facilities Security Reports from Risk Management to TEI and copies GBBN.
01/09/19 – TEI informs GBBN the approved SOSS and Purchase Order were recieved from DDS.
01/15/19 – GBBN and TEI met with DDS Administration to discuss scope and direction for project.
01/16/19 – TEI and GBBN send updated budgetary information to DDS for Budget Analysis.
01/22/19 – DSS sends to TEI and GBBN the Proposed Security Assessment Budget for review and input.
02/08/19 – GBBN contacts bullet resistant glazing and frame contractors to discuss material and system selections.
02/11/19 – GBBN meets DDS at Fairfax School to discuss issues and options for the Receptionist renovations after reviewing the original renovation drawings for this earlier renovation area.
02/15/19 – GBBN forwards preliminary Scoping Drawings, for eaach floor of each of the four facilities to DDS for review and comment.
02/18/19 – DDS requests meeting with Administration to review scoping drawings and Optional Plan Layouts for the Support Center Receptionist area.
03/13/19 – GBBN communication estimated fee and scope to TEI for Owner requested Life Safety Plan updates.
04/05/19 – Owner review meeting with TEI and GBBN is held. Opinion of Probable Costs are reviewed. Owner indicates scope and estimated Construction Costs are per Owner’s needs and wihtin budget. Design team is approved to proceed with next phase SOSS for services.
04/18/19 – DDS confirms new door hardware on existing restroom doors is to be of a locking type.
04/23/19 – GBBN recieves confirmation from Owner that new Support Center Receptionist Layout and Safe Harbor Rooms are to be added to the Life Safety Evacuation Plans.
04/24/19 – Owner review documents are sent to DDS for review, of the LIfe Safety Evacuation Plans.

DDS – Security Upgrades Read More »

800 – City Water Main Replacement

12/15/18 – TEI spoke with CWW on adding new city water main and abandoning old main underground. This seems to be an acceptable solution for everyone.
12/31/18 – SOSS approved, ThermalTech can start design for replacement.
01/31/19 – ThermalTech has completed several field trips for this work and worked out replacement with the CWW for this job. THP will provide notes for sealing up the wall after piping is removed. We will try to have ready for ITB and bidding in early February. We will get prices now for Facilities to see about funding.
02/28/19 – Project updated with revised scope and sent to Bert. TEI met with GBBN and THP to discuss their role in the final TEI drawings and got some information about how the project will work. TEI to update drawings and cost estimate with final scope.
03/21/2019 – THP Finalized foundation repair detail and related specification sections and emailed to TTE for review.
03/27/19 – THP submitted drawing package to ThermalTech. TEI incorporated details into job and updated floor plans. Final review set going out this Friday.
04/24/19 – Prices submitted, project awaiting approval by County.
05/28/19 – Project on hold awaiting release by the County.
06/27/19 – Project on hold pending funding.
07/25/19 – Project on hold pending funding.
08/28/19 – Project on hold pending funding.
09/25/19 – Project on hold pending funding.
10/30/19 – Project on hold. Fire Pump Study working on peripheral items associated with this update.
12/11/19 – Project on hold.
01/24/20 – Project SOSS for Bidding & Const submitted to County for approval. Drawings are pretty much ready for bidding upon County approvals.
02/20/20 – SOSS and PO forthcoming after speaking with Facilities. TTE should prepare the bid document work in Feb/March.
03/23/20 – Final review drawings are nearly complete. TTC need to check over and send to Tony.
04/16/20 – Drawings will be sent to Tony Matre for final review by May 1. Spoke to Tom Frimming about pump requirements and new water main installation for this job; forwarded those comments to Tony for review.
05/27/20 – Final markups not included yet from TTC markups. I am thinking that I will pick up the final markups myself beyond this markup set but I do need to send Tony his final dwg set for his markups.
06/23/20 – Project on hold awaiting funding.
07/29/20 – Project on hold awaiting funding.
08/26/20 – City performed work in the alley this month for new sidewalks, curbs and concrete. TTC measure the depth of the city water line while the alley was demolished. The piping is 19″ below grade with the alley removed and potentially another 9″ below the landscaping in front of the 800 Broadway building.
09/18/20 – No updates this month.
10/28/20 – No updates this month. But we did refresh the drawings a little bit and try to improve the PID.
12/10/20 – Tom F called to say that SA Comunale ran the annual fire pump test last week and the building does not hold on one water main. TTC reached out to Daryl Meadows at the CFD about what the Fire Watch would include during the City Water shutdown and TEI will update the drawings accordingly. Also, however, TTC reached out to SA Comunale for the actual failure points. The low water cutoff means (i.e. if the pump can’t pump 125% of the flow, that doesn’t mean it can make 100% of the flow and that may be critical in the fire watch work over the weekend). The sensor turned the pump off before the pump reaches maximum by design.
01/25/21 – TTC sent latest drawings to Nester.
01/26/21 – TTC printed out final set, met with TAB to start final layout, planning on having review set to County on 2/5.
02/24/21 – Project going to bidding today with a prebid on March 12 and a bid opening of March 31.
03/22/21 – Addendum #1 issued last Monday. TTC has been coordinating with CFD on alternate methods to keep the fire pump running while the work is completed but no definite direction was agreed upon between CFD and ThermalTech so the fire watch will remain in the base bid and used for this project. Add 2 will increase the budget to $100,000. The final Addendum is due today.
04/29/21 – QCM was apparent low bidder on project. ThermalTech held a post bid summary with QCM and recommended them for this job. Base Bid and Alternate for Fire Tee accepted, contract in for review.
05/26/21 – Final contract sent to QCM. Site Safety, safety, and tax-exempt certificates have been shared. We are ready for a pre-const meeting with Facilities and QCM.
06/17/21 – Kickoff meeting with contractor on-site at 800 Broadway. Schedule, submittals, SOV, background checks all requested from QCM. TTE to submit plumbing drawings to city for permitting with QCM.
07/28/21 – Waiting on QCM background checks to clear so they can do the work in August.
08/06/21 – QCM preparing project site.
08/10/21 – Trench work underway and mostly done. Fire watch set for Saturday.
08/12/21 – Final connection work at CWW tee has issues. TEI on-site surveying the issues. New water line cannot be connected to existing water line with Duke electric duct bank in the way of our water line. Weekend cutover postponed to Aug 20. Hydro excavating is scheduled for Monday.
08/16/21 – Hydro excavation revealed more pipe, valve, and tee structure. QCM is not comfortable connecting any of the existing piping and suggest getting CWW involved to allow us to replace the valve and tee. TEI working with CWW on solution and approval.
08/22/21 – Working with CWW to resolve the new connection.
08/24/21 – Approvals received from CWW on replacing CWW valve and tee to extend out new water main into the building. QCM change orders received.
08/25/21 – QCM remobilizing for rest of 800 work. Valve and tee on order.
09/27/21 – CWW permitting discussions went well. CWW process requires fire calls. TEI to reach out to city to get the original 1992 fire protection calcs.
10/15/21 – TEI reached out to Dalmatian, Dalmatian fire companies for original calcs. Dalmatian reported they don’t have them. TTC asked a local fire protection to help with the calcs if we can’t find them, they will help.
10/22/21 – City came through with 800 permit drawings from 1992. They sent us over 1000 files and Coty found the fire calcs in the downloads. We are working on fixing the contrast so we can submit them for this job. This is good news.
10/28/21 – We are working with CWW and City permit office to submit a FA Calc plan to city and CWW for approval of changing the fire pump feed. We have the city permit documents and found the original calcs. We will get this out in a week.
11/23/21 – ThermalTech working with City and QCM for revised fire protection piping change for fire pumps. GCWW rejected the first permit application due to non-licensed plumber being selected in the application process.
11/30/21 – GCWW permit has been resubmitted to the water works. No update on city permit status yet.12/01/21 – Weekend work postponed for approved city and GCWW permit.
12/08/21 – TTC spoke with GCWW on permit and it is on hold until the city water main can be brought up to current standards. TTC emailed John and Rick and needs to set up a follow-up call with John about the feasibility of the GCWW request.
01/25/22- TTC needs to update the drawing for the GCWW review for the remote valve they want on the property line. TTC going to do his own cad for this work.
02/24/22 – Revised drawing is ready for review. Rick Seaver has left QCM, TTC will call and coordinate with Bryan Gilbert who is taking over for Rick.
03/31/22 – Drawings and study complete.
04/28/22 – No updates this month, try as I might.
05/25/22 – Met with the GCWWW last week on potential updates to give them what they want on this job. They will not accept either of the proposals that we gave them to modify the fire and domestic water feed. ThermalTech working on acceptable domestic water solutions that gives the county some savings for the cost needed to meet GCWW requirements.
06/25/22 – Created change order drawing for QCM to provide pricing on city water valve option.
07/22/22 – Change order received from Queen City and forwarded to the County for consideration.
08/19/22 – We are moving to close out the project. We are getting final prices from QCM for closeout. TTE working with Bryan on closeout documents.
09/22/22 – Keeping this open for QCM to do some selective valve replacements at 800. Coty working on the final list and cost for us.
10/26/22 – Project closeout documents received. TTC has final change order to review to close out.
12/15/22 – OK to close out.

800 – City Water Main Replacement Read More »

CH – Overhead Door Project

01/15/19 – TEI talked to Tony Matre about a new project to power up a new overhead door that will be installed on the attorney entrance on the back of the Courthouse including access control for the door after hours. Mike Barth will lead this project for ThermalTech since it appears to be mostly electric in nature. Overhead door will be allowed to provide equipment for this job. ThermalTech will coordinate this with facilities and the vendor and we can reach out to GBBN for door support as needed. ThermalTech to provide SOSS for this (hand delivered at the 01/31/19 partner meeting).

02/26/19 – Project pending the SOSS approval and PO.

03/26/19 – Project pending the SOSS approval and PO.

04/24/19 – Project pending the SOSS approval and PO.

05/29/19 – TEI receives Approved SOSS and PO. TEI contacts AKM for project kickoff.

06/26/19 – TEI has meeting with AKM, RM, and HCSO to kick off project. RM indicated long range card reader was proposed, but only works with Bluetooth, which the HCSO does not want to use Bluetooth. TEI sends HCFD options to discuss with team and upon reciept of direction will complete drawings for owner review.

07/24/19 – TEI gets quote from DK to install work with Overhead Door as a sub to them and sends to AKM for review/approval. AKM to have install work per the approved design concept (issuance of RF clickers for vehicles that park in the garage, and card reader access control for those not in vehicles with approved credentials in the system.

08/27/19 – DK awarded contract to complete the work. DK scheduling install through Rob Edwards and Tony Matre. This all to be installed as soon as possible. Risk Mgmt is upgrading the access control system in the CH to a Vax system by Vicon. This new system to be Vax, and may be installed before Vax head end.

09/25/19 – DK moving forward with installation. Ramp was trenched on 09/20 and 09/21 with conduit installed to locate reader on the east ramp wall. DK to submit schedule to AKM.

10/30/19 – Overhead Door Company is scheduled (again) to install the door on 10/31/19. Upon installation of the door, DK to coordinate with Risk (who is in having the new access control system installed) to tie in the new card access to the new door.

12/11/19 – Overhead door installed, and DK missed an internal CR. TEI calls DK to inform them to install it. AKM states that there are items on the project that are not installed. Instructs TEI to advise DK that all work associated with his PO to be completed. SK states that the VAX system is incomplete, and AKM says get his PO worth of work installed, and he can close out his work and then the operation of the system is dependent on the completion of the VAX project.

01/28/20 – According to DK – the install of the work associated is complete with the exception of the VAX connections. DK has the door able to be operated with Pushbutton in the guard booth until a time when the VAX system is fully operational.

02/26/20 – HCFD stated that the door shall be interlocked with the FA system to maintain accessible egress path in the event of a FA situation. TEI requests timing and pricing from DK for modifications to the system to interlock with the FA system.

03/26/20 – DK sends in the pricing for the fire alarm interface. AKM asks for cost breakdown.

04/30/20 – Project pending FA interface.

05/27/20 – Project pending FA interface and over ride switch installation.

06/23/20 – Project pending FA interface.

07/29/20 – Project completion pending access control system completion and fire alarm interface.

08/21/20 – DK has been directed that all pending items to be completed prior to Labor Day weekend. The man-trap features will not be active until the entire VAX system is up and running and programmed. All construction work not associated with the VAX turnover to be completed.

09/23/20 – DK installs keypad and card reader so walk-ups (with appropriate access) can operate man trap doors. DK on site on 09/23 working on programming and finalizing the issues with the system.

CH – Overhead Door Project Read More »

A&D – Cooling Tower Replacement

01/07/19 – ThermalTech met onsite with BAC representative and reviewed condition of existing towers. TEI sent in an SOSS for the study for approval to Facilities later that day in hard copy and email.
01/21/19 – SOSS approved TTC setting up report and getting prices for replacement and repairs.
02/28/19 – All prices are in and preliminary report has been written. TTC to review, updated and send to Bert and Steve for their use.
03/27/19 – TTC must review final cost estimate tonight to share with County tomorrow.
04/25/19 – TTC will submit report today.
05/27/19 – Prices and Study submitted to County. Awaiting County decision on repairs.
06/27/19 – Talked to Tony Matre about bidding out the replacement of the cooling towers this year and he said check in with Bert about project viability. The schedule would be to start after cooling season and be complete prior to 2020 cooling season.
07/24/19 – Meeting schedule with County on 7/25 to discuss options. TTE fieldwork is complete for the cooling towers. PID has been converted to CAD for use on this project. There are questions about the design and cooling tower sizes to be discussed at Thursday meeting.
08/28/19 – Project is in to the owner for review. Funding is set for approval from JFS in August.
09/24/19 – Project undergoing some funding and County review. TTE will have project ready to bid when final okay comes from Owner, looking to mid November.
10/30/19 – Project on hold. TTC checked with lead times on Evapco towers who claim to still be two to three weeks.
12/11/19 – Had some movement on this project this week. TTE to submit a small SOSS for some additional services for extra design work.
12/12/19 – The money has been approved for this project but the paperwork is not fully approved at this time.
01/24/20 – ThermalTech putting final bid documents together for bidding in February 2020, award in spring, be read to construct in November 2020. TTC discussed project with Steve Terheiden last week on Ameresco walk through.
02/20/20 – SOSS and PO should be on their way for work in Feb/Mar.
03/19/20 – Prebid meeting at the site with about 6 bidders. Several items to be released on Addendum including a 6th Floor drawing clarifying sweeper piping.
04/23/20 – Bids were open to five bidders, most were underbudget. TEI conducted a post bid review with Debra Kuempel and found them to well recommended bidder for this project. They have the scope covered, would really like to start the job early if possible and have all of the Alternates covered in the bid.
04/28/20 – TTC spoke to Tony Matre about Alternates on this job and awarding the rest of the work. We will need contracts and a PO to get started, County thinking about allowing the CT to be replaced over the summer long weekend.
05/25/20 – Project in for approval. Debra Kuempel check on approval of job on Monday. We are accepting several of the Alternates but not the extra basin heater extras.
06/22/20 – Project setup and communication this month with RT this month for doing the work this fall. TEI updated Debra on project status and assured them this project is still a go. I don’t think this work will be done over the summer even in multiple parts over weekends, but this is something we can discuss at the Pre-Const mtg.
07/23/20 – Pre Const Mtg held on site with Debra Kuempel, TTE and County. We are getting all things in place for this job and potentially look for an earlier than fall start if we can get the equipment earlier. TTE issued the Const Mtg notes this night.
07/29/20 – 3D scanning schedule for Thursday. Submittals have been preliminarily worked out with Stoermer Anderson, Debra and TTE. The SS towers will weigh less than the existing towers and fit on the existing steel. We are discussing ladder and drainage details for the final submittal which should be next week. The delivery time for the towers may be as fast as 6 weeks per our discussions with Marley. DK has submitted the SOV, Schedule and Employee list for review.
07/30/20 – Lightning protection questions on the A&D was discussed. We have enough UL listing verification and THP will fix the drainage issues when they do their project.
08/24/20 – Debra inquired about roof build. TTC contacted GBBN for basic roof layout and send photos showing the roof structure from underneath to DK for this job. DK also inquired about submitted a payapp for this project this month which TTC said would be okay.
08/26/20 – No payapp has been submitted that TTE has seen yet.
09/18/20 – This month we approved final submittals. DK should have the CT on order with Marley. Now we are prepping for install.
09/24/20 – We got 30-day electric data back from DK. MCB says we will work with this data for the IBI permit. BW mentioned that we have to check the LED light pattern on the new CT so we don’t affect the historic district lighting effects.
10/28/20 – Checked in with Debra this month, got a handle on final background checks. Cooling Towers scheduled to ship Nov 11, being confirmed. TTC to check on permit status with Debra tomorrow.
11/18/20 – THP – as part of the Cooling tower replacement project, City of Cincinnati requested a structural review of the cooling tower structure and the proposed replacement towers. As part of the Cooling tower replacement project, City of Cincinnati requested a structural review of the cooling tower structure and the proposed replacement towers.
11/20/20 – THP completed site visit.
11/24/20 – THP published a letter addressing the City’s letter.
12/02/20 – THP submitted a SOSS for the work completed.
12/09/20 – THP received approved SOSS.
12/10/20 – We have been working on permitting, submittals and structural steel approvals with DK and THP this month. The permit appears to be approved at the City for DK to pick up. We need an update on the background checks, which seem to be taking longer than anybody would like. The county issued a PO direct to THP for their work getting the permit through the City office. All the equipment is in town for the job and TEI went to the rigging yard to approve it and send pictures of it for invoicing.
12/29/20 – Working with Debra to get guys through background checks to get started. Bert and Rycca have followed up with several emails on the subject. Phone conversation with DK has them starting in January and completing the job in January as well.
01/23/21 – Contractors on-site removing cooling towers today. Some issues with disassembly prevented them from getting both towers off the roof but they were able to get west tower, piping, and ladder removed. And for the east tower they removed the piping and ladder and full prepped the CT to be removed. The next crane lift is scheduled for Jan 30 and DK will remove the old tower and put up both new towers. The structural will be wire brushed and repainted and we are getting a change order to replace some more of the CWR piping.
02/24/21- DK moved inside during cold weather and started working in the basement. Slow progress as of last week. Weekly const mtgs set for Thursday until the project is complete.
03/23/21 – Punchlist Tuesday by Terry and Mike. TTC has been following up with Debra & Marley this week on several items pertaining to the construction of the tower. DK pricing replacement of the final platform behind the east tower. Punchlist due out Friday, County comments welcomed.
03/25/21 – TTC to check on OSHA compliance on the top of the tower including the gate, and kickplate. TTC to reach out to THP and get contact information for LJB.
04/20/21 – Change Order #2 approved for additional painting, grating and hot tap from high pressure city water system.
04/28/21 – DK reports all change order work is complete, final cleanup being done.
04/29/21 – Project is complete, punchlist is distributed, DK finalizing clean up on project.
05/26/21 – Change Order for electrical and controls work is in final approval. DK controls punchlist work has been complete and the system is running under revised control. Electrical and Mechanical inspections are complete and approved. Steps are not installed. Change Order control work to monitor the condenser water pumps via CT is not complete yet.
06/25/21 – We’ve checked in with DK several times on the final items to complete this job. (1) Steps are in fabrication. (2) Control programming is complete. (3) CWP circuit monitors are ordered but not installed yet. The good news is that the cooling towers are working well.
07/28/21 – Project is complete minus the steps. Safety docs sent to Rycca for record. DK is starting closeout manuals.
07/29/21 – Debra reported in today with updates. Warranty set for 5/26, closeout manuals being created, safety reports were sent to Rycca and steps over sweeper piping will be fabricated this week.
08/26/21 – DK is complete except for the steps which Joe is bringing over this week for the building.

10/28/21 – This job cannot be closed out until Maxwell provide actual pay stubs for their work. County will not pay final invoice until this is resolved. Debra contacted today to get this resolved.

A&D – Cooling Tower Replacement Read More »

THP – General Structural Services

PM: Bert Watts, John Millar
11/06/18 – Hamilton County requested SOSS.
11/15/18 – THP provided SOSS.
11/19/18 – Hamilton County executed the SOSS.
03/28/19 – THP completed internal review of Master Agreement. THP will forward to County by 3/29/19.
— New Contract —
04/08/19 – Hamilton County requested SOSS.
04/10/19 – THP provided an SOSS for review.
04/22/19 – THP provide updated SOSS with new F series number.
04/24/19 – THP SOSS approved.
05/10/19 – A small piece of Terra Cotta fell from the Alms and Doepke Building. THP coordinated contractor support to remove the remaining loose pieces of terra cotta. THP to follow up with a summary report.
06/07/19 – THP issued a draft Terra Cotta report for review.
06/10/19 – THP issued final A&D Terra Cotta report.
10/07/19 – THP attended kick off meeting for review CAB entry project. Based on current project request, THP will not have a role in this project.
10/31/19 – THP estimate up loaded into Archibus.
11/20/19 – 250 WHT Trench Drain work order for cleanout and review planned. THP to review concrete conditions.
12/4/19 – 250 WHT Trench Drain – THP reviewed initial conditions and is reviewing with the City options.
12/10/19 – 250 WHT Trench Drain – Trench drain partially collapsed and is closed. THP and American Façade Restoration reviewed the conditions. AFR placed plates over the main drive lane.
12/11/19 – 250 WHT Trench Drain – THP issued a repair for pricing. AFR hopes to provide a price on 12/13/19.
02/13/20 – County requested THP review corroding steel at the Burlington Garage facility.
02/20/20 – County requested an SOSS for Courthouse bridge issues noted in City bridge inspection report.
02/26/20 – THP completed an initial visit to Courthouse bridge.
02/21/20 – THP and County reviewed field conditions at Burlington Garage. THP to generate an SOSS.
02/27/30 – For 250 WHT Trench Drain work refer to F117 for project status.
06/09/20 – THP met with Champlin at Juvenile Justice Center to review flooring field conditions. No visible structural deterioration or distress, but much of the structure is covered (flooring & fire proofing). THP to review approach with Champlin.
10/29/20 – THP has sent multiple email request to City to try to close out City Facade Inspections for 2020 Auburn and 230 East Ninth.
02/18/21 County requested THP review planned installation of two freezer units in 800 Broadway.
02/22/21 THP reviewed new refrigerator units at 800 Broadway basement. THP made recommendations via email for installation and location on the raised platform flooring structure.
04/05/21 – County reached out to review replacement RTU on the Florida roof of the 800 Broadway building. THP reviewed documents and visited the site the week of 4/13/21.
04/23/21 – THP published a review of the condition. Big picture new unit should work. Existing unit and new unit are schedule to be placed on unknown wood members. THP noted wood structure should be reviewed after the existing unit is removed, prior to the installation of the new unit.

THP – General Structural Services Read More »

BOE – Fire Alarm System Modifications

10/23/18 – BW contacts ThermalTech about pricing for additions required by the City of Norwood to the existing fire alarm system at the BOE. ThermalTech, HCFD and DK meet at the site to develop budget pricing for HCFD. BW to advise next steps upon approval of funding.
1/28/18 – Signed SOSS and PO received to complete the work. ThermalTech receives Drawings from Notifier (RP Biederman) and there are additional devices from what was priced. TEI has DK call RPB to question where/why these devices were added (where did the direction come from?) DK to respond back to TEI with RPB response.
01/29/19 – There are doors at the facility that the BOE has asked to have door hold opens on that did not have closers. Also – due to door and rack configurations, there are doors that only open 90 degress so an alternate closer/hold open device was suggested. DK submitted a CO request, but BW stated that it needed to come from Tumlin since Tumlin holds the contract. TE contacted Tumlin and DK to request the CO appropriately, and it is still pending.
02/26/19 – HamCo Signs CO for the additional door closers for the project (there were doors that had doors that BOE requested hold opens that had no closers). Door hardware scheduled to be delivered first week of March and then installation will be scheduled immediately upon receipt.
03/26/19 – All equipment has been installed and pre-tested on 03/21/19. Final inspection scheduled with Norwood on 03/28/19 at 1:30 PM. After the final inspection, ThermalTech to perform final punchlist and project closeout documents can be completed.
04/24/19 – ThermalTech and Facilities performs and issues punchlist. DK completes their portion of punchlist and waiting on Tumlin for a few items on the punchlist.
05/29/19 – ThermalTech waiting on final closeout documents from Tumlin to close out the project.
06/26/19 – ThermalTech waiting on final closeout documents from Tumlin to close out the project.
07/24/19 – ThermalTech reviews and certifies final pay application and submits to Bert Watts. DK submits close out documents to Bert Watts.
07/25/19 – BW says after PW Rates arrive we can close this job out.

BOE – Fire Alarm System Modifications Read More »

250 WHT – Trench Drain Investigation (F115)

09/20/18 – County requested a SOSS to investigate the south trench drain and provide recommendations to repair.
03/21/19 – THP visited the site. THP to review conditions with County.
03/21/19 – THP visited the site. THP to review conditions with County.
04/05/19 – THP completed a follow up to visit the Trench drain.
04/25/19 – Follow meeting with Bert work on hold.
09/26/19 – Project ready to archive.

250 WHT – Trench Drain Investigation (F115) Read More »

DDS – Rost and Franks Re-Paving and Sealcoat Project

04/27/18 – DDS and GBBN hold kick-off meeting to discuss project scope of work and services.

05/23/18 – DDS and GBBN hold first project and document review meeting.

07/19/18 – DDS and GBBN hold final review meeting before release of contract documents for bidding.

07/23/18 – Preliminary Bidding Documents sent to ARC for review and comment.

07/24/18 – Final Contract Documents posted to ARC and Purchasing.

08/14/18 – Pre-Bid Meeting held at Rost School.

08/21/18 – Addenda #1 posted.

08/23/18 – Bid Opening held. Three bids were received. Westside Paving & Excavation, Inc. was the apparent low bidder.

08/24/18 – GBBN holds bid interview meeting with Westside. GBBN issues letter of recommendation to DDS in favor of Westside as low and responsible bidder.

08/27/18 – GBBN completes authoring of AIA contract for Westside and delivers to DDS.

09/14/18 – Notice to Proceed sent from DDS to Westside.

09/17/18 – Contracts delivered from DDS to Westside.

09/21/18 – Pre-Construction Meeting held at Rost School. 10/3/18 established as the contract date.

09/24/18 – Schedule of Value Preliminary received by GBBN from Westside

09/26/18 – Schedule of Values and Mix Design Approvals sent back to Westside Paving.

10/17/18 – Logistics meeting held with WPI, GBBN and DDS Directors and Facilities Manager. Schedule agreed to in principal, with dependency on weather.

10/22/18 – WPI starts with Site Mobilization.

10/23/18 – Milling and parking block removal are started. By end of day all milling at Franks up to Rost service drive are completed.

10/24/18 – Paving is completed at all areas. Striping should be completed by 10/27/18.
04/15/19 – DDS Facilities Manager requests status of close-out repairs remaining. Indicates painting of speed bumps has beeen completed by Owner.
04/16/19 – GBBN and Facilites Manager meet on site to finalize the remaining close-out repairs required. GBBN transmits findings to Westside Paving.

DDS – Rost and Franks Re-Paving and Sealcoat Project Read More »

JC- Press Package Rendering Services

09/05/18 – Facilities and Administration request the “Press Package”, discussed during Commissioner Driehaus’s impromptu Press Conference be generated by GBBN.

09/06/18 – GBBN meets with Facilities to discuss direction to be used for structuring the Press Package, graphics to be used and Language to be generated and added by Facilities/Administration.

09/07/18 – GBBN emails a preliminary packet of renderings for Facilities to review and comment.

09/08/18 – Administration and Facilities comment back to GBBN about suggested formatting and title direction. The option for new window placement was selected.

09/12/18 – GBBN has internal meeting to finalize layouts and direction for titles and implementation of the language sent by Facilities. GBBN sends proposed “Milestone” verbiage to Facilities for approval.

09/12/18 – Facilities indicates via email that GBBN’s attendance will be required at the 9/17/18 BOCC meeting for any required input needed for approval of the Press Package.

09/17/18 – GBBN is notified the Press Package was not included on the BOCC Agenda for today.

09/24/18 – GBBN is notified the Press Package was not included on the BOCC Agenda for today.

 

JC- Press Package Rendering Services Read More »

GBBN – CAFM CAD General Maintenance

09/13/18 – Facilities requests GBBN/In4 to author a SOSS for General CAD related items that may happen as Facilities is migrating the Space Module to Web Central.
10/22/18 – Facilities requests status on project. GBBN responds indicating intentions to mobilize by 10/25/18.
05/22/19 – GBBN isssues updated drawings for Facilities related to WebCentral new updates to the system.
02/26/20 – Facilities is finalizing the Space migration/ARCHIBUS v24 project, hopefully by next month. The Facilities Department is in need of some tweaks to the published drawings in the UAT site:
https://hamiltonuat.asset-fm.com/archibus/
Steve Farashian is the new Facilities PM for the project and he will be going to contact GBBN regarding those tweaks.

GBBN – CAFM CAD General Maintenance Read More »

JC – Elevator Modernization Study

09/14/18 – TEI and GBBN contacted about a possible study in an attempt to obtain a budget cost for the Design Services.
09/14/18 – GBBN made contact with Otis Elevator to discuss consulting assistance for the Modernization Study if it proceeds.
09/15/18 – Otis makes request for drawing files or any other pertinent information. GBBN reports the County has not initiated an official request for design services as of yet.
09/27/18 – TEI drafted an SOSS for cost for Bert to review. It will delivered at the monthly partner meeting.
10/25/18 – SOSS for study is approved. We will take out a new Archibus number for the elevator study. The old one will be kept for reference and used for data.
11/28/18 – TEI to schedule a kick-off meeting once all parties respond with their availability.
01/15/19 – TEI met with facilities to kickoff project and will have GBBN as sub-consultant for use on this study and report. Mike Barth will lead the project with the help of an assistance electrical engineer.
01/16/19 – GBBN contacts Elevator Engineer consultant to discuss possible dates for field verification meeting in Cincinnati.
02/26/19 – Pending meeting with Elevator consultant (GBBN working to get Scheduled)
04/02/19 – GBBN contacts Building Manager about vendor contact for future site visit. No contact has been made by vendor.
04/03/19 – GBBN coordinates vendor and Building Manager site vist for Friday, April 26, 2019. Vendor to have Study input to GBBN by 04/30/19.
04/24/19 – Otis scheduled to be on site 4/29/19 for final coordination walk though and determination of needs, and then will turn over findings and costing data to GBBN. Report will be sent to AKM upon receipt of the data from the elevator consultant.
05/09/19 – Otis Modernization sends final report and Opinion of Estimated Costs to GBBN. Copy sent to ThermalTech.
05/20/19 – GBBN sends Opinion of Estimated Costs, for Elevator Cab Finishes Installation Costs, to ThemalTech, for inclusion into the final report.
05/29/19 – TEI and GBBN drafting the report to send to HCFD for review and comment. TTC confirmed that we have added cooling to the North Tower last year but not the South tower yet. We are looking to get temperature trends for these spaces.

06/26/19 – GBBN receives final design requirements from HCFD to complete the pricing and write up of the report. Upon receipt of GBBN information, TEI will finalize report and send to HCFD for review.

07/24/19 – TEI and GBBN finalize the report and send AKM electronic copy for review and request how many hard copies that AKM would like for distribution to the HCSO.

08/27/19 – Final report pending any comments from HCFD or HCSO.

09/25/19 – Final report pending any comments from HCFD or HCSO.

JC – Elevator Modernization Study Read More »

CAB – 8th Floor- P&D Space Planning

07/25/19 – GBBN and IPM finalize SOSS for Facilities and delivers.
09/25/18- Facilities contacts GBBN about a new project for Space Planning and existing systems furniture inventorying. Existing P.O’s to be used to fund.
09/26/18- GBBN contacts IPM about role in project and requests scope proposal.
10/08/18 – GBBN and IPM meet with Facilities and Planning Development onsite for Kick-off Meeting. A site walk through is held at end of meeting.
12/11/18 – IPM and GBBN meet with Planning and Developement and Facilities to discuss direction of project and deliverables.
12/21/18 – IPM meets with Planning and Developement Director to discuss IPM recommendations and Schematic Design schemes developed.
04/25/18 – On Hold.
07/25/19 – P&D to check over proposed plan and give comments.
09/26/19 – No project updates.
10/31/19 – No project updates but are shooting for prior to digital which is July 2020.

CAB – 8th Floor- P&D Space Planning Read More »

JC- Room 120 HVAC Study

09/04/18 – Pulled the original Trace Calc to show we are using 11.5 tons of a 20 ton chiller, this chiller can do more work.
09/21/18 Met Andy and took off all fieldwork in the Room #120 area tracking down the piping and ductwork associated with the new fan coil units for the 20-ton system and the single zone system. The fieldwork showed us that there are more FCU’s than in the original PO with Motz and these are connected to the 20-ton chiller unit. TEI is certain the old ductwork and diffusers are still in place providing ventilation to the space and the new FCU were added for additional space conditioning. We will update the load calculation and look at expanding this system into the Employee Services area across the hall with additional FCU’s. Bill this to the AKM General Service number.
10/22/18 – Sent Tony and Andy a full schematic design and cost estimate for Room #120 expansion and replacement project using the existing chiller. Raw cost was about $58k and about full cost including engineering and permitting was about $90k.
11/29/18 – No updates this month.
12/31/18 – No updates this month.
01/22/19 – No updates this month, TTC has decided to archive for now.
03/08/19 – Andy contacted Terry about report and TTC reissued email to Andy and Tony with cost and floor plans.

JC- Room 120 HVAC Study Read More »

CH – Room #160 HVAC Study

07/16/18 – Sent Tony and updated summary of the fieldwork and load calculations associated with Room #160. Provided basically four options for possible HVAC changes that may help with cooling issues.

  • Unit appears to size large enough for the design day load
  • Add reheat to all interior zones for additional comfort control
  • Replace the unit and add zoning
  • Add DX unit to just #160
  • Relocate Judges to rooms that match their cooling request

08/01/18 – AAB provides hard quote for work based on ThermalTech drawings; they are estimating three to four days of field work to rebalance everything and test it.
08/03/18 – Tony contacts ThermalTech about moving forward with project.
08/23/18 – TTC sent a follow up email to Tony and Rob outlining what Honeywell found while on site performing additional research. Al the existing VAV boxes are pneumatic and any control strategy with intelligent reset design is not possible unless they are upgraded to DDC boxes. Hot water not available on this floor but is available in the basement with the unit. TTE provided a general estimate to upgrade the boxes and extend hot water reheat to the new spaces. What we have not found is what temperature the hot water is disabled based on OAT and what that may do to this design.
09/27/18 – Court decided to wait for funding before they do anything and what they have now will work for the foreseeable future.
10/23/18 – This project archived by TTC.

CH – Room #160 HVAC Study Read More »

JC – Switchgear AC Unit Project

01/08/16 – Met with Merkt on site to kickoff new AC unit in UPS room.
01/26/16 – Discussed scope of work with Tony and Joe over email today. Requested quote from Ray Weyman on Mitsubishi split at 4 tons for this room. This work may be a change to existing elevator work for cooling with Debra or owner will self-perform this work.
02/08/16 – The 4-ton unit only comes in a heat pump option but that heating can be locked out to provide cooling only. The 3-ton unit is a single wall unit with a single condensing unit. The 3.5 ton unit is ceiling cassette with a 3.5 ton condenser.
05/18/16 – Tony requested new SOSS for this work.
06/23/16 – ThermalTech was onsite performing fieldwork for equipment layout for about 3 hours today. We tracked down equipment locations for the Liebert and Mitsubishi Units and possible power sources for both.
07/18/16 – Phone conference today between Cannon, Merkt, Denton and Matre has decided to use an inline DX coil for HV-9 to cool this space similar to the work we are doing in the elevator room upstairs for additional cooling when the CHW plant is down. ThermalTech will modify the design.
07/20/16 – TTC on site for more fieldwork and duct measurements for new coil design.
07/21/16 – ThermalTech got design data from Habegger on just coil pack and we are having some airflow and discharge air temp issues with the design that we will have to work through.
07/21/16 – ThermalTech got design data from Habegger on just coil pack and we are having some airflow and discharge air temp issues with the design that we will have to work through.
07/27/16 – We changed the design of the switchgear room AC to a coil and condenser unit and started requesting new cuts from Carrier. We are updating the plans now. The Data Room AC unit was changed for low supply and top return and we will try to collect the hot aisle air with a return duct above the data racks.
08/03/16 – Some progress made on design. Cad files received from Liebert this week, we are updating outdoor equipment.
08/25/16 – Design will be complete and ready for bidding in mid September for both phases.
09/01/16 – Review drawings due Sept 16.
09/23/16 – Project set to bid on 9/29/16. Prebid Oct 6, Bid opening Oct 20.
09/28/16 – Project is issued for bidding. Switchgear AC unit is the base bid. Liebert Unit and Medical Unit are Alternate bids.
11/10/16 – Contracts are written and sent to Tony.
12/09/16 – Contracts sent to Tony for Debra Kuempel. Waiting on approval and kickoff meeting.
02/02/17 – Precon schedule for 2/8 with DK.
02/21/17 – Submittals are in for approval. We are definitely having some trouble finding the medical valves but Peck is working with us to find them.
03/09/17 – TTC to finish submittals this week.
03/21/17 – Submittals are marked up and ready to go back to Debra.
05/17/17 – Submittals returned, equipment ordered, waiting for DK to get started.
06/28/17 – Const Mtg today to restart the project.
07/17/17 – Equipment is ordered and en-route. We have agreed to use a ceiling mounted cassette on this project. DK submitted a change order allowance usage for this work.
07/24/17 – Equipment should be here next week per Debra Kuempel.
08/10/17 – Coil is installed downstairs in UPS room. Medical unit is installed upstairs.
08/30/17 – Work is progressing well, Cassette is installed upstairs. Coil is installed downstairs, balance report is short on airflow from existing unit.
09/25/17 – TTC crafted and sent the allowance usage to Dave Gleason for this project and he signed and sent back to the County. We are waiting on owner signed documents but are moving forward.
10/24/17 – Debra reports that most work is complete. TTC checking on progress on the electric and controls portion of the job.
11/28/17 – ThermalTech checked in with Debra on update on project today.
02/02/18 – Punchlist distributed to Debra Kuempel for project closeout.
04/04/18 – DK committed to wrapping this project up including controls by 4/30/18.
04/26/18 – Purchase order came out this week. ThermalTech agreed to perform the airflow readings for Debra and will share the results with the team. Then we will setup that conference call to discuss the results and proposed upgrades with the new motor.
08/01/18 – New motor is installed. Balance report shared by DK, commented on by TTE and send to County. Project is complete and DX unit is working well so far. Project is ready to archive.
09/04/18 – Systems are working well per Facilities. Project should be ready to archive.
10/25/18 – TTC delivered O&M’s to Tony Matre for closeout at Thursday Partner Meeting. The final permit is not approved and closed yet on the City website, TEI email Debra instructing them to close it out ASAP.
11/29/18 – The electrical permit is ready for DK to get the final inspection for closeout on this job.
01/10/19 – Final inspection appears to still have issues according to the website. TTC contacted Debra Kuempel to resolve. 9070-FINAL INSPECTION 11/26/2018 Defective (14X) Defective: 1. Label unit on roof. 110.22 2. Accurate panel schedule. 408.4 3. Bonding bushing on 480V. 250.97.
01/22/19 – According to DK the inspections are complete and they will send in all final paperwork ASAP for closeout.

JC – Switchgear AC Unit Project Read More »

JC – Liebert Unit Replacement Sheriff Data Rm 3rd Fl.

11/14/16 – Final Addendum went out to bidders. Bid opening is schedule for Thursday.
12/07/16 – Contracts sent to Tony for Debra Kuempel. Waiting on approval and kickoff meeting.
02/02/17 – Precon schedule for 2/8 with DK.
02/28/17 – No updates from Tony on approved contract.
03/09/17 – Waiting for kickoff on this project.
03/15/17 – PO and Contracts are ready, TTC requested meeting times from contractors and owner.
03/21/17 – We are ready to have the kickoff meeting for this project.
04/26/16 – Submittals requested. Pre Const Mtg was held.
05/17/17 – Submittals approved. Equipment ordered.
06/28/17 – Const Mtg today to restart the project.
07/17/17 – Unit is on order and should arrive late July.
07/24/17 – Equipment should be here next week, DK people approved for access but some JCI people not approved yet.
08/10/17 – TTC met Debra and Andy on site to discuss break down and reassembly of the Liebert unit in the data room today. Debra not a fan of breaking down the unit, we are exploring the option of taking out the window and
08/30/17 – We are going to order the door for the replacement of the single door. TTC to work out allowance with Debra.
09/25/17 – TTC crafted and sent the allowance usage to Dave Gleason for this project and he signed and sent back to the County. We are waiting on owner signed documents but are moving forward.
10/24/17 – Piping is ran to the unit. The scaffolding is coming down this week. Insulation appears to be installed as well. Outdoor unit is set. The interior door work is underway. KFI ran into a frame issue today and is having the frame modified for a Wednesday install. Once we get the double doors installed the Liebert should be rolled into the place the rest of the job can commence.
11/28/17 – ThermalTech checked in with Debra on update on project today.
02/02/18 – Punchlist distributed to Debra Kuempel for project closeout.
04/04/18 – DK committed to wrapping this project up including controls by 4/30/18.
04/25/18 – Project is complete and I believe final training is complete. Final payapps are being delivered to Tony on Thursday.
08/01/18 – Project is complete and running as design; ready to archive.

JC – Liebert Unit Replacement Sheriff Data Rm 3rd Fl. Read More »

Admin CHW Pump Replacement

12/26/16 – Contract sent to Tony for approval on this project.
01/26/17 – DK says controls will be done my same team as controls project. Gleason has sent all required paperwork to Tony.
02/01/17 – Project kickoff to be schedule soon. CHW pump size will need to be coordinate with new chiller.
02/16/17 – Kicked off project with Tony, Bert and Gilbert. We are collecting chiller information now and rates for LCC equations. We will choose the chiller during the LCC and design around one chiller during design.
03/09/17 – Pump is on hold pending new size from LCC equations.
03/15/17 – Emailed Dave Gleason for update as work was supposed to begin last week and be done by end of March.
03/21/17 – Tony talked to Dave and they are starting next week with pipe fitting work. Steve Yockey is waiting on TEI to provide new pump size for selection work.
04/11/17 – ThermalTech provides new bypass size and flow for DK to install the bypass.
04/26/17 – TTC checked in with Dave Gleason on progress. Given the cooling season is here, they are going to have to work weekends and off time to fix these issues. The new bypass size was sent to DK but I do not know if it was installed yet.
05/02/17 – TTC checked up on project again with DK for progress.
05/25/17 – Debra stated they will replace the pumps and piping at the same time, later in June.
06/28/17 – Met Debra today on project update and they are getting employees finalized for this project understanding it will be weekend work at this point. Pumps are on order, VFD”s are a new change order, TTC to give to Tony, will be from new project on new PO for up charges.
07/18/17 – Met with Design time to redesign the piping for the new larger pumps on teh CT and CHLR job. Spoke with the manufacturer about sizes and head. Debra submitted new change order for entire project. TTC to estimate the entire job again for Bert with Construction budgets.
08/10/17 – We are waiting for the weather to break to start the pump replacement.
08/26/17 – Debra to drain system and install isolation valves Saturday but this was postponed due to material arrival issues. They will try the week after Labor Day.
09/25/17 – Isolation valves are installed and working. DK needs to insulated still. TTC met with DK and went over remainder of project on site. The scope of the original project lines up perfect with the chiller replacement project except this project does not need to install the bypass piping on the fifth floor. The CHW pumps will be installed by DK in this project, the VFD”s and submittals must be ordered ASAP, and the change orders have been sent for approval to DK and the County.
11/2/17 – Pump replacement work is schedule for December 2017. Debra is currently on site and working on this job.
02/02/18 – Punchlist distributed to Debra Kuempel for project closeout.
04/04/18 – Only insulation remains to be completed. DK committed to wrapping this project up including controls by 4/30/18.
04/25/18 – Debra stated that all work on this project is complete including insulation. Final paperwork is being completed by DK now for all closeout paperwork. The final invoices are being delivered to Tony with a cover letter or remaining items.
08/02/18 – TTC inspected all final work including insulation and it looks really good. No additional punchlist items. Project is ready to archive.

Admin CHW Pump Replacement Read More »

Records Center – Building Envelope Assessment (F112)

05/01/18 – THP visited site to document conditions at rusted area of metal decking for purposes of developing SOSS.
05/15/18 – County requested Tremco be included with the assessment, because roof is a Tremco system.
05/31/18 – THP and Tremco have worked out an approach. THP to published SOSS for the County’s review.
06/21/18 – County approved SOSS for the project.
08/26/18 – THP sent consultant contract to Tremco for review.
09/25/18 – THP and Tremco finalized subconsultant agreement.
09/27/18 – THP to schedule field work with County.
10/25/18 – THP looking to start work week of November 5, 2018.
11/07/2018 – THP visited site to survey facades, roof, interior of metal deck, and coordinate with Tremco during test cuts.
11/15/18 – Tremco provided draft report.
11/29/18 – THP developing report.
01/17/19 – THP received final report.
01/30/19 – THP completed internal draft report. Final report expected to be submitted on 2/7/19.
02/07/19 – THP submitted final report.

Records Center – Building Envelope Assessment (F112) Read More »

A&D – Interior Finishes- Phase 2 and Phase 3

05/29/18 – GBBN is contacted by Facilities to begin assembly of the SOSS for this project. ADA Inclusion and THP Load Study must be included.
05/30/18 – IPM sends input to GBBN. GBBN requests SOSS input from THP and ADA Inclusion Consultant.
06/25/18 – GBBN receives SOSS input from THP and Preview Group for inclusion into SOSS.
06/26/18 – GBBN delivers final SOSS to Facilities.
07/26/18 – GBBN receives approved SOSS from Facilities.
07/27/18 – GBBN informs all design team members of approval and returns signed copies of Proposals to each design team members.
08/13/18 – Facilities requests GBBN make revisions to the “Project Scope of Work and Schedule” after consulting with all design team members.
08/15/18 – GBBN completes revisions to the “Project Scope of Work and Schedule” and transmits to Facilities.
08/30/18- GBBN to have internal design team meeting to kick-off Construction Document phase of project.
09/17/18 – GBBN begins Construction Document layout and production.
09/27/18 – Facilities requests GBBN and team put SOSS together for Construction Administration Phase 3 together. GBBN constact IPM and Accessibility Consultant for Proposal.
09/28/19 – GBBN contacts Facilities about LEED component of Phase 3 SOSS. Silver certification is requested.
10/04/18 – GBBN and TEI discuss LEED component of Phase 3 SOSS. TEI reviews LEED C.I. Checklist for MEP involvement.
10/07/18 – GBBN has internal office meeting to discuss LEED C.I. possibilities for this project. Findings shared with TEI.
10/16/18 – THP contacts GBBN about Floor Loading Study. Requests more information on types, sizes and weights of existing file cabinets shown on Second Floor West.
10/17/18 – GBBN performs site visit to document and photograph existing file cabinets. GBBN researches weights of fully loading file cabinets and reports findings to THP.
10/18/18 – IPM revises Second Floor layout to show a mirroring of West Side and East Side Departments to facilitate files moving from wood structure to steel frame structure.
10/21/18 – JFS approves IPM proposal to mirror the departments on the Second Floor.
10/24/18 – JFS reports additional changes to IPM/GBBN related to transaction Kiosks and Transaction Windows in Core, and cubicles on the West side, of Second Floor.
10/25/18 – THP completed initial field survey and review of the proposed floor plan. THP presented findings to GBBN for review with the County. We discussed LEED-CI feasibility with County at Partner Mtg. GBBN to submit a review of our findings that this building will not have enough credits to qualify for LEED certified and does not meet some of the pre-requisites for plumbing and water efficiency (an exemption would have to be requested).
11/02/18 – THP completed initial floor loading analysis of the proposed floor plan and published a summary letter.
01/14/19 – Entire Design Team meets to discuss project deliverables and scheduling in preparation for JFS and Facilities update meetings.
11/16/18 – THP developed a loading criteria and proposed a modified floor plan for review.
11/20/18 – THP and GBBN finalized a new plan to based on the loading criteria.
11/26/18 – GBBN receives approved SOSS and associated Purchase Order for Phase 3 of the project.
01/23/19 – GBBN and ADA Inclusion Consultant perform field verfication of all floors and spaces of entire buildings.
01/03/19 – Results of Mock-up Survey distributed to Design Team.
01/28/19 – GBBN/IPM/TEI meet with Facilities and JFS for Design Team update meeting. Revised Project Schedule presented to all attendees.
02/04/19 – GBBN holds in-house LEED review meeting. Contacts TEI via teleconference to discuss LEED Certification possibilities and shortcomings.
02/05/19 – GBBN relays findings of LEED Certification review by GBBN/TEI to Facilities.
02/07/19 – JFS sends clarification email on status of “supervised visits” for the Visitation Conference Rooms.
02/24/19 – GBBN receives ADA Inclusion Study from The Preview Group.
02/25/19 – GBBN and IPM meet with Facilities and JFS for Design Team update meeting. Meeting Mintues from last meeting distributed. IPM presented their recommendations for furnishings of the Peripheral spaces to JFS. Clarifications were made related to JFS’s provisions of task chairs. GBBN presents update on ADA Inclusion Study and LEED update for the revised project scope. IPM sends latest updated electronic drawing files to GBBN for Room and Door Numbering purposes.
03/08/19 – IPM updates owner on outlet/data wiring types and locations for new proposed spaces.
03/20/19 – ADA Inclusion Study language modifications as requested by Facilites is negotiated.
03/22/19 – GBBN transmits new floor plans with room numbering and finish/room schedules ot JFS for Safe Harbor Committee use.
03/26/19 – Progress meeting held with Owner. New plans, with Room and Door Numbering completed. Room Schedules with room areas completed, three sections per floor, for Claude Toulson’s use.
03/28/19 – IPM confirms wall verses core drill outlet locations for new Conference Rooms. Owner review meeting held with Facilities and JFS.
03/29/19 – IPM completes preliminary Recycling Specification for Owner review.
04/01/19 – GBBN copies Phasor As-Built outlet/data locations for TEI on thumbdrive.
04/02/19 – GBBN and IPM confirm to TEI that the new systems furniture will have task lighting, LED which will replace the existing fluorescent task lighting on the existing stations. Not all existing workstations have task lights. Facilities confirms any future workstation whips/outlets should be included in this Bid Package. Location of new and/or relocated thermostats has been decided by Facilities.
04/11/18 – GBBN conducts on site field verification of hte existing reflected ceiling conditions. Facilities decides to match the 6th floor light well soffits on the other floors with existing windows located insidethe new Offices. TEI confirms this decision will not adversely affect the lighting of the Offices.
04/12/19 – GBBN informs IPM and Facilities the Fourth Floor Plans do not show the existing small stair in the Core leading up to the East Side.
04/15/19 – TEI sends specifications section for Mechanical discipline. Meeting held with Owner to review project status.
04/22/19 – IPM sends updates on floor plan changes for JFS requested changes.
04/24/19 – TEI attends progress meeting with facilities, IPM and JFS. Reviewed MEP progress and left progress copies for all in attendance. TEI requested that IPM meeting to review every furniture power feed location.
05/06/19 – GBBN completes IPM Floor Plan and Furniture changes to the electronic drawing files. Copies of final plans sent to ThermalTech for their use as background drawings.
05/28/19 – Facilities confirms there will be no scope for the project related to “Safe Rooms”.
05/29/19 – IPM sends revisions to the Third Floor Plan to GBBN. ThermalTech drawings are mostly updated to last set of background drawings. HVAC, Electrical, and Plumbing should be read to review end of week.
06/13/19 – GBBN/IPM/TEI attend Design Progress Meeting.
06/26/19 – GBBN sends updated background electronic drawing files with updates from recent field verification.
07/01/19 – Design Team is scheduled to present the Owner with Review set of latest documents for Owner Review.
07/08/19 – GBBN submits Owner Review Set with Specifications, to Facilities, two sets, for review.
07/10/19 – GBBN issues additional specification sections to Facilities to be added to the Owner Review Set.
07/19/19 – GBBN, TEI and IPM coordinate discussions about project schedule and agree to the concept of eight weeks per phase. GBBN reports decision to Facilities.
07/23/19 – IPM requested that GBBN add addtional verbiage, in the specifications, requiring all General Trades Contractors, submit detailed line item quotes for the systems furniture. The Architects and Consultants will be allowed to review these quotes, to determine compliance with the specification,s before bids are awarded..
07/24/19 – Conversations with Facilities agreed that this additional information be added to the Supplementary INstructions to Bidders, Post Bis Instruction, 6.1.2.
08/26/19 – Facilities informs the design team that Project specific Federal Bidding language will be forthcoming by the end of the month or in early September for inclusion i nto the specifications. Facilities will also plan on delivering any review comments, from the earlier Owner Review Set, to the design team at the same time.
09/23/19 – The design team requests a meeting with Facilities to discuss added scope from JFS to determine what additional esitmating input is required for Project Request Estimate update.
09/24/19 – A meeting has been established for Friday 9/27/19 at 10:00 am.
10/18/19 – GBBN and TEI complete Opinion of Probable Costs updates for all disciplines. All discipline updates are sent to Facilities for their use. Facilities reports that review of the upddates have resulted in the project still being on track and the Design Team may proceed in wrapping up the Bidding Issuance Documents.
12/04/19 – GBBN contacts Purchasing Department for ITB information. ITB Number is #005-20.
12/09/19 – GBBN field verification of Fifth Floor Core offices to be demolished.
12/11/19 – Drawing Index updated. 160 sheets in set. Specification updated for all disciplines.
12/12/19 – ITB drawings and specifications to be distributed to Purchasing and ARC.
12/20/19 – Pre-Bid meeting held at Alms and Doepke Building. Meeting Minutes generated, along with Sign-In Sheet and issued by Addenda #1.
01/03/20 – Addenda #1 released to ARC and Purchasing Department. Specifications, drawing and Question revisions issued.
01/16/20 – Addenda #2 released to ARC and Purchasing Department. Question and Answer deadlines moved back one week. Specification and Questions addressed.
01/31/20 – Addenda #3 scheduled to be released to ARC and Purchasing Department. Bid Opening to be moved back one week to 2/13/20 at 11:00 am.
02/13/20 – Bid Opening held by Purchasing Department. Four bids received. Apparent low bidder is Graybach.
02/14/20 – GBBN conducts bid Interview telephone with Graybach following the bid opening. Telephone memo authored and transmitted to Facilities Department. Irregularities in responses summarized at bottom of memo, including apparent low bidder’s inability to provided required detailed breakdown within 24 hours as required by project manual and addenda. Follow up email sent to Graybach accordingly.
02/14/20 – GBBN receives telephone call from Graybach with additional Bid Rejection Interview questions. Facilities emails answers for transmittance to Graybach.
02/15/20 – Pursuant to the request by the Facilities Department, GBBN contacts Graybach, LLC to inform them of the ruling jointly by the Facilities Department and the Purchasing Department finding their apparent low bid to be non-responsive.
02/15/20 – Bid Interview conducted with Triton Services, Inc. at the request of Facilities Department. Telephone Memo authored and transmitted to Facilities. Triton Services delivers detailed breakdown used in Bid preparation to GBBN and Interior Project Management aa requested by Facilities.
03/02/20 – Pre-Award Meeting is held. Owner indicates the Recycling and WiFi Alternate Bids were to be accepted. Minutes to be distributed by GBBN.
03/03/20 – Triton Services confirms the manufacturer of the WiFi System will be as specified by ThermalTech.
03/15/20 – GBBN authors and distributes the Pre-Award Meeting Minutes to all attendees.
03/16/20 – GBBN solicits the successful bidders actual bid construction cost figures for the General and Mechanical disciplines for the permit application. The digital electronic submittal is completed and the CD burned for delivery to the City of Cincinnati.
03/17/20 – GBBN delivers and submits the hard copy and digital electronic permit submittal to the City of Cincinnati, for both Building and Mechanical Permits.
06/04/20 – BOCC rejects ITB-005-20.

A&D – Interior Finishes- Phase 2 and Phase 3 Read More »

A&D – System Furniture Mock-ups

05/16/18 – Design Team is notified that JFS has signed off on the latest IPM Floor Plan designs for all floors of Systems Furniture layouts. GBBN is asked to put together a preliminary schedule for the entire project including design.

05/24/18 – Design team and Facilities meets in Kick-off meeting to discuss scope of work. GBBN presents Preliminary Schedule.

05/30/18 – GBBN is notified by Facilities that JFS desires to have the mock-ups located in the Field Office Configuration. Exact locations to be determined. Standard configuration ‘B’ later chosen.

06/14/18 – SOSS is completed and submitted to Facilities. F058A is designated for the SOSS.

06/21/18 – SOSS approved and delivered to GBBN by Facilities.

07/05/18 – Decision was made to pull new workstation mock-ups from existing walls to allow staff to completely walk around the cubicles. No whips will be connected to the building system so no permitting is required.

07/06/18 – Meeting between Facilities and Design Team to finalize scope and deliverables.

07/11/18 – No Alternate Bids are required in the specifications.

07/13/18 – All three selected contractors have confirmed interest in the project. Documents are to be completed and issued.

07/16/18 – Facilities agrees to sixty (60) calendar days for receipt of Small Bid Packages from bidders.

07/19/18 – Documents are emailed to the three pre-selected bidders by Facilities.

07/26/18 – Pre-Bid Meeting to be held at Alms and Doepke Building Lobby.

08/03/18- GBBN issues Addenda #1 to bidders including the Pre-Bid Meeting Minutes.

08/10/18 – Bid Opening is held at CAB 5th Floor Purchasing Office. Three (3) bids are received.

08/11/18- GBBN interviews KFI by telephone and confirms complete understanding of scope of work. GBBN makes recommendation to Facilities to accept KFI as Lowest and Responsive Bidder.

08/13/18- GBBN makes revisions to AIA contract and delivers to Facilities.

08/28/18- Facilities mails copies of approved AIA contracts to KFI for their signature and Insurance requirement confirmations.

09/20/18 – Pre-Construction Meeting held at A&D Building. Facilities requests Background and Tax Exempt Package to be sent to KFI.

09/21/18 – Facilities sends Tax Exempt Package to KFI.

09/24/18 – Facilities sends Background and Tax Exempt Package to KFI.

10/16/18 – KFI sends Sales and Use Tax Construction Contract Exemption Certificate.

12/06/18 – GBBN authorized Application for Payment #1 and delivers to Facilities.

12/11/18 – GBBN authorized Application for Payment #2 and delivers to Facilities.

12/14/18 – KFI onsite for repalcement of existing damaged worksurface. Incorrect surface was delivered. Vendor authorizes order for correct damaged worksurface replacement.

1/18/19 – KFI onsite to replace damaged worksurface countertop. All work is successfully completed. Facilities agrees to closeout project.

A&D – System Furniture Mock-ups Read More »

CAB – 10th Floor IS & RM Relocation

06/15/18 – GBBN receives phone call to introduce the project and establish the date and time for the Kick-off Meeting. .
06/21/18 – GBBN meets with Facilities for the Kick-off Meeting. Project Request Estimate #1826 is to be revisited and updated to current bidding environment.
06/22/18 – GBBN scans all Kick-off meeting handouts and emails to TEI. A conference call is held with TEI to explain the scope.
06/22/18 – GBBN and TEI discuss scope of new project. TEI submits sub-consultant proposal to GBBN for this work.
06/25/18 – GBBN and TEI work on occupancy number for the training room people for the HVAC ventilation calculations for this work and scope. GBBN provides floor plan for use on this cost estimate.
06/26/18 – Owner sends final occupancy numbers to use for HVAC calculations on this project. Staff indicated by the owner is CAGIS- 16 and 4 interns, Community Development 4 staff and CLEAR vacant.
06/27/18 – SOSS approved and delivered to GBBN by Facilities.
07/26/18 – TTE sets up backgrounds and prepares job for design for Trades build-out.
10/11/18 – Meeting is held with GBBN, Facilities and Sheriff. Scope of project is discussed and GBBN requests amounts of existing shelving to be relocated be inventoried by the Sheriff IS Department.
10/12/18 – Amounts of existing shelving, to be relocated, was inventoried by the Sheriff IS Department, and forwarded to GBBN. Relocation Programming Study from 6/21/18 is to be used.
10/25/18 – Demo is complete. Abatement is underway. Carpet tiles are being ordered.
03/28/19 – County has completed abatement, put in new carpet tiles, moved IT racks over to new space. People are moved over to the CAB. It’s an open space for now.
09/26/19 – No project udpates; we are waiting on direction from County on next steps.
01/30/20 – This project has been re-scoped. This version can be archived.

CAB – 10th Floor IS & RM Relocation Read More »

GBBN – In4- Web Central Drawing Publishing

05/15/18 – Jack Randall and In4 meet with Facilities to discuss Web Central Drawing Publishing. In4 is requested to begin SOSS process.

05/15/18 – GBBN creates internal Opportunity and Network File Structure.

05/30/18 – In4 drafting SOSS to be submitted to Facilities by 06/01/18.

06/25/18 – SOSS is approved and delivered to GBBN by Facilities.

08/25/18 – In4 makes first push of publishing to the Web Central Website.

08/29/18 – In4 is completed with uploading to Web Central. Facilities is performing a quality check on drawings that have been uploaded.
08/28/19 – GBBN continues to update percentage of line weights for publishing to WebCentral. No other updates at this point from the Owner.
09/24/19 – IN4 indicated Purchase Order and Invoice reviews are underway to clarify remaining balance on Purchase Order for this project. No other feedback from Owner related to uploading process.

02/26/20 – Facilities is finalizing the Space migration/ARCHIBUS v24 project, hopefully by next month. The Facilities Department is in need of some tweaks to the published drawings in the UAT site:
https://hamiltonuat.asset-fm.com/archibus/
Steve Farashian is the new Facilities PM for the project and he will be going to contact GBBN regarding those tweaks.
03/26/20 – GBBN is working with ThermalTech to derive and estimating method for editing the website for As-Builts during an ongoing project.

GBBN – In4- Web Central Drawing Publishing Read More »

All Buildings – 2019 Project Request Estimating

04/30/18 – Facilities sends final listing of 2019 Project Request Estimates to GBBN.
05/02/18 – IPM sends SOSS input to GBBN.
05/03/18 – GBBN delivers SOSS to Facilities.
05/11/18 – GBBN receives SOSS and Purchase Order from Facilities.
05/14/18 – IPM begins User Group interviews on appropriate Estimate Requests.
05/30/18 – GBBN meets with JCC Building Manager and Sheriff’s Office to discuss Estimate #1953 on overhead door replacement.

06/12/18 – GBBN meets with the CAB Auto Title Department about Employee Restroom Estimate Request.

06/13/18 – GBBN meets with Rick Hoffman and Greg Brufh about the estimate request for the Courthouse Room #315.

06/18/18 – GBBN holds telephone conversation with Electric Power Doors, the original installer and manufacturer of the four-fold hydraulic doors.

06/19/18 – GBBN holds telephone conversation with Overhead Doors of Cincinnati, the current maintenance contract holder.

06/20/18 – GBBN requests information and pricing from Pinnacle Engineering related to ACM abatement scope of work.

06/25/18 – GBBN receives Security Glazing input from Tony Matre and Geiger Construction Products. Sheriff confirms overhead and four-fold hydraulic doors are not required to be ballistic rated.
06/26/18 – TEI has finished fieldwork on all cost estimate. Vendor quotes have been received where needed and coordination with partners has been an ongoing process. Most estimates are entered and ready for final review by TTC and MB. we are shooting to be complete by the end of June on this project.

06/26/18 – GBBN receives estimating input from the four-fold hydraulic door vendor.

07/06/18 – GBBN completes all estimating and reports the same to Facilities.

All Buildings – 2019 Project Request Estimating Read More »

All Buildings- 2019 Project Request Estimating- Binder Assembly

07/16/18 – Facilities emails listing of 318 Project Request Estimates. Request is made for SOSS for the Binder Assembly

07/24/18 – Facilities confirms final count of Estimates, number of Binders and delivery date of binders to Facilities.

07/25/18 – GBBN submits SOSS to Facilities.

08/02/18 – GBBN receives approved SOSS from Facilities.

10/22/18 – GBBN is completed with all Project Request Estimating printing.
01/29/19 – GBBN recieves Facilities final binder Summary Files for printing.
02/08/19 – GBBN transfers empty binders from Courthouse to GBBN.
02/14/19 – GBBN bundles entire printing files, on CD, along with empty binders, and past years’ binders for pick-up by ARC Reprographics.

All Buildings- 2019 Project Request Estimating- Binder Assembly Read More »

CH – Law Library Re-Bid

04/16/18 – GBBN, Facilities, TEI and Law Librarian meet to discuss strategy for project that came in over-budget. Proposal was made to wait until June of 2018 to observe it construction activities and pricing stabilizes.
04/17/18 – Meeting held with Facilities, Law Library, GBBN and TEI. Decision to reject bids. BOE Board to vote 04/18/18, and decide to proceed or cancel project.
04/18/18 – Board votes to proceed with Facilities recommendation to proceed with generating re-bid construction documents to be reviewed by Board in June. Original reduced scope to be represented in documents to meet original estimating.
05/08/18 – GBBN and TEI meet with Bob Martin, City of Cincinnati Head Plans Examiner to discuss needs for fire dampers at existing Penthouse Floor Structure.
05/11/18 – GBBN meets with Facilities to clarify resubmittal scope of work.
05/14/18 – GBBN sends revised Background Drawing to TEI.
05/16/18 – TEI and GBBN have conference call to kickoff rebid phase of the project. Revised design documents due in June. We don’t’ see a lot of issues with the new plan as it seems like a good plan that we can make work. WE will update all Alternates to match in number and scope to GBBN new dictates.
05/21/18 – GBBN clarifies flooring scope with Facilities.
06/15/18 – Facilities notifies GBBN that Board for the Law Library has voted to proceed with redistribution of bid documents based on Facilities recommendations for scope changes to reflect current bidding environment.
06/25/18 – Coty has updated the HVAC drawings for the rebid project. TTC to review on 6/26 and coordinate new scope and Alternates with GBBN prior to issuance. HVAC, Fire and Plumbing should be complete by end of June for review.
06/28/18 – Owner Review Meeting held with Facilities, GBBN and Law Librarian. Revised drawings (Architectural/MEP) and Front End Specifications are reviewed.
07/26/18 – TTE kicked off rebid scope and will have drawings and specifications updated for Rebid per the schedule 8/13/18.
08/21/18 – GBBN receives final ITB information from Purchasing.
08/22/18 – GBBN sends final documents to Purchasing for Posting.08/23/18- -GBBN issues final documents to ARC for review and comment.
08/24/18 – ARC suggests minor revisions which are completed by GBBN.
08/27/18 – Purchasing Issues final bid package.
08/29/18 – Law Library Re-Bid documents are on the street. The prebid meeting is scheduled for 9/11/18 at 1:30pm. Purchasing makes request to GBBN, for issuance with Addenda #1, the Bid Tabulation and sole bid received from KFI, from the earlier bid process t hat was rejected due to exceeding of the Published Estimate.
09/11/18 – Pre-Bid Meeting is held at the Law Library Boardroom. A tour of the areas to be renovated is held after the meeting.
09/18/18- Additional Questions are received by GBBN from Purchasing after the last day for Questions has past. Answers included in Addenda #1
09/25/18 – GBBN issues Addenda #1 to Purchasing and ARC.
09/26/18 – Triton Services requests additional answers with direct email to GBBN. Answers/clarifications were sent.
10/03/18 – Bids are received. Triton Services Inc (TSI) is apparent low bidder. GBBN calls and conducts telephone bid analysis interview.
10/04/18 – GBBN authors Meeting Minutes from interview and sends to Facilities with recommendation to accept TSI.
10/11/18 – Law Library Board meets and decides to accept Bas Bid only from Low Responsive Bidder. GBBN authors AIA Contract and sends to Facilities for review.
10/12/18 – Facilities requests two small changes. GBBN responds and completes contract and delivers to Facilities.
11/29/18 – Contract is approved and we will be looking to have a kickoff meeting shortly.
01/22/19 – GBBN submits Permit Response Letter to City of Cincinnati.
01/25/19 – Submittals approved are now Acoustic Ceilings, Ladders, Glass, Plaster, Gypsum Board, Logo, Metal Studs, Resilient Flooring, Roller Shades.
01/17/19 – Triton delivers mock-up sample of Glass Door film.
01/29/19 – GBBN sends submittal response to Triton concerning wood door/custom cabinetry wood species and finish selections.
01/31/19 – In partner meeting we decided to remove ladder access to the mechanical spaces and take a credit for that work. County is meeting new Triton project manager, Tony, next Monday.
02/20/19 – Pre-Construction Meeting held. Agenda produced by GBBN and meeting minutes completed.
02/26/19 – TEI and GBBN attend pre-construction meeting with Triton and Spade Electric on 02/20/19. Triton scheduled to mobilize to project on 03/11/19. Door finish samples were presented by Triton to GBBN. GBBN meets with Facilities later to make selection of approved finish.
02/27/19 – GBBN sends preliminary meeting minutes to Facilities and TEI for reveiw and comment. Facilities reponses iwth minor corrections.
02/27/19 – Facilities and Triton confirm next mobilization meeting date of 03/07/19 at 1:00 pm.
03/28/19 – Add wall to Conf Room to hide the water pipe and vacuum pipe in the Large Conference Room. The plumbing line will be rerouted as high as possible in the space. Paint to match new ceiling color. GBBN approves and transmits approved Custom Millwork submittals to Triton.
03/29/19 – GBBN sends approved Millwork Submittals to Triton. Approved Door, Frame and Hardware submittals also returned to Triton
04/01/19 – GBBN approves color for Pendant Light Fixture.
04/05/19 – GBBN finalizes the wood stain sample submittal for millwork and doors. GBBN visits site to document existing MEP lines uncovered by Demolition.
04/08/19 – Revised Lighting Fixture Schedule submitted by Triton to GBBN. Transmission of same to TEI for review. TEI confirms revised schedule contains all required revisions and modifications.
04/09/19 – Pencil copy of Application for Payument #02 submitted to GBBN. GBBN authors Construction Change Directive #1.
04/10/19 – Construction Mmeeting #01 is held.
04/11/19 – RFI on door hardware and finishes submitted by GBBN.
04/15/19 – Pinnacle Engineering requests information on Abatement for this project. A new Abatement Contractor is now on the project and has subcontracted with Pinnacle for Air Sampling.
04/18/19 – TEI approves Fire Suppression submittals. GBBN approves ans delivers Application for Payment #2 for Triton.
05/01/19 – Construction Meeting #04 held on site. Walk through of site conducted after meeting. GBBN issues sketch on steel stud framing dimensions for monitor enclosures in three new Conference Roooms.
05/06/19 – ThermalTech and GBBN answer Electrical RFI’s from Bill Spade Electrical.
05/15/19 – Construction Meeting #05 held on site. Walk through of site conducted after meeting.
05/17/19 – Glass Film sample arrived from McAndrews Glass, via Triton. GBBN visits Courthouse and receives approval for the Solar Tint version without the patterned background. Triton is notified of approval.
05/27/19 – Application for Payment #3 Pencil Copy approved for processing.
05/29/19 – Facilities reports rough-in inspection failed due to lack of Permit Drawings on site and lack of proof for the Fire Alarm Permit for the IBI Inspector.
05/29/19 – Construction Meeting #06 held on site. Walk through of site conducted after meeting.
06/12/19 – Construction Meeting #06 held on site. Walk through of site conducted after meeting.
06/20/19 – GBBN receives pencil copy of Application for Payment #4.
06/26/19 – Construction Meeting #06 held on site. Walk through of site conducted after meeting. Sample of countertop material is delivered by TSI to GBBN.
07/03/19 – GBBN performs an inspecion of the Lighting Luminaires at the Courthouse Archive Rooom for the purpose of signing and approving the latest Application for Payment.
07/05/19 – GBBN approves and hand delivers the Appplication for Payment to Facilities.
07/10/19 – GBBN attends the bi-weekly Progress Meeting. A walk-through of the site was held after the meeting.
07/15/19 – GBBN issues Construction Change Directive #002 to Triton Services.
07/16/19 – GBBN issues Construction Change Directive #2 to Triton Services via mail.
07/18/19 – GBBN issues corrected sketches for Construction Change Directive #2, with corrected outlet relocation directions, to Triton Services via email.
07/24/19 – Construction Meeting held at the Courthouse, Room #608.
07/24/19 – There was discussion at the meeting that IBI might not accept the cleaned sconces due to the old sconces not being UL listed. The scope is to re-use them according to the approved plans, and if inspector takes issue during inspections, the team will address at that time. Triton receives pricing from DK for FA work on this project (since DK is installing FA throughout the whole building) and has pulled FA scope from Bill Spade Electric and authorized DK to do the FA work.
08/07/19 – 07/24/19 – Construction Meeting held at the Courthouse, Room #608.
08/13/19 – GBBN and TEI review and approve Pencil Copy nof Application for Payment #005. TSI is informed to mail three original copies to GBBN.
08/20/19 – GBBN hand delivers Application for Payment #005 to Facilities.
08/21/19 – Construction Meeting held at the Courthouse, Room #608. GBBN sends detail for wall base revised to conceal new Wiremold raceway to TSI.
08/21/19 – TEI sends approval forr Altnerate Work SOSS to GBBN to initiate new work to commence.
08/22/19 – GBBN receives CCD #001/#002 pricing from TSI. Owner approves pricing with GBBN’s recommendations. GBBN authors Change Order #001 to include CCD #001/#002 and the Alternate Scopes of Work. Change Order is mailed to TSI for signature.
08/26/19 – GBBN recieves telephone call, and subsequent follow up email, from City of Cincinnati Plans Examiner approving additional Alternate Scope of Work to be issued as an “Engineering Change” to the original Building Permit.
08/28/19 – TTE reviewed and approved payapp for work completed and sent an list of items for Triton to work on for the plumbing and HVAC work on this project in regards to piping materials, ductwork connections and control valves for the VAV units. Brent is checking on these items for us but the payapp was approved for the submitted percentages.
08/30/19 – Application for Payment #6 approved and hand delivered to Facilities.
09/10/19 – GBBN and TEI submit Engineering Change to Permit #2018P09968. Both hard copy and digital submission are included.
09/11/19 – GBBN meets Triton onsite to discuss finish details including base and new wall cap at plumving extension.
09/13/19 – GBBN attends Progress Meeting with TEI. A site visit was held after the meeting to discuss issues that arose in the meeting.
09/16/19 – GBBN meets Triton Forement to discuss additional finish details including base anchorage to plaster and concrete walls.
09/24/19 – ThermalTech performed punchlist on mechanical, electrical, plumbing and fire for the project.
09/25/19 – City said to finish door handle, fin coil and clean up the area, send them a picture and we can get our TCO. 98% complete for occupancy to use the space. IBI 98% done.
10/09/19 – Application for Payment #7 approved and hand delivered to Facilities.
10/21/19 – GBBN completes and issues General Construction Punch List and includes Law Librarian comemnts in list.
10/23/19 – GBBN contacts City of Cincinnati Plans Exmaminer concerning lack of approval or notification on Engineering Change submission. GBBN told verbally to correct Code Summary visuals and Ventilation Schedule.
10/24/19 – GBBN answers RFI on Alternate Scope doors, frames and hardware questions to TSI.
10/25/19 – GBBN and TEI submit required corrects to Engineering Change to City of Cincinnati Buildings and Inspections.
10/28/19 – GBBN inquiries about status of Engineering Change approval. GBBN notified Plans Examiner had been on vacation all of last week and no progress was made by the City.
10/28/19 – TSI copies Owner and Design Team on Phase 2 Suppression Permit. TTC stops in the Courthouse and still does not see where the additional sprinkler is required base don the wall locations.
10/29/19 – Triton asks about existing diffuser on face of wall. Originally TEI says to remove it, the existing diffuser have enough air for Ventilation but in a subsequent email, Bert and Terry decide to extend the diffuser into the room.
10/30/19 – GBBN answers additioanl RFI on Alternate Scope doors, frames and hardware questions to TSI.
10/31/19 – Discussed project scope at meeting and upcoming change orders with Triton for windows from original project, LL will move computer workstations, Triton will move into the computer lab next and we are waiting on a project schedule for the new offices. TTC will reissue the RFI for the HVAC duct and call the sprinkler contractor.
11/13/19 – GBBN meets with Triton at the site to clarify wall paint colors.
11/14/19 – Application for Payment #8 approved and hand delivered to Facilities.
11/30/19 – GBBN walks site to verify Application for Payment #09 from Triton.
12/06/19 – GBBN performs Back Punch List walk through with Facilities.
12/09/19 – TTC asked Triton about Controls finalizing the project and they are waiting on a switch to be installed by the County. County emailed they are working on getting this final piece installed as soon as they can.
12/13/19 – Application for Payment #9 approved and hand delivered to Facilities.
01/20/20 – Back Punch List sent to Contractor.
01/29/20 – Certified Payroll forms hand delivered to Facilities.
03/25/20 – Facilities Department indicates to the Design Team and Owner that the City of Cincinnati has signed off on the Final Inspection.
03/26/20 – GBBN sends an email, with the standard closeout document samples attached, to Trition Services, displaying those normally required for final Closeout of the project.
06/25/20 – Punchlist still needed in the alternate area of the job. TEI and GBBN to punch the Alternate Work.
09/24/20 – EC removed switch from job for new door. Emergency switch wasn’t available for night lights. County said that they would accept night lights. We can forego the receptacle switch. They also need to fix the continuous hinge on the new security door, Triton replaced with heavy duty bolts. Stay of Ohio room Trilogy lock being fixed under warranty. New microphone in boardroom was working but the front one stopped working. Thing being addressed now too; new controllers being replaced under service vendor. Triton to fix plaster in CR #1, VAV leaking and now fixed. One ceiling tile needs to be replaced.
10/28/20 – Microphone needs repaired prior to closeout.
01/28/21 – Microphone work is complete. Final payapps are getting signed. Law Library ordered some additional furniture, keep the project open for now.
02/25/21 – Construction is closed, just waiting on some furniture to arrive. All data and cable mgmt is ready, should be here in March.
03/25/21 – Furniture delivered, hold open one more month.

CH – Law Library Re-Bid Read More »

CAB – Chiller Rebid Project

03/05/18 – Terry and Colin onsite doing additional fieldwork for redesign. We are investigating new piping connections and existing pipe routes for new configuration. The good news is that some of the piping we thought had to be extended and modified already exist for AHU-1 & 2. The piping changes required on the tenth floor and roof are possible albeit a little tough to do.
03/24/18 – TEI submitted revised SOSS for new design and bid cost for TEI and THP. LCC equation is ready for bidding for air cooled chillers. Revised design is about 50% complete for mechanical changes for the new design.
04/19/18 – ThermalTech release LCC bid documents to manufacturers for rebidding this project for Air Cooled chillers only. Trane, JCI, Carrier and Daikin all invited to bid. The nominal tonnage of the chillers will be 200 tons. Bids and performance numbers are due to ThermalTech April 30 at noon.
04/25/18 – Addendum #1 release today with updated calculations and some other updates to the bidding worksheet.
05/17/18 – The LCC results were published to the bidders, Facilities and Purchasing. Carrier High Efficiency Option #2 was the best LCC chiller for standard refrigerant, model 30XV-2006M40–4-2 using R-134a. And the Next Generation Chiller best LCC went to the York JCI chiller using R-513A model number YVAA0213.
05/23/18 – Terry and Colin perform fieldwork to wrap up new piping changes for new chiller design. We go everything we needed and marked up all the piping on the 10th floor for future changes. We are confident we can do all the piping changes required for convert the building to Air-Cooled Chillers.
05/25/18 – Mechanical drawings are ready for TTC review. Final chiller equipment has been sent to THP for structural design and upon initial review, all seems to be in order. Good news on the piping front, we can find a decent path from the penthouse to the new chillers and route the piping about 41″ above the room and miss the Liebert unit piping rack, found a space to create a walk over the new piping for easy access and can make a new door in the penthouse using existing louver material.
06/26/18 – TTC has marked up final mechanical drawings for editing. Electrical drawings are being updated now for bidding. TTC will get new ITB this week and put the project out for bidding first week of July. I need to coordinate prebid with Bert and John Gilbert.
07/26/18 – Rebid project is on the street. Prebid meeting schedule for August 2 and Bid Opening scheduled for August 23.
08/29/18 – Bid were opened on schedule. Triton Services was the apparent low bidder on the project. TTE held a post bid interview with the bidder and sub-contractors on Tuesday at our offices and reviewed the project is detail. Most everything was covered and Triton appears to understand the project well good sub-contractors for this project. They would like to get submittals started ASAP on this project.
09/24/18 – Contract appears to be approved and on its way to Triton for signature. Duke released some data on next year’s rebate program which we should be inline for with this chiller purchase. THP review the structural proposed questions and returned satisfactory answer to keep the job moving forward.
10/23/18 – PO in for approval and then TEI will schedule the Pre-Const Mtg with Triton.
11/27/18 – Pre Construction meeting was held onsite with Triton Services. Permit response came back and we are working with Triton to get the four responses answered for this job. Terracon must be engaged as a special inspector on the job, and we provided some additional permitting material to take to the city, plus the city will require a General Permit for the structure.
12/31/18 – Two construction meetings so far. Project is underway. Submittals are moving along and being approved. Background checks are almost completed. Triton is mobilizing to site. Crane lift being scheduled for early January. Chiller delivery is February and we are working on getting that moved up. Steel and piping are being fabricated now and that will be the first lift up t the roof.
01/10/19 – Triton directed to get CHLR-3 online first for hot days. Control meeting was conducted with TEI and Emcor on Monday for coordinating control sequences on new chillers. TEI issued updated sequences to Owner, Triton and Emcor for use on this project from this meeting.
01/21/19 – Glenwood found that a 1000A breaker with the correct lug alignment was not available from GE at this time. They submitted a change order for the work. TEI contacted CE power to find a direct replacement for the breaker that will hopefully be less expensive than the submitted change order.
01/22/19 – Control submittals have been received and return immediately. TEI and Emcor worked through specific control questions and TEI issued an updated sketches for 10th floor piping that has to be coordinate with Triton during installation. We also approved a ball valve in the bypass even thought that technically won’t be used until the three way valves are replaced later.
01/31/19 – THP update: Structural steel shop drawings reviewed and returned.
01/29/18 – Const Mtg #4 held. Project is moving along well. Glenwood is setting the transformers today. Piping is connected in 10th floor and along roof to structural steel location. Basement piping is demolished. The 5″ bypass will be started in the mechanical shaft and then routed over the ceilings to the mechanical room. ThermalTech will use Terracon fro the special inspections on the structural platform for this project.
02/17/19 – Steel was erected by 2/17, inspected, fixed and reinspected. Chillers were set on frame on 2/19 without incident. Everything looks good.
02/26/19 – Glenwood pushed to power outage to the backup date of 3/9/19 due to ship date of the circuit breaker being 02/28/19, and Glenwood was not confident that the breaker would be on site in time for the original outage date. TEI and Glenwood revised drawings and submitted to IBI engineering change for the revised plan. TEI to schedule a meeting with Triton and Glenwood for pre-outage conference the week of 3/4/19. Const Mtg #6 was held and Triton reported almost all their work is complete. They are waiting on Glenwood and Emcor to finish up the job. the glycol feeder and chemical test company should be on site within the next week for their work.
03/01/19 – Triton reports that glycol feeder is here and being installed. Emcor workers have their background checks in place and will start controls. Glenwood reports after Nester checked in that the breaker should have arrived yesterday and today for sure.
03/11/19 – TEI attended Admin Chiller Startup with County.
03./12/19 – TEI attended Admin Chiller startup for second day with County. Items brought up during startup are weatherguards, heating circuit, convenience outlet, trouble light, local disconnects, additional support on chiller base, additional glycol and differential pressure reader. ThermalTech to start working on these items for resolution. TEI can start the punchlist on the job as well.
03/26/19 – Electrical transformer and breakers installed and turned on. The electrical final did not pass. TE and Triton/Glenwood working to resolve issues on project to pass inspections.
03/27/19 – TEI held conference call with Glenwood to discuss change orders. TEI went to site and measure disconnect locations and redoing the work to make it easier for contractor and Owner.
03/28/19 – Barth, Glenwood and Nester met at the building to discuss final location of the new 600A disconnects this morning. Chiller #1 disconnect will be mounted on the West Side of chiller. on Chiller #2 we are basically doing the same thing but we need a junction box and extend the feeders in seal tight.
04/22/19 – TEI releases electrical and mechanical punchlist for final wrap up of project. TEI reviews and gets approved balance reports from vendors and factory for this project.
04/24/19 – Change orders approved for the power items that IBI required. TEI performs and issues electrical punchlist. Glenwood on site week of 4/22 making all corrections and CO work with the exception of ground detectors, which are on order but not received to date. Upon receipt, ground detectors and final IBI will occur. Triton on site doing punchlist items and TEI meets them for new pipe label coordination. TEI asked for Training to be complete ASAP.
04/25/19 – Send Bert change order prices for CT and Chlr. Duke rebate check received and credited to the account, however this money probably can’t be used for additional change order work.
05/27/19 – Glenwood wrapping up change order work and final permitting of electric work for the project. Weather panels are coming very soon. There is a breaker setting we have to coordinate with Glenwood and then we should be able to get our final inspections in the next week or too.
06/27/19 – All construction work in complete. Glenwood set to call for final inspection next week to get final permit closeout for this project. TTC and Emcor meeting on July 9 to do some functional testing of the chillers. Triton approved via change order to remove abandoned and old piping on the project site prior to closeout.
07/25/19 – Triton finalizing all permits. IBI is approved. Triton also performing alternate work for the owner this week. Project ready for closeout.
08/28/19 – Project is complete and final inspections were approved on 8/12. However the owner called with glycol feeder issue with the Pulsafeeder unit. We met last Friday and review the installation with the salesman. They requested we remove all the control interface to the unit and put it back to factory conditions or else they consider the unit “tampered with”. We did everything they asked and then spent another two hours trying to make the unit work with limited success. We contacted the vendor and asked him to bring in the manufacturer to assist. To me this is all warranty work for Triton on this job.
09/20/19 – TTE met Triton on site and verify an AAV on the CHW glycol feed does seem to fix the issue. Triton will install and pipe the overflow back to the glycol tank.
09/24/19 – TTE verified the work is done. This project is ready to Archive.
01/27/20 – Bert called for final closeout confirmation today. TTC checked and all the paperwork and O&M’s are in. However the final payapp is not process. it was found that #10 and #11, balance of contract must be submitted. TTC confirmed with Triton on needed closeout documents.

CAB – Chiller Rebid Project Read More »

JC – State Grant Budget and Schedule Analysis

04/20/18 – GBBN is contacted by Facilities to convert email with estimated General Services expenses into a formal SOSS. Facilities dictates that a formal SOSS be authored for the update of the Opinion of Probable Costs and Gantt Chart for the entire four pod configuration.
04/23/18 – GBBN authors and delivers SOSS to Facilities.
04/24/18 – Facilities, GBBN, TEI and Sheriff meet to discuss displaced offices and program spaces. Design decisions were rendered concerning pod designated uses and design concepts.
04/30/18 – Facilities creates new Archibus Project Request Estimates #1966 and #1967 for design team’s use.
05/08/18 – Facilities forwards approved SOSS and Purchase Order to GBBN.
05/14/18 – GBBN sends new typical pod layout (Kenton County style) to TEI for estimating.
05/15/18 – GBBN confirms existing Corridor items, Door Ballistic Ratings, OB/GYN Room requirements with Sheriff’s Office.
05/17/18 – GBBN confirms existing slab floor coating with Sheriff and Facilities.
05/17/18 – TEI receive security grade plumbing fixture pricing from vendor.
05/18/18- GBBN sends revised Pod layout with improved sightlines and Sally Port to Administration, Sheriff and Facilities. GBBN sends status report to Administration.
05/22/18 – /GBBN coordinates interior door estimating approach with Facilities for ballistic ratings.
05/29/18 – GBBN forwards completed Archibus Project Requests #1966 and #1967 along with associated Gantt Charts to Administration and Facilities.04/21/18 – GBBN receives input for SOSS from TEI and THP.
06/27/18 – GBBN prints off both Gantt Chart Schedules and both Project Requests (Phased and Progressive) for the meeting 6/28/18.

JC – State Grant Budget and Schedule Analysis Read More »

CH – Room #205 Renovation

04/02/18 – Facilities notifies GBBN that Municipal Courts has approved the project, estimated with Project Request #1949, for submission of an SOSS, to be performed by Trades. SOSS to cover the scope of the Project Request #1949. GBBN solicits input from TEI. Facilities confirms Trades to handle project including systems furniture scope.
04/03/18 – TEI sends input for SOSS to GBBN.
04/04/18 – SOSS issued to Facilities.
05/29/18 – TTC and SJ discussed starting this project after the JC Recovery is finished. The SOSS is in place for our firms. GBBN will develop the floor plan and TEI will star the load calcs and preliminary work right after the floor plans are ready.
04/03/18 – TEI sends SOSS input to GBBN.
04/03/18 – GBBN submits SOSS to Facilities.
05/10/18 – GBBN receives approved SOSS and Purchase Order from Facilities.
06/26/18 – TEI and GBBN discussed schedule for this project to be completed the first couple of weeks of July 2018. TTC, Coty and Barth scheduled to work on this project.
07/25/18 – GBBN has construction document set started. GBBN questions were answered from Facilities to keep documents moving ahead. TTE checking load and ventilation calcs.
08/20/18 – TEI confirms that no fire protection modifications are required from the existing layout and configuration.
08/28/18 – Facilities requests three minor revisions to Owner Review set of documents after review by Municipal Court Administrator.
08/29/18 – TEI and GBBN have submitted final drawings for Owner Review. Facilities confirms only one small revision, of adding data wall mounted outlet for future printer/copier, is required before issuance for Permit. GBBN and TEI agreed upon 09/04/18- Issuance for Permit date in issue block.
09/05/18 – GBBN and TEI submit Applications for Building and Mechanical Permits to the City of Cincinnati.
09/26/18 – TEI receives code comments and re-submits drawings to IBI.
10/03/18 – GBBN receives letter from the City of Cincinnati requesting additional information for permitting. This information is far in excess of any required by the City for comparable projects since GBBN has been doing Facilities projects.
10/17/18 – GBBN requests proposal from The Preview Group to provide part of the information requested by the City mentioned above.
12/21/18 – GBBN submits City of Cincinnati Permit Response Letter.
01/07/19 – GBBN pays for and obtains Building Permit from City of Cincinnati. Facilities agrees reimbursable expense to be billed to General Services SOSS.
01/29/19 – ThermalTech obtained the permit and delivered to John Nester for trades to do the work.
02/26/19 – Work is in progress with the county trades. As of 2/15/19, there was no electrical roughed in to date. Wall framing was nearing completion. TEI tells John Nester to let us know when the trades are ready for a rough in inspection with IBI and TEI will schedule the inspection.
03/08/19 – GBBN performs site visit with Facilites. Inspector questioned location of two sprinkler heads. TEI responds to question with data input in email to Facilities.
03/26/19 – Work continues to progress in area. Electrical rough in inspection was passed and work continues in space. Trades (JN) to notify TEI when to call for final on the project.
04/24/19 – HamCo to notify TEI when to call IBI for final on the project.
05/29/19 – TEI was notified to contact IBI for final electrical inspection. IBI scheduled for final inspection on 5/31.
06/26/19 – Project final IBI approval received. on 06/25/19, while on site for a different project, the rooms were being moved into the space.
06/27/19 – Project is complete. Ready to archive. Partners can send in CAFM updates.

CH – Room #205 Renovation Read More »

CAB – 10th Floor Community Development Renovations

03/26/18 – GBBN contacted by Facilities to plan Kick-off Meeting with Community Development.
03/29/18 – Kick-off Meeting date and time decided.
03/30/18 – Kick-off Meeting held at Room #1022, 10th Floor, of CAB. Discussions held related to the requested scope.
04/03/18 – Facilities sends marked-up plan showing clarified scope for SOSS creation. Photograph of front desk sent later by Facilities to GBBN.
04/06/18 – Facilities clarifies card reader access system is desired by Community Development.
04/09/18 – TEI sends SOSS input to GBBN for SOSS.

CAB – 10th Floor Community Development Renovations Read More »

SPHQ – RTU-5 Replacement

11/14/16 – Prebid meeting was held on site.

11/15/16 – TTC investigate using the existing architectural and mechanical plans to reword the ductwork on RTU-5 so that the unit will keep its ductwork up on the second floor and penetrate the side wall on the second floor and intercept the ductwork where it comes up through the floor. TTC spoke to Kevin Maue, Greg Smorey and Tom Speer about the original build today.

11/16/16 – Addendum #1 was sent out this morning for bidding answering prebid questions.

11/18/16 – Addendum #2 was sent out.

11/22/16 – Addendum #3 was sent out.

12/07/16 – Contracts sent to Tony for Debra Kuempel. Waiting on approval and kickoff meeting.

01/13/17 – Discussed equipment vendor selection with Feldkamp and JCI. Carrier was submitted but they are probably going to purchase JCI as an equal vendor for this project. Spoke to Jackson and Tony about this.

02/02/17 – Precon schedule for 2/14.

02/17/17 – Met contractor on site to review possible new placement and routing for ductwork on this job. ThermalTech to draw up new location and routing and get THP approval.

02/27/17 – Revised downflow design completed and sent to contractor for pricing on Thursday, revised again on Friday and emailed, revised again on Monday and sent to contractor.

02/28/17 – Final design and schedules revised again and sent to Feldkamp and Owner. Submittals rejected twice this week but third submittal was sent back Furnish as Corrected. Also told Tony today that the redesign used $2040 of the const budget and leaves about $500 for Const Services.

03/09/17 – Unit is ordered, a revised set of submittals was sent to Feldkamp this week. A controls meeting is scheduled for 3/22 at ThermalTech with Alpha and Habegger.

03/15/17 – TEI sent PO provided by Tony to DK for processing and requested project schedule from Feldkamp for this job.

03/21/17 – THP – THP and TTE had a conference call to discuss scope and fee. TTE to review fees with County.03/21/17 – Controls meeting rescheduled until 3/28 at 9am at TEI.

04/03/17 – TTE requested a formal proposal.04/21/17 – Control submittals have arrived. ThermalTech to review and return ASAP.

04/11/17 – THP provide a proposal for review.04/25/17 – Updated Drawings were given to Jackson and Feldkamp was on site locating the curb on the roof per the new structural drawings. Unit schedule to arrive in May for installation.

04/13/17 – THP proposal approved.

04/25/17 – THP analyzed AHU loading and proposed shifted the unit. Unit location was shifted. THP provided roof top support channel detail.

05/19/17 – TTC stopped by for field inspection. Curb looks good, ductwork looks good, fire dampers look good. DK trying to locate electric for new power to pull new feeders. Pictures from roof support work appeared to be acceptable to ThermalTech and THP.

06/27/17 – Project is complete and we are punchlisting the work.

07/19/17 – Punchlist was distributed today to both Debra Kuempel and Feldkamp Enterprises.

08/03/17 – Met Feldkamp on site to get quote for new boiler options using allowance money leftover on this job.

08/17/17 – Met Jackson onsite today and collected more information for the Alpha quote. Talked to DK and they are coming out to change the restrictor plate on SVH-204 soon, they will also be giving Alpha the K values to program into the VAV boxes on the FE system so we can see the correct CFM’s. I also emailed Alpha a full email explaining that I wanted to simplify and reduce their scope and price on this job and that all of the controls we need are already installed and on the graphics.

08/30/17 -All prices are in for the heating boiler and we can award this work to Feldkamp as part of this job. Still working on a cost from Alpha.

09/08/17 – When the electrical inspector (Ken Spille) came to the field for the final, he had the wrong drawings for the work with him. DK contacted TEI (Mike Barth) and we delivered another copy of the correct drawings to IBI. Ken told DK in the field that once those drawings were dropped off and processed at IBI, that he would get the final for the permit. IBI is now telling DK that they have to call and schedule a final inspection for the project (although they have already had a final), and that IBI cannot close out the project. We told DK that we need to get this closed out, and since the inspector is not recalling his field statements, please work this out and get the final completed. DK working with IBI to resolve.

09/25/17 – Feldkamp and DK were both on site last week installing the new hot water boiler form Lochinvar. We went with the 155,000 btuh boiler for this installation in the fire tube design which is a new offering from Lochinvar. The piping is connected, the exp tank is relocated, the gas piping is connected and the venting is hooked. Feldkamp confirmed the venting is ready and clear of caps and ready to use. This week Feldkamp is to startup the boiler and Alpha controls or Feldkamp will complete the installation of the systems. TTC stopped by last Thursday but not contractors were on site, TTC may stop by again to review the work if he can around his meetings and vacation.

10/24/17 – Boiler is up and running. The controls enables and disables the boiler based on outdoor air temperature. The owner has the boiler set to 140F and can adjust as needed seasonally. TTC sent out the allowance usage and change order for this project and asked Feldkamp to close it all out. The roofer came out and applied another patch to the job around the unit to quell a roof leak and hopefully that works. Everything seems to be up and running well.

10/25/17 – Allowance usage came back from Feldkamp and was forwarded to Tony Matre for signature. Boiler went out on alarm this morning. Feldkamp dispatched to investigate.

11/28/17 – In the past month we have had Feldkamp, Alpha and Corken all on site working on the boiler system. The boiler is running well and Feldkamp has upgraded the gas supply to the boiler, added the combustion tee for tuning up the boiler plant and added the neutralizer to the boiler drain. Alpha has reprogrammed the hot water pump to run through the system at all times and we are awaiting the controls upgrade to supply the setpoint to the boiler. Then Corken can come in and provide a full startup on the boiler.
03/30/18 – After a lot of work to get revised O&M’s for this job from the contractor that TTC felt were good enough for the owner, the final PDF was downloaded and printed by ThermalTech and three O&M’s were created for Tony Matre. I am not sure why TEI is making O&M’s for the contractors nowadays but in an effort to bring the project to completion, they were made and UPS ground to Facilities. The only item we know is open is the CAFM updates for these drawings.

SPHQ – RTU-5 Replacement Read More »

CH – Critical Façade Repairs (F103)

12/28/17 – THP publish SOSS to Hamilton County as requested.
03/16/18 – Hamilton County approved SOSS.
04/26/18 – THP provided owner review documents to the County.
05/24/18 – Revised Owner review documents sent to County.
05/25/18 – County provided comments.
05/29/18 – Documents issued to purchasing for review.
05/30/18 – Purchasing provided comments to the review documents. Project issued ITB 044-18.
06/1/18 – Issued bid documents to County and ARC for publication.
06/5/18 – Documents available to bidders
06/11/18 – Prebid meeting occurred at Courthouse.
06/12/18 – Addendum No.1 and No.2 issued.
06/26/18 – Bid opening occurred with four contractors submitting proposals. Two of the four bids under published estimate. American Façade Restoration is the apparent low bidder.
06/27/18 – THP had phone conversation with AFR to review their bid.
07/02/18 – THP provided a bid summary letter and draft AIA contract for review by the County.
07/05/18 – County published updated AIA contract and documents for review by AFR.
7/25/18 – County published executed AIA contract.
08/21/18 – Background checks approved and submittals in process.
08/30/18 – Preconstruction meeting scheduled for 9/1/18.
09/1/18 – Preconstruction meeting completed.
09/26/18 – American Scaffolding erected swing stage equipment for courtyard repairs.
10/12/18 – Change Order #01 Executed. During the dentil repairs it was discovered the cornice steel supports were heavily corroded. Change order #1 provide new support detail, that is integrated into the dentil repair.
10/25/18 – AFR working on courtyard dentil repairs.
11/16/18 – Change Order #02 Executed. Work to address loose stone, concrete, masonry materials observed during city façade assessments.
11/29/18 – AFR completed Courthouse base bid repairs. Roughly 60% of knock down survey and stone stabliziation work complete. Work scheduled to be completed December 8th (weather permitting).
12/07/18 – AFR completed all knock down work for Change order #02
12/31/18 – AFR completed final window repair for Change order #02.
01/17/19 – THP submitted the certified AFR pay application to the County.
01/18/19 – AFR submitted close out documentation to THP for review.
03/21/19 – THP forwarded final close out documents to the County.
04/25/19 – Project complete

CH – Critical Façade Repairs (F103) Read More »

A&D – Critical Façade Repairs (F104)

12/28/17 – THP publish SOSS to Hamilton County as requested.
02/15/18 – Hamilton County approved SOSS.
02/20/18 – THP published review documents.
03/09/18 – THP published bid documents.
03/15/18 – Prebid meeting completed.
03/29/18 – Bids received. American Façade Restoration the apparent low bidder.
04/3/18 – THP sent a letter of recommendation after a phone interview with AFR.
04/4/18 – THP sent draft AIA County / AFR contract to the County for review.
04/26/18 – County prosecutor reviewing the contract.
06/06/18 – Hamilton County and AFR under contract.
06/28/18 – AFR reported they plan to start work mid to late July. Work should take about two weeks.
7/23/18 – Preconstruction meeting completed.
7/26/18 – Anticipated start of construction will be 8/6/18 with work expected to be completed 8/31/18.
08/30/18 – AFR actively working on North, South and West elevations. Concrete and stone patching repairs 90% complete. South Elevation pilaster repair 50% complete.
9/5/18 – AFR substantial completion reached. THP reviewed work and generated a punchlist.
9/11/18 – AFR completed punchlist work.
9/27/18 – AFR working on closeout documentation.
10/25/18 – Project complete and closeout documentation complete.

A&D – Critical Façade Repairs (F104) Read More »

800 – City Facade Assessment (F105)

12/28/17 – THP publish SOSS to Hamilton County as requested.
01/25/18 – Hamilton County approved SOSS.
03/06/2018 – THP completed ground survey of façade.
03/29/2018 – THP to schedule rappelling survey early April.
04/26/18 – THP schedule rappel the facade.
05/21/18 – THP completed draft of Cincinnati façade ordinance report and published.
5/31/18 – County reviewing report.
6/26/18 – THP submitted drafts of the Envelope Assessment Report and City Report
07/26/18 – THP finalized and published Cincinnati façade ordinance report. Signature by Ralph Linne’s required before THP submits report to City of Cincinnati Buildings & Inspections.
08/24/18 – THP received letter from City of Cincinnati acknowledging the submitted report.

800 – City Facade Assessment (F105) Read More »

CAB – Building Envelope Assessment (F106)

12/28/17 – THP publish SOSS to Hamilton County as requested.
01/25/18 – Hamilton County approved SOSS.
03/29/18 – Field work to start first week of April.
4/13/18 – THP completed rappelling surveys.
4/23/18 – THP completed survey work from the ground and roof.
4/26/18 – THP compiling data for report.
5/31/18 – THP finalizing draft report for review by the County.
6/26/18 – THP submitted drafts of the Envelope Assessment Report and City Report.
07/26/18 – THP finalized and published Cincinnati façade ordinance report. Signature by Ralph Linne’s required before THP submits report to City of Cincinnati Buildings & Inspections.
08/24/18 THP received letter from City of Cincinnati acknowledging the submitted report.

CAB – Building Envelope Assessment (F106) Read More »

230 – City Façade Assessment (F107)

12/28/17 – THP publish SOSS to Hamilton County as requested.
01/25/18 – Hamilton County approved SOSS.
04/19/18 – Completed visual survey from grade.
04/20/18 – Rappelled all four elevations.
04/26/18 – Report under development.
05/21/18 – THP completed draft of Cincinnati façade ordinance report.
05/22/18 – THP developed Opinion of Probable Cost for recommended repairs specific to Cincinnati façade ordinance review.
05/24/18 – THP finalized Cincinnati façade ordinance review report and application form.
5/31/18 – County provided verbal comments. THP reviewing comments.
7/26/18 – CORRECTION, comment on 5/31/18 for 800 Broadway assessment. Report approved as submitted.

230 – City Façade Assessment (F107) Read More »

JC – Building Envelope Assessment (F109)

01/22/18 – Hamilton County requested an SOSS
01/25/18 – THP provided SOSS as requested by Hamilton County.
02/15/18 – THP approved SOSS.
04/26/18 – THP scheduled field work to begin the first week of May including rappelling. Work is weather dependent.
05/02/18 – THP completed site rappelling surveys.
05/11/18 – THP completed site ground survey.
05/31/18 – THP working on reports.
06/28/18 – THP working on reports. THP verbally noted the façade did not have any safety issues that would impact a City of Cincinnati building façade inspection report.
01/31/19 – THP working on report. County draft report anticipated February 15 and final report completed February 28.
05/29/19 – THP completed internal City Draft of report and Façade section. Roofing assessment to be complete the first week of June.
06/05/19 – THP completed roof assessment.
06/06/19 – THP completed roof assessment.
06/27/19 – THP issued City Facade Application report to County for review.
02/27/20 – THP published the report to the County.
07/30/20 – Discussed at Partner meeting. Leave open for now.

JC – Building Envelope Assessment (F109) Read More »

JC – Video Visitation Service Agreement

03/27/18 – Final draft of RFP submitted to Sheriff’s Office for review and comment. Issuance of RFP pending comments from Sheriff’s Office.

04/25/18 – Final draft of RFP submitted to Sheriff’s Office for review and comment. Issuance of RFP pending comments from Sheriff’s Office.

05/30/18 – TEI receives final comments form HCSO and facilities. RFP to be issued June 1 for bidding.

06/27/18 – RFP issued for bids. Prebid meeting held and bids are due to purchasing on July 12, 2018.

07/25/18 – Bids received from 4 vendors and results sent to HCSO for approval and contract execution.

JC – Video Visitation Service Agreement Read More »

JC – Security System PM Bid

03/27/18 – Project is out to bid (ITB # 018-18). Bids open on 03/28/18.

04/25/18 – Project bids received. DeBra Kuempel is apparent low bid. Contracts sent to prosecutors office for approval.

05/30/18 – Facilities to confirm if contracts have been received and returned to DK.

06/27/18 – PM Contract pending prosecutor review.

07/25/18 – PM Contract pending prosecutor review.

08/29/18 – PM Contract pending prosecutor review.

JC – Security System PM Bid Read More »

JC – Backflow Preventer Replacement

03/23/18 – TTC met with John Nester and Andy Stafford about replacing the BFP at the Justice Center.
03/24/18 – TTC talked to City plumbing department and Blue Chip plumbing about replacing the BFP and what it would take. The city is not keen on downsizing the BFP at all and Blue Chip agreed they don’t need to be dual detector check but they do need to be reduced principal backflow preventers. TTC code research agrees.
05/21/18 – TEI Issued 30% review set and begins working on 4″ BFP replacement scenario. TEI sets up additional fieldwork on site for this project, TTC & RAJ.
05/22/18 – TEI puts together equipment cost differences after receiving Vendor quotes form Watts for this project. TTC and JN discuss bidding options. TEI to further design on 4″ scenario vs 6″ scenario for backflow preventers. There are two major issues with the first being if we need a full building shutdown to do this work and the second deciding if we are going back with 4″ BFP or 6″ BFP.
05/30/18 – Review drawings are complete and ready for TTC review but fitting to fitting work not complete by TEI quite yet in TTC opinion.
06/14/18 – ThermalTech create full 3D model to try to fit the BFP in this building without a building shutdown. Nothing aside form $20,000 in additional fittings worked so far. WE just don’t have enough room.
06/24/18 – We did a lot of design and fitting work this month on this project and confirmed neither 6″ nor 4″ BFP’s fit into the existing piping without shutting down the building and removing the existing gate valves which are not holding watertight. The team came up with the idea of changing the BFP model to a smaller skinner model with less flange to flange dimensions. We are still 6″ short of keeping the existing valves installed and reusing the old valves. Dan ordered a fire hose that we can test bypassing the inlet of the water piping to the filtration units, keep one set of valves and replace one set of valves and do this work without a complete building shutdown. This will be tested prior to bidding out this work.
07/26/18 – Revised drawings are complete and ready for review by County for Small Project Bid with latest BFP and bypass design included.
08/23/18 – Prebid held on site with five bidders. Bids are due 8/31.
08/27/18 – Addendum 1 released to bidders.
09/27/18 – PO approved, contract over at Prosecutors Office for approval. Project is moving forward.
10/23/18 – TEI to setup kickoff meeting with DK next Wednesday at 10am. TEI to submit small SOSS for additional services.
11/27/18 – TEI returned submittals earlier this week and equipment should be ordered for this project.
11/07/18 – Site safety plan issued for this job. Equipment is ordered. Proejct schedule should be finalized shortly.
01/22/19 – HC checked in with DK on project schedule again today. So far background checks are in place and we are awaiting on the equipment to arrive to perform the work.
01/31/19 – We are shooting for 2/14 or 2/21 for doing this work. Prework will happen that week during they day.
02/21/18 – Debra Kuempel completed the backflow preventer replacement by 1:30am and had the city water back online and the building up and running. TEI was on site from 6pm to midnight for const assistance.
02/28/19 – Debra is performing the annual test on the BFP for the city paperwork, finishing the drains off the BFP and the insulator is coming down to insulate to wrap up the project.
03/27/19 – O&M have been received and approved and sent to County for closeout. Final payapp has been received and approved. No PW rates on this project to approve.
05/27/19 – Project completed and ready to archive. Annual test is complete and passed, good until next year. It’s working great.

JC – Backflow Preventer Replacement Read More »

JC – Recovery 3rd Flr Build-Out

02/22-18 – Created new project to track the actual construction project. THP and TEI to send final proposal data to Spencer for use on this project. Our proposal will include all the assumptions taken on this project for code review, relocation of existing spaces and basic construction intent.
03/20/18 – ThermalTech met with GBBN to review schedule for project design and construction at GBBN offices.

04/13/18 – Meeting held with Administration, Prosecuting Attorney, Facilities, Sheriff and GBBN to discuss Grant Application and Gantt Chart timelines.

04/18/18 – GBBN had telephone conversation with Steve Holland of ODRC to discuss 5 phases of State Review process for this project. Sheriff sends email documenting names of existing spaces within Justice Center for displacement communications.

04/20/`8 – Facilities determines a formal SOSS is needed for the State Grant Budget and Schedule Analysis. See new project Post.

04/23/18 – Sheriff sends email with displaced space designated locations within existing Justice Center and Courthouse JAX space.

JC – Recovery 3rd Flr Build-Out Read More »

GABP- Diamond Club Kitchen Epoxy Floor

11/11/18 – GBBN contacted by Director of Operations to review potential two Kitchen Epoxy Floor Replacements. Projects to be constructed by 3/318.

1/11/18 – GBBN contacts manufacturer to inquire about existing product that has begun to fail and preparation required to recoat.

1/21/18 – Samples of colors and slip resistance sent to Operations for selection by Owner.

1/23/18 – Owner color and slip resistance level selections presented to GBBN.

2/1/18- Pre-Bid meeting held at GABP. Three attendees present. RFP documents distributed.

2/3/18 – Addenda #1 distributed.

2/12/18- All three proposals received. GBBN contacts low and responsible bidder to verify scope. GBBN recommends J Wesselman Specialty Flooring, LLC to Owner.

02/19/18 – Contractor to commence work at GABP. Background Checks required by Reds.

GABP- Diamond Club Kitchen Epoxy Floor Read More »

JC – Capacity & Recovery Expansion

01/24/18 – Judi Boyko requests GBBN begin drafting Proposal/SOSS for Build out design services for scope of work requested in State Of Ohio Grant Application. Copy of Grant Application emailed to GBBN. GBBN requests same from THP and TEI.
02/02/18 – GBBN and TEI meet to discuss proposal scope and requirements for language to be contained in document.
02/04/18 – GBBN solicits proposals for ADA Comprehensive Audit from potential consultants.
02/11/18 – GBBN also contacts potential Justice/Corrections consultants for Potential PEER Reviews of design documents.
07/03/18 – GBBN submits SOSS based on recent meetings that have finalized all enabling projects to relocate existing staff, furniture and equipment. GBBN completes updates to the Gantt Chart for the Progressive Project Approach.
07/25/18 – GBBN receives approved SOSS and Purchase Order.
07/26/18 – GBBN, Facilities and Sheriff meet to discuss logistics and update meeting schedule.
07/30/18 – TTE received approval for design, bidding and construction proposal from GBBN.
08/02/18 – GBBN completes updates to Gantt Chart, for the Progressive Process, adding Leadership Meeting Milestones, and forwards to Facilities.
08/20/18 – THP confirms existing shelf angle locations and construction details from original construction. This exercise will assist the detailing and location of the new proposed security glass and glazing into the existing wall construction.
08/23/18 – TEI confirms existing MEP locations along existing long wall of proposed Recovery Unit for the purposes of locating proposed sloped ceilings.
08/23/18 – State of Ohio DRC responds to request for information concerning documentation of Enabling Project Scope within the JCC on this project.
08/27/18 – GBBN requests Room Naming protocol for the new Recovery Units and associated rooms inside. Numbering has been discussed with Facilities and In4 internally at GBBN.
08/28/18 – GBBN meets internally to discuss design and footcandle measurement requirements for the new proposed Recovery Security Window sizes and locations.
08/29/18 – TTE has started updating our background drawings and we have finished our first pass at the final load calc for people and space HVAC loads. We are working on the Ventilation Calculations next.
08/30/18 – GBBN, Facilities and Administration meet to discuss Media Press Release Packet of documents.
09/05/18 – GBBN and Facilities trade communications with the Sheriff about Room Naming and Numbering.
09/18/18 – GBBN, TEI and THP meet with the Sheriff’s Technical Committee for the Schematic Design phase approval. Product selections and changes to the locker box design were made.
09/20/18 – TEI and GBBN perform field verification of all spaces affected by the scope of work.
09/24/18 – TEI sends sketches for proposed Second Floor work for plumbing under-floor work.
09/27/18 – TEI sent flush mounted SS temperature sensor cut sheets, we plan on replacing the pneumatic stats with DDC stats and new wiring in the wall, no wireless sensors unless there is absolutely no other way to make this work. TEI ask unit prices for fixing DD boxes or replacing DD boxes if we find broken HVAC hardware. TTC sent a new combo LAV/WC that has a smaller footprint to fit into the RR better. We are adding trench drains to the door ways to the thresholds. TEI asked about washer connections for security protection.
10/08/18 – GBBN and Facilities makes Press Package and Project Review presentation to BOCC.
10/22/18- GBBN and TEI send requests for information regarding shower mixing valve controls and Kiosk wiring logistics to the Sheriff.
10/22/18 – TEI sends to GBBN cut sheets on Floor Drain/sink, plumbing fixtures and plumbing routing information.
10/23/18 – Sheriff responds with answers to above.
10/24/18 – Facilities corresponds with State of Ohio ORC concerning Civil Rights Compliance.
11/14/18 – GBBN and TEI send State of Ohio Schematic Design approval drawings to Facilities for submission to the State Department of Rehabilitation and Correct.
11/27/18 – GBBN and TEI send updated Opinions of Probable Costs to Facilities.
12/19/18 – GBBN meets with Facilities to discuss State of Ohio submission and GBBN signs applicable portion of submission.
01/31/19 – Project is in review. Designers to wait until next approval phase to create DD documents and then CD documents a month later.
02/28/19 – Project is in review. We are waiting on State Review comments.
03/28/19 – Project is ins review. We are waiting on State Review comments and Grant Rebate information on this project. We could have information back on April 5 from the State.
04/21/19 – Facilities notifies GBBN of confirmation of proposed Schematic Design Meeting request from STate of Ohio.
04/22/19 – GBBN and Facilites agree 4/29/19 will be date for Phase 1 meeting, to be held in London, Ohio. Proposal is for Phase 2 and Phase 3 meeting, with State of Ohio Rehabilitation and Colrrection, has been tentatively agreed upon by the State.
06/24/19 – GBBN/TEI attend Discussion on Update of J.C. Build Out Schedule.
07/18/19 – GBBN meets with Facilities, to discuss restarting the design portion of this project. The goal is for Facilities, to have all future deliverables, related to the State of Ohio SD response packet, required from the design team, documented by August 1, 2019.
08/08/19 – GBBN confirms with KFI, additonal existing conditions from the Server Room door removal project from 2018. KFI recalls latch sides of the existing hollow metal door frame were not grouted solid, as if to leave future possibilities for electronic door hardware wiring to be added.
08/14/19 – GBBN informs design team all Rooom Numbers and Door Numbers have been added to the Base Floor Plan drawings. Door numbering forwarded to the Door Hardware Consultant.
08/15/19 – GBBN meets with Door Hardware Consultant for this project. Questions on door functioning are developed and later forwarded to the Sheriff’s Office for input.
08/15/19 – GBBN emails State of Ohio DRC with questions generated by Door Hardware Consultant related to Corrections Grade door hardware specifications.
08/27/19 – GBBN meets with THP, to finalize the Architectural-Structural interface. THP to generate additional structural detailing language, for inclusiion into the Architectural drawings.
08/28/19 – TTE committed to completing this project in September on owner deadline.
09/23/19 – GBBN recieved email, from Facilties Electrician, relating contact information, for exisitng electromechanical lockset replacement parts vendor. GBBN makes contact and is informed about matching locksets, both mechanical and electromechanical, and other peritnent vendors. Infornation is shared with TEI and Facilities.
09/24/19 – GBBN and TEI establish a meeting with the Sheriff to vist an existng LC to determine full am ount of racks and equipment to be housed in the new Pod Guard Post Obsevation desks. Meeting is set for 09/30/19 at 10:00 am.
09/25/19 – GBBN contacts Corrections hollow metal door and frame manufacturer. Details for door frame, doors, sidelights and vision windows are secured and documented.
10/25/19 – GBBN and TEI send Phase 2/3 Drawing and Specification hard copies to FAcilities for submission to the State of Ohio ODRC.
10/29/19 – GBBN delivers signed copies, of the ODRC Phase 2 and the Phase 3 Checklists, to Facilities, for transmission to the ODRC.
11/20/19 – The project teams finalizes a meeting with Christopher Darlington of the State of Ohio ODRC for the purpose of the final approval for the Phase 3 Bid Issuance.
01/30/20 – ARC must send a copy to Chris Darlington at the State for approval on this project when we issue. Grant funding and State of Ohio requirements has some additional language to be included.
02/13/20 – ITB#020-20 Bidding Documents issued to ARC Reprographics for review.
02/14/20 – ITB#020-20 Bidding Documents issued to Purchasing for BidSync uploading.
02/25/20 – Pre-Bid Meeting held at 9:00. North and South Buildings toured along with the JAX area of the Courthouse. Meeting Minutes to be authored and included in Addenda #1.
03/25/20 – Bids were opened today and appeared to be overbudget. Facilities asked the Partners to get more definition on the reasoning behind the overages and report back to the County. Facilities also indicated the BOCC will be issuing a resolution to reject all bids.
03/26/20 – GBBN has already called Triton Services, and has called scheduled for 10:30 with KFI and 11:00 with Graybach for today to discuss bid results.
06/25/20 – The County has requested a repricing for this job and updated for Covid and budget. GBBN, THP, TEI working on recollecting prices from scratch and verify availability for fourth quarter of 2020.
07/30/20 – Cost was submitted to commissioners and they are finding the money for the project. County directed us to repackage this project for last week of August to first week of September timeframe.
08/27/20 – BOCC agenda has this items on the agenda today. Rebid 9/3, Prebid 9/10 and Opened on 9/24.
09/24/20 – Rebid Project was started and this page Archived. See JC Capacity & Recovery – REBID

JC – Capacity & Recovery Expansion Read More »

JC – Administration Inmate Space Study

01/24/18 – Judi Boyko requests GBBN begin drafting Proposal/SOSS for Build out design services for scope of work requested in State Of Ohio Grant Application. Copy of Grant Application emailed to GBBN. GBBN requests same from THP and TEI.

02/02/18 – GBBN and TEI meet to discuss proposal scope and requirements for language to be contained in document.

02/16/18 – Sheriff Department requests copies of Grant Application drawings for presentation to Department of Corrections. GBBN requested to appear at tour with DOC on 2/20/18 at 1300 hours.

JC – Administration Inmate Space Study Read More »

A&D – Access Control System Study

02/20/18 – ThermalTech met with the facilities department and A&D staff to discuss the need for a study for the existing access control system. ThermalTech submits SOSS for study for the project. Project pending the approval of the SOSS and PO.
03/27/18 – Project Pending approval of SOSS and PO.
04/25/18 – Project pending approval of SOSS and PO.
05/30/18 – Project Pending approval of SOSS and PO.
06/29/18 – Project Pending approval of SOSS and PO.
07/25/18 – Project Pending approval of SOSS and PO.
08/29/18 – ThermalTech receives approved SOSS and PO (5778030). ThermalTech, Facilities and JFS conduct study kick-off meeting on 08/28/18 and schedule field investigation of 09/13/18. ThermalTech beginning code research and product research beginning 09/01/18.
09/26/18 – ThermalTech completes field investigation with JFS (Claude Toulsen). Report is in progress. ThermalTech to send draft copy to BW for review upon completion.
10/23/18 – ThermalTech working to complete draft of report, and will send to BW and CT for review by 11/09/18.
11/28/18 – Report Draft is still in process. ThermalTech to wrap up draft and send to BW and CT for review.
01/29/19 – Report Draft is still in process. ThermalTech to wrap up draft and send to BW and CT for review.
02/26/19 – ThermalTech reached out to Basis of Design (VAX) for final pricing, and opinions of probable cost in report pending reciept of the pricing from the supplier. NOTE – Supplier local rep resigned and has not been replaced to date. TEI communicated with corporate offices.
03/26/19 – ThermalTech issues report to HamCo facilities and Claude Toulsen for review and comments. ThermalTech receives comments from BW, and final issuance pending comments from CT.
04/24/19 – Issuance of final report pending receipt of comments from Claude Toulsen.

A&D – Access Control System Study Read More »

ROUND BOTTOM GARAGE Asbestos Study

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sends list of buildings to be included in Asbestos Abatement Reporting.

02/14/12 – Pinnacle Engineering requested drawing files for the purpose of documenting findings.

02/15/12 – GBBN sent drawing files to Pinnacle Engineering in PDF form.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/03/12 – Field work completed, draft report completed and ready for initial review.

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

01/26/13 – BRG confirms entry of ACM data into Archibus is completed.

01/28/13 – GBBN conducts spot review and confirms data entry is accurate.

02/28/13 – Pinnacle sends GBBN a proposed completion schedule for remaining work.

03/18/13 – Tony Matre calls GBBN to request a status check on Pinnacle’s delivery schedule.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

02/24/14 – GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/Web Central is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14- GBBN sends another email and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

08/29/14- Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications with Tony Matre to finalize invoicing for these projects.

ROUND BOTTOM GARAGE Asbestos Study Read More »

RECORD CENTER Asbestos Study

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sends list of buildings to be included in Asbestos Abatement Reporting.

03/30/12 – Meeting with Tim Schuh of Facilities Department to discuss Archibus Input Strategy

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/04/12 – GBBN receives drawing files from C-R Architecture upon request for use by Pinnacle.

05/07/12 – GBBN transmits drawing files to Pinnacle for use in field documentation.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

12/22/12 – GBBN sends request to Pinnacle Engineering for remaining ACM translation data for continued Archibus data entry.

02/26/13 – GBBN inquires with Pinnacle for status of remaining documents to be sent to GBBN.

02/27/13 – Pinnacle reports back that progress has been made and further timetable for receipt will be coming 2/28/13

02/28/13 – Pinnacle sends GBBN a proposed completion schedule for remaining work.

03/18/13 – Tony Matre calls GBBN to request a status check on Pinnacle’s delivery schedule.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

0611/13 – GBBN receives floor plan updates in electronic form. GBBN updates CAFM drawings for the 1916 for future reference.

02/24/14 – GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/WebCentral is ongoing. GBBN was granted access to the database to complete the drawing downloads. No existing drawing of 1916 Central Parkway exists in Archibus. GBBN to visit site and do field ottom: 2px”>

02/20/15 – GBBN in communications with Tony Matre to finalize invoicing for these projects.

RECORD CENTER Asbestos Study Read More »

GALBRAITH RD GARAGE Asbestos Study

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sends list of buildings to be included in Asbestos Abatement Reporting.

03/30/12 – Pinnacle Engineering requested drawing files for the purpose of documenting findings.

03/31/12 – GBBN sent drawing files to Pinnacle Engineering in pdf form.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/03/12 – Field work completed, draft report completed and ready for initial review.

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

01/26/13 – BRG confirms entry of ACM data into Archibus is completed.

01/28/13 – GBBN conducts spot review and confirms data entry is accurate.

02/28/13 – Pinnacle sends GBBN a proposed completion schedule for remaining work.

03/18/13 – Tony Matre calls GBBN to request a status check on Pinnacle’s delivery schedule.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

06/10/13 – Pinnacle Engineering response with email indicating CAB report will arrive 06/11/13 and CAB on 06/14/13.

06/14/13 – Galbraith Road Garage Report arrives from Pinnacle. CAB report is not included.

02/24/14 – GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/WebCentral is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14 – GBBN sends another emial and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

08/29/14 – Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications with Tony Matre to finalize invoicing for these projects.

GALBRAITH RD GARAGE Asbestos Study Read More »

RIPPLE RD GARAGE Asbestos Study

10/20/11 – Kick-off Meeting with Pinnacle and Facilities Department

11/04/11 – Facilities Department sends list of buildings to be included in Asbestos Abatement Reporting.

02/23/12 – Pinnacle Engineering requested drawing files for the purpose of documenting findings.

02/24/12 – GBBN sent drawing files to Pinnacle Engineering in pdf form.

02/24/12 – Pinnacle began field investigation at the site.

03/30/12 – Meeting with Tim Schue of Facilities Department to discuss Archibus Input Strategy

04/03/12 – Field work completed, draft report completed and ready for initial review.

04/05/12 – Meeting with GBBN and Facilities to discuss drawing format.

05/10/12 – Meeting with GBBN and Pinnacle to discuss drawing format for reports. Tony Matre’s request for ‘General Information Notes to occur on each floor plan are discussed.

10/27/12 – Pinnacle Engineering sent ACM list from Archibus/BRG for purposes of designation conversion from Pinnacle report to Archibus data entry.

01/26/13 – BRG confirms entry of ACM data into Archibus is completed.

01/28/13 – GBBN conducts spot review and confirms data entry is accurate.

02/28/13 – Pinnacle sends GBBN a proposed completion schedule for remaining work.

03/18/13 – Tony Matre calls GBBN to request a status check on Pinnacle’s delivery schedule.

04/05/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response.

04/20/13 – Email sent to Pinnacle Engineering inquiring about status of project reports and unmet schedule milestone goes without response. Reported to Tony Matre via telephone call.

06/09/13 – GBBN inquires with Pinnacle Engineering about delays in deliverables.

02/24/14- GBBN and Pinnacle Engineering met with Tony Matre to deliver the final reports and electronic copies of the reports. GBBN is completing final report drawings for Pinnacle as final preliminary drawings are delivered by Pinnacle to GBBN. All drawings are to be completed by 2/28/14.

03/26/14 – All asbestos reports and associated drawings are complete. Final drawing input into Archibus/WebCentral is ongoing. GBBN was granted access to the database to complete the drawing downloads.

07/01/14 – GBBN sends another emial and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

08/29/14 – Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications with Tony Matre to finalize invoicing for these projects.

RIPPLE RD GARAGE Asbestos Study Read More »

1916 CENTRAL PARKWAY Asbestos Study

07/01/14 – GBBN sends another emial and follow-up voice mail to Pinnacle Engineering inquiring about status of billings and final completion.

08/29/14 – Pinnacle Engineering sends invoices for services to GBBN.

10/29/14 – GBBN sends Tony Matre SOSS invoice status with all of the Pinnacle Engineering invoices included.

10/31/14 – GBBN pursuant to Tony Matre’s request sends letter of documentation regarding scope overruns.

02/20/15 – GBBN in communications with Tony Matre to finalize invoicing for these projects.

1916 CENTRAL PARKWAY Asbestos Study Read More »

2014 GBBN GENERAL SERVICES

09/17/13 – Bert Watts requests Partners to submit SOSS for 2014 General Services.
09/18/13 – SOSS submitted to Bert Watts.
01/30/14 – GBBN attends monthly Partnering Meeting.
02/27/14 – GBBN attends monthly Partnering Meeting.
02/24/14 – Bert Watts indicates the JCC Mural project services will be billed to the General Services.
02/25/14 – GBBN and TEI meet with Bert Watts to discuss moving the Recorder’s File Storage to the CAB 10th Floor CLEAR area. Bert requests the services for the Schematic Design and Opinion of Probable Costs be billed to the General Services.
03/18/14 – GBBN delivers estimating binders to Facilities after review finds all printing and assembly of binders to be in order.
04/24/14 – GBBN attends monthly Partnering Meeting.
03/27/14 – GBBN gets new Partner ID Badge at Sheriff’s Office in Courthouse to replace lost badge.
04/24/14 – GBBN attends monthly Partnering Meeting.
05/29/14 – GBBN attends monthly Partnering Meeting.
06/23/14 – GBBN completes the CAB 8th Floor As-Built drawing layering standard review and reconciliation.
06/26/14 – GBBN attends monthly Partnering Meeting.
07/28/14- Facilites sends Master Service Agreement Admendment to GBBN for signatures.
07/28/14- Facilities sends three building (230 WHT Law Center/CAB Basement/A&D) existing As-Built drawings to GBBN for layering verification review.
07/31/14- GBBN attends monthly Partnering Meeting and delivers signed Master Service Agreement Admendment to Facilities.
09/02/14- Bert Watts contacts GBBN about a project to renovate an existing space in 800 Broadway, 6th Floor.
09/05/14- Sketch sent from Bert Watts about pop-up project at 800 Broadway.
09/15/14- GBBN attends kick-off meeting with Bert Watts, JFS and Juvenile Court.
09/16/14- ThermalTech sends the MEP Estimating Documents to GBBN. GBBN sends combined project Estimate to Bert Watts for review.
09/30/14- GBBN receives email invitation to visit Patrol Headquarters to investigate addition for a Kennel and to investigate an operable partition renovation to the Comm. Center.
10/16/14- GBBN receives email with Operable Partition quote, developed by OKI (7/7/14), from Bert Watts via John Nester.
10/07/14- GBBN receives email from Bert Watts about estimate project requests created in Archibus for estimating.
10/09/14- GBBN sends first iteration of Patrol Headquarters Kennel addition floor plan to Facilities and TEI for review.
10/15/14- GBBN completes estimate for Patrol Headquarters Kennel addition.
10/16/14- GBBN receives comments and suggested floor plan revisions for the Patrol Headquarters Kennel estimate.
10/17/14- GBBN contacts Metallic Building Systems about Burlington Garage siding repairs by email off the link from the website.
10/20/14- GBBN sends updated Patrol Headquarters Kennel floor plan to TEI and Facilities for review and estimating.
10/20/14- GBBN sends deflection criteria information to THP to review for roof joist loading. Structural drawings received from TEI are forwarded to THP for investigation.
10/24/14- GBBN contacts Metallic Building Systems about Burlington Garage siding repairs by telephone. Voice mail was left.
10/27/14- GBBN receives call from Valcom Enterprises related to inquiry about floor mounted operable partition system. Telephone memo forwarded from GBBN to Facilities and THP.
10/29/14- Bert Watts forwards final design criteria on Comm. Center operable partition for estimating (three separate estimating options) purposes. GBBN calls Valcom Enterprises for quotation on actual floor mounted operable partition.
10/30/14 – GBBN attends monthly partnering meeting. Next Meeting scheduled for January 2015 if GBBN awarded contract extension.

2014 GBBN GENERAL SERVICES Read More »

800 Broadway Polygonal Pavilion Roof Repair

Current Comments (10/26/2011)
October 26, 2011 Update THP develops test repair options and met with SSRG to review for pricing. THP to submit separation SOSS for contractor work.

Past Comments

Due to findings, weather sensitive repairs, and schedule; THP proposed completing a safety survey and trial repairs. County requested a letter report summarizing needed work to be possibly incorporated into a larger 2012 project. A SOSS for the letter reported was requested.

September 23, 2011 THP met with County to review conditions of roof.

Early September THP completed field review and design analysis.

August 3, 2011 SOSS approved.

July 18, 2011 THP Submitted SOSS for review.

800 Broadway Polygonal Pavilion Roof Repair Read More »

2011 General Structural Services

Current Comments (10/26/2011)
Hourly budget funds exhausted for F24A. THP directed to submit for additional $5,000 as F24B.

Past Comments

July 26, 2011 County approved SOSS F24A.

July 18, 2011 THP submitted SOSS F24A for additional funds.

Hourly budget funds exhausted; Bert Watts requested a SOSS for the second half of the year.

Bert Watts requested THP provide a SOSS for the study and repair of the 800 Broadway limestone panels.

THP reviewed reported cracking of Hillcrest Oak Cottage and provided a summary letter on May 5, 2011. Bert Watts requested an SOSS to complete a study of the cracking issues.

THP completed initial review of 800 Broadway limestone condition and provided summary email for review.

THP reviewing 800 Broadway LEED EB proposal structure.

May 5, 2011 SOSS approved.

April 28, THP provided SOSS.

April 24, 2011 SOSS requested SOSS.

2011 General Structural Services Read More »

Parkhaus Garage Repairs

Current Comments (10/26/2011)
October 26, 2011 Update – Contractor noted they are waiting on Joint and several warranty from the manufacturer, which is anticipated later this week.

Past Comments

All pay requests minus retainage approved; waiting on warranty and closeout paperwork.

August 31, 2011 Substantial letter completion letter issued; along with final deduct change order due to liquidated damages.

All work complete as of early August.

July 22, 2011 RAM issued via email that the new hand rail embed should be fabricated and on site at the end of the week of July 25.

July 12, 2011 THP issued new hand rail embed replacement details to RAM. RAM submitted details for embeds to be fabricated.

July 7, 2011 THP approved and forwarded to Hamilton County, RAM request for payment, Pay Application No 4, in the amount of $20,617.20.

July 6, 2011 THP noted, RAM damaged some existing handrail embeds when removing existing handrail. THP to review conditions and issued repair details.

July 5, 2011 RAM re-mobilized on site to begin replacement of the handrails at the NW stair and liquidated damages begin.

June 9, 2011 THP approved and forwarded to Hamilton County, RAM request for payment, Pay Application No 3, in the amount of $29,794.20.

May 26, 2011 THP approved, with exceptions noted, the steel hand rail shop drawings for NW stair tower.

May 23, 2011 RAM demobilized from the project site so Hamilton County has full use of the garage facility. RAM will re-mobilize on site once the steel handrail shop drawings and fabrication are complete. Per liquidated damages letter RAM is scheduled to return for installation of the steel hand rail on July 5, 2011.

May 25, 2011 steel hand rail shop drawings for NW stair tower received.

May 23, 2011 substantial completion date but RAM has not satisfied the substantial completion date requirements. No steel hand rail shop drawings submitted for NW stair tower. Liquidated damages letter pertaining to steel hand rail to be issued by THP per Bert Watts (Hamilton County) direction and approval. Steel hand rail shop drawings and fabrication were never weather dependent work items.

May 23, 2011 THP issued Field Report No 05 for Phase 2 (final) membrane strip installation.

Weekend of May 20, 2011, RAM completed vault slab placement over anodes, and remaining Phase 2 membrane strip installations. Inclement weather postponed this phase of membrane installation till this date.

May 17, 2011 Anode testing report by Bushman and Associated issued.

May 13, 2011 THP issued Field Report No 04 for completion of Phase 1 membrane strip installation. THP also approved and forwarded to Hamilton County, RAM request for payment, Pay Application No 2 in the amount of $54,344.40.

May 10, 2011 Membrane manufacturer (Neogard) letter pertaining to exposed membrane aggregate being compromised was issued.

May 6, 2011 THP issued Field Report No 03 for Phase 1 membrane installation. Inclement weather prevented completion of all of Phase 1 membrane strip installation areas.

May 6, 2011 Final T&M tickets submitted by RAM for anode relocation.

April 29, 2011 Change Order No 01 work items approved by all parties for a deduct to the projects Cash Allowance in the amount of $8,735.00. Total project budget remains unchanged.

April 26, 2011 THP issued Change Order No 01 to reflect Bulletin No 01 pricing so RAM may begin the additional work. This Change Order added two weeks to the substantial completion date. New substantial completion date is May 23, 2011.

April 25, 2011 Hamilton County accepted Bulletin No 01 pricing which was within the projects original Cash Allowance.

April 25, 2011 RAM submitted Bulletin No 01 pricing.

April 21, 2011 RAM began membrane work on Levels 2 through 5.

Week of April 18, 2011 Anode placement began in the vaults.

April 15, 2011 THP issued Bulletin No 01 to RAM for pricing for additional concrete and waterproofing repairs.

April 13, 2011 Progress Meeting.

April 8, 2011, THP issued Field Report No 02.

April 7, 2011 RAM completed construction joint sealant replacement on Levels 2 through 5.

As of March 24, 2011 RAM has not submitted steel shop drawings for hand rail.

March 18, 2011 THP approved RAM’s Pay Application No 1, in the amount of $40,194.80, and forwarded to Hamilton County.

March 3, 2011, THP issued Field Report No 01.

Anode installation scheduled to begin week of April 4.

Weather conditions for this weekend appear favorable, so RAM may perform sealant replacement April 1 weekend.

January 6, 2011 preconstruction meeting completed. Work to scheduled to begin February 7 to allow for weather.

THP has all submittals except cathodic protections.

Contract approved.

County commissioners reviewing contract.

Contract signed by Ram reported to be returned to County.

September 27, 2010 THP sent updated contract for County review.

September 9, 2010 THP sent draft contract for County review.

Bids received and Ram Construction apparent low bidder.

Bids due August 18, 2010.

Pre-bid meeting scheduled for August 4, 2010 at 10:00 a.m.

Project out to bid on July 23, 2010.

Project Documents sent to County for review on July 19, 2010.

THP and Jim Bushman accessed vaults to confirm conditions for implementing corrosion protection system on June 23, 2010.

THP is coordinating work with corrosion consultant.

Parkhaus SOSS approved May 14, 2010.

SOSS submitted 3/3/10.

THP anticipates SOSS delivery by 3/5/2010. (2/24/10

Kickoff meeting complete.

THP needs to schedule a kickoff meeting.

THP working with subcontractor to develop proposal.

Parkhaus Garage Repairs Read More »

1021 Patrol Headquarters Waterproofing Repairs

Current Comments (10/26/2011)
October 19, 2011 THP, SSRG and County met to review the leak to determine if work is warranty or a new item. Due to lack of water/leak; the team decided to wait until rain/leak event and review the condition at that time.

New leak reported in same switch gear room in late September during a heavy rain.

Past Comments

September 15, 2011 County finalizing process of SSRG final pay application.

September 14, 2011 SSRG sent prevailing wage information to County.

September 11, 2011 THP forwarded final pay application and close-out manual to the County.

SSRG completed punch list items early August and THP verified items were complete.

July 13, 2011 THP published punch list to SSRG. Steven noted the work will be completed and THP is holding onto the final pay application (retainage) until the work is complete.

THP is waiting on warranties to process final pay application.

THP plans to punch on June 30, 2011.

Change Order No. 1 work (Window repairs) complete as of Friday, 5/20.

Change Order No. 2 sign by HGC, awaiting County approval.

THP forwarded Change Order No. 2 for the urethane injection of the electrical and sprinkler rooms to HGC for signature on 5/16.

During heavy rains of late April, leaking at the switch gear room and sprinkler room (new leak) occurred. THP recommended injection of crack from interior of both room. April 25, 2011 THP and HGC met to discuss the condition and request pricing.

During restoration repair, additional window sill and steel structure repairs associated concrete sill were identified. THP requested cost from HGC to complete the repairs. Change Order #1 approved by the County.

Subsurface waterproof and exterior injection work complete by HGC.

January 27, 2011 Work on hold until weather is within allowable specifications (early spring). The County requested all submittals and background checks be completed this February.

March 30, 2011 THP sent HGC the change Order form for the repair work associated with the window deterioration.

March 28, 2011 THP received approval from the County to proceed with a change order for HGC to repair the deteriorated window.

March 25, THP received final pricing from HGC regarding the work to repair the deteriorated window.

March 25, 2011 HGC finished the drain tile and landscaping work which completed all base bid work.

March 23, 2011 THP requested pricing from HGC for associated window deterioration.

March 23, 2011, HGC completed injection repairs and installation of the drain tile / back fill.

January 27, 2011 Work on hold until weather is within allowable specifications (early spring). The County requested all submittals and background checks be completed this February.

THP is waiting on submittals and contractor background check.

County conducted preconstruction meeting on 12/29.

Project needs to schedule a preconstruction meeting.

The requested project schedule and submittals from Structural System.

Contract approved.

October 29, 2010 the County provided updates to the proposed Contract. THP updated and returned the contract.

October 8, 2010 THP sent draft contract to County for review.

September 30, 2010. Bids were within budget and THP recommended Structural Systems (HGC).

Bids are due September 30, 2010.

September 21, 2010 Addendum #1 was issued, which was the meeting minutes from the prebid meeting.

September 17, 2010 bid documents were sent to HGC, ZSR, Lithko Restoration, and Langenheim & Thomson Company.

September 16, 2010 THP provided bid documents to the County.

September 9, 2010 County provide comments to review documents.

September 3, 2010 THP provided review documents to the County for review. Project estimate is below County threshold for publically bid project, so project bid is by invitation.

County requested construction budget and THP reviewing.

THP provided owner review documents on August 23, 2010.

County approved drainage system.

County reviewing THP proposed approaches of a new slab or drainage system (THP on hold).

THP and County had kick of meeting on June 21, 2010 to complete repairs recommended in report

THP issued letter report on June 18, 2010.

THP arranging with contract excavation of wall area.

Excavation needed for investigation is planned for mid-March, due to adjacent utility lines and required handwork.(2/24/10)

SOSS approved 2/3/2010.

THP submitted SOSS 2/1/2010.

THP needs to submit SOSS and complete survey.

Kick off meeting completed with Bert Watts and John Millar.

1021 Patrol Headquarters Waterproofing Repairs Read More »

Memorial Hall 2010 Facade Assessment

Current Comments (4/27/2011)
Project complete.

Past Comments

Can project be closed out?

March 8, 2011 report entered into Archibus.

March 4, 2011 report sent to County.

THP working on report.

January 3, 2011 THP & Lithko completed a water test of the south wall parapet.

January 2, 2011 Lithko restoration a safety survey to remove all loose stone material. THP completed façade lift inspection during safety survey.

THP working on project.

January 3, 2011 THP & Lithko completed a water test of the south wall parapet.

January 2, 2011 Lithko restoration a safety survey to remove all loose stone material. THP completed facade lift inspection during safety survey.

December 10, 2010 THP completed initial visual survey. Survey revealed loose sandstone and THP recommended completing a knock down survey by a contractor. Due to weather conditions repairs should occur in the spring. THP getting pricing from the contractor.

November 15, 2010 SOSS approved.

October 26, 2010 THP submitted SOSS for review.

October 26, 2010 THP and County completed kick off meeting.

October 19, 2010 County requested SOSS from THP.

August County and THP discussed preliminary Memorial Hall assessment numbers.

Memorial Hall 2010 Facade Assessment Read More »

CAB 10th Floor Community Development Expansion

2/9/10-Meeting with Bert Watts at Community Development

2/18/10- Issued SOSS to Bert Watts.

2/19/10-Bert questioned GBBN verses TEI scope and permitting costs.

2/22/10-Terry Cannon of TEI issued email with scope, SOSS and permitting resolutions.

3/6/10- Received signed SOSS.

3/8/10- Met with Mike Florimonte to field measure adjacent storage space. Receive directive to eliminate one workstation for a total of 3. The fourth area to become storage.

3/15/10-Received Purchase Order (538771) from Bert Watts.

3/17/10-Susan Walsh approved rotated third workstation.

3/31/10-Final Design Development drawings submitted to Bert Watts for Susan Walsh’s review.

4/6/10- Building Permit Application, Drawings, Electronic Submittal and Check delivered to Cincinnati Buildings and Inspections.

4/21/10- Approved Building Permit paid for and picked-up from Cincinnati Buildings and Inspections.

4/22/10- Approved Permit and Drawings Delivered to Bert Watts.

5/18/10- Inspector Larry Keifer has requested an additional sprinkler head be added in the expansion space.

6/24/10- Sprinkler permit has been filed and still pending.

7/29/10- Bert Watts declared this project closed and ready for Archives.

CAB 10th Floor Community Development Expansion Read More »

Sheriff HQ – Electrical Device Identification and Arc Flash Study

05/30/08 – Ginter sent the panelboard schedule in excel format. TEI forwarded to County and sent allowance usage certificate to Ginter for signing. Ginter has to provide an approved IBI permit at conclusion of this project.

04/09/08 – All Work is complete. TEI will finish and stamp the permit drawing for Ginter. Ginter will get IBI for making the conference room on emergency panel for colonel. This will use the last of the allowance money and closeout the project.

01/07/08 – Ginter has completed punchlist items. MAH will conduct back check when meeting on extra work takes place. The Colonel would like to have some receptacles on emergency power in the conference room so they can use as a command center. The work will be discussed with final approval from Tony Matre.

12/14/07 – Change order was requested for Ginter to access the $2000 allowance. TEI has requested additional itemized backup and an explanation of the additional devices from Ginter. Jim Ginter sent the additional items to TEI and MH is reviewing for approval today. MH created the punchlist for the project and is distributing the punchlist to the contractor today as well.

12/11/07 – Construction meeting was conducted and punchlist was created moving toward a final closeout. Punchlist items will take a few weeks because of the lead time in ordering engraved labels. Aside from some misunderstanding in the labeling requirements the work appears very thorough. Ginter turned over mark-ups. Ginter to submit pay apps and TEI to write a deduct change order for unused allowance.

11/30/07 – As promised Ginter reported today that this project is complete. TTC responded back to their email that we would use the const mtg for our punchlist and to advise about allowance usage on this project so TEI could write a deduct change order for closeout. TTC also sent all the closeout documents to Ginter for use on this job.

11/28/07 – Ginter provided an update today stating the the ID project was going well. TEI will setup a const mtg the week of 12/10.

11/09/07 – TTC distributed Pre Const Mtg minutes from last week. Ginter is on the job and ready to complete by the end of this year.

08/31/07 – TTC received word from HCFD that the insurance issue has been resolved. TEI awaiting word from HCFD so that this project can move into the Construction Phase.

08/15/07 – NR wrote: “Any idea about when this project is going to be ready for construction?” Bert( HCFD) responded: “I am still working out Insurance issues with Michael Ginter, he is working on getting me the correct Certificate of Insurance. Jim and I are working on getting the LEADS background checks completed.” TEI awaiting word from Hamilton County Facilities Department to move into construction phase.

08/10/07 – TEI awaiting word that the contract has been signed by Ginter Electric so that this project can move into the construction phase.

07/30/07 – NR received word from Bert Watts at the Hamilton County Facilities Department that the contract was sent to Ginter Electric last week for their signature. TE is awaiting word that the contract has been signed so that this project can move forward with the construction phase.

06/29/07 – TE awaiting word that the contract has been signed to that this project can move into the construction phase.

06/22/07 – Contract has been awarded to Ginter Electric. The contract has been sent to Mark Donnelly; TE is awaiting signed contract to proceed with pre-construction meeting.

06/15/07 – Hamilton County Facilities is reviewing the bid tabulation. TE is awaiting word about which contractor has been awarded the contract so that we can move forward with this project.

06/08/07 – This project opened for bid yesterday. TE is awaiting the bid tabulation from the Hamilton County Purchasing Department.

06/01/07 – This project is set for bid opening on June 7, 2007.

05/25/07 – The pre-bid meeting was held on site today. Those in attendance included Kevin and Steve Kallmeyer of Kallmeyer Electric, Jim Ginter of Ginter Electric, Nick Richmond of ThermalTech Engineering, and Walt Hendrick/ Mike Jackson/ Ken Caruso of Hamilton County. A site tour was given as well as a specification and drawing review. This project is expected to go to bid on June 7th of 2007.

05/21/07 – Project went out for bid on May 18, 2007. Pre-bid meeting has been scheduled for Friday, May 25 at 10:00am. Meeting place is the lobby of the Patrol Headquarters. NR contacted Captain Mark Hendrick to discuss working hours. It was decided that normal working hours would best suit this project because of limited access to certain areas of the facility. NR sent an email to Mark Donnelly informing him of this.

04/27/04 – Drawings for the Device Identification portion of this project are complete and will be present for Hamilton County review in the meeting today, April 27 of 2007. The Arc Flash Labels are at the printer and should be completed within the next 2 weeks.

04/20/07 – Arc Flash Labels are being dropped off to the printer next week. The Device Identification portion of this project is complete and the drawings will be complete next week.

04/13/07 – Single Line Diagrams have been established and Arc Flash Study has begun. TE found discrepancies with the As-Built drawings and what was found in the field so they are making another field visit today, April 13, 2007. This visit is meant to trace the source of the panels in the barns and out-buildings. There is an automatic transfer switch in the Property Room that needs to be traced also. Dan Myer of TE will also be on site to meet with a county employee to locate above ceiling equipment.

04/06/07 – Kick-off meeting was held. Project is moving along as expected.

03/30/07 – Kick-off meeting is scheduled for next Thursday, April 5th of 2007.

03/23/07 – Project progressing as expected. Kick-off meeting tentatively scheduled for the first week in April. TE to set up meeting with Hamilton County Facilities.

03/20/07 – Fieldwork is progressing and is about 80% complete.

03/14-07 – NR created project journal and filled in back data from previous meetings. Project awaiting signed SOSS to be returned to TE. 90% of field work has been completed for the Device Identification portion of this project. Field notes not inputted electronically per awaiting signed SOSS.

Sheriff HQ – Electrical Device Identification and Arc Flash Study Read More »

SHERIFF PATROL HQ Street Widening

09/29/10 – Project closed and archived.

08/16/10 – We talked to Debra Kuempel today. O&M’s were submitted and I believe sent to the County last November. We have been holding for the final change order. Kevin and Donna at DK agreed the Change Order Credit was going to be $5761 for this job. Laurie is typing, we will delivery for signature to DK today and then they can get their closeout docs in order and we can close this job.

08/13/10 – Payapps updated for both contractors. As Built dwgs completed by TEI. QCM needs to sign the change order and send to Bert.

07/28/10 – Check on DK change order work and approve as-builts for project completion.

05/26/10 – DK is installing the fiberglass pan in June. We are awaiting QCM closeout docs.

05/15/10 – TTC is working on closeout documents for QCM. We have the final payapp but I don’t know if we have the O&M manuals so I contacted QCM again to check the status.

04/26/10 – Project is complete save the fiberglass pan issue.

03/23/10 – DK got an okay to provide pricing for a new fiberglass drip pan for the panel as we wait for THP to work on better site drainage.

02/22/10 – TTC signed additional payapps for QCM and DK for payment on this job. We are ready to close it out. There is an issue about a ground fault alarm and wiring on the fire pit. DK said they may just replace the wire and be done with it.

12/31/09 – Debra Kuempel did the overnight work on the conduit sealant upgrade and I believe we are down to final closeout. We have a warranty issued with the pit having a grounding issue at the fire alarm panel. DK has sent a technician to repair.

10/20/09 – TTC sent out punchlist today to contractors with instructions to closeout project. We are accepting CO#09 for blacktop from QCM. We have to work out the $10,000 allowance with Debra Kuempel and the $7500 with QCM for this project to write the final Change Orders. The email included instructions to closeout and finalize change orders and allowances.

09/22/09 – The project is nearly complete. TEI will be performing the punchlist in the next few weeks. DK is going to be on site on Thursday to finish up their work. Queen City Mechanical submitted change orders for processing today. We received a new COR #8 for piping. TEi asked for more info on this change order. We should be able to close out in a month.

08/26/09 – Final tie-ins for both fire protection and fire alarm are being made. By the end of this week, everything should be 99% complete and ready for punchlist.

07/27/09 – Bert and Terry talked last week about having TEI modifying our permit to list the Fire Pit as existing equipment. TTC called but the Inspectors office was closed. I will try back again later. The County has asked for the CWW to submit their drawings and apply for a permit for the work separately.

06/23/09 – All the permit issues have been resolved. TTC contact QCM mechanical by email and phone to get an update on status of fire main trench. No update but TTC will check on 06/24 when he visits the site for the FA project. DK has not been back to the site since the new power was brought back online. We believe they will return when they work on the trench with QCM.

05/22/09 – DK has finished the transformer relocation. The building is back up on Duke power from the new transformer. The cables are being collected for pickup. Prus provided the new fire main and fire pit for us. QCM will be out 05/26/09 to begin trenching the parking lot for the remaining work on fire alarm and fire sprinkler work.

04/03/09 – TTC sent an email update to the team for the pit, given it is located in the parking lot. Tony is going to look at the final location. Bert and Tony to advise. Luckily, we talked about this happening in the pre construction meeting.

02/19/09 – GCWW has brokered a deal to have Ray Prus provide the water tap to the R/W for QCM from the new water main. Ford Development will build the pit from that location. We have asked for a credit from QCM for the smaller scope.

02/0509 – QCM informed us that a new water main is being installed in Hamilton Ave. I advised QCM to investigate using that main instead of the one we originally projected for use.

02/02/09 – TTC modified the project schedule and sent out for approval to all the vendors. Jackson questioned the actual shutdown and switchover date but TTC told him that was not set in stone yet. The City has approved the water permit. We are waiting on ODOT approval of the plans before digging.

01/05/09 – Payapp #3 came in for DK and ThermalTech approved and sent to Bert. This payapp went to Bert first which may delay this payment.

10/16/08 – ThermalTech sent profile drawing to QCM for submission to state. TEI sent new permit drawings to Debra Kuempel for permit application. DK is getting price from Duke for work on this project per the scope of work on the specs as TEI wrote.

08/29/08 – Contracts approved. Pre Const Set for next Thursday.

08/22/08 – No update from County. TEI inquired about proceeding. Tony answered that contracts will be in front of the Board next Wed. 08/27.

08/08/08 – Tony reported the Prosecutor has contracts for approval. They are pushing hard.

07/31/08 – County reported that all contracts are at Prosecutor’s Office awaiting approval.

07/30/08 – TEI has delivered all contracts to Contractors for signing. TEI sent stamped permit drawings to Queen City Mechanicals for CWW permit application. QCM stated that CWW will want permit tap fee as soon as permit is awarded. This process may be the longest lead item of the whole job.

07/18/08 – Pre Award Meeting complete. All contractors recommended for project. Debra and Queen City Mechanical both stated they understood the project, the schedule and agreed their price was valid for this scope.

SHERIFF PATROL HQ Street Widening Read More »

SHERIFF PATROL HQ Signage Upgrade

01/24/11 – TTC asked for a written letter from KFI to proceed with closeout as the punchlist is not fully complete as the scratches on the sign have to be touched up.

10/28/10 – We have visited the site several times as the foundation has been poured, electrical has been run and masonry work is ready to begin.

09/29/10 – Holding for State to complete road work.

08/13/10 – Payment 1 has been sent.

07/28/10 – TEI to approve payapp and send to Bert. It looks good, have to visit the site to see the sign.

04/26/10 – We are on hold until June.

03/23/10 – It has been reported that the sign is complete.

02/24/10 – John Brockman called with a question about backlighting the can. TEI will return the call.

02/05/10 – TTC visited Ernst signs and worked out final details on the sign building scheduled for April. TTC updated all parties.

12/31/09 – TTC submitted a permit answer to HamCo building inspections. The next step is theirs. We may have to resubmit to start the project again.

09/22/09 – The new street is very close to the sign. The County is working with ODOT to finalize the sign work. Our contractors are preparing a new shop drawing to the County permit office with the galvanized steel frame.

07/29/09 – No updates because Street Widening is still on hold.

06/23/09 – KF has not returned our call or emails about sign permit approval. At this time it is being held for review by Marty in HamCo Bldg Dept awaiting our clarification on how the sign post will be embedded into the sign base and what material it will be. We may need a meeting or conference call with KF and Brockman signs.

05/22/09 – Zoning has approved our sign permit. The bldg department is questioning the supports for the sign. Tom Speer is checking his design for us.

03/02/09 – Pre-Construction meeting held. KFI will order materials and store sign at HQ to allow invoicing. On hold until street widening is complete.

SHERIFF PATROL HQ Signage Upgrade Read More »

SHERIFF TARGET RANGE Match House Investigation

01/29/15 – County requested THP review the Match House walls.

02/23/15 – THP sent email with general recommendations and an opinion of probable cost.

02/24/15 – County requested a full letter report and authorized additional field work.

03/26/15 – THP anticipates publishing the final letter report.

03/26/15 – THP published final letter report.

SHERIFF TARGET RANGE Match House Investigation Read More »

PBS – Sound System Repair Project

03/21/06 – TEI asked for an engineering change order which covers extra time spent by ThermalTech during the construction phase and occupancy permit time on this project. Joe said he signed it and went on to his boss Eric Stuckey. This project is officially complete.

02/13/06 – TTC finally approved the closeout documents, final pay applications # 6 & 7 and as-built drawings for this project. The only thing left is TE request for additional payment.

12/02/05 – TE requested a revised final payapp reflecting $6200 change order that was approved for the north end zone speakers. All final paperwork and as-builts have been received from Durrell in hard copy and CD. TTC made a copy of this information and is sending all originals to Joe Feldkamp for his use included 3 binders of O&M’s required by spec. TE will have have a hard copy of the 1/2 sized dwgs, just the CD.

11/30/05 – Chris Schaeffer called to inform Terry that the County reached settlement with Ed Simon and his lawyer’s and that a court appearance would not be needed.

11/28/05 – Upon final check the sound system is working, the new speakers are installed and working and the final paperwork has all arrived including the as-builts for this building. TTC has to write an engineering change order for ThermalTech’s Extra Time and WJHW Extra Time on this project and submit it for payment for the year 2005.

11/14/05 – Durrell and TJ’s total change order totaled $6200 ($5600 + $600). Joe Feldkamp approved. TTC confirmed with both contractors. Chris Horrell and Scott have scheduled Durrell’s visit for this Wed 1/16/05. Work to be completed by Thursday. TE shall send out the hard copy paperwork to all vendors.

11/10/05 – TTC was contacted by Chris Schaeffer about a possible court appearance in December over the bidding of this project. TTC discussed County bidding procedures and current ORC requirements for bidding and how the Sound Engineer, Audio Contractor and Electrical Contractor was selected for this project.

09/12/05 – Pay Application #4 is being resent to TE. TTC will approve and send to County for payment. TJ delivered payapp to TE today.

09/08/05 – TTC emailed contractors about closeout for project and punchlist. Sound was excellent last Friday when TTC went to the Colts-Bengals preseason game. TTC sat in section 315 and was impressed with quality of sound and clearness of PA announcer.

08/09/05 – Durrell reported that, Tom and I went over these items and will have most knocked out this week prior to this weekends game. What will be left will have to do with getting QSC down to make the cosmetic changes to the amplifier control system to make it that much more user friendly and correctly control the amplifiers that are being displayed.

08/08/05 – TTC coordinated the final change order amounts with TJ Williams and will modify the change orders for final signing today. Both change orders are complete. TTC will deliver them by hand to PBS tomorrow and try to get Bill Meyer to stop down and sign them. Punchlist was compiled and emailed out to contractors (hyperlink below).

08/01/05 – WJHW and Durrell completed the punchlisting work. Ron Baker is going to send the punchlist to TTC for distribution. TTC talked to Scott Simpson about items that he needed added from his end and left a message for Joe about his items. The consensus appears to be that everything is very nearly complete and everyone is very happy. Hopefully this will lead to a quick closure and a working sound system ready for the season in a very short time period.

07/19/05 – We have reached resolution on the PBS Sound Change Orders. Amy will approve change order #1 8855.00 for the countertops and change order #2: 2,060.74 for restocking fees from TJ. TE will write the new change orders for these amounts and send them to TJ for signatures and then onto JF for signatures by the County. WJHW and Durrell have scheduled the Engineering Commissioning for this project on 07/27 thru 07/29. TTC will be out of town on Wednesday but will assist on Thurs/Fri as needed. Punchlist should be fine as Durrell and Scott Simpson have been working hand in hand during the project. TE and WJHW will supervise and TE will try to set up and Const Mtg on Friday for a final update on progress before we start the as-built drawings for this job. Durrell reported by email on 07/18/05:

Last week Durrell got all the speakers working (with only two exceptions) and wired to the correct amplifiers. The West amp room is complete, all racks laced and cleaned, all amplifiers working. The East we ran out of time Friday, but we have all amplifiers working with the correct speakers, we need to spend one day lacing up and minor cleaning.

We found one 2″ driver not working on the East side that will have to be accessed and one crossover on a full range speaker on top of the north end zone – each will require one day’s work.

The west club area is finished and working and the east is about two hours away (got held up due to a wedding party).

The control room is up and working. We had a MediaMatrix card fail (used backup for tuning) and Scott Simpson has to provide us with info where to mount the two computer screens and the Volume meter, both minor installs. The console and all the other equipment is in a functioning correctly including the software upgrades. We want to rebuild the control block that exist for the control screens for QSControl – some coordination will need to exist between Scott Simpson, Tom Moores and we would like Ron Baker’s input – when the commissioning is done.

Durrell will schedule two days prior to WJHW’s coming to PBS for their commissioning to be sure all of these minor items are finished. We are waiting on Ron Baker for that date (date has been set see above)

07/08/05 – Eric Stuckey, Joe Feldkamp, Diana Craynon and Bill Meyer called today to inform me that the change order has be stopped and no work will be done on it and it is most likely canceled until later. We informed TJ Williams and TTC is supposed to cancel Monday’s field trip to work on it.

07/05/05 – TTC emailed Eric Stuckey the final Change Order #01 cost including the cabling and the countertop for approval. PDF. TTC met Chris Schaeffer, Scott Simpson, Steve Durr, Sam Kinman and Ed Simon and his associates downtown today to supervise a field visit and walk through with the County for the County lawsuit.

06/27/05 – TTC sent out CD’s to HamCo for law suit.

06/23/05 – TJ Williams sent the revised ACO out today. PDF. Terry and Joe asked for TJ to redo the change order to reelect the credit that the County will be receiving in place of the speaker parts that won’t be installed. TTC and JF will then talked to Amy about writing a change order to finish the project off with the cabling upgrade. The Const Mtg verified that many, many of the issues with the speakers were resolved by fixing wiring and termination points. ThermalTech believes that by knowing this it is a fair inference that the 3000 foot cable splices are probably not infallible.

06/22/05 – Const Mtg #02 was held. Durrell reported that all base work is complete except for software upgrade on MM. Durrell offered to do all the CO work except for the cabling for the $50,000 allowance. TTC agreed that this work be a fair barter. We decided to accept the countertop change order from jb schmitt. We will pursue a change order to get the cabling issue taken care of this year and Joe and TTC will talk to Amy about it after TJ provides an update T&M price NTE for the work.

06/16/05 – TTC visited the site earlier in the week with JB Schmitt and they turned in a quote today for the new countertop work at PBS. TTC forwarded the quote to the team for a decision. Countertop = $5695.00 and New Window = $3160.00.

06/06/05 – Durrell sent an email request Topper be added to all correspondences on this project. TE forward to Joe Feldkamp for approval. PDF.

05/31/05 – TE tried to reach WJHW for a conference call to discuss moving forward with additional bidding on Change Orders for this project. CO# 2 and CO# 4 are significant and may have to be bid out separately. TJ Williams called today to see about CO approvals. TTC sent the Allowance email to Bill Meyer. TTC should have sent last week when it was approved but somehow that didn’t happen. TE and WJHW still need to talk to Joe about Club Level work and scope.

05/24/05 – TE issued a recommendation letter to PBS about Change Orders for this project. TE spoke to Durrell and told them they must proceed with scheduling on the assumption that the Change Orders # 2 and # 4 are not approved. The County will issue a formal approval as soon as it can. This may lead to scheduling conflicts later near substantial completion but bidding and change order policies must be adhered to for this project. PDF

05/17/05 – Consultants and JF are in consultation about approving change order request. TE has requested direction from their sub WJHW on what is essential and what is not. First TJ payapp is approved and sent to JF.

05/11/05 – TJ submitted 5 change orders today to the project. PDF TE setup a construction meeting for Thursday at 1:30 p.m. to discuss project progress. TJ contracts are signed and in security for contractor to pick up.

04/27/05 – Contract has been approved by the Commissioners. TTC advised the contractors that the contract and PO would soon be in their hands. TE and WJHW will have subs complete by the end of the week.

04/26/05 – WJHW has submittals for AV work on the job. TE has reviewed the submittals fro EC compliance and found no errors so we will approve them with “No Exceptions Noted” to that end, we have told TJ the same. TJ inquired about contract approval and TE told them Wed at Board meeting, we should know. Please advise us when you hear information about Contract.

04/22/05 – TE received submittals for TJ yesterday. TE is checking for EC items. TE shipped one to WJHW for AV items. TE has delivered all dwgs and specs to TJ for permit application. JF reported that contract is in front of board for approval on 04/27/05. Everyone is still working at their own risk to date. Durrell has sound system working in bowl for weekend draft picks. County Prosecutor asked for some video footage of splice problems in the amp rooms. PBS reported that some have been fixed but other still remain to be documented and that Durrell may know best which ones to document. JF and TTC communicated about this pre-work in email PDF.

04/19/05 – TE sent out an email stating the Durrell may be doing some additional work in the Club levels that is above the scope of work outlined in the contract. Monies for this work shall be determined later.

04/18/05 – TJ sent their employee list into the County for this project. PDF. JF reported that contracts have been submitted and the project is up for Board approval on 04/27/05.

04/12/05 – TE had TJ resign new contracts forms and delivered to Kerry Dowling for approval. Kerry said that she would sign these on 04/11/05 and TE would have City Dash pick up the newly signed contracts and have them delivered back to Joe Feldkamp for submission to the County Commissioners for approval. TE sent 3 sets of dwgs to Dallas for WJHW to sign for TJ to turn into IBI for permit sets. TE and JF told TJ at the pre construct mtg on 04/11/05 that all work done by Durrell and TJ before receiving the contract and the PO is “at your own risk” type work.

02/23/05 – TE delivered contact to Joe Feldkamp. TTC and JF discussed contractor over phone and coordinated paperwork due to prosecutor. JF will submit contract for prosecutor review. TE will hold on notification to contractors until all paperwork is finalized. TTC would like to see 2 week turnaround in contract to keep scheduled intact.

02/22/05 – TE has received all required bid paperwork and finalized the Contract. Contract, Drawings, Spec Books and Drawings will be sent to Joe Feldkamp today.

02/16/05 – County and PBS indicated to proceed with Base Bid and Alternate 2 for this project.

02/16/05 – TTC and WJHW discussed the Alternates from the bids and are basically recommending that the County accept Alternate # 2 at this time and wait on Alternate # 1 because of the unknown variables included with updating the system. TE recommends fixing all the existing problems first before adding a new layer of master control that my contribute new and undiscovered problem of us to troubleshoot in the field plus upgrading to the BIAMP system will add additional dollars to the existing SOSS as this is a scope change for engineering (WJHW is working on an adder price). We will write the contract with Alternate #2 for the time being.

02/08/05 – Bids opened. TJ Williams appears to be the low bidder. TE has contacted contractor for additional paperwork and will begin contract work immediately. County needs to provide a signed bid evaluation form with Alternate recommendations for contract.

01/25/05 – Addendum 3 distributed. Durrell asked a new question for Addendum 4. The bid was extended to February 3, 2005.

01/21/05 – TE coordinated with WJHW and County to extend bid date one week and to send out Addendum 03 on Monday with updated information for bidding and alternate. Purchasing Department instructed TE to contact ICB Audio via email about non-inclusion into the accepted bidder’s list for this project.

01/20/05 – TE distributed Addendum 01 on 01/11/05 and Addendum 02 on 01/20/05. Addendum 03 should come out on 01/21/05. TE has written a rejection letter and given it to Purchasing to give to ICB as they do not meet the Professional Stadium Experience Requirement on this project. The SoundCom qualifications have been sent to WJHW for review and we are currently waiting on SoundCom to confirm a couple of questions about which office will serve this project but they most likely will be approved for bidding as they do meet the quals. TTC asked if the bid should be extended since SoundCom is being added. TE is awaiting the County’s decision. The second prebid was attended by about 8 contractors. Muzak declined to bid and left the prebid after we stated that OEM equipment must be used for repair.

01/19/05 – Prebid is finished. Addendum # 01 wads distributed. Addendum # 02 is going out tonight. Addendum # 03 is scheduled out tomorrow. ICB will not be an approved vendor. TE has to provide a letter to Purchasing for the use, modify and send.

01/14/05 – Joe Feldkamp called to inform TE that because the prosecutor wants a firm number for cost to provide as-built drawings that we can change the bid for to add an alternate to have the AV contractor provide a complete set of as-builts encompassing the entire scope of work at the stadium. TE shall modify the bid form accordingly.

12/24/24 – TE invited Audio Specialist Contractors. Project Manual is on the street, on schedule. Prebid set for January 5th. WJHW will be in town for the prebid. Everything appears to be set for bidding att his time.

11/04/04 – TE found and sent the AV drawings to WJHW today. Final design is still scheduled for final delivery on 12/08/04.

10/25/04 – WJHW sent an informal report from the field trip last week. PDF

10/19/04 – TE, WJHW, PBS and HamCo had a meeting and set the following schedule for this project (see below)

10/19/04 – TE and WJHW met onsite with the owners and ironed out the scope of the project, schedule of the project and the expectations of the project. WJHW will begin design and target first week of December for final engineering documents. TE will release minutes in a follow up email. Contract will be bid to a local EC with a Audio Specialist assigned as a sub.

10/15/04 – TE will meet WJHW onsite on Tuesday for kickoff meeting. WJHW will be onsite late Monday afternoon. They have coordinated their time with Scott Simpson.

ThermalTech solicited consultant bids and wants to team with WHJW from Texas for this project.

Conference call on August 17 between Eric Brown, Bob Bedinghaus, Joe Feldkamp and Terry Cannon with WHJW was held to discuss itemized consultant cost and scope of consultant work on this project.

TE is awaiting a signed SOSS from the County.

The County is awaiting a one page report from WHJW outlining the added benefits of using WHJW on top of the Durrell report.

Project scheduled to be signed in August 04, Designed in Sept – Oct 04, Bid Nov 04, Awarded in Dec 04, Construction Jan 05.

PBS – Sound System Repair Project Read More »

PBS – Occupancy Redistribution Project

03/20/06 – Joe approved TEI’s cost on the ECO for Sound project. This project is officially complete and ready to be archived.

11/30/05 – After speaking with City Permit office they confirmed that TE did pay for these permits. TTC called Randy this morning and told him that these permits were paid for on 10/18/05. TTC is awaiting a call back to clear this up.

11/25/05 – Randy Campion called to inform TE that there is a remaining balance on these permits. TTC called the city to see what that cost was because TE has already paid for the new permits with a check. Once this is cleared up Randy will send new Certificates of Occupancy.

10/18/05 – All revisions have been accepted and approved by the City. New permits costs = $354.00. New occupancies have been set to 1021 (East Club) and 986 (West Club). According to Randy Campion once the permit is paid for, which TTC did today, the permit will close and information will be sent to Fire Dept. They will issue a new occupancy for private club events. to PBS.

09/28/05 – The City received all the information from Cole & Russell but need it properly inserted into the permit dwg sets. TTC will stop at the permit office and manually do this on Friday or earlier if possible.

09/20/05 – After the City sent the letter emailed by TTC to PBS yesterday requesting additional egress information, TTC talked to Cole & Russell about this information. C&R believes that they already have all that information collected from the sliding door project and will call Carl Graeber and discuss directly with him. They can get all that information to the City on Friday or early next week. TTC will check back with city and C&R about progress at that time. We believe the city will accept this and process the permit app immediately thereafter for final inspection.

09/08/05 – TTC contacted city. Permit should be reviewed by 09/13/05. TTC will check back at that time.

08/25/05 – The permit is still being reviewed by the City. TTC will continue to check on status.

0815/05 – TTC met Randy Campion at the PBS site on Monday, Randy approved the 821 and 851 increased occupant load and will sign the CO paperwork and send it to PBS. After the meeting, PBS said that the 30% OA was not a problem so that they want even higher occupant loads. TTC turned in another set of prints with the higher numbers of 986 and 1021. The city made us turn in for all new permits: 2005P06669 and 2005P06670.

07/18/05 – City called with Approved Permit numbers today. Permit was split up into 2 permits 2005P05544 AND 2005PO5589 ($284). TTC will pick-up permit on Tuesday morning. Inspector, Randy Campion has to come to the site to approve and give us a new CO for the space. This will be coordinate with HamCo & PBS in the next couple of weeks.

06/30/05 – TTC got GD to sign occupancy permit drawings in regards to HVAC OA requirements. TTC submitted for permit. Permit # 2005P05544. TTC informed all parties that permit can be checked at www.cincinnati-oh-gov at anytime. Amit was also promoted to Project Manager, so we are unclear if he will review this permit.

06/16/05 – Eric called today and TTC reported that Amit had returned one of his phone calls stating that he was seriously behind in permit reviews. With that knowledge, TTC stated that we should just go ahead and subject a revised CO application and talk to him them as opposed to conferencing in with him early.

06/06/05 – TTC sent an email outlining TE’s field findings to Joe, Sam and Eric. TE need direction from PBS to proceed on next level or work.

06/03/05 – Sam Boehringer of TE collected field data to update actual occupancies of the space.

05/25/05 – Eric Brown setup a meeting with the CFD department about occupancy requirements of the club level space.

PBS – Occupancy Redistribution Project Read More »

PBS – Deep Well Pump Replacement

03/23/06 – TTC spoke to John Wagner of Moody’s today and here is where the problem is: the actual repairs cost $15,573 not $6573, the 6573 +the 9000 already paid = the total cost of repairs on this job. This means that they are still giving you back $4427 on the job. John outlined this in a letter in September which I am having faxed to me. With this information, I will redo the paperwork and send it up to John for use on completing this project. I have to write a new change order, allowance usage and final pay application to make all the numbers work out right.

03/20/06 – TEI received final paperwork on this project today from Moody’s. This will be forwarded to Joe for payment on this project. TEI to begin phase II service contract immediately.

02/16/06 – Moody contacted TEI to request AIA forms. TTC sent them out in US mail for their use. They should complete these, notarize them and get them back for closeout.

02/06/06 – After an inquiry by Sam Kinman, TTC found the payapps sent to ThermalTech for approval. They were approved by Sam on 11/21/05. The problem is that they are not on AIA invoices which means there is no where for TTC approve. Assuming they are approved by TTC on these forms, the Contractor still has not turned in standard county documents for project closeout. TTC will forward a copy to Moody’s and ask for return of these documents. TTC completed a full packet of information required and mailed to Moody’s today via US Mail. TTC will follow up with a phone call today as well.

11/30/05 – Sam Kinman reported today in an email back to TTC that the deep well pump replacement job is complete. Since TE wasn’t used very much during construction, TTC assumes the punchlist is fine and no additional work needs to be done. TTC will archive the project from the database and closeout the project number. TE has never received a payment to approve, nor the final County paperwork to approve for that payment, nor manage any of the allowance monies. All this will need to be done before the project is closed out in the County’s books.

08/08/05 – TTC contacted the County about status of the Deep Well Pump Contracts. The previous entry does not state that the contracts were sent to PBS.

07/18/05 – Bid were opened. Moody was apparent low bidder at about $29,400. $20,000 in Alternates can be taken (ALT #1 and ALT #3). TE has contract written for $49,400 and will give 4 original copies to PBS for approval with Board. Bid PDF

07/05/05 – TTC worked on July 4 to get Addendum 2 complete and sent it out for distribution. PDF

06/27/05 – TE worked on Add01 and it will go out to the Contractors on 06/28/05. PDF

06/13/05 – TE sent out Project Manual for bidding. PDF

06/06/05 – Comments received from Sam and John Wagner of Moody in Dayton. TTC will update Project Manual and prepare for bidding ASAP. PBS talked about including a 3-year service contract on top of the bid. TE has done these in the past and can add this scope to the project if so directed by the County for bidding. This would be an engineering scope change to this project but it makes very good sense to include it now (12 hours x $80 = $960) and that includes the contract modifications for the Alternate bid to take optional years.

06/01/05 – Comment received from Joe and Eric. Nothing from Sam yet.

05/30/05 – TTC sent a project manual out for review over the weekend to PBS and County. Once comments are received, TE will distribute to public for bidding. All dates must still be coordinated with HamCo Purchasing.

05/26/05 – TTC contacted Moody’s for some specific questions about parts replacement. The Project Manual is built for front end. TTC needs to add dwgs and mechanical section. Bid Form needs to be modified for this job.

05/17/05 – The team had serious discussions about project schedule today. PBS re-iterated their concern about flooding. TE provided a timetable for construction that appeared not to be acceptable to PBS. TE had discussions with JF about project and will try to speed up project manual creation significantly to lessen risk. It is TE’s belief that County Purchasing has already decreed that this project does not meet Emergency Status.

PBS – Deep Well Pump Replacement Read More »

PBS – Pro Shop Metering Project

03/29/06 – TTC reviewed the billed KW and KWH to the PBS Pro Shop and the numbers looked good. The pro shop is using less than 1% of the total power consumed at the building.

KW KWH
February

50.91 21,863
January

34.91 28,950
December

79.91 25,448
November

59.28 16,077
October

72.30 14,661
September

63.67 16,528
August

53.30 4,166
02/01/06 – TTC check on the meters and to review monthly billings at the site. The meters appear to be reading in the Megawatts which seems really high at first glance. TTC to reconcile with actual building data.

11/16/05 – TA visited the site today. Reviewed punchlist and determined that Bond Electric has not completed the issues described on the punchlist. TE called Bond to tell that them that can’t get paid until these items and the final paperwork is complete.

11/15/05 – As-Built drawings for this job were turned over to Wayne Trent of HamCo Facilities today.

06/17/05 – Const Mtg was held at PBS. Sam did not attend. Equipment is not on site yet but Bond is ready to get to work as soon as it arrives.

02/28/05 – Purchasing called to inform TE that Bond does NOT have a performance bond or check submitted for this project. We should not let them begin work without this paperwork in place. TA to confer with Jack Boland today and emphasize the need for this check immediately.

02/10/05 – Contracts and Bid Results are in County’s hands. TE awaiting further direction on this project.

11/17/04 – Bid Results

10/12/04 – Project is out for bidding.

Addendum#1 distributed.

Addendum#2 distributed.

Addendum#3 distributed

PBS – Pro Shop Metering Project Read More »

PBS – Deep Well Pump Service Contract

02/02/07 – After many contract revisions, phone calls and problems, the Prosecutor finally allowed preventative only maintenance contract that Kerry wrote and gave back to everyone to use. Other repairs and emergency repairs must be bid our as prevailing wages. TEI does not and will not every agree with this approach. We took prices for many other services to save the County money but those were not accepted as part of this job by Hamco Prosecutors office.

01/10/07 – TTC got Kerry’s new email address and forwarded the revised contract to her for any final changes that she would like to make. Kerry confirmed that the packet was received at her office.

01/08/07 – TTC hand delivered the final contract with Kerry’s marks to security for Jenny and Joe to pick up and resubmit to the Prosecutor’s Office.

12/26/06 – TTC will finalize the deep well pump contract this week.

03/29/06 – TEI has not heard from Daktronics with a registered service repair list yet so I called and got Greg’s email and sent him the request again.

03/21/06 – TEI finished the SOSS and will drop it off at the HamCo Facility Department on Wednesday for this project.

PBS – Deep Well Pump Service Contract Read More »

PBS – Energy Study

03/20/07 – Project ready to archive.

11/30/05 – TTC and GD have to meet internally to review the 10/11/05 findings and energy usage. GD believes there can be savings found in schedules and space control but we will need “buy in” from facility department to implement. TTC has to setup meeting with GD to review other items but County end of year crunch on projects has dampened progress. All work will be done by end of year.

10/11/05 – TTC and GD met on site and reviewed the whole facility with Sam, Joe, Eric and the financial manager.

05/10/05 – Kickoff meeting for project with JF, TTC.

PBS – Energy Study Read More »

PBS – Video Wall Replacement Project

12/19/07 – Nor Comm has provided the AIA closeout paperwork, warranty letter and payapps. TTC signed and City Dashed it to Joe Feldkamp. This project is complete.

09/03/07 – TTC has received and approved the O&M’s. TTC is hand delivering the box of O&M’s and final payapp to PBS tomorrow at 9am at the Deep Well Pump prebid.

08/28/07 – TTC contacted Nor-Com again about final payment via email with a Read Receipt.

08/20/07 – Nor-Com contacted Joe today about final payment. TTC emailed Joe back station what happened to Payapp #2 as listed below. To date, we have not received any additional paperwork.

07/02/07 – TTC has contacted Howard Milkis and Nor-Com several times for closeout on this project. No response to TEI. TTC will try to contact the office directly today and find out how we are going to close out this project.

05/14/07 – PBS did not use TEI service much at all on site during this project. TEI has been in contact with Joe and Scott numerous times during construction as things were going well. TEI contacted owner today for punchlist and closeout items for Nor Comm. As far as TEI knows, this project is complete.

03/30/07 – TE received submittals for review and promised to work on them this week. Nor-Com has a schedule forthcoming.

03/16/07 – Scott and Joe held a kickoff meeting. TTC to follow up and publish some const mtg notes this week. A second Const Mtg is to be scheduled. PBS would like TV in before draft day.

02/13/07 – All contracts and information is in the Prosecutors office for review. Comments have been added and the contract should be approved very soon. TEI provided a copy of the bid results to Kerry Dowling per her request last week. Joe Feldkamp is following up with the Prosecutor Office.

01/30/07 – TEI finished the revised contract and returned it to PBS for use on this project. Now TEI is waiting for approval and signatures to move into a pre construction meeting.

01/10/07 – TTC hand delivered the contract based on the Base Bid cost to Joe for submission to the Prosecutor’s office. TTC included a $2500 allowance in the project after the bids were opened.

12/26/06 – TTC will finalize the deep well pump contract this week.

PBS – Video Wall Replacement Project Read More »

PBS Video Switcher

10/26/09 – Final paperwork is received. TTC approved and mailed to Joe.

09/22/09 – Project is complete. We have approved payapp #2. Once all the closeout paperwork has been received and training is complete. We can close out this project.

08/25/09 – One payapp has been approved. Punchlist has started. Training continues.

07/29/09 – Project has been bid and awarded to Rosco. Work is proceeding and Chris Williams will be able to check in on progress on August 4th when he visits Cincinnati for the Brewers game.

06/23/09 – This project is in contract approval stage at HamCo.

PBS Video Switcher Read More »

PBS Z-Ramp Replacement

09/14/09 – Additional documentation has been sent to Kerry for contract approval.

08/25/09 – Joe needs additional bid information for the project. United needs to provide final bid paperwork to Joe.

0729/09 – Project has been bid. Prices were tabulated and sent to bidders. Final contract was $16,300 and included $500 in allowance monies. TEI has written the contract and given to the County for signing.

06/23/09 – This project is out for small project bidding.

PBS Z-Ramp Replacement Read More »

Parkhaus Garage Assessment

September 7, 2011 THP sent assessment report to County

THP anticipates completing the report by August 5.

July 25, 2011 THP completed all field survey.

Assessment placed on hold until Ram completes stair tower work.

THP anticipates field work in next two weeks and report to be complete by June 30.

April 26, 2011 SOSS approved.

County reviewing SOSS.

April 18, 2011 THP provided requested SOSS to complete garage assessment for the Parkha

Parkhaus Garage Assessment Read More »

Northside MR/DD Masonry Review

THP closed out project.

October 29, 2010 THP provided a summary letter of masonry work.

THP anticipates publishing a letter to GBBN documenting field condition on October 29, 2010.

October 14, 2010 THP notified GBBN that lintel repairs were not recommend and THP will follow-up with a letter documenting the field visit.

September 29, 2010 the County, GBBN and THP met to review the lintel condition of the west wall of the Northside MR/DD facility.

Northside MR/DD Masonry Review Read More »

DDS-Beckman Adult Center Change of Use Remediation Project.

This is second SOSS for overall project. This second SOSS is to await results of complete code investigation and response from Colerain Fire Department to determine complete scope of work for project.

This project was determined to have ThermalTech as the lead design professional. GBBN is a consultant only.

5/17/10- GBBN received final Structural Analysis for Beckman Change of Use Code Review.

5/25/10- Arcodect delivered final Code Review for implementation into Permit Set of Construction Documents.

5/26/10- Final Permit Set of Construction Documents printed, signed and stamped. Set to be hand delivered to TEI at the Partnering Meeting for issuance to the Hamilton County Planning Department.

6/4/10- Issuance of ITB#047-10 by Hamilton County Purchasing Department.

6/14/10- Attend Pre-bid Meeting at Beckman Adult Center.

6/15/10- Issuance of Addenda #1 with Pre-bid meeting minutes.

6/23/10- Bid question sent directly to GBBN. Bidder instructed to send question to Purchasing per the bidding documents.

7/1/10- Building Department Response Letter received from TEI with two items concerning occupany separations. Building Department requesting drawing showing Use Group separations, net/gross areas and occupancy locations on floor plan.

7/02/10- Responses for Building Department Response Letter received from Wayne Meyer at Arcodect.

7/19/10- Newly created Occupancy Summary Drawings for Building Department Response Letter delivered to TEI.

9/15/10- Construction meeting was held.

9/27/10- TEI announced the Plans Examination was completed and approved for Building Permit by Hamilton County.

1/27/11- TEI and Kevin Maue confirmed the permit is now closed on this project. The Certificate of Occupancy and the Colerain Township Fire Department Letter of Release have been obtained.

1/27/11- Kevin Maue indicated at the Partnering meeting this project can be archived.

DDS-Beckman Adult Center Change of Use Remediation Project. Read More »

DDS-Beckman Adult Center Change of Use Code Investigation

3/19/10-Met with Jim Bowman, Colerain Fire Department, and Kevin Maue at Beckman Adult Center for walk-through on current renovation project.

3/20/10-Kevin Maue requested SOSS be submitted. This is first of two SOSS’s for this overall project.

3/21/10-Preliminary Code Investigation performed and submitted to Kevin Maue by email.

3/23/01-Fee proposal from Arcodect (code consultant) received. GBBN spoke to Cindy Rutherford, Hamilton County Building Department to discuss Change of Use requirements and submissions.

3/31/10-Schedule of submissions to Hamilton County Building Department submitted by email to Kevin Maue.

4/1/10-SOSS to be revised and re-submitted showing THP as a structural consultant to GBBN for any seismic implications per directions of Kevin Maue at Partnering Meeting.

4/7/10- GBBN met with Kevin maue, Terry Cannon (TEI) and Tom Frimming of Communale Fire Protection to review proposed AFSS implementation.

4/14/10- Signed SOSS without Ralph Linne’s signature and approval delivered by Kevin Maue to GBBN.

4/27/10- Signed SOSS with Ralph Linne’s signature and approval delivered by Bert Watts via email to GBBN.

4/27/10- Bryan Korb of GBBN assigned to project. Bryan to meet with Wayne Meyer code consultant at Beckman on Thursday and Friday for site investigation

4/29/10- GBBN to meet with owner, Colerain Fire Department, and Hamilton County Building Department to review building and change of use scope.

5/12/10- Kevin Maue announced ThermalTech Engineering would be the lead design professional on this project and GBBN would be the consultant. GBBN established estimated hours for completion to TEI for SOSS.

DDS-Beckman Adult Center Change of Use Code Investigation Read More »

DDS Signage Refacing

10/01/09 – Kevin Maue of MR/DD contacted GBBN about the pending name change as mandated by the State of Ohio. Sign letters on 1520 Madison to be removed as part of ceremony and will be handled as a purchase order. The signage refacing of all other sites will be on a SOSS through the Partnership contract.

10/05/09- ASI Modulex was approved to handle the purchase order work for 1520 Madison based on a submitted quote to MR/DD.

10/07/09-Existing electronic drawings sent to ASI for signage permit with City of Cincinnati.

10/23/09- Shop drawings for 1520 Madison approved for layout and lettering style.

10/30/09- Signage Refacing RFP sent to four selected bidders.

11/24/09- Adams Signs was selected for Signage Refacing and P.O. 536683 released.

12/08/09-1520 Madison sign permit approved. ASI
to order building sign letters.

1/04/10-Adams Signs re-submittal shop drawings approved.

2/19/10-Adams Signs has completed all installations. Kemper Meadow Road sign has bleed through of old signage.

2/22/10-Email sent to Rick Cain of Adams Signs about corrective measures at Kemper Meadow Road location.

2/25/10-Received signed SOSS from Bert Watts at monthly partnering meeting.

3/15/10-Resent email to Rick Cain with photos of Kemper Meadow. Rick claimed the corrections would be completed soon.

4/3/10- Email sent to Rick Cain of Adams Signs about corrective measures at Kemper Meadow Road location.

4/10/10- Rick Cain called to indicate Adams Signs very busy but will try and expedite completion of remediation measures to Meadow Road location.

5/19/10- Kevin Maue sent an email to Adams Signs indicating Application for Payment non-payment until corrective work is accomplished at Meadow Road location.

6/18/10- Notified Adams Signs to submit warranty information to comply with close-out documentation.

6/23/10- Sent Invoice from Adams Signs to Kevin Maue.

6/24/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

6/29/10- Rick Cain called to indicated work is commencing to author standard warranty details.

7/28/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

7/30/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

8/24/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

9/27/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

10/25/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

11/25/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment.

12/14/10- Contacted Rick Cain (copied Kristal Dadisman) by email to comply again with the warranty requirements for closeout of contract and release payment. Rick Cains email was returned as undeliverable.

DDS Signage Refacing Read More »

MRDD – THOMAS KIDD CLASSROOM ADDITION

02/14/08 – Punch list submitted.

02/13/08 – CRA sent additional service signed 2/13/08 to Bert

02/13/08 – TEI attended the const mtg today for MRDD. EDI is almost complete. Additional concrete will be installed around the new air handlers.

12/07/07 – CRA job meeting held on 12/05/07

11/14/07 – CRA received and approved shop drawings and substitution request for automatic door operators.

11/10/07 – The construction has commenced.

11/01/07 – Pre-construction meeting was held. See Meeting Minutes below.

10/26/07 – GC/EC submitted revised insurance certificate. GC/EC contracts have been approved approved. HVAC contract is still pending.

09/28/07 – Awaiting GC/EC to submit revised insurance certificate for final executed Contract.

08/16/07 – Contracts submitted 07/31, CRA received comments, re-issued 08/16.

08/02/07 – C+RA and TE submitted the Building Permit Application to the Village of Evendale Building Department.

06/25/07 – Addendum issued. Bids are due 07/02/07.

06/15/07 – A pre-bid meeting was held on location yesterday, June 14, 2007. This project is set to open for bid on June 26, 2007.

06/08/07 – This project has been sent to Cole & Russell for review. TE is awaiting comments back.

04/27/04 – Final review meeting is scheduled for next week.

04/20/07 – Updated drawings are being sent out today, April 20 2007.

04/13/07 – Project is progressing as expected.

04/06/07 – Preliminary set of drawings were sent to Architect today, April 6, 2007. Awaiting review comments.

03/30/07 – Final field work has been assessed. TE working on design.

03/23/07 – Project is progressing as expected.

03/20/07 – Kickoff meeting complete. Check CRA for updates.

MRDD – THOMAS KIDD CLASSROOM ADDITION Read More »

Scroll to Top