CH – B-95 Facilities Accounting Renovation

PM: Mike Murphy
05/25/21 SOSS Submitted to County
06/25/21 Meeting Scheduled for 7/13
07/13/21 Meeting occurred.
07/16/21 SP-1 and SP-2 sent to county with two option.
07/29/21 Meeting scheduled to review options.

08/26/21 Layout settled. Waiting pricing from furniture vendor.

10/13/21 – Site visit to confirm existing conditions with Champlin, Thermaltech and County.

10/19/21 – Final SD set and Estimate uploaded to Archibus.

12/14/21 – Signed SOSS received for DD thru CA.

02/24/24 – Permit applications

03/31/22 – Building permit picked up and delivered to County.

04/28/22 – No update.

05/26/22 – No update.

07/28/22 – Building and IBI inspection scheduled for 8/4.

08/25/22 – Final building and IBI inspections preformed.

CH – B-95 Facilities Accounting Renovation Read More »

Comm Center – Building Masterplan

05/22/21 – SOSS Submitted to County
06/02/21 – Received signed SOSS
08/09/21 – Meeting held with users to review scope.
08/26/21 – County said to let THP look at floor loading for this work. OK to get them involved now. Previous work created a lot of penetrations in the existing floor and new furniture was heavy. THP to review. New furniture should be less substantial than existing spaces.
10/28/21 – Keep masterplan work in place because this building will remain in the county portfolio for repurposed training facilities.
12/14/21 – No Update.
02/24/22 – Combined Estimate required. need to schedule a meeting to resolve scope overlap.
03/31/22 – SD plan of Combined 2022 estimates created. Meeting is needed to confirm final SD scope.
04/28/22 – We discussed the scope in the Admin Office spaces? Were the Radio Room involved? and we decided that we have not. Should we include Mission Critical involved in this report? Kitchen and Locker room are included.
05/26/22 – Finalizing estimate.
06/30/22 – Combined scope plans provided to TEI for estimate. Finalizing estimate
08/25/22 – SD set sent to HC. Plans need further broken down and resent.
09/29/22 – Site visit scheduled for 10/11.
10/27/22 – Scope refined after field visit. Owner Review Issuance scheduled for 11/11.
12/15/22 – Masterplan drawings need to be changed to reflect current project. waiting until bids are accepted to update according to which alternate is chosen.
01/26/23 – Updated plans will be completed by end of next week.
03/30/23 – Updated plans and estimate uploaded to Archibus.
04/27/23 – No Update.
05/25/23 – No Update.
07/27/23 – No Update.
08/31/23 – No Update.
09/28/23 – No Update.
12/07/23 – No Update.
02/29/24 – No Update.
03/28/24 – No Update.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – No Update.
08/29/24 – No Update.
09/26/24 – No Update.
10/31/24 – No Update.
06/26/25 – No Update but keep on list per HC.
03/26/26 – Leave on list.
07/30/26 – OK to Archive, RT

Comm Center – Building Masterplan Read More »

TPC – Commissioners Conference Room Upgrades

04/30/21 – SOSS Submitted to County
05/11/21 – Signed SOSS received.
06/23/21 – Meeting on site to review scope. Champlin finishes scope removed. Light fixture selection and photometrics to be done.
07/29/21 – Sconce selection is made. acoustical selection is not required. Researching main light fixtures.
08/11/21 – Provided cutsheets for suggested fixture replacements.
08/18/21 – County provided feedback on fixture selections.
10/27/21 – Draft Rendering/Photo provided to County. Fixture cuts provided to Thermaltech for photometric calculations.
12/14/21 – No Update.
01/26/22 – No Update.
02/24/22 – No Update.
03/31/22 – No Update.
04/28/22 – No Update.
05/26/22 – No Update. Ready to archive.

TPC – Commissioners Conference Room Upgrades Read More »

2022 Project Request Cost Estimates

04/21/21 – Cannon created post from Bert Watts email for 2022 Project Request.
05/27/21 – Bert sent the preliminary list out to the partners for SOSS authoring. Kickoff meeting next Tuesday with TEI, THP, and Champlin.
06/11/21 – Started research on 230 MEP upgrades including new above grade boiler and chiller room.
06/22/21 – Met at Comm Center to discuss project scopes for repurposing and academy rework.
06/25/21 – User meetings held to discuss the scope for most Champlin lead estimates.
07/28/21 – Work continues on the individual estimates. Some will be complete by July 31 and all will be complete by August 31. Cost, data and scope still coming in the CH controls, Mechanical Yard items which are the “biggies” for TTC. Champlin is making progress. Smaller estimates will be done by 7/31, the rest by 8/31.
08/20/21 – Champlin has provided almost all of the floor plans we need to complete estimates. TEI is currently putting together the cost and scope documents for the remaining estimates.
08/24/21 – Teleconference held on the 230 East 9th estimates between all partners to finalize the scope and estimating. TTC followed an update later that day with additional information after speaking with BW about the #2105 estimate.
08/26/21 – TEI – work continues and we plan on making the 8/31 completion date as discussed. Estimate and drawings are being uploaded daily.
10/28/21 – Project complete. A couple of final projects have been added and updated to the list.

2022 Project Request Cost Estimates Read More »

P&D – Restroom Renovation

PM: John Nester, Terry Cannon
04/21/21 – Nester requested SOSS for small restroom renovation, emailed next day.
05/26/21 – Kickoff meeting scheduled Friday at 2:00 pm on site.
06/11/21 – Sent preliminary layout with new fixtures located.
06/18/21 – Sent owner review set to John & Greg for review.
06/21/21 – Answered budget questions & Small Project bidding questions via email.
06/25/21 – Use as many BOLD participants as we can.
04/28/21 – Prebid held last week. Addendum #1 issued this week. Addendum #2 will be issued Friday with some cost savings ideas included. Bids are due August 5.
08/16/21 – Bids received and tabulated and sent to County for approval.
08/20/21 – Post Bid review with DK went well. County, TEI and DK working through contract documents.
09/30/21 – PO and Contract approved, all paperwork sent to DK for processing, and project information requested.
10/28/21 – Paperwork received from DK. PO and Contract are in place and the project is ready to go.
12/08/21 – Pre-const mtg scheduled on site but rescheduled to next week for availability.
12/13/21 – Pre-Const mtg schedule for Wednesday.  Submittals are returned.  Permit drawings will be hand delivery to DK at meeting.
01/21/22 – Tumlin has measured for toilet partitions and Debra is updating the project schedule. Permits are ready for this job. DK arranging for temporary toilets. We just need to get started.
02/24/22 – DK almost done. Rough-in work complete and passed plumbing inspection. Walls are being reconstructed, partitions installed and fixture to be hung next.
03/31/22 – Tumlin performing change order work for extending toilet partitions this week. DK performing punchlist work this week. Change Order 1 approved.
04/28/22 – The project is complete. Punchlist was distributed and completed including change order work. Some minor touchup may still need to be done. We can start closing out this project.
05/25/22 – Working on closeout with DK at this time. No additional paperwork has been received yet. Bill says they are close.
06/17/22 – Spoke to Bill & Donna at DK. They are working on getting closeout documents.
07/27/22 – Most of the closeout documents have arrived. I think JN reached out for a PW document.
08/24/22 – Reached to DK for more closeout docs. PW received so far.
09/25/22 – All closeout documents received. Project ready to close out.

P&D – Restroom Renovation Read More »

CH – Chiller & Boiler Room Control Updates

PM: Terry Cannon, Tony Matre
04/23/21 – Tony requested an SOSS for a chiller study on controls and operations.
05/26/21 – Discussed scope with Tony Matre today and he wants better control of the system and better maintenance.
06/25/21 – Based on recent conversations with everyone about upcoming projects, I have not submitted a separate SOSS for this work yet.
07/28/21 – SOSS approved. The study will begin next week.
08/18/21- TTC discussed similar scope with Ameresco and their findings on the Courthouse Chillers
08/24/21 – TTC met with Honeywell and discussed chiller, cooling tower, free cooling controls and programming and learned a lot about what has been changed in the last few years. Honeywell can meet with ThermalTech and the County late September given Randy current scheduled. TTC will advise Matt and Tony on this schedule.
09/27/21 – Reached out to Ameresco and discussed previous jobs with Garyne and Brad and get download on what they’ve done.
10/27/21 – Contacted Randy for pricing on recommissioning project and scope.
10/28/21 – Emailed and called Randy today for pricing for recommissioning today. Randy called back today and promised to give us his recommissioning cost by Nov 4, TTC to turn over to Matt and Tony immediately afterward.
12/13/21 – TTC scheduled the Chiller Recommissioning work with Randy and County for 12/27 at 9:00am on site.
12/30/21 – TTE collected and sent sequences to Honeywell for use on this project. Cc’ed the County.
01/22/22 – Honeywell working on new sequences and project schedule. TTC to check on VFD repairs.
02/24/22 – Honeywell started the fieldwork and deficiency report work last week and was down at the Courthouse collecting data.
03/31/22 – met Randy and corporate on-site. Getting deficiency report for next steps.
04/28/22 – Honeywell turned over all the existing points list and we have gone through it. We have not seen the due diligence report yet but Randy is working on it. I have stayed in touch with Randy weekly on this job. CH-3 will not be here unit August for installation. Comm is Bacent MSTP on the existing chillers.
05/25/22 – Randy is working up a new controller that will handle the sequences we need for this job and getting pricing, all hopefully, within his budget. And help promises to send an deficiency report to me via email.
06/30/22 – As soon as Randy is done with the Server Room, he will start the Chiller Room work.
07/27/22 – Randy is onsite now working on controls, he may get to some of the Chiller Room controls this week.
08/03/22 – Trane Chiller #3 ships 9/18/22, Tony wants chiller controls completed before then.
08/18/22 – Met with Dave Johnson on CH Boiler Room Controls today. We discussed his scope and schedule for integrating the boiler plant into two control scenarios. 1) Courthosue controls which will be minimal boiler operation and 2) CH & JC and what does that look like? Dave will update his controller for two scendarios and we will work in the HTX-5 operation with the Summer Reheat operation.
08/24/22 – Reached out to Randy for Chiller update and reminded him this work to be done before 9/18.
09/22/22 – Randy back on 9/21 but he spent that time on CH Server Room job. He is coming back next week.
08/24/22 – Randy will be back on 8/31 with a new controller board and continue to work on CH updates. He owes us a quote for a new controller to get the chiller RECX done before 9/19.
10/26/22 – Randy has made some progress. Honeywell will be back Monday. NO updates form TPC on CH boiler controls.
12/15/22 – Vendors have been contacted multiple times to complete this work but I have not gotten them on site to do this work yet. I will have to try harder this month.
01/24/23 – Randy promised he will be down to do the CH Controls work on Friday. Dave Johnson does not call me back.
02/21/23 – Honeywell on-site twice last month but the new controller is not installed yet. Met with DJ and he is working on new controls programming.
03/29/23 – Honeywell Randy to install new controller this week. Dave Johnson working with TTC.
03/30/23 – Randy confirmed this morning is installed and controls completed.
04/26/23 – Honeywell coming back May 5 to finish programming on the chiller plant.
05/21/23 – Checked in wtih Honeywell last week, no updates yet.
06/28/23 – Chiller and Cooling Tower controls are in place. Next step Boiler Controls.
07/26/23 – ThermalTech will check programming on Thursday when on the building BAS system. DJ having open heart surgery, his work may have to wait.
08/29/23 – Chiller controls in place. Boiler controls awaiting DJ recovery.
09/27/23 – No updates on this yet, will check in with DJ in October.
10/25/23 – TTC contacted DJ on health condition to see if he is ready to return to work yet, no answer yet.
12/06/23 – Chiller Controls are in. Dave Johnson said that he will call me back with a day to come down and do the boiler reprogramming so he is feeling better and back in business. We will get this on the schedule and get it done very soon. TTE reviewed the plan for having a Courthouse Mode and a Justice Center mode. DJ has to program some of this ahead of time.
01/31/24 – Randy Waddell to be onsite by this date for CH Chiller Controls. Trane sent all data he need for Chiller integration. Dave Johnson not answering phone calls about boiler controls.
02/23/24 – Randy Waddell was onsite this month installed controller for chillers. New wires ran to VFD, but no power is on new VFD’s yet. MCC update coming soon.
03/22/24 – Honeywell was onsite two days last week and pulled their controls back to the front end. four VFD’s powered up with controls. The Carrier chilled is not hooked up yet.
04/24/24 – Honeywell says they are done but the Carrier chiller is not hooked up to DDC nor can we see the KW on it. TTE to reach out to Don Webber. Randy Waddell has to come back to the building to work on Bacnet points, add the generator to the systems and the deficiency report items. Dave Johnson has suggested May 18 and 19th for his weekend work at the CH.
05/28/24 – Chiller work is complete, all chillers are on graphics.
06/26/24 – Honeywell has completed their work and the systems appear to be working. Dave Johnson is being scheduled for July.
07/24/24 – Chillers are complete and working well. Boilers are scheduled August 24,25th with Dave Johnson.
08/10/24 – Met Dave Johnson and Tyler Laws on site and reprogrammed the boilers. We got most of the reprogramming done on Saturday but we will have to come back on Sunday.
08/11/24 – Met Dave Johnson on site Sunday to wrap up the boiler programming updates. The boiler room was flooded due to the boilers being off and some of the recirculation pumps being off. Later we discovered a room upstairs flooded too, note to self turn off all pumps when the boilers are off. Programming complete with two operator settable modes and three working modes. (1) Courthouse, (2) JC Low Load March-November, and (3) JC High Load Dec-Feb.
09/24/24 – Dave J contacted multiple times this month for Summer Boiler troubleshooting and Modbus map for boiler controls to ALC to no affect.
10/30/24 – Dave Johnson coming back in November to finish up but boilers are running okay so far.
12/12/24 – Dave Johnson has not returned yet and I have not gotten a new commitment date from him.
01/28/25 – Talked to Dave last weekend and he is going to send some availability for February to finished the Summer Boiler work.
02/27/25 – Original proposal cancelled by Auditor. TPC sent new proposal for recommissioning and troubleshooting services. New proposal rejected due to wording. Tony requested new proposal.
03/25/25 – New proposal sent last week with updated language and 2025 rates including additional troubleshooting for the summer boiler. TPC also included sole source letter.
04/23/25 – PO sent to Dave Johnson for troubleshooting work and summer boiler integration.
05/28/25 – TTC trying to get summer boiler date from Dave Johnson. No luck on confirmed date of work yet.
06/25/25 – No commitment from Dave Johnson on summer boiler startup.
07/30/25 – No updates from Dave Johnson, spoke to Tony about Emcor proposal to take over boiler controls.
08/26/25 – Helped Tony get BBC in the vendor database, now we can schedule David through BBC.
09/24/25 – Sole source letter on BBC letterhead received. TTC requested schedule dates to troubleshoot summer boiler.
10/29/25 – Repeated attempt to schedule Dave Johnson back down for summer boiler startup were unsuccessful.
12/12/25 – No updates from Dave on performing the summer boiler work. Just Archive and put this job out of its misery.

CH – Chiller & Boiler Room Control Updates Read More »

250 WHT – Public Health Lobby Renovation (2nd Flr)

03/31/21 – SOSS approved. Kickoff meeting scheduled for 5/6.
04/29/21 – Kickoff meeting schedule for 5/6/21.

05/06/21 – Kickoff meeting held

05/17/21 – Field visit to verify existing conditions

06/04/21 – Progress set sent to Greg Varner for review

06/08/21 – Updates from Greg received

06/10/21 – Updated plan sent to Greg

06/22/21 – HC, PH, and ES decided to combine project scopes of 2nd floor lobby and 1st floor lobby into one bid.

06/23/21 – Updated plan sent to Greg.

07/09/21 – 95% review meeting to review scope and budget. Raised questions related to code requirements. required additional research.

07/29/21 – Meeting scheduled for Final Review Set.

08/10/21 – Project Issued

08/23/21 – Pre-bid Meeting Held

09/09/21 – Bid opening – Triton was apparent low bidder.

09/15/21 – Zoom meeting with Champlin, Thermaltech and Triton to vet the bid. Sent Letter of Recommendation to County.

10/28/21 – Ready to archive.

 

 

 

250 WHT – Public Health Lobby Renovation (2nd Flr) Read More »

230 – 11th and 12th Floor Renovation

03/08/21 – SOSS approved.

04/06/21 – Kickoff meeting with users to go over scope.

04/20/21 – Field visit to confirm existing conditions. Working on selecting finishes and furniture.

05/20/21 – User meeting presenting initial room layouts

06/10/21 – Sent updated plans to further define scope

06/22/21 – User responded to refocus efforts in light of new funding. meeting scheduled 6/28

06/28/21 – Sent county plans and estimate for flooring replacement and wallcovering removal and paint. furniture estimate outstanding.

07/28/21 – John to remind users about need for additional information in order to finalize furniture estimate.

08/26/21 – Project part of 2022 Estimates.

10/28/21 – Ready to Archive.

 

 

230 – 11th and 12th Floor Renovation Read More »

RSC – Regional Safety Complex Phase 1

PM: Bert Watts, David Toombs, Terry Cannon
04/02/21 – SOSS approved. Waiting for contacts from County to begin programming.
05/27/21 – No Update.
06/17/21 – Toured City and County facilities.
06/23/21 – Site planning concepts sent to Bert for input. Input received the same day.
07/16/21 – Review meeting with County Commissioner, City Council Member, County Administrator, and representatives of Hamco Sheriffs and City of Cincinnati Police.
07/26/21 – Final rendering and diagram packet sent to Bert.
08/25/21 – SOSS Submitted to County
10/28/21 – No Update.
12/14/21 – No Update.
01/26/22 – No Update.
02/22/22 – Champlin presented at Residents Meeting in Colerain Township.
02/24/22 – Elected officials outnumbered the residents who were in attendance at the meeting and Champlin presented the project. 5 residents were in attendance, sheriff, county, other people were there. Concerns: Acoustic study, traffic study, and site environmental range. Even though it’s a firing range now.
04/27/22 – Champlin sent kickoff meeting invite for May 10.
05/10/22 – Kickoff meeting with County Cincy Champlin and Kleingers held. Reviewed program and concept
05/24/22 – Progress meeting with County Cincy Champlin and Kleingers to review floor plans and ancillary buildings.
06/30/22 – Progress meetings ongoing. SD package to be completed on schedule
08/25/22 – Final SD package sent to HC. Estimate breakdowns to be finalized.
09/29/22 – No Update.
10/27/22 – No Update.
01/26/23 – Meeting held with County and City to discuss funding. Estimate is being broken down by item to value engineer the project.
02/03/23 – THP – Champlin requested SOSS for structural services.
02/09/23 – THP provided an SOSS to Champlin for review.
02/22/23 – SOSS received for DD-CA.
03/08/23 – THP and Champlin have executed contract.
03/30/23 – Site survey is complete. Developing Topo basemap to be complete middle of next month. the Acoustical Engineer has completed existing condition sound testing.
04/27/23 – Draft of Acoustics report received. Champlin had questions and is finalizing a report. Topographic survey complete and base map received. Champlin and Kleingers are coordinating scope of work.
04/28/23 – Moved project out of Champlin General Services to Satellite Offices for future updates.
05/21/23 – TTE attended DD development meetings wiht Champlin & Kleingers for site work.
05/25/23 – Site package sent to County for review. Drawing to begin development.
06/29/23 – DD page turn held 6/23. Hud environmental assessment exhibit materials are due to Bert by friday June 30. Flood plane exhibit sent 6/27. Final acoustics report is ready to send upon request. Design team has reworked architectural site plan with the temporary building location moved.
06/28/23 – THP coordinating with Champlin on Phase 1 documents in July.
06/29/23 – Septic Engineer will be onsite Jully 6 for site survey and cores for their work. The Water Test from Veolia is on hold for supply issues with our test kit, but we hope they can also be on site the week of July 7.
07/20/23 – ThermalTech met SCS engineers onsite for septic design ground samples and septic tank locations.
7/24/23 – Champlin sent email: Phase 1 design coordination with structural (THP) is expected start this week for CD due end of August.
07/26/23 – Veolia water testing scheduled for August 1 with Ian, TTE, and Veolia.
07/27/23 – Meeting held with Sheriffs. Program and plan confirmation for temporary range and ancillary structures locations occurred at that meeting. Expect phase 1 CD submission for end of August. Geotechnical work is ongoing.
08/31/23 – Schedule for bid package 1 and 2 distributed to all consultants 8/28. Coordination is ongoing. Bid package 1 completion date is 9/22.
08/31/23 – THP no project updates.
09/28/23 – Meeting held with CPD. Cincinnati had scope requirements to continue involvement with the safety center. County is working on an agreement.
09/29/23 – THP issued Phase I bid review documents.
10/25/23 – Revised estimate submitted to County for review. Waiting on meeting to be scheduled with CPD to answer some outstanding questions. EPA issue has not been resolved.
12/07/23 – Meeting with Cincinnati, CPD, Sheriff, and Hamilton County held to discuss status on 11/6.  US EPA review comments continue and we are providing answers as required.
1/24/24 – THP – No update. Paused.
02/01/24 – EPA questions submitted answered. HC continues to have meetings with the EPA. We will most likely require some sort of testing wells for this site to monitor content in the aquafer. Currently this project is on a design hold until these administrative tasks are complete.
2/28/24 – THP – Phase 1 is on hold. Expected official response 3/1/24 and issue bid document 30-45 days. Design is done. Phase 2 is on hold with no date planned.
02/28/24 – Met with Morgan and Anson on Feb 23 to discuss approach to hiring engineering for water main extension. City of Cincinnati determined that GCWW was OK with not hiring the design as long as standards are met. All agreed it made sense to have Kleingers due the work because of head start on project understanding. USEPA verbal commitment to have a letter by March 1 has slipped to mid March.
02/29/24 – Bert asked for operational cost, environment, utility cost and lab test.
03/28/24 – Land swap negotiations nearing completion. Zoning variance for sniper lanes to be submitted in near future. Coordination between architectural and civil to wrap up this week.
4/23/24 – Phase 1 Bid Review set submitted on 4/12/24. Phase 2 on hold with no date planned.
04/25/24 – 95% review set submitted to the County 4/18. Cost estimates are being developed. Zoning meeting scheduled for 5/22.
05/30/24 – Board of zoning appeals voted to approve the required variance on 5/22. Bid set sent to purchasing 5/23. City comments on phase 1 received with no impact to phase 1 drawings.
06/27/24 – Project is out to bid. Pre-bid held, Addendum #1 is issued.
07/24/24 – Bids were opened and five underbudget bids were received
08/28/24 – Phase 1 Bids in. Phase 2 on hold with no date planned.
08/29/24 – Bid review complete. Project in contract phase.
09/23/24 – ThermalTech sent “Issued for Permit” drawings sent to Champlin for distribution and submission for this project.
09/25/24 – THP – Pre construction meeting with Monarch next week. Phase 2 still on hold.
10/31/24 – Groundbreaking ceremony held last Friday. Phase 2 to begin.
12/11/24 – in CA. submittal reviews. Phase 2 still on hold.
01/30/24 – Phase 1 – Site work to start ramping up due to weather. Zoning and Permit issues are close to resolved. Phase 2 – SD plan approval received from Cincinnati and Hamilton County. DD development ongoing.
02/26/25 – Phase 1 – we have returned adn submitted all the OEPA permits to keep the permitting phase of the job moving forward, the contractor is getting close to running out of work on Phase 1 I think, we need to get permitting on place. Phase 2 work for DD is due March 3. TTE working on Revit model updates and working on cost estimates as well. We have been meeting with David Toombs regularly on MEP updates.
03/25/25 – We have multiple DD design meetings with Champlin this month. Bluebeam studio being used for markups, DD drawings and cost due this week to Champlin for Final DD tear-off set. MEFP and Architectural design being tweaked for final DD adjustments. Phase 1 submittals are being received and returned as they come in, submittals are acceptable. The Septic permit is still elusive but we continue to work towards resolution, SCS says most of the paperwork is already submit, but he needs to fill out one more new electronic form.
04/24/25 – THP update – County requested changes to the design. THP provided pricing for additional services to be included in Champlin’s request.
04/24/25 – DD for phase 2 is complete. Revised estimate submitted to county. Phase 1 work ongoing.
05/29/25 – Project schedule shared for phase 2. Phase 1 work in progress.
06/25/25 – DD submittal in Apr. Team is waiting for approval to proceed into CD.
08/04/25 – We received an Anti-Degradation email from Bert and forwarded that to Dan Brennan SCS engineers to handle. SCS sent a memo to Glenn per their request but will call him back to make sure that is all they need. We also got the approval to send in the revised submittal drawings from the contractor for Monarch. TTC passed all this information on to Bert and David.
08/26/25 – Construction continues on site. Pilot holes are being drilled to assist in figuring out how to get under the roadway. Soils change order being developed. Bulletin 6 issued to Monarch for pricing and coordination.
08/27/25 – on Phase 1 the large retention system walls are nearly complete, and the Phase 1 temporary range was completed last week. The Ph1 grounds building cladding is in progress and the staging to raise the parking lot grading has also started. On Phase 2 the Design Team received DD approval and is proceeding with CD Phase. Over the last 3 weeks all remaining in-person owner meetings for Security, Technology and Interior Design have been completed.
10/30/25 – 90% documents for phase 2 will be submitted to county tomorrow. Phase 1 work continues and on target for January completion. Retaining wall movement has been rectified with additional wall in front of original retaining wall.
12/11/25 – 90% set is under owner review. Ohio EPA approval is still in process. Grounds building is complete and sheriffs are moving in. Existing building Demo to begin shortly. Phase 1 work on target for completion in January.
02/26/26 – Project complete. Punch work ongoing.
03/26/26 – One site issue still outstanding. Kleingers is working on a solution.
04/30/26 – Guardrail posts being installed next week. Closeouts outstanding.
05/28/26 – No Update.
07/30/26 – Monarch sent closeout documents, Partners have been commented on them this week. Concrete joints and curb issues being addressed.
08/27/26 – OK to Archive.

RSC – Regional Safety Complex Phase 1 Read More »

800 – Plumbing Study

PM: John Nester, Terry Cannon
03/25/21 – SOSS submitted.
04/21/21 – SOSS approved. Terry, Coty, Ryan will work on this project.
04/29/21 – Contract sent to QCM for signature. Check on progress. Okay to do fieldwork during city water main shutdown.
05/26/21 – ThermalTech secured the services of Mike the plumber from Triton (same guy that installed the work at the CH) for the plumbing survey at 800 for one daytime and two nighttime visits). We will probably do this work in June.
06/09/21 – Met with County, walked the building, started reviewing existing installation.
06/25/21 – Updated drawings since 6/9 meeting, almost ready for field work.
07/27/21 – Day 1 Night Fieldwork with Terry, Coty, Danny, Triton, Tom. Basement, First, Second, 14,15,16 floors were completed.
07/28/21 – Day 2 Night fieldwork with team complete for the rest of the building. We have to return to finish the basement, access the drug testing labs and some judge’s private RR. Very little galvanized piping found. The building appears to be in good shape for plumbing piping materials.
08/26/21 – Existing drawings slightly updated from fieldwork. We will be on this in earnest the second week of September. There is limited scope to change based on what we found in the field. Our basement fieldwork will coincide with the city water main work on QCM Saturday.
09/30/21 – Drawings are complete and ready to TTC review. Study report started, TTC going to let Coty have a shot at it first and then will edit for final submission.
10/28/21 – Working on Fire Department design this month and did not make a lot of progress on wrapping this up yet. We could send drawings in for review.
12/13/21 – Project completion pushed to the end of December for this work.  TTC coordinating with Coty on putting the final touches on this work.  The laminated CH placards drawings were emailed to the County.
01/22/22 – Drawings are being completed now.
02/22/22 – Plumbing schematic ready for review, floor plans mostly completed and on final review and editing.
03/31/22 – Final Draft report complete, TTC will send today.
04/28/22 – Plumbing report and recommendations were sent to the County. Design SOSS requested.
05/25/22 – Design SOSS is almost ready. It’s a simple one but I need to finalize it and get it to John. We did meet with QCM this week and tell them we’d like their help.
06/30/22 – TEI has a field trip setup next Tuesday at 800 to final water shutdown plans and finalize valve locations.
07/27/22 – TEI performed additional fieldwork and found more valves and useful locations for valves. We’ve schedule another field trip to wrap up final details next week.
08/24/22 – Two additional field trips were held this month for finalizing changes. Updated drawings and revised report will be ready 8/30.
09/22/22 – Coty has prices back from QCM, they are revising and sending back for final scope on Monday. Some more valves were fixed during the last walk through.
10/26/22 – New pricing submitted by QCM. They called twice wondering which way we are going to go with the change order. I told Drew, we are probably just doing a material purchase and a fire detector restock.
10/27/22 – JN sent change order to TTC for review.
12/15/22 – Change order awarded to QCM. Drawings are updated for final scope, limited rework in the building is necessary. OK to close and archive this project.

800 – Plumbing Study Read More »

Blackout Vulnerability Study 2021

PM: Bert Watts, Mike Barth
03/25/21 – New post started by TTC and assigned to MCB.
06/23/21 – TEI working on Study. Site visits to the buildings to be scheduled by TEI with building managers over the next few weeks. Study proceeding.
07/28/21 – TEI continuing to work on study, researching existing conditions and vulnerabilities.
08/26/21 – No updates.
02/23/22 – No updates per discussion with HCFD.
10/26/23 – TEI assigns work to EE Conn Gerard, who is reviewing the study and working on completing the study.
12/06/23 – Conn for TEI is continuing to work on study.
02/29/24 – Conn has report ready to review with Barth.
10/30/24 – Conn sends out questionnaire to bldg mgrs. If they are replying to conn, he on honeymoon and will address upon his retturn.
12/11/24 – Conn returned and finalized information from the buildings has report ready for my review. will send to HCFD once QC review complete.

Blackout Vulnerability Study 2021 Read More »

TEI General Service – Archive

01/01/14 – County has approved a new SOSS for 2014. The 2013 SOSS however is not expired yet.
06/26/14 – Minimal work and time charged. Website updates mostly.
08/26/14 – TTC sent in new SOSS for energy, watchdog, 2015 project estimates projects to Bert.
01/27/15 – Updated website, worked on B201, etc.
05/25/15 – Reformatted tables on website, fixed some broken links in the Archive section, moved old buildings out of the main pages.
06/11/15 – Doteasy had to restore the FrontPage extensions this week. TTC had to remake all the user ID and send out new username and passwords.
06/24/15 – Website Updated.
08/26/15 – Website updated, Prevailing Wages Updated.
09/23/15 – Website updated. Facilities requested new General Service SOSS. TEI collected the Hourly Rates bid for plumbing and electric today. We will drop those bids to Bert tomorrow at the Partner meeting.
10/02/15 – Website updated for partner meeting.
12/08/15 – Website updated. ThermalTech working on new MSA agreement with Bert Watts.
01/08/16 – FrontPage extensions corrupted. TTC trying to fix.
01/15/16 – FrontPage extensions fixed, website data missing, TTC Website Updated.
01/21/16 – hamco.biz fully fixed. $45 restore cost from Doteasy. TTC will download a local copy from now on every month after the partner meeting for safekeeping.
01/26/16 – Bert said the contract is over a Prosecutors Office. We will wait until Friday Jan 29 and then move forward with the edits that we have approved.
04/25/16 – Created updated Archibus and Building Operation pages for Tim and Tony.
05/25/16 – Performed some maintenance and cleanup on the website this month.
06/27/16 – Website update and backed up locally by ThermalTech.
09/28/16 – Website updated. Building Ops renamed.
10/26/16 – TTC made a change in Tony project page on the server.
12/29/16 – Website updated for end of year and backed up by TTC to local server for archive purposes.
02/17/17 – Website is updated and formatting is updated too.
02/23/17 – TTE to investigate replacement website for hamco.biz that is compliant with Windows 10 and partner editing moving into the future. Try to find something that we can host and make better moving forward.
03/09/17 – TTE investigated WordPress at this time as an alternative and we updated the website for data.
03/21/17 – In an effort to find an easier method to edit the hamco.biz website, I have tested four new website locations. One at Wix, Penzu, Bluehost and sub-domain on hamco.biz. So far Penzu seems the easiest to use but cost money to get the full functionality, Doteasy does not support WordPress without an upgrade, Wix seems possible but so far no luck in creating multiple forums for each building and Bluehost was installed tonight. I need to find a way to upload a new theme on the website.
04/26/16 – Minimal work on website this month. Regular website was updated.
06/06/17 – TTC edited the new Wix website some more and had people enter comments, its seems to be working. It still requires a lot of formatting and work.
07/24/17 – Website updated. TTC contacted WebFeat for website design as well. No return emails.
08/30/17 – TTC contracted WebFeat for finishing the website design this week, $2800 total, $1400 now, $1400 at completion. Kickoff meeting next week for design, look, feel of the website. We will share some prelim looks when they draft the up.
09/25/17 – WebFeat sent preliminary look at new website. ThermalTech returned initial comments back to designer for security, NAV menu’s and content to fill the database. They immediately responded with a follow up email about working on this this week, very nice. The temporary website is located here: http://hamco.wfcstaging.com/
10/24/17 – WebFeat has made decent progress on the website. TTC is working on populating the site with the old data now and tweaking the security, input, active projects, archived projects and tony projects pages along with the management console and eventually migrating the test site to a live server.
11/28/17 – Had another round of emails with WebFeat and they made some final changes in their opinion of the scope of work. TEI has to integrate the remaining data into the website.
02/22/18 -All partners updated projects on new website. ThermalTech postponed final conversion to new hamco.biz until mid-March. WebFeat updated and added the new pages on the new website. TTC must create the Tony Matre projects on new website. Terry has created a copy of all the old data on the hamco.biz website so when we update the site to WordPress we still have the data saved.
03/24/18 – New website is published and live. ThermalTech input new usernames and sent to the group for editing.
04/01/18 – This is a test edit using the new inline editing too. Works inline editing plugin is activated.
04/26/18 – Website updated. Several plugins were updated several times this month for security reasons. The website domain name and server were updated for another year with Doteasy.com for hosting.
05/30/18 – Prevailing Wages updated, security patches applied and new projects created for use on the site this month.
06/30/18 – Prevailing Wages updated.
07/26/18 – Prevailing wages updated, security applied, some project management for formatting completed.
08/29/18 – Prevailing wages are updated, no other security updates were required this month however TTC edited and fixed some naming and category discrepancies, also updated all Tony Projects and created a new category for them.
09/24/18 – Website Updated, PW uploaded, Security Patches applied.
10/23/18 – Website has been updated. TTC to add October PW soon.
01/15/19 – Website updated. PW uploaded. Database updated.
02/28/19 – Website has been updated this week for meeting.
03/28/19 – Website was updated on 3/26 and 3/27. TTC and Bert agreed to extend the annual renewal with Doteasy for hosting the website. Note that hosting is not the same as domain name renewal. Each year there are two renewals.
04/25/19 – Website updates complete earlier this month. PW rates downloaded and uploaded to this site but TTC needs to do script updates for end of month and upload April PW rates.
05/28/19 – Updated the website for County meeting, saving widget updates until after the Partner meeting.
05/29/19 – Created Champlin Login, migrated all Terry Cannon post to TEI and updated our Archive projects to clean up migration of old project.
08/28/19 – Website has been updated for this weeks Partner meeting. TTC will update scripts and website next week.
09/24/19 – Website updated, PW uploaded, scripts updated but two more need to be updated soon.
10/30/19 – TTE Update website and update PW rates last week. Created new projects and categories for several projects and performed website cleanup. Assisted Champlin with front end documents.
12/05/19 – Updated scripts on website, upload PW information, start updating website for next meeting on 12/12.
01/27/20 – Website update, PW rates uploaded a couple of weeks ago. Scripts not updated this month yet.
01/30/20 – Called to 800 Broadway to troubleshoot boiler issues and was onsite 1/30, 1/31, and 2/1 to resolve the issues. TTC will send Tony a field report as several things were found to contribute to the issues at 800 Broadway this year. It was a good bit of troubleshooting and quite the enigma to figure this one out but we got it.
02/02/20 – General Service names were renamed to [General Service] so they appeared at the top of the list form now on.
02/27/20 – PW updated and website updated Monday-Wednesday.
03/13/20 – TEI issued Work from Home mandates for all employees limited access out of the office, for fieldwork or meetings for all projects starting 3/20/20. We are to continue servicing clients as best as we can remotely and only do onsite meetings as necessary.
03/23/20 – Doteasy renewal is up for next 12 months for hamco.biz. TTC and BW agreed to renew another 12 and TTC sent in renewal.
03/24/20 – Website updated for PM meeting. We are not meeting in person but will have details updated for Facilities.
07/29/20 – Website updated, PW rates uploaded and fixed for some hyperlinks.
08/26/20 – Website due for major updates including WordPress 5.5. PW rates updated for August and September will be early for JC Project.
09/18/20 – Block editor was automatically installed. TTC trying to disable that feature on the website. Updated the website mid-month this month. September PW waged already updated.
10/28/20 – Scripts updated, working on classic editor settings, PW rates updated.
12/10/20 – Website updated mid-November although there was no meeting. Reupdated in December for 12/10 meeting.01/26/21 – Website updated, jquery issued addressed, 3 plugins updated, PHP security issued researched.

TEI General Service – Archive Read More »

JC – HVEC-1 Replacement

PM: John Nester, Terry Cannon

03/25/21 – SOSS Approved
04/29/21 – The first draft of drawings are ready for review. TTC to send to JN.
05/26/21 – TTC initial review is finally complete and back in for changes. We will get a review set to the County by Friday, June 18 that includes both mechanical and electrical.
06/18/21 – Review set sent to County. The basic design is complete. TTE reached out to JCI for a controls budget number for the project.
06/21/21 – JCI provided existing sequences that were missed from our as-built drawings. We confirmed the existing unit has steam heat, city water cooling and a VFD that is linked to the washer control. We are are proposing upgrading the controls to monitor the dryers, running the VFD at three speeds, insulating the lint collection plenum and reducing the required outdoor air for better space control.
06/24/21 – County sent AIA contracts for inclusion in the bid manual. 90 Days completion time.
07/26/21 – New equipment submittal received from Trane with budget pricing. $18k for new unit. TTC working out new control sequence with JCI and finalizing pricing for bidding. Target bid issuance in next two weeks.
08/23/21 – Mechanical drawings and equipment selections are complete. Drawings sent to JCI for final controls sequences for the job. Electrical needs VFD information to relocate VFD to EF wall for reuse in new scheme.
08/26/21 – Project will be ready for bidding 9/1.
09/25/21 – Addendum 1 issued.
09/27/21 – Addendum 2 issued.
09/28/21 – Prebid went well, many bidders attended.
10/07/21 – Bid opening complete. two bidders, Debra & Blau. DK apparent low bidder.
10/28/21 – Pre-Award meeting with Debra went well, recommended for this job. project pending contract for the contractor.
12/13/21 – Project contract and PO are being finalized by the County.  DK has sent submittals that TEI has reviewed.  We are awaiting the project paperwork to be in place to return submittals and hold pre-const meeting.
01/22/22 – Submittals returned to DK and project schedule requested.
02/24/22 – update forthcoming from DK.
03/31/22 – Control submittals are in, TEI to review.
04/28/22 – Checked with DK and Trane, Unit will be here in June. Control submittals are returned and ready. DK to verify delivery date so we can setup the next const mtg.
05/25/22 – Dave and I both have reached out to Trane to get an updated delivery on this unit but we cannot get it out of them yet. As soon as we have that, we can set the schedule.
06/14/22 – Trane delayed the delivery until 8/17/22. We will schedule the pre-const meeting closer to this delivery.
07/27/22 – Checked in on delivery date – no confirmation from Trane yet.
08/24/22 – DK mobilizing for unit replacement work. We don’t have an isolation valve where we need one to work on this unit without drawing the entire north building so we will do hot taps and run new 2″ piping to the HVAC unit. The existing unit can remain on and cool during the demolition work doing it this way.
09/22/22 – HVEC-1 is demolished. New piping and hot taps are done. The new unit is being installed now. Some spacing issue is going to make changing the filter tricky.
10/26/22 – Everything installed with the unit, piping under pressure test, only electric and controls are left to complete.
12/15/22 – Per Debra all work is complete except for the controls work, waiting on JCI to finish. Ready for punchlist.
01/24/23 – I have been working with JCI to get their subs background check approved so they can finish the control work on the unit. The MEP work is complete. It’s down to controls. I can punchlist this job.
02/2/23 – JCI has background checks complete, working on final controls programming, rest of work is complete.
04/17/23 – Electrical and Controls vendors on site this month to startup up the unit. After some back and forth we finally have power and controls. the unit is ready for a punchlist.
04/26/23 – The unit was making noise yesterday. ThermalTech and DK on site to get this resolved. The blower motor was realigned by noon and put back online.
05/21/23 – Unit is up and running JCI made additional control changes last week. First stage cooling and fan where scheduled on anytime the space was in operation. 2nd and 3rd stages tied to the dryers. TTE needs to commission and punchlist this project.
06/28/23 – After checking on the unit three times this month, I can confirm it is providing cold air to the laundry room measure air at less than 65F this week. I still need to do the final punchlist. JCI technician has left JCI, trying to find who our new engineer is.
07/26/23 – Punchlist scheduled 7/26 at 1pm.
07/27/26 – Punchlist distributed to project team.
08/29/23 – Request closeout documents from DK again. I am holding final payapp.
09/27/23 – DK says they are working on closeout documents but we do not have them yet. We are also working on JCI controls punchlist with JCI but they have not confirmed who is out new technician. I asked DK to find out who is finishing this job for JCI and reached out to Dustin Stewart, our new sales engineer.
10/25/23 – JCI working on new technician for closeout and controls punchlist but no one has been assigned yet. County sent approved list through TTE to JCI today. Working on closeout with Debra Kuempel. Unit seemed to do fine this summer, it was definitely better in the room with the new unit running.
12/06/23 – TTC has been talking to DK and JCI about assigning a new technician for our work. But as of yet, no avail. TTC called Dustin Stewart and Greg Platt to get this moving!
01/24/24 – Motor bearing bad on unit. DK removed motor and took it out for rebuild at A-1. They will reinstall the motor ASAP.
01/30/24 – Closeout documents received from DK. JCI cancels punchlist visit due to family emergency. TE rescheduled to next Tuesday.
02/23/24 – Met JCI onsite this month and it went well.
03/22/24 – Project is ready for closeout.

JC – HVEC-1 Replacement Read More »

JC – Drinking Fountain Replacements

PM: John Nester, Terry Cannon
03/25/21 – SOSS approved.
04/23/21 – Acorn and StreamKey suggested moving the airtrol valve inside. After discussion with Facilities, this doesn’t seem like a solution. About 30 drinking fountains need a close connection. We are working on better solutions.
04/29/21 – The first draft of the drawings are ready for review.
05/26/21 – StreamKey reaching out to Acorn to send a revised mock-up for the close quarter’s actuation valve for us to test before we bid out this work. 32 drinking fountains required this type of actuator. We rejected the interior drinking fountain installation.
06/15/21 – Worked with StreamKey this week to iron out final samples of the AirTrol retrofit kit. Acord will manufacturer one item and send it to the County for testing. It will ship to StreamKey who will deliver it to County for testing.
07/28/21 – Drawings and Specs sent to HamCo for final review. Project will be Issued for Bidding on 8/2/21.
08/18/21 – Addendum 1 issued.
08/25/21 – Bids were opened today and we received several good bids within reason of each other. They are all significantly under the published estimate.
08/28/21 – Triton was the apparent low bid. TEI vets the bid and sends a recommendation to HCFD to proceed with Triton. Pre-construction meeting and kickoff meeting conducted.
12/02/21 – Onsite kickoff & coordination meeting with Facilities and JC held with Triton.  The material is onsite and Mike Adams will be our lead plumber from Triton.  We meet with John, Andy, and Danny for previous plumbing work and kickoff.
01/24/22 – All work complete and TTE to start punchlist.
01/25/22 – North Building Punchlist complete. TTE to send to Triton for rework. Relocate controllers mounted on the duct, provide tubing management.
02/24/22 – Triton says all punchlist is complete in the North building and almost done with the South building.
03/31/22 – Punchlist completed in North building, same work was proactively done in South building. TEI coming down to punchlist the South building in April.
04/26/22 – South building punchlist is complete. TTC to distribute. All drinking fountains are working expect one does not drain and one does not have a drain pipe any longer. All base bid work looks good.
05/25/22 – Punchlist distributed to Triton. County fixed a couple of owner-related items. Requested pricing from Triton on helping with Lobby sinks but prices seemed a little high. We have some money left in the PO from the allowance. I will request closeout documents from Triton next, the project is complete and working well.
06/30/22 – The project is done, closeout documents are here. Waiting on final payapp from Triton.
07/27/22 – Closeout documents are being finalized. O&M manuals are at the Courthouse awaiting final paperwork.
08/22/22 – Taking project to closeout, requesting additional equipment from Triton.

JC – Drinking Fountain Replacements Read More »

CH – Boiler Rm Carrier Fan Platforms (F029)

01/13/21 – SOSS requested by Hamilton County.
01/20/21 – THP completed a site visit to determine scope.
01/28/21 – THP developing the SOSS.
02/25/21 – SOSS submitted to THP for internal review. Proposal should be issued on 2/26/21.
03/24/21 – SOSS submitted for review.
03/25/21 – SOSS will be combined with the 230 work.
04/01/21 – SOSS approved.
04/19/21 – THP completed field work.
04/27/21 – THP sent SD drawings with draft platform options.
04/29/21 – THP and County to schedule review meeting.
05/11/21 – THP and County met to review SD plan.
05/21/21 – THP DD review drawings and OPC published.
07/26/21 – THP issued “For Bidding” submittal with drawings and project manual.
08/03/21 – THP hosted pre-bid meeting at HC Courthouse and 230 WHT Center.
08/06/21 – THP issued Addendum #1.
08/17/21 – THP issued Addendum #2.
08/24/21 – Bid opening. Received 2 bids from Triton and ZSR. THP to begin vetting process.Bids under advertised budget.
08/26/21 – THP has meeting schedule with Triton on 8/27/21 to review bid proposal.
08/27/21 – THP has phone call with Triton to discuss/review bid. THP sends Hamilton County bid summary/award recommendation letter for Triton.
10/27/21 – THP to schedule kick-off meeting with Triton and Hamilton County.
10/28/2021 – Kick off meeting scheduled for November 4 at 11am.
11/4/21 – Pre-construction meeting with THP, Hamilton County, Triton, William Lang & Sons Co, and Neiheisel Steel.
11/12/21 – THP submitted building permit application.
11/15/21 – Hamilton County Courthouse Boiler Room Safety Platform Shop Drawing Submittal Reviewed and Returned.
12/6/21 – 230 WHT Roof Stair Shop Drawing Submittal Reviewed and Returned.
12/7/21 – CO#1 executed authorizing use of project allowance funds and increase to existing allowance funds to furnish a replacement kitchenette at Courthouse 6th floor.
12/7/21 – Planning for January 2022 for installation of Courthouse Boiler Room Platform.
1/12/22 – THP submitted permit response letter and supplemental documentation to the City for Building Permit Application. Waiting for response from City.
1/25/22 – Building permit application for the Hamilton County Courthouse has been approved. Hamilton County suggests another pre-construction meeting with Hamilton County, THP, and Triton to go over schedule/details before starting work on the boiler room platform. Schedule pre-construction meeting as soon as possible.
2/10/22 – THP, Hamilton County, and Triton had another Pre-Con meeting at Courthouse to go over schedule.
2/16/22 – Triton mobilized to Courthouse to begin site layout and scanning existing boiler room floor.
2/21/22 – Triton to begin sawcutting existing floor for new footers.
3/15/22 – Existing slab sawcut for (4) new column foundations. Other two column foundations will be anchored to existing concrete.
3/18/22 – Terracon onsite to inspect existing soil conditions. To achieve the necessary bearing capacity for the new footings, Terracon recommended to excavate another 6”-8” of material, add a little water, and then tamp the soil for compaction.
3/19/22 – Platform steel delivered to Courthouse Boiler Room.
3/30/22 – Triton starts to pour concrete for (4) new column foundations. Terracon was onsite for special inspections (soil, rebar, concrete). Other two columns will be anchored to existing concrete. Platform installation, steel erection to follow.
4/26/22 – Courthouse platform installation is complete. Triton to coordinate final cleanup and paint touch up before final walk through. THP to coordinate final inspections.
5/25/22 – Courthouse platform installation is complete. THP and Triton to coordinate final cleanup and paint touch up before final walk through. THP to coordinate final inspections with Terracon and City.
06/24/22 – Terracon completed steel inspection.
07/28/22 – Triton finishing punch list work this week.
08/02/22 – Walk through with Hamilton County and Triton to review punch list items. Hamilton County satisfied with completion of the project.
08/24/22 – Final inspection with City of Cincinnati Building Department completed. City to close permit.
09/27/22 – Final Inspections have been completed. Waiting for City Inspector to close Permit. Called City Inspector on 9/27/22 to get update. City Inspector said he was going to close Permit.
10/12/22 – Permit has been closed by City of Cincinnati. Triton is working on finalized pay app and required closeout documents.
12/07/22 – Required close out paperwork and final pay app submitted to Hamilton County.
01/19/22 – THP requested CAD files from Hamilton County to update Master Files.

CH – Boiler Rm Carrier Fan Platforms (F029) Read More »

A&D – First Floor EMF Study

PM – Rycca Thacker, Mike Barth

03/24/21 – HCFD requests SOSS from TEI for an Electromagnetic Investigation of the first floor of the A&D building. ThermalTech soliciting venders to provide us a quote to measure the EM waves in the area, and will submit SOSS once we receive the quotation.
04/28/21 – TEI submits SOSS to HCFD. Project pending approval of SOSS and PO.
05/26/21 – TEI receives signed SOSS and PO. Study phase started.
06/23/21 – TEI, Rycca, Steve T, and Claude T perform walk through of space on 06/23/21 to document the EMF readings in the area of concern. Initial readings were higher than expected levels. Report and recommendations to follow.
07/28/21 – TEI working on report – with continued research for appropriate recommendations.
08/26/21 – TEI nearing wrapping up draft of report to deliver to HCFD. Will complete the report upon completion of 2022 estimates.
10/26/21 – TEI to deliver draft of report to HCFD 11/05/21.
12/13/21 – TEI submitted hard copy draft of report to HCFD for review and comments.  Final report pending HCFD review.
01/25/22 – Final report pending HCFD review.
02/23/22 – Final report pending HCFD review.
04/27/22 – TEI receives comments from HCFD on  04/18/22.  TEI incorporating comments and will deliver final draft to HCFD.
04/28/22 – Today’s discussion centered around adding to the study with a physicist recommendation on lead abatement protection. Champlin will lead collecting the information for the additional study and pulling in a third party person to help us update our report. Eventually, this will turn into a new report to the County. Meeting next Tuesday with THP, TEI and Champlin.
09/26/22 – TEI hand delivers (4) hard copies of the EMF report to HCFD.
10/26/23 – Project still on hold until further notice from HCFD.
12/12/24 – BW said to go ahead and send the final report to Rycca and close the project.
02/27/25 – OK to Archive.

A&D – First Floor EMF Study Read More »

Arc Flash – Heliport, P&D Garage and Records Center

03/24/21 – HCFD requests and TEI submits SOSS to provide Arc Flash Electrical System modeling and labeling at the Sheriff’s Heliport, the P&D Garage, and the Records Center. Project Pending SOSS approval and PO.
04/28/21 – Project Pending SOSS approval and PO.
5/26/21 – TEI receives signed SOSS and PO. TEI scheduling kickoff meeting with JN to begin field investigation and calculation phase of the study at all three facilities.
06/23/21 – TEI requests available fault information from Duke Energy for all 3 facilities. Upon receipt of data from Duke Energy, field work will be scheduled for each of the 3 facilities and studies will be completed.
07/28/21 – TEI receives data from Duke on Heliport and P&D garage, still waiting (and repeated requests) on Records Center Data. Upon receipt, we will schedule field work for input into models.
08/26/21 – Data from Duke still pending for record center. Multiple phone calls, when we talk to a rep, they pass along to someone else and the process starts over again.
10/26/21 – Data received from Duke. All buildings have been visited. Conn (EE on project) will schedule Phasor with Ian Zellner upon his return from vacation.
12/13/21 – site visits with EC to confirm feeder sizes etc.  Finalize the model and submit to Charlie for final approval prior to application of labels.

02/23/22 – TEI submits finalized model calculations and report to CMI for review.   We will schedule application of labels upon receipt of approval from Charlie.

04/27/22 – TEI receives CMI comments – and incorporated into the model.  TEI printing labels on 04/27/22 and scheduling time with building manager to apply labels (week of 5/2/22).

05/26/22 – All labels complete and applied at building sites.   Project complete.

Arc Flash – Heliport, P&D Garage and Records Center Read More »

Animal Shelter – Kennel HVAC Modifications

03/24/21 – AKM requests SOSS for the installation of mini-split HVAC systems for (2) kennels. TEI is authoring and will submit by end of the day 03/26/21.
04/28/21 – SOSS submitted. Project completion pending SOSS approval.
05/26/21 – TEI receives signed SOSS and PO. TEI completes drawings and submits to IBI for Plan review. Plan review approved and TEI applies for permit. Installation work to be coordinate with Trades and building manager.
06/23/21 – Permits received. Work installed. Upon repair of boards in the units (due to pest infestation, electronics were compromised), final inspections will occur.
07/28/21 – Repairs have been completed and ready for TEI to call IBI and Schedule a final. TEI coordinating with Trades and IBI and will schedule in the next few days.
08/26/21 – IBI final inspection scheduled for 08/27/21. Time TBD, per IBI standards, must call day of the inspection to get timing. TEI coordinating with John Kleeman and John Nester.
10/26/21 – IBI required to have HVAC permit prior to the final for IBI. TEI developed HVAC documents and are awaiting permit approval and inspection to re-schedule the IBI final.
12/13/21 – Plan review and zoning have verbally approved.  TEI was told full approval for the HVAC permit will be approved on 12/17/21.  Once approved and picked up, we can have inspection, approval, and then have IBI final inspection.
01/25/22 – HVAC plans approved.  Need to schedule final HVAC inspection and also final IBI
02/23/22 – Per building manager – 3 out of 4 units not functioning currently due to rodent issues.   building manager will contact TEI when the units are operational so that we can schedule the finals.
04/27/22 – inspections pending units being operational.
05/26/22 – HVAC inspection complete/passed.  IBI pending repairs to work by NK heating and Air.  Building manager to notify TEI when we can schedule final.
06/28/22 – IBI pending repairs to work by NK heating and Air.  Building manager to notify TEI when we can schedule final.
07/27/22 – IBI PASSES inspection!  Project complete!

Animal Shelter – Kennel HVAC Modifications Read More »

800 – Elevator Monitoring System Upgrade

PM: John Nester, Mike Barth

03/24/21 – HCFD requests SOSS for project. TEI submits SOSS and receives approval of the SOSS and the PO. kickoff meeting with facilities and building manager to be scheduled week of 03/29/21.
04/28/21 – TEI and HCFD meet with building manager and kick off design of the project. Project in design process.
05/26/21 – Project in process. TEI to confirm pathways from machine room to machine room, and then will submit review set to HCFD for comments.
06/23/21 – Project in process. TEI to confirm pathways from machine room to machine room, and then will submit review set to HCFD for comments.
07/28/21 – TEI submits drawings to HCFD for review comments. Receives comments from JN, awaiting comments from building manager. Package will be issued upon receipt of all comments.
08/26/21 – TEI and HCFD PM finalize bid set. Project out to bid date is 08/31/21, and bids due on 09/22/21. ITB # = 081-21
10/26/21 – Bids received. Fujitek is low bidder. TEI vets their bid, and the contract and PO was approved. Materials are on order, and upon receipt, installation will be scheduled.
12/13/21 – Installation pending arrival of parts.
01/25/22 – Installation pending contractor background checks.
02/23/22 – Preconstruction meeting scheduled for 02/22/22 – cancelled due to vendor having C-19.   Pre Construction meeting re-scheduled for 3/8/22 at 9:00 AM.
04/27/22 – Project construction has began.   Work occurring in the penthouses.
05/26/22 – Construction completion pending materials arrival.
06/28/22 – Construction completion pending materials arrival.
07/27/22 – Fujitec, HCFD and TEI meet to discuss the existing software and the proposed software, and the incompatibility issues.  TEI and HCFD to develop response and plan moving forward.
09/26/22 – Fujitec to install updated software.
10/26/22 – Waiting on install from Fujitec.
12/15/22 – Waiting on Install from Fujitec.
01/25/23 – John Nester receives notice from Fujitec that all project personnel are no longer working for Fujitec.   TEI and HCFD working to get new contact information to have Fujitec complete the project.
02/23/23 – Fujitec new personnel working to complete project.
03/29/23 – Fujitec experiencing a lot of personnel turn over.   This project still pending.  There are issues with one of the elevators on the monitoring system and until that is repaired, Fujitec not comfortable taking down the other cabs.
04/27/23 – No update from Fujitec.
05/23/23 – No updates from Fujitec.
06/28/23 – No updates from Fujitec.
07/26/23 – Fujitec!!!
08/31/23 – Fujitec and Kone working together to repair obsolete equipment in the building. Billing is not right.
10/26/23 – TEI works with Fujitec to correct billing (several attempts).  TEI certifies pay application and delivers to HCFD for payment.
12/06/23 – No updates from Fujitec.
06/27/24 – No updates. Fujitec needs Kone aftermarket group to furnish some missing parts so they can continue working.
07/24/24 – HCFD, TEI and newer Fujitec regional sales mgr meet in B-90. Speak of issues. Fujitec asks for 3-4 weeks to look into issues and solutions.
08/28/24 – No Updates from Fujitec.
07/30/25 – This will be picked up in the elevator modernization project.
08/28/25 – OK to Archive.

800 – Elevator Monitoring System Upgrade Read More »

237 WHT – HCPHD TB Clinic Entrance Security Access Control.

PM – John Nester, Mike Barth

03/24/21 – HCFD requests SOSS from TEI for SD/Estimating. TEI and HCFD conduct phone call with Greg Varner of Public Health to clarify scope on 03/24/21 and then TEI will finalize and submit SOSS.
04/28/21 – TEI and HCFD meet with Greg Varner and walk the space. TEI authors and submits SOSS. Project pending SOSS approval and PO.
05/26/21 – Project pending SOSS approval and PO.
06/23/21 – TEI receives approved SOSS and PO. Project field work to be scheduled with JN of HCFD
07/28/21 – TEI develops SD drawings and estimates for HCFD review. TEI to send to JN for review and comments by 08/06/21 – then finalize for official submission upon receipt of JN comments.
08/26/21 – TEI sends SD package to HCFD to send to public health. TEI sends HCFD PM estimate of fees for taking project through CD’s and CA. Project pending approval funding.
10/26/21 – Project pending approval of SOSS and PO.
10/28/21 – SOSS approved and work can continue.
12/13/21 – Final review documents to be sent for owenr review on 12/17/21.  Review teams Meeting scheduled for 12/20/21 at 2:00 PM.
01/25/22 – Project has been issued for bids.  Prebid meeting is scheduled for February 2, 2022
02/23/22 – Project issued for bidding per HC small project bidding process.   Bids due to TEI on 02/25/22.
04/27/22 – Project re-bid per ITB process.   (1) bid received from Triton.   TEI vets bid and recommends Triton for project.  Contracts drafted and at prosecutors office for review.  Construction to commence upon approved contracts and PO issuance.
05/26/22 – Construction to commence upon approved contracts and PO issuance.
06/28/22 – Construction to commence upon approved contracts and PO issuance.

07/27/22 – Project to commence upon material procurement.

08/24/22 – Project to commence upon material procurement.  All submittals retturned.

09/26/22 – Project to commence upon material procurement.

10/26/22 – TEI, HCFD and HCPH have kick off meeting with Triton.  Materials on order and project schedule being developed by Triton.

12/15/22 – Walls and door frames installed.   DK to mobilize Monday 12/19/22 to begin the Electrical install.

01/25/23 – Construction progressing.  Upon approved inspection, walls can be closed up.   Final door hardware not arrived yet.  Powered door operator not on site yet.  Construction completion pending materials arrivals.

02/23/23 – Ready to Archive.

03/29/23 – HCFD and TEI provide preliminary punchlist.   Items being addressed and waiting on final inspections.

04/27/23 – HCFD and TEI to perform final punchlist.

05/23/23 – Once punchlist is complete, the project is complete, with the exception of the door outside of the scope of the project that the inspection agency wants panic hardware installed on.

06/28/23 – Triton working to resolve final panic hardware issues, and then will have final inspection.

237 WHT – HCPHD TB Clinic Entrance Security Access Control. Read More »

JC – 2021 Cell Door Replacement (Ph 1)

PM: Matt Butz, Sam Hofmann
02/22/21 – Received approved SOSS. waiting for more information to proceed with design.
03/18/21 – Design Kick-off meeting with County, Sheriffs, Champlin and ThermalTech.
03/22/21 – Site visit by Sam Hofmann and Jeff Cyrus. Further developing plans and gathering information.
04/29/21 – Several Manufacturers researched. Wrapping up DD set for review.
05/21/21 – User meeting to finalize scope. Shereen provided existing building door details for coordination purposes.
06/08/21 – Updated plans sent to manufacturers for pricing. still waiting on Door and frame prices. Requested county to investigate existing hardware.
06/15/21 – Received information on low voltage locks. still waiting on information on high voltage locks.
07/14/21 – Champlin identified current contractor in building and requested updated specs and estimates.
08/25/21 – Final meeting held. scheduled to go out to bid on 9/2
09/02/21 – Bid issued
09/23/21 – Bid opening. Triton is apparent low bidder.
10/15/21 – Zoom meeting with Triton, Champlin, and Thermaltech. Letter of Recommendation sent to County.
12/09/21 – Contract and PO Issued. Permit filed.
01/26/22 – Construction kickoff meeting scheduled for 2/7.
02/24/22 – Submittals starting to be received. Progress meetings will start in June when construction starts.
03/31/22 – CA ongoing.
04/28/22 – CA ongoing. Information required from the sheriffs in order for Triton to order locksets. phone call with vendor confirmed the information is in the sheriffs possession. Our attempts to contact Sheriff have not been successful.
05/26/22 – Information from Sheriffs received. Submittals returned. Triton to provide a construction schedule when determined.
06/30/22 – Submittals resubmitted and returned. Triton to provide schedule when materials are ordered.
07/28/22 – Triton selected new Project Manager. Jeff W to provide update.
08/25/22 – Final submittals returned. project kick off to be scheduled.
09/29/22 – Kick off to be scheduled in near future.
10/27/22 – Update from Triton puts project start in late January.
12/15/22 – No update.
01/26/23 – Project on schedule to start in February.
02/22/23 – Update from Triton stated doors wont be delivered until end of March
03/30/23 – Triton mobilized on site. Jails delayed some materials but shouldn’t impact schedule.
04/27/23 – Phase 1 and 2 to be complete by 4/29.
05/25/23 – Phase 1 and 2 complete. Phase 3 ongoing.
06/29/23 – Phase 3 and 4 complete. Final phase to begin next week.
07/27/23 – All doors installed. Punchlist items outstanding.
08/31/23 – Backpunch returned to Triton for final touch ups.
09/28/23 – Project complete. Triton to provide closeouts.
10/25/23 – No Update.
12/07/23 – No Update.
02/29/24 – No Update.
03/28/24 – No Update.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – Closeouts received. Need to be reviewed.
09/26/24 – Sam to continue closeout paperwork reviews.
12/12/24 – No update
01/30/24 – Triton and County held meeting to review all outstanding documents needed.
03/27/25 – Closeouts received.
05/29/25 – Final payment released. OK to Archive this project.

JC – 2021 Cell Door Replacement (Ph 1) Read More »

CH – Server Room Construction

PM: Matt Butz, Terry Cannon

01/06/21 – Foundation submittals arrived and was approved by THP.
01/26/21 – Graybach is ramping up the start of the project again shooting for a 2/15 restart date. The schedule is being updated for this start date. We will start sending out weekly updates on background checks and project updates this week. More steel submittals have been submitted and returned and we are currently finalizing and coordinating efforts with all the sub-contracts on status of equipment approvals from last year. A couple of RFI have been submitted, answered and returned for the GC.
02/02/21 – Change Order #2 arrived. Very large change order, TEI requested additional backup to this change order before taking it to the County. On 2/10reached out to Graybach for additional information and further breakdown on Subs costs for this CO.
02/03/21 – Updated LEADS list arrives, only one Graybach employee aprp2/10 – Permits approved for Building and HVAC work. Paid for and picked up by Graybach. Skip Zimmer is our inspector for this job.
02/06/21 – Three sets of questions/suggestions have been sent in on the steel submittals have been sent it and THP has been reviewing and answering. Everything has been approved except for the weight of the hatch. The county asked that the hatch weight 50 lbs or less and the submittal has them at 92 lbs, we continue to work with Graybach and their sub for an acceptable weight. As of 2/17 we do not have the final solution and they believe there is a cost impact to that solution when we make the change.
02/10/21 – Graybach making headway on badging. One superintendent, Nick Neyer, approved. He will be ready to go on March 1. Several other people have been. Graybach requested we setup Pre Const Mtg #2. Send me good days this week for that meeting please. Barth and I can do Tuesday afternoon, Wednesday morning, Friday all day.
02/16/21 – Concrete mix submittal arrived and uploaded to Procore.
02/17/21 – Rebar submittals returned. Fall arrest submittal submitted, uploaded to Procore on 2/22.
02/19/21 – Safety guide submitted arrived, forwarded on 2/22.
02/22/21 – Background check update worksheet attached.
02/24/21 – Pre Const Mtg held. Graybach furnished SOV and Project Schedule for final review. TTC to distribute meeting notes and changes order to the county. Graybach scheduled to start on March 8 with demo and complete the job in July 2022.
03/09/21 – Const Mtg #1 held. Graybach started its own Procore site for this project. Room 263 scope discussed and reviewed with Graybach. Ceiling heights were discussed in regards to the HVAC and Fire devices.
03/16/21 – Const Mtg #2 held. Parking lot spacing and usage discussed. RFI submitted to Procore site. Hallway door options discussed, project schedule closer to final, change order #2 and #4 were discussed and submitted for consideration.
03/23/21 – Const Mtg #3 held. Project schedule submitted, follow-up afterwords targetted dates for site work and eventual server room work. TTE reviewing material change order cost from 2021 means. Geiler, Graybach, County, ThermalTech to have a conference call on upcharge for Liebert units. TTE working on Rack options for the job to discuss with CMS and Facilities. Data cable and server racks to be purchased by owner, fiber provided by DK, HC telecom providing data and phone in Room 263.
04/29/21 – Weekly Const mtgs underway. Room 263 progressing, studs are up, rough-in inspection is complete, HVAC and electrical work is started. In the Courtyard the concreate has been poured and THP has checked on progress. Terracon has been on site for special inspections. The grade beams and column bases are in place and getting wet today. Additional meetings for finalizing racks, discussing change orders and coordinating with CMSNet.
05/27/21 – Room #263 work continues for mid-June move in date. GBBN punchlist 5/28, TEI punchlist 6/4.
05/28/21 – GBBN punchlist distributed to contractors. Spencer’s last day on the project.
06/04/21 – ThermalTech punchlist visit complete and distributed.
06/08/21 – Met on Platform questions and generator placement.
06/09/21 – Met Kohler on-site for generator placement questions and code requirements.
06/17/21 – Prosecutor moves into Room #263.
06/22/21 – Met with Fire Marshal on generator placement, code questions and CFD requirements. ThermalTech summarizes meeting notes for CFD, following up on additional research for generator needs.
06/24/21 – Created bollards drawings, sent to Graybach for pricing.
06/25/21 – Discussed resolving the CFD and BPS issues on the generator and platform placement work and needs. Steering committee meeting when very well. FM-200 safety characteristics passed along to committee. If the generator fits on the existing platform and can be five feet from the wall, that is preferred. Add bollards around the platform okay, adding paint for fire proofing on structure okay too, THP to get more info for TEI.
07/06/21 – Const Mtg. Progess continues. We are working on change order items and starting server room demo.
07/13/22 – Const Mtg. Server room demolition continues. Questions from GC, controls and fire protection.
07/20/21 – Const Mtg move to 7/22.
07/22/21 – Full Const Mtg with all subs. We are working on plumbing pan, fire protection coordination, mechanical layout, window removals, schedule, demo and HVAC controls. Server room demo well underway. Work in CMS spaces making good progress and new walls and wall openings are looking good. Follow up meeting with County on reclaiming the HVAC shaft into an electrical room was held. COR sent to Graybach for pricing.
07/28/21 – No const mtg this week. CFD emails resent and permit drawings were sent directly to fire department per their request.
08/24/21 – Weekly Const Mtgs continue. First floor mechanical and fire work continue. Coredrills plans for this week. Patching continues and painting to start next week. The schedule is becoming clearer for Server Room work but we need a decision on the generator placement. Pipe support RFI submitted for comment.
08/25/21 – CFD returned our calls and emails and agreed to our proposals on the emergency generator so we can move forward with moving the generator 5ft away from the building in all directions, no bollards, no painting and fuel oil system is okay.
08/26/21 – Material change order cost submitted for approval.
09/07/21 – Const Mtg. Generator placement and structural changes discussed.
09/14/21 – Const Mtg.
09/21/21 – Const Mtg.
09/28/21 – Const Mtg. Sprinkler piping relocation requested.
10/05/21 – Const Mtg. Condensing units set on platform.
10/12/21 – Const Mtg. Battery charging question.
10/19/21 – Const Mtg. Condensing Unit placement, disconnect locations discussion.
10/26/21 – Const Mtg. Condensing unit orientation, disconnect location picked, generator steel rework finalized. Fuel oil routing discussed. RFIs for electrical (Clean agent panel power and Fiber optic cable selection ) responded to in Procor. Projected date to set the Egen on platform is 11-11.
11/02/21 – Const mtg discussed project updates, fire protection changes for hot aisle design and generator controls meeting.  Working with CDW on Rack order.
11/09/21 – Const Mtg. JCI submitted revised hot aisle fire protection drawing.  TEI approved.  Fiber rating and telecomm wiring discussed.  Generator lift scheduled for 11/11.  DK to complete steel modifications prior to setting the generator.
11/11/21 – Const Mtg. Generator lift schedule in Courtyard.  TEI on-site and logged with pictures and video.  The generator was set without incidence.
11/16/21 – Const Mtg. Discussed next stages of work including CO for armored cable, server rack selections, fiber cable requirements, fuel oil excavation and generator control.
11/23/21 – Const Mtg. Graybach working on updating change orders from the previous PM.  TTC and Reid meeting on CO status. Final fuel oil line coordination discussed.  We confirmed the racks would arrive unassembled to the job site.
11/30/21 – Const Mtg. COR 21, 22 sent in by Graybach this week.
12/04/21 – Fuel oil excavation begins in Courtyard, Geiler working weekends and late nights.  Geiler hit several underground conditions while digging the trench for the fuel oil pipe but in the end the line is in adn it was pressure tested adn held for days.  Geiler backfill adn cover the pipe.  Plates cover the trench.
12/07/21 – Const Mtg.  Fuel Oil line pipe is underground Reviewed Generator controls sequences.  Fuel Oil valves provided by TEI to Geiler for official submittal from WC Storey.  Blacktop and sealing later this week.  Under platform to be turned over to DK next week.
12/09/21 – Several options for temporary boiler power submitted to county for approval by MCB.  TTC and Matt review and comment.  TTC working with Ameresco and feasibility to use new JC steam boilers ahead by Jan 17 to carry the load temporarily.
12/12/21 – TTC working with Bert and Matt on potentially changing the number of server racks purchased and sending out surveys to departments that are interesting in coming over to the new server room.  TTC latest density calculations show that we have plenty of spare capacity even if we reduce the number of server racks in the server room to 22 total racks instead of 24.  Physically this appears to fit better in the space with the latest equipment layout.  TTC to follow up with CDWG.
01/25/22 – Flooring work mostly complete. Generator controls and sequences worked out with Buckeye, testing of the generator tanks can begin. Final piping and fuel oil ties can be scheduled. Electrical outage and temporary power plan in place for Feb 5, 12. Geiler will be back for Gen exhaust and venting work. 9 server racks have arrived and are at the DK warehouse. The CH Server Survey has been sent for distribution.
02/24/22 – Met Fire Marshal on site and got approval for generator and fuel oil installation from CFD. Generator tanks have been tested and passed, exhaust and venting work completed, cable trays are being installed in the room now. Electric work continues, power outages complete, temporary connections made, Server Racks on on site, floor waxing tentatively scheduled for early March, and Server survey came back from CMS yesterday.
03/31/22 – All racks are in the room. Power being pulled to room this weekend. HP was onsite and assembled half the units. HAC coming soon, RFI for new duct size opened. Rack Survey being converted to rack loading. CMS gets 6 or 7 racks in the layout. Equipment startup next week.
04/28/22 – Final electric shutdown is scheduled for this weekend. HPE was onsite to verify missing parts this week and will be back on Thursday and Friday to install accessories. Missing parts are on order (I think). Door access control and security cameras hookup was resolved and email sent. DK to test fuel oil pump system and start coordinating Al Harden field visit for final testing with Buckeye and TEI.
05/25/22 – The contractors are almost complete. Graybach has performed their punchlist review and uploaded to Procore for ThermalTech review. HPE has not given us an update on the warranty replacement parts yet so we are field changing some stuff to make this work out for us when the parts arrive. The Clean Agent system is live and all water removed from the room. Door access and security cameras are on. The facilities switch is programmed with Honeywell IP addresses, we need to get a Cat6 cable pulled from 2 to 5 for Honeywell to communicate. Randy will be back June 6 week to finish up. Liebert startup is being scheduled. Internal fuel oil pump testing next Tuesday with TEI then we will schedule Al Harden for final. Final department survey due from TTC to County. Rack switches were not included in our budget. We should setup a design meeting with CMS about final configuration details in the next couple of weeks. TTC to help provide update at next steering committee meeting.
06/14/22 – Telecomm meeting about fiber interconnects was held with Mitch.
06/17/22 – TTC replaced the warranty items on the server racks and got them to a place where they all work and the HAC is contained.
06/20/22 – The Generator Load Bank testing was completed today. The second fire alarm test was conducted with unsatisfactory results. TEI trying to get contractors to rectify issues and troubleshoot the system. The remaining fuel oil pump started leaking today and was shutdown but testing continued.
06/23/22 – Bert asked about the condenser coil cleaner and protecting the refgrigerant lines.
06/29/22 – A change order meeting was held with the county today to review the cost submitted with change order COR4 for the job. The contractors provide cost and hour backup for their change order COR-4. We reviewed with County.
06/30/22 – Graybach punchlist items are starting to be completed. TEI needs to issue its punchlist this week.
07/27/22 – This month the Facility Switch was installed and Honeywell setup communication was started. The fiber connections are in. The HAC are finished. The fuel oil containment pipe is installed but no terminated. The final generator test is being scheduled for early August. IBI permit for modified grounding is approved and was paid for on 7/26. JCI submitted revised change order for fire alarm devices in the Server Room, DK and Graybach to fully submit.
07/29/22 – IBI Grounding permit was approved today. Information sent to contractors.
08/11/22 – Generator Testing passed city inspection. We still need to connect fuel oil drain line to county detection system.
08/22/22 – We have been working on final change order cost all week adn finalized remaining change orders with Graybach. Sent to County for review.
08/23/22 – Attended change order meeting with Graybach and DK and resolved final change orders with contractors. Worked on finalizing and inspection schedule to wrap this project up with the city and contractors and turn over to the city.
08/26/22 – All inspections to be complete by 9/15/22. Schedule backup testing for the generator.
09/10/22 – Final electric testing scheduled. Kirk key operation tested. All test passed.
09/21/22 – Fire Alarm pretest scheduled with JCI & Dk. Discrepancies found and rectified.
09/22/22 – Fire Alarm and General Const final fire alarm test scheduled in the evening. Final inspections passed.
09/23/22 – Final change orders being collected. Next payapp reviewed.
09/25/22 – CRAC training scheduled for 10/6 with County & ThermalTech.
09/10/22 – Final electric testings for backup power sources. Test passed.
09/20/22 – Final Fire Alarm & General Const inspection. Inspection passed.
09/29/22 – TTC to check on parking lot spaces, coordinate with Tony, Rycca, Matt.
10/26/22 – Clean agent training complete, electric training complete, signs arrived, final cleanup instruction issued to Graybach. Closeout documents coming in for final approval. Floor condition needs to be addressed by Graybach for dents and paint on floor. CMSnet ready for access.
12/15/22 – Graybach says floor tiles are replaced, clean and wax scheduled for this Saturday, coordinating with Jesse on access. Met with Planning & Development, requested data from Facilities on server counts, met with CMS and Telecom on core switching and interconnection. Reviewing and approving closeout documents from Procore.
01/24/23 – Telecomm finishing their work for communications. TTC really needs to get the rest of the departments ready to start migrating to the server room by reaching out to each of the departments. I have been in contact with HP a multitude of times and been passed to two new sales reps trying to find the keys. Birdscreen in production. Labels need to be made.
02/22/23 – Closeout documents are approved, Graybach working on hard copies. Meeting on 2/27/23 for RCIC cutover.
03/30/23 – Signage on switches complete, birdscreen to meet DK on site, O&M one hard copy complete we need two more hard copies for the county, backup generator is below critical high alarm after last weekend work, firmware patch delayed for two weeks for generator comms, surveys sent out to tenants, core switch coming next week, RCIC meeting mid-April with CMS and CAGIS.
04/26/23 – Currently working on telecom communications, decommissioning the Admin 9th floor, repathing the fiber connections, survey final room tenants, applying firmware patch to generator and some controls checking on Honeywell system. We’ve met with CMS, Telecom, CAGIS and City this month several times.
05/21/23 – Several department meetings coming up next two weeks. Most departments have returned our calls and we have space for them in the server room. We are working on getting the fiber cable ran from CH to Admin right now so we can close out.
06/28/23 – This month we finalized meetings with the end users for spaces and confirmed nobody has too much equipment for the Rack they’ve been assigned. We’ve also had several meetings with Debra Kuempel on providing this fiber line but they are not doing the work nor are they giving us a cost to do the work. Our next step is to solicit a price from another vendor for this work. Both CMSnet and Telecom have communications up and running in the server and are ready to start testing communications in the room. Next month we potentially can have equipment in the room full time.
07/26/23 – Fiber meeting wtih DK scheduled for this Friday. Prices came in from Glenwood. We are working with City on their fiber prices.
08/29/23 – City prices coming Friday. Working with P&D, DDS and Risk Mgmt for move-in timelines. CMSnet is in the space and using the system. The second Liebert has been started, the temperatures have been turned down some.
09/27/23 – Risk Mgmt released to move in on their schedule. P&D scheduled to move in October 5. Met with Chris yesterday and measured his equipment and confirmed it all fits in the Rack we’ve designated for P&D. Scheduled a meeting with the Treasurer for Oct 6 for a walk through with them in the server room. All equipment appears to be running and operating properly.
10/25/23 – Room is ready for occupancy. The Emergency Power Off button was accidentally engaged this month. The room was restarted and ThermalTech created as step by step guide for a cold system restart. An alarm Lexan cover was installed by TTE to prevent another accidental EPO. Keys assemblies were removed and given to Acme to match locks and keys, no final word back form Acme yet. HPE can source new locks for about $3500 for 12 (6 front, 6 rear) locks, TTE would install these if accepted but we are hoping Acme can rekey them for cheaper. Jack Wilson at Acme is our contact. Mickey Halls at HPE is leaving the company and we have a new contact to finish the order if we go that route.
12/06/23 – Email to DK and Graybach today about the scope reduction letter. No final acceptance from DK has been forthcoming. We have shared everything the city gave me with Graybach and emailed them an update. HPE has provided the Sole Source letter for the keys. We are in the process of getting a PO for the new keys. Met with City CAGIS this week and showed them the server room specifics and access.
01/31/24 – This month P&D has moved into the server room. HCSO has moved into the Server Room and the final key order was placed and is scheduled to arrive on 3/4/24. The remote temperature sensor is not working for TE.
02/23/24 – Closeout documents updated and turned over to Matt on two USB’s.
03/22/24 – New CMSnet locks are installed on CMS racks. Keys left for CMS and marked for each rack. The new locks are individual to each rack. CAGIS is currently moving over to the server room this evening. Matt and Terry were on site while the movers were onsite. As of 11pm Telecom got communication pathways all setup. Switches are installed, servers are installed, i know telecom can ping the equipment. Just waiting for CAGIS to come back online now.
04/24/24 – Project is complete. Closeout documents are submitted. Ready to Archive.

CH – Server Room Construction Read More »

JC – Pneumatic Delivery System

09/03/20 – SOSS and scope of work discussed for this project.
09/22/20 – Initial fieldwork.
09/23/20 – Pulled drawings from the Archive and scanned them for use on this job.
10/27/20 – Talked to Colombo and got a quote for system replacement, shared cost with county.
12/15/20 – Very preliminary cost and options sent to county and sheriff for review.
12/30/20 – Email summary sent to county and sheriff, repair options and replacement options discussed. TTC reached back out to Colombo for additional pricing on 12/31.
01/26/21 – Recommissioning cost never came back from Colombo, TTC woefully behind on final report to Bert. All work to be bid through this estimate, don’t use trades labor on this job.
02/24/21 – TTC needs to send final report with costs. Not done yet.
03/01/21 – ThermalTech sent Draft Report with costs to the County for review. The recommendation is to bid out the repair of the existing system replacing major equipment but all existing tubes can remain. Colombo sent in additional information for pricing today. TTC reached out with request for full replacement cost.
03/25/21 – Report complete and with the County, Facilities and Sheriff discussing next steps.
04/29/21 – Awaiting next steps.
05/24/21 – Colombo sent an email stating that the replacement carrier they had manufactured is ready for testing. I put us down for one at $350 when they are ready for public purchase.
05/27/21 – County reported the Sheriff has some movement on this project, TBD
06/25/21 – No updates from TTE this month.
07/28/21 – No updates.
08/26/21 – No updates.

10/28/21 – No updates. OK to archive.

JC – Pneumatic Delivery System Read More »

CH – Boiler Room Exhaust Fan Platforms (F024)

01/13/21 – SOSS requested by Hamilton County.
01/20/21 – THP completed a site visit to determine scope.
01/28/21 – THP developing the SOSS.
02/25/21 – SOSS submitted to THP for internal review. Proposal should be issued on 2/26/21.
03/24/21 – SOSS submitted for review.
04/01/21 – SOSS approved.
04/19/21 – THP completed field work.
04/27/21 – THP sent SD drawings with draft platform options.
04/29/21 – THP and County to schedule review meeting.
05/11/21 – THP and County met to review SD plan.
05/21/21 – THP DD review drawings and OPC published.
07/26/21 – THP issued “For Bidding” submittal with drawings and project manual.
08/03/21 – THP hosted pre-bid meeting at HC Courthouse and 230 WHT Center.
08/06/21 – THP issued Addendum #1.
08/17/21 – THP issued Addendum #2.
08/24/21 – Bid opening. Received 2 bids from Triton and ZSR. THP to begin vetting process.Bids under advertised budget.
08/26/21 – THP has meeting schedule with Triton on 8/27/21 to review bid proposal.
08/27/21 – THP has phone call with Triton to discuss/review bid. THP sends Hamilton County bid summary/award recommendation letter for Triton.
10/27/21 – THP to schedule kick-off meeting with Triton and Hamilton County.
10/28/2021 – Kick off meeting scheduled for November 4 at 11am.
11/4/21 – Pre-construction meeting with THP, Hamilton County, Triton, William Lang & Sons Co, and Neiheisel Steel.
11/12/21 – THP submitted building permit application.
11/15/21 – Hamilton County Courthouse Boiler Room Safety Platform Shop Drawing Submittal Reviewed and Returned.
12/6/21 – 230 WHT Roof Stair Shop Drawing Submittal Reviewed and Returned.
12/7/21 – CO#1 executed authorizing use of project allowance funds and increase to existing allowance funds to furnish a replacement kitchenette at Courthouse 6th floor.
12/7/21 – Planning for January 2022 for installation of Courthouse Boiler Room Platform.
1/12/22 – THP submitted permit response letter and supplemental documentation to the City for Building Permit Application. Waiting for response from City.
1/25/22 – Building permit application for the Hamilton County Courthouse has been approved. Hamilton County suggests another pre-construction meeting with Hamilton County, THP, and Triton to go over schedule/details before starting work on the boiler room platform. Schedule pre-construction meeting as soon as possible.
2/10/22 – THP, Hamilton County, and Triton had another Pre-Con meeting at Courthouse to go over schedule.
2/16/22 – Triton mobilized to Courthouse to begin site layout and scanning existing boiler room floor.
2/21/22 – Triton to begin sawcutting existing floor for new footers.
3/15/22 – Existing slab sawcut for (4) new column foundations. Other two column foundations will be anchored to existing concrete.
3/18/22 – Terracon onsite to inspect existing soil conditions. To achieve the necessary bearing capacity for the new footings, Terracon recommended to excavate another 6”-8” of material, add a little water, and then tamp the soil for compaction.
3/19/22 – Platform steel delivered to Courthouse Boiler Room.
3/30/22 – Triton starts to pour concrete for (4) new column foundations. Terracon was onsite for special inspections (soil, rebar, concrete). Other two columns will be anchored to existing concrete. Platform installation, steel erection to follow.
4/26/22 – Courthouse platform installation is complete. Triton to coordinate final cleanup and paint touch up before final walk through. THP to coordinate final inspections.
5/25/22 – Courthouse platform installation is complete. THP and Triton to coordinate final cleanup and paint touch up before final walk through. THP to coordinate final inspections with Terracon and City.
06/24/22 – Terracon completed steel inspection.
07/28/22 – Triton finishing punch list work this week.
08/02/22 – Walk through with Hamilton County and Triton to review punch list items. Hamilton County satisfied with completion of the project.
08/24/22 – Final inspection with City of Cincinnati Building Department completed. City to close permit.
09/27/22 – Final Inspections have been completed. Waiting for City Inspector to close Permit. Called City Inspector on 9/27/22 to get update. City Inspector said he was going to close Permit.
10/12/22 – Permit has been closed by City of Cincinnati. Triton is working on finalized pay app and required closeout documents.

CH – Boiler Room Exhaust Fan Platforms (F024) Read More »

230 – Cooling Tower Safety Maintenance Stairway (F025)

01/13/21 – SOSS requested by Hamilton County.
01/20/21 – THP completed a site visit to determine scope.
01/28/21 – THP developing the SOSS. OK to combine bids as long as the bids can be separated or itemized.
02/25/21 – SOSS submitted to THP for internal review. Proposal should be issued on 2/26/21.
03/24/21 – SOSS submitted for review.
05/27/21 – Project update County located existing drawings which included a previous THP design. THP plans to issue review drawings by June 2.
06/25/21 – THP to send review set next week to County.
07/26/21 – THP issued “For Bidding” submittal with drawings and project manual.
08/03/21 – THP hosted pre-bid meeting at HC Courthouse and 230 WHT Center.
08/06/21 – THP issued Addendum #1.
08/17/21 – THP issued Addendum #2.
08/24/21 – Bid opening. Received 2 bids from Triton and ZSR. THP to begin vetting process.Bids under advertised budget.
08/26/21 – THP has meeting schedule with Triton on 8/27/21 to review bid proposal.
08/27/21 – THP has phone call with Triton to discuss/review bid. THP sends Hamilton County bid summary/award recommendation letter for Triton.
10/27/21 – THP to schedule kick-off meeting with Triton and Hamilton County.
10/28/2021 – Kick off meeting scheduled for November 4 at 11am.
11/4/21 – Pre-construction meeting with THP, Hamilton County, Triton, William Lang & Sons Co, and Neiheisel Steel.
11/12/21 – THP submitted building permit application.
11/15/21 – Hamilton County Courthouse Boiler Room Safety Platform Shop Drawing Submittal Reviewed and Returned.
12/6/21 – 230 WHT Roof Stair Shop Drawing Submittal Reviewed and Returned.
12/7/21 – CO#1 executed authorizing use of project allowance funds and increase to existing allowance funds to furnish a replacement kitchenette at Courthouse 6th floor.
12/7/21 – Planning for January 2022 for installation of Courthouse Boiler Room Platform.
1/26/22 – THP began process for William Howard Taft Center building permit application. Construction for WHT Center Roof Maintenance Stairs to commence after HC Courthouse
1/26/22 – THP began process for William Howard Taft Center building permit application. Construction for WHT Center Roof Maintenance Stairs to commence after HC Courthouse Boiler Room Platform project. Schedule and start date TBD. Most likely March/April time frame.
2/21/22 – Triton to mobilize to site to field measure site conditions.
2/23/22 – Waiting to hear back from City on the Permit Application.
3/2/22 – Permit application has been approved. Approved drawings and approved project manual has been sent to all parties involved.
4/25/22 – Triton submitted crane lifting plan. Hamilton County asked for additional information be provided for County review. Plan is still to crane material to roof on Saturday, May 7th. Roof stairs installation to begin following week.
5/10/22 – Stair posts installed by Neiheisel and roofing repairs performed by Tremco this week before crane lifting the rest of the material onto the roof.
5/14/22 – Remaining stair material crane lifted onto roof and installed onto posts.
5/16/22 – Neiheisel performed final stair installation and detailing. WHT roof stairs installation completed this week.
5/25/22 – THP and Triton to coordinate final cleanup and paint touch up before the final walk through. THP to coordinate final inspections with Terracon and City.
06/24/22 – Terracon completed steel inspection.
07/28/22 – Triton finishing punch list work this week.
08/02/22 – Walk through with Hamilton County and Triton to review punch list items. Hamilton County satisfied with completion of the project.
08/24/22 – Final inspection with City of Cincinnati Building Department completed. City to close permit.
09/27/22 – Final Inspections have been completed. Waiting for City Inspector to close Permit. Called City Inspector on 9/27/22 to get update. City Inspector said he was going to close Permit.
10/12/22 – Permit has been closed by City of Cincinnati. Triton is working on finalized pay app and required closeout documents.

230 – Cooling Tower Safety Maintenance Stairway (F025) Read More »

TPC – Lobby Renovation

PM: Mike Murphy, Mike Barth
01/08/21 – SOSS Submitted to county for approval.
01/28/21 – PO and SOSS approved.
03/10/21 – Field visit by Sam Hofmann and Tracy Pohl. Further developing plans and selecting finishes.
04/01/21 – Sent renderings and finish options to Bert. A review meeting to select finishes is necessary before continuing.
05/27/21 – No Update.
06/25/21 – Design review committee meeting scheduled for 6/28
07/21/21 – Design Committee review meeting #2.
07/27/21 – Revised rendering and light fixture cut sheets sent to Bert.
08/26/21 – No update.
10/28/21 – Drawings and rendering completed. Estimate in progress.
11/02/21 – Updated Renderings and executive summary sent to County.
01/26/22 – No Update. We should have an update next Tuesday.
02/24/22 – No Update.
03/31/22 – Deadline of end of April to be bid ready.
04/26/22 – field visit to review artwork to be replaced. Bert supplied some additional information. Champlin to provide a suggested strategy for owner approval.
05/26/22 – Final Review set submitted to county. Changes have been made according to Berts comments. To be determined if this project will be combined with the elevator renovation project.
06/30/22 – Project to be bid out separately from Elevator Modernization project on July 7th.
07/28/22 – Project in bidding phase.
08/25/22 – Triton awarded the bid. Contract in progress.
09/29/22 – Contracts in progress
10/27/22 – Contracts in progress
12/15/22 – Contracts signed and returned. Kickoff meeting to be scheduled
01/26/23 – Kick off meeting held. Submittals being returned.
02/22/23 – Submittals returned, ready to issue notice to proceed.
03/30/23 – Notice to proceed sent and schedule received.
04/27/23 – Preconstruction meeting held. Phase plan finalized. Mobilization to start 4/28.
05/25/23 – Construction ongoing. Triton has had issues with staffing and maintaining a properly maintained work area. Phase 1 and 2 complete. Phase 3 in progress.
06/29/23 – Abatement is complete. Triton submitted new schedule.
07/27/23 – Construction ongoing. Axis was on site to begin floor leveling and could not continue due to current state of the floor. Triton to further demo the floor to acceptable conditions. Sconces have been turned rightside up on one column. Mike in contact with King lighting to provide sconce solution.
08/31/23 – County to make decision on installing light kit themselves, sending back to the manufacturer or leaving the fixtures as is. Flooring to be complete early next week. Wall tile installation to begin next week. Reviewed tiling work with County and small changes in how it was tiled is okay. Streetcar scheduled was discussed and posted in the Admin.
09/28/23 – Construction ongoing. Flooring and wall tiles to be complete next week. Second Mural approved.
10/25/23 –  Construction ongoing. Murals to be hung this week. Floors to be polished the next week.
12/07/23 – Punch list complete. Additional signage installed. Back punch to be scheduled in near future.
02/29/24 – Triton to provide closeouts.
03/28/24 – No update.
04/25/24 – No update. Triton getting closeouts in place, discussing some extra from the work on the job.
05/30/24 – No update. Triton owes us about five closeouts for projects, this one included.
06/27/24 – No Update.
07/24/24 – Triton owes us closeout documents for this job.
08/29/24 – No update.
09/26/24 – No update.
12/12/24 – No Update.
01/30/25 – Triton and County held meeting to review all outstanding documents needed.
02/27/25 – No update.
04/24/25 – Closeouts requested from Triton. No response.
05/29/25 – No Update.

TPC – Lobby Renovation Read More »

TPC – Auto Title Office Renovation

01/26/21 – Received signed SOSS from county.
01/28/21 – SOSS and PO approved. We discussed project scope with the team and how to proceed with the new scope and schematic design. CHA and TEI to review proposed furniture layout and make sure their design is permittable and legit, update the cost estimate in Archibus. 19 staff members for new restroom, no men or women signage on new RR.
02/25/21 – TTE to provide opinion of most efficient location for restroom to continue with design
03/12/21 – Furniture meeting on-site attended by County, Autotitle, Champlin and ThermalTech.
03/19/21 – MEP Drawings and cost uploaded to Archibus #2022; extra cost for two bathrooms in comments Section, breakdowns uploaded as PDF.
04/07/21 – Received furniture quote from RCF
04/14/21 – User review meeting. SD estimate modified.
05/27/21 – No Update.

06/25/21 – No Update.

TPC – Auto Title Office Renovation Read More »

Animal Shelter – Exit Signs

01/06/21 – SOSS signed and received.
01/21/21 – Champlin and TTE walkthrough with John Nester to review existing locations and review scope.
02/09/21 – Champlin uploaded Estimate to Archibus.
02/25/21 – TEI needs to add cost to Archibus for this project.
03/02/21 – All estimates are uploaded. Final report to come.
04/29/21 – Estimates are in and final report uploaded to Archibus.
05/27/21 – No Update. OK to Archive

Animal Shelter – Exit Signs Read More »

SPHQ – Furnace 1, 2, 3 Replacements

PM – John Nester, Terry Cannon
12/10/20 – SOSS submitted.
12/28/20 – SOSS approved.
01/11/21 – Fieldwork. ThermalTech & Ian.
01/25/21 – Verified furnace units new and old. Talked to Jackson about historical work at SPHQ and what “3” furnace replacement meant back then. He confirmed what we found on site last week. F-3 in the main SPHQ is new circa 2019. F-17 and F-18 are in the Academy and were installed in 2015, 2016. F-19 is in the Fitness area and was installed in 2004. Thse units may a newer condenser. TTE to verify this.
01/26/21 – Reached out to Ian to setup second field trip for TTE to take off HVAC for CAFM drawings and get information on the Property Barn unit so it can be replaced as part of this project.
02/24/21 – Fieldwork and CAD complete on existing Fitness center. Loads complete on all spaces. TTC to review work.
03/25/21 – HVAC design complete, TTC needs to review and share with the County.
04/29/21 – Marked up changes, awaiting CAD changes and TTC will send to JN for review.
05/26/21 – Talked to Ian and agreed that we need to do more fieldwork on the Property Barn before putting anything on paper for that Alternate. Base Bid and Alternates marked up and turned in for edits. I am waiting to get the electrical on board until the HVAC is complete. I am shooting to have this bid out this summer.
06/11/21 – We met on site and discussed basic scope and alternates with Ian and John. It was decided to demo the non-working Reznor unit and replace the three ceiling hung Reznor units on the back wall. Investigate expanding the ductwork in the property barn for additional comfort control as an alternate.
06/25/21 – MEP drawing mostly ready for county review except for the Alternate on the property barn. The Reznor units are obsolete but we found very similar replacement from our local rep. A cost and new venting was provided for our use in the Alternate design.
07/28/21 – Revised design into CAD for final markups. This will go out for bidding in August.
08/26/21 – TTC getting help to finish this project in the next couple fo weeks.
10/28/21 – Project released for bidding. Addendum #1 was issued on 10/27/21. Bids opening 11/08/21.
12/13/21 – Bids were received and Northern KY was the apparent low bidder.  A pre-award meeting was conducted by TTE and NKYHC was recommended for the work  The PO and Contract were approved in late November.  Submittals were sent to TTE and returned on Sunday 12/12 by TTC.  A pre const meeting is scheduled for 12/22 with the County and contractor.
01/25/22 – Revised scheduled sent to County from NKHC for work in February.
02/24/22 – Work is coming along nicely. New furnace is in, two new unit heaters are installed, RTU is on grade.
03/31/22 – Property Barn thermostat replaced and reprogrammed. Temperature swings still happening overnight but we think the unit heater is off. Ian to check for us.
04/28/22 – New thermostat seems to be working fine. Tony asked about heat in garage because door is being replaced and I told him all new units are installed and working. the old Reznor above the bathrooms is defunct and not being replaced. F-3 is complete and working.
05/25/22 – All work complete on the original scope. IBI permitting getting updated by Rick and Holstegge Electric. We are looking at change order work now with Ian and Rick.
06/30/22 – Electric rework is complete. Rick submitted revised change order for new Condensing Units and is fixing a bad fan on one now.
07/26/22 – Change Order #1 was approved and signed for the replacement of two condensing units. We solicited a change order bid for the full ALC control package which came in and was forwarded to the County for review.
08/09/22 – Sent Change Order #2 request to NKYHC for pricing.
08/23/22 – Checked back on CO progress for the condensing units and the reheat pricing. Controls pricing is already here.
09/22/22 – Submittals received from NKYHC. Payapps received and process for payment. Change Order for the condensing units and coils approved. Hot water reheat change order is but not officially approved yet. County working on PO increase for rest of work. Emcor provided reduced prices for remaining control work.
09/29/22 – Meeting on Monday to review change order work at SPHQ.
10/26/22 – Change Order 3 drawing ready for pricing. TTC coordinate with Rick. Permit drawings almost ready to give to rick for permitting on this job. We updated the floor plan to include the additional RHC locations and upsized the piping for the new work.
12/15/22 – Condensers are installed and ready. The initial refrigerant charge is on the new units. We have a controller question on on of the air handlers but both are wired up and running. Additional change orders are out for pricing. Emcor conversion of existing JCI field components came through this week.
01/24/23 – We have been working all week on getting the change order in placed and the submittal for the hot water coils approved. We are working on Rev-3 versions now. All change order #1 work is complete and inspections are approved.
02/22/23 – Revised RHC drawings sent to Rick and CAI for coil sizing and prices with new temperatures and CFM’s. Base bid and change order 1 work is complete.
03/30/23 – Working on repricing the CO#2 and CO#3 cost with Emcor and NKYHC. CO3 came in at $51,000 but ALC offered a $9000 credit for combined work.
04/17/23 – Controls submittals have been received. NM reviewed the RHC, TTC to do the rest.
04/26/23 – Change Order #3 approved for rest of RHC conversion and controls upgrades for the DDC system at SPHQ. The first batch of RHC are here. Check on start time with Rick.
05/21/23 – RHC are in. Piping is complete for all 15 RHC coils to valves . 7 valves are installed. TTE ready to punchlist first phase.
06/28/23 – Punchlist completed and sent to NKYHC. Requested update from Emcor on ALC progress. New compressors need controls update.
07/26/23 – Emcor upgrading controls, this work should be done in August.
08/23/23 – The project is nearly complete, only a couple of controllers are left.
09/27/23 – All work for this project is complete including HVAC, Electrical and Controls. However there are operational issues we are still addressing which include 1) HW pump did not appear to be pumping enough water, contacted vendor reset control sequence. 2) new condensing units did not have the right controller for dual circuit operation, but this is not fixed but led to question in #3. 3) one of the AHU has a VFD on it and NKYHC reset the speed of this fan in the summer for full load but now that it’s fall, they had to reset to fan to a slower speed. We are working on this to fix it for all seasons because it’s too cold in some areas. NKY working on final punchlist items.
10/25/23 – NKYHC is complete and finalizing punchlist. Emcor is complete but controls have not been commissioned. Boiler is going out on high limit. NKYHC has been working on reprogramming the unit with help from Lochinvar. We are meeting Friday to work out control issues with the pumps, boiler and new reheat coils. So far new the boiler had to be reprogrammed because ALC landed new controls on the boiler, a jumper had to be changed on one Admin VAV box, water had to be added to the HHW system. We will find out more on Friday.
12/06/23 – Project is complete and in final punchlist phases. We need to spend some time commissioning with Emcor to get the sequences worked out with them.
01/09/24 – This week we worked on AHU-2 gas heating furnace not working correctly. After several trips and replacements, the furnace is working but may not be working well all the time, the rollout switch was replaced with a non-automatic reset switch, creating more nuisance work for Ian. When the first floor heater is working the building work a lot better. The first floor boiler was not sized for full heating of the entire building, it is sized for heating on the second floor and some reheat on the first floor only. We must have the gas furnace working on the AHU-2 to heat the building in the winter.
01/31/24 – This project is complete and the final programming work moved to SPHQ BAS Recommissioning project.
02/23/24 – Closeout documents sent to NKYHC for use on closeout docs.
03/22/24 – Closeout documents AIA forms sent to County, we need the rest of the closeout paperwork, requested from Lisa today.
04/24/24 – NKYHC doing warranty work on AHU-1 and AHU-4 as part of this project. Emcor commissioning the dual circuit control for the new units. Closeout paperwork submitted to John Nester with a thumb drive. This project is ready to Archive.
05/28/24 – O&M manuals updated and complete, this project ready to archive.

SPHQ – Furnace 1, 2, 3 Replacements Read More »

CH – AHU-B4 Replacement

PM: Terry Cannon, John Nester
12/10/20 – SOSS submitted for approval.
12/28/20 – SOSS approved.
01/26/21 – Kickoff meeting scheduled for 2/2/21 at 9:00am with Jesse.
02/24/21 – Project setup and work underway. TTC and TAB to meet next week on Alternate work.
03/25/21 – HVAC design pretty much complete, TTC needs to review and share with the County for comment.
04/29/21 – Still need TTC review and then to JN for comments.
05/26/21 – Reviewed and back in for editing. Our plan is to have the mechanical and electrical sets in for County review by June 18, 2021.
06/18/21 – Review drawings submitted to owner for final review.
06/24/21 – AIA contracts sent to TTE for bidding purposes and calendar days set at 120 for this job.
07/21/21 – Ready for ITB request. TTC to create project manual and get ready for bidding next week. This project will be bid in August.
08/26/21 – Project will be finalized after JC HVEC goes out for bid.
10/28/21 – Project issued for bids and DeBra Kuempel is apparent low bid. Expectation is to award Base bid, plus Alternates #1 and #2. HCFD to confirm. TEI will schedule pre-award meeting week of 11/1.
12/13/21 – Bids were received and DK was the apparent low bidder.  TTE conducted a pre-award interview with DK and recommended them for the Work.  Contract and PO were submitted for approval and we await their return.  Submittals have been sent to TTE for approval.  The Trane unit submitted has an extra coil access panel that makes the unit longer.  we are going to approve this unit as it provides better maintenance of the unit and doesn’t affect access around the unit.  A pre-const mtg will be scheduled soon.
01/25/22 – Submittal returned for equipment order. Project is ready to begin.
02/24/22 – Controls discussion with Honeywell.
04/28/22 – Const Mtg next Tuesday for full kickoff and construction start.
05/25/22 – Const Mtg was held. DK putting together the final schedule but we don’t have good dates from Honeywell yet. For now, we are scheduling the AHU replacement over the weekend of 6/25. Controls submittal was received, marked up, and sent back to Honeywell but some statements in the sequences didn’t match actual conditions, waiting on revised control sequences.
06/30/22 – Shutdown is scheduled for 6/7,8,9 with County and DK. CH VAV box replacement scheduled the 7/12 at 8am for next phase.
07/27/22 – AH B-4 is up and running. Controls are being upgraded this week and next. Debra scheduled to begin Alternate Work the weekend of August 6.
08/16/22 – DK has made coredrill for new hot water reheat piping and made hot taps for connection to HTX-5 system. VAV boxes are being installed and Honeywell will be right behind them for control work.
08/17/22 – One set of hot taps not on an active line, TTE to investigate. TTC met with County and determined that this was correct, we showed one set of lines coming off the HTX-2 header. We will update the drawings and coordinate with DK on getting both lines fed from HTX-5.
09/22/22 – The unit is installed and working. The programming is not complete yet. The county is working on providing a new data drop near the B-4 unit for Honeywell to finish their programming. TTC met with Ameresco on the solar water heating components because we need the solar water heating to reheat for B-4 courtrooms.
10/26/22 – Honeywell programming and adding three extra VAV boxes on Monday, then the job will be done and ready to punchlist.
12/15/22 – All mechanical and electrical work is complete, and the unit is running. Honeywell scheduled last Friday to make their final programming changes have not gotten confirmation on if that work is complete.
01/24/23 – Honeywell was down last Friday to complete controls on this unit. The labor is complete.
02/22/23 – Honeywell worked on the controls two times and is currently troubleshooting an IT compatibility issues.
03/30/23 – Balance report sent to TTE for review. JN asked for updated PM’s.
04/26/23 – Unit is complete and in use. TTC requested training from Honeywell on new system. It is ready for punchlist.
05/21/23 – Work is complete, TTE ready to punchlist.
06/28/23 – Unit seems to be running well but I need to see the Courtrooms and check unit from front end.
07/26/23 – Punchlist scheduled for 7/27.
07/27/23 – Punchlist distributed to team members.
08/23/23 – No updates on closeout, DK checked earlier this month.
09/27/23 – Still not closed out, nor has DK confirmed punchlist work. We will check in with Dave again.
10/25/23 – DK contacted Randy for closeout documents yesterday. No payments sent until final closeout is completed.
12/06/23 – Trying to get DK to closed this job out. Need documents from contractor.
01/18/24 – The CHW line froze across the driveway. DK dispatched to fix the line and and added insulation and heat tape for future protection. Heat tape not hooked up but ready.
01/30/24 – DK has submitted the closeout documents for this project.
02/23/24 – TTE needs to get final closeout from Honeywell for this job.
03/22/24 – B-4 not on the Bacnet yet but running manually remotely.
04/24/24 – Can’t close out this project unit Honeywell gets the unit back on the front end and under Bacnet control.
04/25/24 – Give this work to Emcor and have them integrate B4 early in the HVAC Controls job. TTC to coordinate between the contractors.
05/28/24 – B-4 is back on graphics. Final closeout documents requested from DK. Some received, but we need the rest.
06/26/24 – Not completely closed out yet. TTC waiting on final documents from DK.
07/24/24 – Closeout documents still not received. TTE reached out to DK and Honeywell for final documents earlier this week.
08/28/24 – We have the G706 and G706A now. We are waiting on the Surety and Affidavits. TTE agreed to create the books, thumb drive and As-Builts.
09/24/24 – Project Closeouts paperwork received. TTC to markup final drawing for As-Built then this job can be closed. TTE has dedicated one person for closeout to help with getting these wrapped up. OK to add closeout time to SOSS.
10/31/24 – All closeout documents received except for as-built drawing that has to be updated by TEI now without the heat tape across the hallways.
12/12/24 – Everything submitted for closeout.
01/28/25 – Project ready to archive.

CH – AHU-B4 Replacement Read More »

THP General Structural Service (F021)

PM: Bert Watts, John Millar
11/17/20 – THP submitted SOSS.
11/17/20 – County approved SOSS.
02/18/21 County requested THP review planned installation of two freezer units in 800 Broadway.
02/22/21 THP reviewed new refrigerator units at 800 Broadway basement. THP made recommendations via email for installation and location on the raised platform flooring structure.
04/05/21 – County reached out to review replacement RTU on the Florida roof of the 800 Broadway building. THP reviewed documents and visited the site the week of 4/13/21.
04/23/21 – THP published a review of the condition. Big picture new unit should work. Existing unit and new unit are schedule to be placed on unknown wood members. THP noted wood structure should be reviewed after the existing unit is removed, prior to the installation of the new unit.
05/10/21 – THP published draft flag pole footing sketch to Champlin for review.
05/21/21 – THP published final flag pole footing sketch.
05/27/21 – THP review proposed RTU replacement at 800 Broadway. Planned replacement next week.

THP General Structural Service (F021) Read More »

TPC – Elevator Modernization 2020

PM: Matt Butz, Mike Barth
12/09/20 – TEI submits SOSS for approval from HCFD. Project to commence upon receipt of approved SOSS and PO.
01/26/21 – TEI receives signed SOSS and PO for project. Project kickoff to be scheduled with facilities and project work to commence.
02/23/21 – TEI requests times/days to meet and have a design kick-off with HCFD and Champlin. Meeting to be scheduled as soon as availability is coordinated.
03/24/21 – TEI meets with Champlin, HCFD and building manager. kick off the meeting. lobby beautification project to determine the interiors for the elevators #2,3,4, and 5. project in design phase.
03/25/21 – We talked about phasing of the elevator work and TTC shared the HVAC smoke evacuation procedures for this building as they may be related to the work being done on the AHU, elevators and fire alarm systems.
04/28/21 – Project in design process.
05/26/21 – Project in design process. Interiors shall be coordinated with the lobby beautification project.
06/23/21 – Project design continues.
07/28/21 – Project design continues, will be completed once interior finishes are finalized with lobby beautification project.
07/29/21 – Finishes are selected and the job can go forward with bidding. Keep bronze colors intact, Murphy is working on selections. We have enough information from equipment vendor to give to the Admin committee to move this forward. MB to setup a design meeting for next steps.
08/26/21 – No update
10/28/21 – MCB updating elevator package based on JC learnings, low voltage, coordination issues into the TPC work. County requested elevator cab rendering with new finishes to use with the Lobby Renovation. Keep and polish up the existing mailbox.
05/26/22 – Final review sent to county. To be determined if this will be bid as one project with the lobby renovation.
06/28/22 – Project HCFD review completed and received.   Drawing pack schedule coordinated with Champlin for the Lobby Beautification project.  Drawings to be sent to Purchasing on 07/05/22, available for bidding 07/07/22, with bids opening on 08/04/22.
07/27/22 – Project bidding.    Bid opening on 08/04/22.   Prebid completed and addendum #1 and #2 issued.
08/24/22 – Bids opened.   Graybach is apparent low bidder.  Project contracts drafted and sent to Prosecutors office.  Project to commence upon contract approval and PO.
10/26/22 – Bids opened.   Graybach is apparent low bidder.  Project contracts drafted and sent to Prosecutors office.  Project to commence upon contract approval and PO.
12/15/22 – Preconstruction meeting occurred on 12/14/22 with Graybach, HCFD, TEI.  Submittal are starting to arrive.  Graybach to submit a project schedule.
01/25/23 – Submittals are arriving slowly.  Electrical and Elevator submittals still pending.
03/29/23 – Submittals are arriving slowly.  Electrical and Elevator submittals still pending.
04/27/23 – Submittals reviewed and returned.   There are a couple of submittals (floor base, etc) that Champlin has requested samples and are still pending.  Anticipated start of construction is around the beginning of July ’23.  Graybach instructed to not make sure all materials are procured and received prior to starting actual construction so that there are no material delays once construction begins.  Basement door selected for mock-up of door finish.  mock up to be installed in next 2-3 weeks.
05/23/23 – Sill plate painted.  The door mock up materials arrived at site damaged.  Upon receipt of undamaged materials, the mock up will be installed for approval.
06/28/23 – TEI, Graybach, and HCFD meet on 06/28/23 to discuss schedule.  Door frame finish selection is critical path item.  Prior to taking an elevator off line, all materials for that elevator shall be on site.  Door frame wraps are a 4-6 week lead time item.
07/26/23 – Door frame selections have occurred.  Sent to Graybach and American Elevator.   Permit applications have been submitted.   Graybach anticipates starting on 1st elevator mid/late August.
08/24/23 – Graybach and subs are getting ready to start the project.
09/26/23 – Construction commencing on project.   first elevator to be taken from service early October.
10/26/23 – Elevator #3 (Right hand Side Passenger Elevator) has been taken out of service and machine is being disassembled.  There is a crane lift scheduled for 10/28/23 to remove Machine #3 from the penthouse, and lift the new equipment for #2 and #3.  A second lift will be scheduled once Cab #2 is complete and ready to work on cab #1 (freight).
12/06/23 – Work continues on Cab #3.  Old equipment is removed and new equipment is set in place in penthouse.   work in shaft, cab and landings ongoing.  new doors on multiple floors.
01/30/24 – First cab (cab #3), nearly complete.  Graybach tentatively scheduling inspections for approval on week of 02/05, and pending approved inspections, will turn cab #3 over for use by end of week.
02/28/24 – First CAB turned over and in use.  Working on second cab (Elev #2).
02/29/24 – Graybach sent email about air pressure in the lobby affecting for the doors, TTE advised them to check elevator door settings first before we change the HVAC and Smoke Evac fans in this building.
03/27/29 – Work continues on Elevator #2 (second passenger elevator).  Graybach indicates that they are “on schedule”.
04/24/24 – Elevator #2 inspection scheduled for 05/01/24.  Upon approved inspections and turn over – then #3 (the first one modernized) will be taken out of service for approx 1 week to address manufacturer’s recall on components.  Then both lobby elevators will be returned to service for the building occupants.
05/29/24 – Elevator #2 passes inspections and is placed back into service.  Elevator #3 recall work completed ahead of schedule and placed back in service.  Freight elevator taken out of service and is being worked on.  Anticipated completion late July/beginning of August.
06/26/24 – Project work progressing on the Freight. No schedule delays indicated by American Elevator or Graybach.
07/24/24 – Pretest of the FA connections on 07/24/24. Elevator inspection on 07/26/24. Turnover immediately after the approvals.
08/28/24 – Freight elevator complete, inspected and returned to service.
09/25/24 – Project complete pending closeouts from Graybach.
12/11/24 – Project complete pending closeouts from Graybach.
02/27/25 – Ready to Archive.

TPC – Elevator Modernization 2020 Read More »

CH – Fire Pump Electrical Investigation

12/09/20 – Fire pump and fire alarm are having multiple trouble signals (excessive amount). HCFD had SA Comunale investigate, and also JCI/Simplex, both stated that their systems are working correctly. TEI suggests that a logging meter be installed to determine if it is an incoming voltage issue to the fire pump since the alarm is a single phase alarm. Meter on pump and more data to follow once results from the metering are reviewed.

01/26/21 – Meter data indicated voltage variations and excessive rapid voltage changes. TEI reported to facilities the voltage issues. Facilities requests SOSS for study to determine options for power quality correction. SOSS submitted and approved by facilities. Study in progress.

02/23/21 – HCFD sends TEI email stating that the existing phase loss monitor on the existing fire pump does not have adjustable ranges. Study to develop “clean” power supply to fire pump continues.

03/24/21 – TEi continues working on project, no new developments to report.

04/28/21 – TEI Finalizing owner review draft, will send to HCFD by 5/5/21 for initial review. TEI identifies issues from previous report also associated with the fire pump that possibly may required to be addressed if implementations occur.

05/26/21 – TEI submits draft for owner review. TEI and HCFD evaluating additional options. TEI suggests a temporary solution, and requests a quote from DK (since they did fire alarm project and are working on another project in building). Solution pending pricing from DK.

06/23/21 – The temporary solution was installed on the system, and it was reported to TEI that there are no longer the troubles on the FACP. TEI to finalize report to HCFD with results of solution included.

CH – Fire Pump Electrical Investigation Read More »

Animal Shelter – Trailer Power and Signal

12/09/20 – AKM called ThermalTech to develop Opinion of Probable cost and opinion of engineering fees to communicate to Animal Shelter personnel. AKM to advise TEI if the Animal Shelter wants to proceed with project, at which point AKM to ask for an SOSS. TEI sent opinions of cost to AKM on 12/04/20.

01/26/21 – Trailer delivered to site. TEI speaks with AKM about moving forward. AKM requested revised cost data based upon the location where the trailer was placed. TEI sends AKM data requested and asks about next steps

01/28/21 – Discussed having Duke pulling a separate service for this trailer to keep it separate from the main building’s supply. TEI stated that is how it is planned at this time.

02/23/21 – AKM requests SOSS for design work for the trailer install. TEI sends to AKM.

03/24/21 – Project pending SOSS approval and PO.

Animal Shelter – Trailer Power and Signal Read More »

800 – Critical Façade Survey

09/24/20 THP submitted SOSS for inspection of building facade.
11/30/20 -THP received SOSS and PO for work.
12/10/20 – THP survey and assessment to occur spring 2021, purpose is to assess the façade after the winter freeze / thaw cycles.
01/28/21 – Delayed to Spring.
04/29/21 – THP staff passed background check. Rappelling and aerial platform work scheduled for week of 5/3/21. Thunderstorms and rain, may shift field work to later in May.
05/04/21 – THP and AFR completed aerial platform survey of the base. Loose mortar and limestone debris was removed.
05/13/21 – THP rappelled the tower.
05/14/21 – THP rappelled the tower.
05/27/21 – THP working on the report.

800 – Critical Façade Survey Read More »

A&D – Moisture Investigation

10/27/20 – THP sent SOSS for moisture investigation.
12/10/20 – THP and TEI to follow up on water line testing.
01/28/21 – THP completed multiple water tests and has determined water sources. THP developing excavation proposal. Draft report partially completed.
02/23/21 – SOSS requested by Hamilton County.
03/23/21 – THP provided SOSS. Three posts migrated to this project.
04/22/21 – Excavation completed along the north elevation, along with subbasement excavation.
04/29/21 – THP finalizing draft report. Anticipated publish date 5/7/21.
05/27/21 – THP updating the report with the excavation information.
10/27/21 – Budget issued in September then final report with updated interior repair added issued on 10/27/21

A&D – Moisture Investigation Read More »

250 WHT – First Floor Lobby and Delivery Closet Renovation

10/21/20 – Authorized to proceed with design and bid phase.
12/10/20 – two options sent to county and Public Health for review.

01/06/21 – Review meeting with Users – Finalized scope

01/22/21 – Received TTE sd documents

01/26/21 – Uploaded SD Drawing and Estimate to Archibus.

02/18/21 – Received comments from owner

01/25/21 – Champlin working on SOSS to take project through completion.

03/11/21 – SOSS approved.

03/25/21 – CD’s being developed. Review meeting with users to be scheduled in the near future.

04/06/21 – User Review Meeting. Finalized scope.

04/20/21 – Final CD documents and budget given to County.

04/28/21 – County approves final plans. Champlin to get ITB number from Purchasing.

05/11/21 – Project Posted by Purchasing

05/21/21 – Prebid meeting held at 250 WHT

05/24/21 – Addendum 01 posted.

06/03/21 – One bid received. Budget exceeded and bid had to be rejected.

06/14/21 – Rejection letter sent to John Nester after bid review and discussions with other pre-bid attendees.

06/22/21 – Email from John Nester suggesting to combine this project with Public Health Lobby for new bid.

10/28/21 – Ready to Archive.

 

 

250 WHT – First Floor Lobby and Delivery Closet Renovation Read More »

DDS – Group Homes Renovation

10/29/20 – Site visit to confirm existing conditions. Meeting scheduled for 10/29 with Kevin Maue for preliminary review. Meeting scheduled for 11/5 with Towards Independence.
11/05/20 – Meeting with Towards independence for review
12/11/20 – Submitting SD drawings and estimate to Kevin Maue for review.
01/20/21 – Email from Kevin Maue indicating decision by DDS on direction towards end of February.
02/25/21 – No Update
03/25/21 – No Update
04/29/21 – No Update
05/12/21 – Sent broken down cost estimate ( kitchen renovations for each building) to Kevin Maue
06/25/21 – No Update.
07/27/21 – Champlin spoke to Kevin Maue. Kevin expects approval to proceed on all three homes on 7/28.

08/12/21 – SOSS sent to County.

08/18/21 – Kevin Maue sent Champlin questions related to SOSS

10/28/21 – No Update.

12/14/21 – No Update.

01/26/22 – No Update.

02/24/22 – No Update.

03/31/22 – No Update.

04/28/22 – No Update.

06/30/22 – SOSS approved for Geier renovation DD-CA. Kickoff meeting held to confirm scope.

07/28/22 – Kickoff meeting occurred. Program and scope changes were discussed. New plan in progress.

08/25/22 – Revised plan sent to Kevin Maue for review.

DDS – Group Homes Renovation Read More »

250 WHT – HCPHD Lobby, WM, WQ, Plumbing, HPE

10/29/20 – Furniture confirmation meeting held 10/28. HPE proceeding to furniture bid. Lobby, WM and Copy/Print/Conference room reconfiguration to be estimated for future funding. Plumbing and Water Quality modifications no longer being pursued.
11/23/20 – SD Drawings and Estimate sent to County for review.
01/27/21 – No update.
02/25/21 – No update.
03/25/21 – SOSS sent for 2nd Floor Lobby scope only. waiting on approval to proceed.
04/29/21 – Separating Public Health Lobby into new project. No Update for remaining spaces. Scope is complete, okay to archive.

250 WHT – HCPHD Lobby, WM, WQ, Plumbing, HPE Read More »

237 WHT – HCPHD – Disease Prevention TB Clinic

10/29/20 – Programming meeting held. Planning confirmation meeting scheduled for 11/5/20.
11/05/20 – Meeting to review scope. Proceeding with 2 options to SD and Estimate level.
12/08/20 – Site visit by CA and TTE to verify existing conditions
12/10/20 – ThermalTech has requested information on existing equipment and specifics for using for loads for new space.
12/14/21 – Cost estimate for emergency work needed, minimum renovation plan and minimum plus renovation plan sent to Greg Varner for Board Meeting.
02/25/21 – No update.
03/25/21 – No Update. OK to Archive.

237 WHT – HCPHD – Disease Prevention TB Clinic Read More »

JC – Capacity & Recovery REBID

PM: Matt Butz, Terry Cannon
08/27/20 – BOCC agenda has these items on the agenda today. Rebid 9/3, Prebid 9/10, and Opened on 9/24.
09/24/20 – Five bids came in for this job. We are setting up the post-bid interview with the apparent low bidder. The bids did come in under budget and we are hopeful we can award the project.
09/28/20 – Post bid reviews are complete. The meetings went well and additional follow-up questions were answered and researched. Recommendation sent to County by partners.
10/19/20 – City in receipt of permit drawings and examination fees for initial submit from GBBN and ThermalTech.
10/23/20 – Permit accepted by the City and uploaded to their online upload portal. This does not mean the permit is approved, it has just been successfully uploaded for review.
12/10/20 – Triton started submitted paperwork on this job and the safety plan was approved today. The project is progressing forward with early-stage work by the contractor, design team, and owner.
01/05/21 – Team working on permitting & submittals.
01/20/21 – Pre-Const Mtg held at site with Sheriff, Facilities, and Triton. GBBN distributed meeting notes afterward on 1/22.
01/21/21 – GBBN sends a gig letter from City on permit approval.
01/22/21 – ThermalTech and GBBN work on additional permitting requests by the City.
01/25/21 – City says submission is acceptable but we have to take out a third permit for the Courthouse work. TTE tells GBBN that an HVAC permit is not required for that work.
02/05/21 – Plans reviews say approved and “en route”.
02/24/21 – Project submittals underway. GBBN working on permitting approvals. No devices can be supported by the new security ceilings. Jails suggested that we change the shower doors in lieu of a new shower curtain instead of shower door. Filling out a change order for Phase 4 on this job, could save $20k. IBI will be submitted after the building permits are ready.
02/26/21 – GBBN and TEI working with Josh at Triton on security ceiling submittals. We are coordinated access panel locations and attachment methods for in-ceiling devices.
03/01/21 – Permits are approved and ready for pickup on this project. Your permit applications have been APPROVED and are ready for issuance. The permit numbers are 2020P09115, 2020P09116, 2021P01219.
03/04/21 – IBI to require that their Plan review/permitting shall follow the lead from the building department. TEI to submit for (3) plan reviews to get (3) permits associated with the building permits.
03/04/21 – TEI reviewing Camera submittals from Glenwood. Sent the following in email to Glenwood and cc’ed Triton and GBBN. As a follow up to the voice mail that I left for you at your office the other day, I am trying to review/approve the submittals for the security cameras on the Justice Center Capacity and Recovery Project. On the Bill of Materials, the Camera Model Number indicated is a Vicon V804D-W312MIR, however, the cut sheet included is for a V802D-W312MIR Camera. There are resolution differences between these two cameras, so I was wanting to confirm which Camera that you are actually intending to provide.
03/25/21 – Submittals and permitting were worked on this week. TTC has controls submittals to review, talked to JCI yesterday about status. GBBN, Jails, Triton working on keying issues, Const Mtgs to hopefully start early April. GBBN setting up coordination meeting with Sheriff, Facilities, Triton and GBBN to discuss door hardware items.
04/29/21 – Pre Const and Const Mtg #1 held. Equipment has long lead times, limited demo and mobilization has begun. Triton coordinating with CH and JC on Jax area work and beginning const process. Triton to issue Const Mtg from yesterday. A schedule has been issued. All MEP submittals have been reviewed and return. Most GC submittals have been reviewed and returned. Spencer and Josh working on JAILS submittals. Design team to update completion date with Triton for this job as original completion date was July 2021.
05/26/21 – Additional construction meetings were held and demo work is underway in the JAX area. Payapp #1 pencil copy was submitted by Triton and change order work included VAV Access Panels and table top painting.
05/27/21 – Review project handoff with Spencer including change order work for tabletops and HVAC access panels.
06/25/21 – Bi-Weekly const mtgs are being held. Demo is the South building is underway. JAX area is under construction. Medical records move is forthcoming. The schedule not finalized yet due to door delivery unknowns. Lighting installation questions came in this week and Barth instructed Glenwood to install them per the drawings as lay-in fixutres.
07/28/21 – Weekly construction meetings continue. We are having a hard time getting a project schedule from Triton on this job. Triton to provide one very soon. Demo continues but we are getting to the point where new work needs to begin to keep phasing n place. TEI confirmed with Clay Bryngelson of Triton that the schedule was sent to HCFD (Matt and Rycca) for approval and then will issue to all parties.
08/19/21 – Const Mtg held, RFI #4 submitted on shower location. The preliminary schedule is distributed. State officials were down checking on progress.
08/26/21 – Clay and Scott are doing the project management on the JC Recovery project and things are moving along better than before. Plumbing submittal for Drinking fountain submitted and returned. P, we iping specialties submitted and returned. RFI #4 was answered by GBBN. Work continues in the South building. Jax is nearing completion. Exhaust fans can stay in JAX area as is.
10/28/21 – Construction continues with meetings the first and third Thursdays of the month. Core drill issues and location have been coordinated with THP, Triton and TEI. Walls for showers, toilets, and pipe chases evaluated and coordinated. GBBN and THP coordinate the core drill locations. Currently working in SE pod and building walls. Waiting for asbestos abatement team approval. coordinated core drill locations in the SW last week.
11/18/21 – Const mtgs continued every other week with the Sheriff.  Today we discussed progress in the SE pod and coordinate Medical, Jax, and OB/Gyn changes.  Schedule was briefly discussed. Core drill summary discussed and needs to be done.  Jails products need to get on order, current wait time is 14-16 weeks.
12/09/21 – Schedule mtg with Triton.  We discussed updating the schedule to match the July 1 deadline.  Clay provided a revised schedule with July 1 deadline that we review at the meeting.  This is the drop dead date with the County and State for this work.  THP, GBBN and Triton to meet on Friday to review cores.
12/10/21 – Met on site and picked new locations for core drills for SW pad.  We will meet all THP requirements for coreing the floor in this location.  3/4 core drills are moved to make this work.
12/13/21 –  TTC releases field report with notes and questions from the fieldwork.
01/25/22 – Project meeting this week went well. Plumbing and fixtures are being installed and pipe in SE and SW pods. NE and NW demo is underway. Abatement scheduled for this week. The handwashing sink for the OBGYN sketch was sent by TTE to Triton for piping up new location and we will be using the bathroom sink for the main room.
02/24/22 – Triton making progress in the South building. North building core drills are complete. North demo is almost complete. Window RFI submitted and answered for piping. We have a meeting with Triton this afternoon on project issues. We’re meeting to discuss the project specifics this afternoon.
03/31/22 – Southeast and Southwest pods are progressing ahead of NE and NW. The plumbing equipment is installed, electrical coming along, and ceilings coming in next week. NE and NW demo underway, medical wall not out yet. HVAC and controls are started. Window tint was approved last week.
04/25/22 – THP anticipates reviewing core locations for the northeast area the week of May 2nd.
04/28/22 – NE pod verbally approved for rotation of plumbing fixture. COR #8 and #9 submitted by Triton for consideration. Ceiling is being installed in the South building. Medical and medical wall scheduled for demo and move in May. This will allow core drill and final coordination for NW pod in early May.
5/16/22 – THP, Thermal Tech, Triton, and GBBN met onsite to discuss core hole locations for the NW pod. See GBBN’s field report for summary and pictures of core hole locations and discussion. Also, a couple items in the NorthEast pod were discussed: lintel bearing at 4” masonry wall and existing structural bolts through existing column.
05/25/22 – Weekly meetings continue for coordination with Triton on project progress. Significant progress was made in the North building during the past month. Final core drills are complete in the NE pod. NW pod ADA changes were finalizing with Triton, GBBN to issued Bulletin 2A to capture these changes worked out with Triton and County. We need to revisit scheduled completion for this work with Triton at next core meeting.
05/25/22 – THP working on answers for the lintel bearing at 4” masonry wall and the existing bolts through the existing column.
06/30/22 – The South building pod work is making progress. The ceiling grid is installed. The above ceiling inspection did not pass because the latest IBI drawings were not on site. Triton looking to update this. The North building work is progressing as well. Once the masons are done in the NW pod they will move to the NE and relocate the wall. The door installation was moved ahead of the window and windows cuts.
07/27/22 – Progress continues in all four pods. Clay has moved on and Jason is taking over PM duties. We need to update the Core meetings since Clay moved on. Jason emailed an updated schedule for the window cuts and we are working on final details on the order. ThermalTech scanned the pods this month and turned over the scan files to Matt on a thumb drive for their use.
08/04/22 – Window cutting delayed per Triton. “Bad news from Donaly as well this afternoon after they looked at their files on who were badged. One of the people they had badged is no longer with the company so they only have 1 person badged and cannot do the work next week since they only have 1 person. Please notify the Sheriff team that we are on hold until we get them thru the badging process. We will hold off on scaffolding until the work is ready to be completed. I will also notify the rest of my team, including scaffolding. Sorry for the delay in this portion of work. We will work to reschedule as soon as they are badged.”
08/18/22 – Const Mtg. Triton updated us on project progress to date. Scaffoldign arriving next Monday and Tuesday. Triton to coordinate delivery with Sheriff and Facilities. Two hallway door frames are set into place for masons to start blocking in. Triton to coordinate shutdowns with secure access to space during demo & new work. All plumbing inspections are complete and approved. Relocated WC/LAV set into place on relocated wall. Ceilign work is ongoing, all grid is in, working on tiles. We confirmed there is not ceiling on the observation deck on this job. Change order to fix flooring will be approved but Triton has to improve coordination and phasing so it doesn’t get messed up a second time.
08/22/22 – Washer & Dryer and Caulk submittals came in and were sent back for revisions.
09/01/22 – Good meeting with Triton, they are ramping up work to meet deadlines. Jails coming back next week to keep working on ceilings and doors.
09/08/22 – Core meeting, more coordination with Triton and pushing for completion. Washer & Dryer approved with credit for last two years of warranty from Triton. Windows openings are in the side of the building, Triton and Neiheisel are fabricating the weeps and sill plates for modified design.
09/15/22 – Const Mtg at JC, work continues. Floor grinding is starting second shift and Jails is onsite finalizing all work.
09/24/22 – Core meeting. Big discussion on cabinetry and casework. Triton submitted a laminated multi-use cabinet until the SS arrives. This led to a discussion about who is providing the other cabinets in the Observation Shack. After some research, it was determined the Sheriff is providing the cabinets that Triton is not per Alt 2 adn Triton still needs to provide the Multi-Use cabinet. RFI-28 returned on Sunday to Triton.
10/26/22 – Two secure hallway doors complete, two more hallway doors almost done, concrete polishing complete, observation platform almost done, beds are on site, tables at Jails, ceiling mostly installed, HVAC is complete, fire protection is complete, plumbing and plumbing accessories complete. RFI submitted on Deal Tray, RFI submitted on Observation glass. Exterior Windows are the hang up at this time, Jails is not or will not get them installed. Duct cleaning, tunnel repair and first floor finish will be last.
12/15/22 – Work continues on this project on a daily basis. South pod has been punched. TTC to finish his and send all three by end of week. Final windows for North building to arrive 12/28, Jails says they have 4 to 5 days of work left after the windows are installed. Deal trays, sills, jamb covers and door pulls are final details we are working out. Shower heads needs to be repositioned to keep water in the shower basins.
01/24/23 – Punchlsit were completed on 1/19 for MEP and 1/20 for GC. All punchlist sent to Triton. The windows are installed, the deal trays are installed, the bunk walls are done with painting happening now. The scaffolding was removed last week. Teh first floor epoxy was the wrong color. We are down to a new set of “opportunities” to get coordinated with Triton, including cameras, air balance, epoxy floors, sills and jambs. Change Order #8 was approved, signed by TTE and sent to Triton.
02/22/23 – Triton finished all four pods and acquired TCO for all four pods this week. Back punchlist were distributed to Triton for final work. No weld certificate is needed, TTE to tell Triton.
03/30/23 – Working with Triton on matrix issues and a potential change order for reworking the bandwidth associated therewith. Commissioners scheduled to walk the site tomorrow. Terry, Matt, Mike will attend.
03/23/23 – No updates from THP.
03/31/23 – The walk through was canceled. TTC working on Special Inspections with City after speaking to inspector yesterday. Scheduled for 4/14/23 all day with Terracon.
04/10/23 – Door and all hardware is installed in South pod. Triton is working to schedule the painter down to the jobsite to complete the painting of the door. Replacement shower curtains are installed in all pods. Attic stock has all been moved downstairs and placed by the cages as requested by Andy. All Jail Product crates have been removed from the loading dock area.
04/14/23 – Teracon onsite for weld inspections. Public walk through today with Commissioners and City and state dignitaries.
04/17/23 – Pneumatic actuator replaced in SE pod, Triton sent video showing it was working.
04/26/23 – Scheduling building cleaning with Triton and project closeout documents have been sent in for approvals.
05/21/23 – Project is complete and Substantial Completion sent. Window washing starts this week.
06/28/23 – Project cleaning is complete. Closeout documents have been received. Triton has billed for all but retainage. Issues with Jails have been worked out.
07/26/23 – Triton met us on site two weeks ago. As of today, they have not met their cleaner on site to fix the wall streaks. All As-Buit drawings sent in for this job.
08/28/23 – Triton sent request for second camera model for O&M manuals, and cleanign of the outdoor wall.
09/27/23 – Third party cleaning company was onsite today and recleaned the outside of the building with an 80ft crane and pressure washing with chemicals. Final pictures look good. Triton shared final condition today about 4pm. Triton ordered new part for leak on 3rd floor.
10/25/23 – Waiting on Phase 5 approval from State of Ohio. Outside of building is cleaned and third-party cleaning company worked out. Retainage payment signed and sent by GBBN, hold until county satisficed with State Review process.
01/31/24 – Project closed out and all paperwork submitted. Waiting on final certified payroll before we close this job out.
02/23/24 – Closeout complete and drawings submitted.
02/29/24 – Ready to archive.
03/22/24 – TTE requested updated closeout documents and all AIA closeout forms from Triton.
04/25/24 – Triton stopped over to look at floor tile cracks. Tommy believe the sub-floor came loose in only one pod. They will remove and repair under warranty. Champlin to assit ThermalTech in updating CAFM drawings.
05/28/24 – Project ready to archive.

JC – Capacity & Recovery REBID Read More »

Animal Shelter – Arc Flash Study

09/18/20 – New Arc Flash project SOSS sent to County, followed up with some additional drawings to Tony from study. This project can probably be archived.
09/24/20 – Approved SOSS has been received. Arc Flash to begin.
12/09/20 – Duke Energy information finally received from Duke, and model is developed. Site visit to coordinate and confirm existing conditions to be scheduled ASAP (post quarantine).
01/26/21 – TEI conducts field survey, develops model and is finalizing the model. Model results to be sent to Charlie at CMI for review no later than 01/29/21.
02/23/21 – TEI completes model and sends to Charlie at CMI for review and comments. Upon receipt of Charlie’s comments, TEI will implement, print and apply labels.
03/24/21 – TEI receives and incorporates comments from CMI. Model completed and labels are printed and TEI is scheduled to apply labels week of 03/29/21.
04/28/21 – Labels applied. TEI to submit printed results to HCFD and the project is complete.
05/26/21 – Project complete. OK to Archive

Animal Shelter – Arc Flash Study Read More »

Covid HVAC Study

07/21/20 – First field trips for the Covid HVAC study scheduled.
08/12/20 – First draft of the report submitted for review.
08/21/20 – First draft of the report resubmitted and comments returned.
08/20/20 – Started integrating the Portable HEPA filtration units into the report and finding truly equal manufacturers, lead times, and cost.
08/21/20 – Final Study Report submitted to County with floor plans.
08/23/20 – BW asked to break out the building improvements and send to Tony for each building manager. Send directly to Tony Matre.
08/27/20 – Reports were well received with the County. Phase 2 for HEPA placements and safety PM coming up next.
09/14/20 – Sent building reports to Tony Matre and final information to Prosecutor Office. Answered some additional questions for the prosecutor this week and followed up on some additional articles emailed to me.
06/26/20 – Sent touchless water review to County for review of Ameresco proposal.
10/01/20 – Bid questions sent to bidders who submitted bids on the Portable HEPA Units.
10/05/20 – PO was release to the vendor for the purchase of Portable HEPA units.
10/06/20 – ThermalTech released building Recommendations to Tony Matre for Bldg Mgr use.
10/09/20 – Created cross reference guide for filter replacements from Tony
10/13/20 – County asked for SOSS for PM creation for the HEPA filtration units.
10/28/20 – Safety consultant has submitted a price to TTC to update our SOSS for the PM work on this project.
12/04/20 – Talked to Bert and Joe this past week about delivery of the HEPA units. The UV lights are on a delayed delivery schedule. We are seeing how this affects equipment.
12/30/20 – Working on excel format for equipment PM.
01/15/21 – TTC talks to Tim Schuh about setting up unit PM for this job.
01/21/21 – HEPA units are arriving disassembled. Joe sends serial numbers to TTE.
01/26/21 – TTC sends email response to RWL request for BOMA review.
02/19/21 – TTC commissioned Comm Center Unit to final CFM and moved closer to the plug. Gave county option for the longer plug if needed.
02/24/21 – TTC and RAJ commissioned 230 East 9th & 2020 HEPA units. One HEPA at 2020 has been sent back to the factory for repairs. We will be visiting the other sites in the next two weeks.
02/25/21 – BW asked for TTC email to be rolled up into a memo, general update and usage, add Charlie safety to PM, add Komisky report as an appendix to the memo.
03/25/21 – All buildings CX fieldwork is complete. Several units have had additional issues and CAI has visited the buildings to troubleshoot. Two have to be fixed by the factory, one was reprogrammed in the field and that data shared with building managers for future troubleshooting. TEI starting on the final CX summary report.
04/29/21 – Bert revised the worksheet and request ThermalTech to get all final serials numbers for the remaining units. TTC dispatched Ryan to collect the information.
05/26/21 – This month we retrieved the rest of the serial numbers on the HEPA units, filled out, and sent in the equipment worksheet for Archibus. We assisted with some problem units at 2020 and TPC and we visited the Law Library and provided a recommendation on units in the Law Library.
06/25/21 – Final worksheets were sent to the County on Admin 6th floor waiting and BOCC meeting room and 2020 Multipurpose Rooms. Teh final equipment list including missing serial numbers is in.
07/28/21 – DEV PM entered for County review and comments were sent back this week. We are ready to move to actual PM for these entries. LOTO safety procedures can be uploaded as a PDF with the PM to be performed.
08/25/21 – TTC visited 800 Broadway 6th floor today and took field measurements. Created worksheets and sent out floor plan to facilities. HEPA units not required in this space per the existing HVAC serving this area.
10/28/21 – TTC submits recommendations for the Ohio Means Jobs building. All PMs were uploaded to Archibus on 10/5/21.
10/28/21 – Portable HEPA units PM are uploaded and ready for November 1. Tony found better filter pricing for these units.
11/09/21 – Covid report sent to Rycca for A&D 2nd, 4th, and 5th-floor lobbies. None of these spaces required additional Portable HEPA at this time.
01/22/22 – The lower level study for OMJ is complete and we did add one Portable HEPA in this space.
07/27/22 – No updates to the Covid study this month.
02/22/23 – Met with Rycca and Glen on A&D conference room Covid needs. Backed existing unit down to 100 to 200 cfm each per new calculation worksheet.
04/26/23 – No updates but in May the emergency mandate may expire and we will address the use of the Portable HEPA during that time.
05/21/23 – Units were removed from operation this week in some buildings.
06/28/23 – Update Ralph et al. on Covid updates from his email. No changes necessary.

Covid HVAC Study Read More »

CH – Additional Flagpoles

07/10/20 – On site review. Authorized to proceed on CH only.
08/27/20 – One and Two flagpole settings discussed.
09/09/20 – Estimate and cut sheets uploaded on to Archibus.
10/29/20 – Approved to proceed on adding two flagpoles at Courthouse. Need to measure actual height of existing pole.
11/20/20 – RFP sent to Megen Construction, James Hunt Construction and Triton Services.
11/24/20 – Prebid Meeting at Courthouse.
12/01/20 – Addendum 1 issued.
12/08/20 – Bids received. Triton is apparent low bidder.
12/09/20 – Zoom meeting with Triton to review scope and vet bid. Official Letter of Recommendation sent to County.
01/22/21 – John Nester sent signed contract to Josh Smallwood at Triton.

02/25/21 – Josh Smallwood to deliver Schedule of Values, Project schedule and Submittals mid week of 3/1

03/11/21 – Permit issued. Waiting on approval. Still need lighting submittal.

04/29/21 – Waiting on Triton to answer foundation question for permit response and physical samples for flagpole material.

04/29/21 – THP to provide structural drawing for footing design

05/10/21 – THP provided Champlin with structural sketch

05/21/21 – THP provided Champlin with official design.

06/08/21 – Construction kick-off meeting. still waiting on additional finish sample from Josh.

07/19/21 – Notice to Proceed issued to Triton.

08/24/21 – Submittal returned to Triton.

10/05/21 – Site visit attended by County, Triton and Admiral. led to confusion on total scope.

10/25/21 – Meeting with Triton confirmed scope and gave Triton direction.

11/27/21 – Boring for the hole started. Soil conditions were found to be unacceptable. Terracon was contacted by THP to analyze soil conditions. No schedule has been given for the analysis.

01/26/22 – Ongoing communication between Triton THP and Terracon. Pricing to be submitted for added services.

02/23/22 – Change Order #1 signed and returned.

03/31/22 – Triton waiting on sidewalk permit to restart construction.

04/28/22 – Triton has provided an install schedule from 4/30 to 5/7 with installation complete on the 7th.

05/26/22 – Project Completed. Punch to be scheduled soon.

06/30/22 – Reviewed on site. Official punch to be submitted to triton shortly.

07/28/22 – Punchlist to be issued.

08/25/22 – Punchlist items complete. Final pay app to be submitted.

09/29/22 – Waiting for Triton to submit closeout documents

10/27/22 – Close out documents missing warranties and O&M manuals. Triton working on it.

12/15/22 – Close out documents received.
02/23/23 – OK to Archive.

CH – Additional Flagpoles Read More »

Homeless Shelter COVID Mods

08/20/20 – SOSS signed and returned. Initial provider meetings starting this week.
08/25/20 – 09/15/20 CA, CMTA, GBBN visit all shelter sites.
09/17/20 – 09/22/20 CA, CMTA, GBBN zoom meetings with all property managers to confirm scope of work.
09/22/20 – GBBN provides CA with SD drawings for CA to proceed with implementation.
09/23/20 – CA provides Messer with preliminary drawings for pricing.
09/28/20 – Target date for getting Messer final drawings for pricing.
10/29/20 – Bid packages and Permit ready. Waiting for authorization to proceed.
12/10/20 – Waiting for Authorization to proceed
01/26/21 – Meeting with Lisa Webb and City of Cincinnati to reassign Champlin contract.
02/25/21 – No update. Final stages of dividing contract between county and city.

03/25/21 – No Update

04/29/21 – No Update

05/18/21 – Meeting with City to discuss scope and remaining fee.

06/07/21 – Final signed assignment agreement received.

07/27/21 – Contract transfer complete.

08/26/21 – Project no longer a County project.

Homeless Shelter COVID Mods Read More »

250 WHT – HC Public Health Dept. EPI & IT/PHEP Interior Renovations

08/20/20 – SOSS signed and returned. Champlin notified ThermalTech. Working to schedule field work.
08/27/20 – Champlin sent several floor plans for review and asked about electrical impact. Barth responded that it is really pretty much the same electric scope except one layout requires an additional power pole and data jack which is not a big deal.
09/08/20 – CA site visit to see existing conditions
09/23/20 – CA SD drawings and estimate uploaded to Archibus
10/22/20 – Drawings updated to reflect scope change
10/29/20 – RCF pricing in process with the inclusion of prevailing wage.
11/23/20 – Haworth unable to meet furniture delivery deadline due to covid. Haworth sent a letter to explain the issue for Cares Act Funding. Furniture to be delivered early January
12/01/20 – Drawings submitted to IBI for Plan review.
12/10/20 – IBI and permitting in place. County can start work.
12/17/20 – Epi teardown 1/5-1/6 install 1/7-1/8. IT/PHEP teardown 1/5-1/6. Install 1/7-1/8. HPE teardown 1/11- install 1/12-1/13
01/25/21 – Electrical punch list completed.
01/28/21 – Holstegge coming out Monday to pick up some items and Trades are filling out the rest of the work. Carpet guys are coming out soon.

02/25/21 – No Update

03/25/21 – No Update

04/29/21 – No Update

250 WHT – HC Public Health Dept. EPI & IT/PHEP Interior Renovations Read More »

JC – Emergency Electrical Service Upgrade Study

08/21/20 – TEI submits SOSS, project pending SOSS approval and PO.
09/23/20 – TEI receives PO and signed SOSS for project. TEI to schedule project kickoff with HCFD.
10/27/20 – TEI Develops costing and recommendations for system replacements. TEI final report pending receipt of Russelectric report from outage for inclusion in final report.
12/09/20 – TEI received Russelectric report – to complete report and send to HCFD final draft.
01/26/21 – Still in Progress.
02/23/21 – No updates on this project this month. TEI to complete prior to next partner meeting.
03/24/21 – No updates this month. TEI to complete prior to next partner meeting.

04/27/22 – No updates.

JC – Emergency Electrical Service Upgrade Study Read More »

Fire Alarm & Sprinkler Testing

07/29/20 – SOSS received for these projects. TTE already about 75% done updating the specifications. We have updated three buildings with new Fire Alarm inventories (A&D, Courthouse).
08/26/20 – TTC to finalize testing manuals this week for Tony review.
09/18/20 – Finalized all documents this week, went over project specifics and update the manuals. Got two new ITB and issued for bidding today. Prebid 9/29 and Bid Opening 10/14.
10/06/20 – Addendum 1 issued. Bid extended to 10/28.
10/08/20 – Addendum 2 issued.
10/23/20 – Addendum 3 Issued. Bid extended to 11/04.
10/28/20 – Questions Due.
10/29/20 – Addendum 4 issued.
12/04/20 – TTC reviewed final contracts several times prior to signature by the contractor. TTC participated in research on the bid documents and called the vendor for a post-bid interview prior to recommending this work. At this time the project is set to be awarded to SA Comunale for both Fire Alarm and Fire Suppression.
12/30/20 – Project to be Archived.
07/28/21 – Rebid complete and final documents turned over to Tony.

Fire Alarm & Sprinkler Testing Read More »

2020 Roof Access Assessment (F018)

06/16/20 – Requested a SOSS for an Assessment of Facilities roof access (tie off and OSHA safety).
06/18/20 – County publish list of buildings to be included in the assessment.
06/25/20 – THP contacted LJB to provide anchor consulting support. THP plans to visit and catalog the roofs conditions next week for the SOSS.
07/14/20 – THP, LJB, and County surveyed downtown building roof to understand general conditions and needs of the County
07/28/20 – THP & LJB had a final scope meeting.
07/30/20 – LJB plans to provide a proposal to THP on 7/31. THP plans to submit final proposal early August.
08/11/20 – THP submitted SOSS to the County.
08/26/20 – Project placed on hold.
11/30/20 – THP received SOSS and PO for project.
01/13/21 – THP and LJB under contract for project.
01/15/21 – THP, LJB, and Hamilton County had kick off meeting.
01/28/21 – THP and LJB staff applied for background checks and waiting on approval.
02/25/21 – THP and LJB staff background checks approved. THP started field work on 02/24/21 – THP and LJB field work will continue until March 5th tentatively.
03/25/21 – THP and LJB completed initial site visits.
03/31/21 – LJB sent draft roof assessment report to County for review.
04/05/21 – County, THP and LJB met to review draft report.
04/29/21 – THP and LJB finalizing report based on comments from the meeting.
05/24/21 – LJB uploaded Draft report. THP reviewing cost and presentation.
07/16/21 – THP sent review drawing of report to LJB.
07/22/21 – THP and LJB reviewed comments. Overall minor updates to drawings.
08/26/21 – LJB working on final report.
09/16/21 – THP and LJB presented final documents to the County.

2020 Roof Access Assessment (F018) Read More »

CH – Skywalk Bridge Assessment (F013)

02/20/20 – Hamilton County requested SOSS to address City Bridge Report.
03/16/20 – THP and Hamilton County met to discuss scope of work.
04/21/20 – THP published SOSS with contractor support to assess the two bridges and attach loose metal panel.
06/25/20 – Project is approved. BC will get paperwork over to THP this week.
07/06/20 – THP proposed an inspection plan for mid-July. Bridges were noted to be still wrapped in signage that is planned to be removed this summer. Inspection placed on hold until sign is removed. Inspection tentatively planned for fall of 2020.
10/23/20 – Wrap removed and THP cleared to complete the work.
10/28/20 – THP scheduled to complete work November 3.
11/06/20 – Skywalk bridge ground survey completed.
11/07/20 – Skywalk aerial platform survey completed.
12/10/20 – THP draft report in progress, anticipated completion Friday December 18th.
01/13/20 – THP received previous roof replacement information from Tremco.
01/28/21 – THP updating report and plans to send by 1/29/21.

CH – Skywalk Bridge Assessment (F013) Read More »

2020 – Floor Patching

06/09/20 – Site visit to see existing conditions. SOSS submitted. Waiting for authorization to proceed.
09/08/20 – Received authorization to proceed. CA to schedule site visit
10/29/20 – Site visit to confirm existing conditions. Broadloom carpet made it difficult to confirm extent of cracks. Bid package in process with reasonable assumption for scope of work.
12/9/20 – SD Drawings and Estimate uploaded into Archibus.
01/21/21 – Structural Allowance added to cost estimate.

02/25/21 – No Update

03/25/21 – No Update

04/29/21 – No Update

05/27/21 – No Update

06/25/21 – No Update

07/13/21 – SOSS submitted to County

08/26/21 – No Update

10/27/21 – Bid set sent to County for approval. Ready to bid.

11/10/21 – Pre-bid held on site. flooring replacement scope added to be alternate #1, #2 and #3.

11/19/21 – Bids came in. Triton was the low bid. Waiting for contract now.

01/26/22 – No Update.

02/24/22 – No Update.

03/31/22 – No Update.

04/28/22 – No Update.

05/26/22 – No Update.

06/30/22 – Kickoff meeting held. Notice to proceed issued. Submittals received and returned.

07/28/22 – No Update.

08/25/22 – Kickoff meeting held. subcontractor to provide schedule.

09/29/22 – Ready to begin project when materials arrive

10/27/22 – Construction began.

12/15/22 – Construction ongoing. should be complete by end of next week.

01/26/23 – Punchlist conducted last week. Corrections to be fixed in the near future.

03/30/23 – Damaged doors discovered from flooring repair. Triton to correct.

04/27/23 – Triton to remove and replace wood veneer on doors.

05/25/23 – Doors have been refinished. They need a final sealant coat and will be installed next week.

06/29/23 – Doors installed. Closeouts received.

07/27/23 – Closeouts need final approval.

08/31/23 – Final pay app sent to county and closeouts approved. Waiting on Triton to provide hard copies.

2020 – Floor Patching Read More »

A&D – JFS Furniture Renovation 2020 SD

06/22/20 – Kick-off meeting. Attended by Mike and Christy from Champlin, John from THP, Mike and Terry from ThermalTech, Susan and Megan from IPM, Rycca, Bert, and JFS executive team from County.
07/09/20 – THP provided a proposal to Champlin for structural support.
08/21/20 – SOSS submitted. Waiting for authorization to proceed.
09/23/20 – SOSS Approved. Kick-off meeting attended by Christy
10/29/20 – programming received from Michael Patton. Typical cubicles were revised and sent to Rycca. Ready to present to JFS.
12/10/20 – Regular design meetings in place.
01/26/21 – TEI and IPM worked out details on walls around the fintube radiators along the outer walls.
01/27/21 – Weekly meetings on Fridays. Final programming meeting scheduled 2/5.
02/25/21 – Weekly meetings still ongoing. planning to start on the 1st and 5th floors.
03/25/21 – Ongoing weekly floor-by-floor presentations of space planning to Michael Patton.
04/29/21 – Ongoing weekly meetings. Field verification walk thru scheduled 5/3/21
05/07/21 – Final Coordination meeting with JFS
05/20/21 – Sent final misc. questions to Michael Patton.
05/21/21 – Received 4th and 5th Floor comments and revisions from JFS
06/03/21 – Field verification to determine signage scope.
06/24/21 – Rough draft of SD Set sent to Rycca for review.
06/25/21 – TEI owes Champlin a SOSS for the plumbing work. Gender-neutral question is out there too.
07/28/21 – Archibus #2106 is updated with MEFP cost and sketches for this project including plumbing updates for bad flow conditions.
07/29/21 – SD documents submitted to Rycca for JFS review. The next step will be a design review with TEI on final design decisions. THP will need to review the new layout from the load study perspective.

08/26/21 – Final Review meeting with County, Thermaltech and Champlin.

09/15/21 – Champlin provided County with updated estimate.

10/12/21 – Champlin provided County with a breakdown of door types being replaced for review.

10/28/21 – Project is complete. Ready to Archive.

 

 

A&D – JFS Furniture Renovation 2020 SD Read More »

TPC – Power Loss/Fire Event Study

02/26/20 – TEI authors and submits SOSS for project per HCFD request. TEI receives PO and approved SOSS. TEI and HCFD meet with CE Power for site investigation of existing conditions and remains of the disconnect switch that failed/caught fire. CE power providing forensic’s report to TEI.
03/26/20 – CE Power has sent TEI forensics report. TEI adding CE Power findings to TEI report to send to Hamilton county.
04/30/20 – TEI finalizes report draft to send to facilities for review.
05/27/20 – TEI has sent the draft of the report to facilities for review. Will finalize upon receipt of comments.
06/23/20 – TEI has sent the draft of the report to facilities for review. Will finalize upon receipt of comments.
07/29/20 – TEI has sent the draft of the report to facilities for review. Will finalize upon receipt of comments.
08/21/20 – TEI has sent the draft of the report to facilities for review. Will finalize upon receipt of comments
04/14/21 – TEI incorporates owner’s comments into report and emails JN and BW final report for approval. Upon approval from HCFD – TEI will issue deliverables to HCFD.
04/28/21 – Report finalized, and (5) hard copies delivered to HCFD. Project complete.

TPC – Power Loss/Fire Event Study Read More »

TPC – Community Development Relocation

ThermalTech Led, IPM sub
02/26/20 – TEI Authors SOSS for a new project to relocate Community Development from 10th floor to 8th floor of TPC.
03/26/20 – TEI receives signed SOSS and PO. HCFD working with IPM to program space and then IPM to send the layout to TEI for electrical design.
04/30/20 – TEI and JP visit project site to look at power/telecom existing conditions.
05/27/20 – Project release pending COVID-19 restrictions.
06/23/20 – Project release pending COVID-19 restrictions.
07/29/20 – No updates this month.
08/26/20 – No updates this month.
09/18/20 – No updates this month.
10/28/20 – No updates this month.
12/10/20 – No updates this month.
12/30/20 – TTC archiving this project for 2020.

TPC – Community Development Relocation Read More »

DDS – Franks Center Roof Restoration

01/07/20 – Hamilton County requested SOSS for roof restoration project.
01/13/20 – Meeting setup up, but cancel by County.
02/11/20 – THP and County walked the site for a SOSS.
02/18/20 – THP issued SOSS to County for review.
04/15/20 – County review documents issued.
04/21/20 – THP received summary WTI moisture analysis reports.
04/24/20 – Bid documents issued.
04/29/20 – Alternate No. 1 issued.
05/13/20 – Alternate No. 2 issued.
05/20/20 – Bids received and Imbus Roofing is the apparent low bidder.
05/28/20 – THP issued a bid summary letter and draft contract to the County.
06/15/20 – Contract have been processed.
07/07/20 – County issued PO.
07/30/20 – Roof work anticipated to start mid-August.
09/21/20 – Gravel removal started.
10/2/20 – Gravel removal completed. THP and Imbus located 400 S.F. of unit cost repair items.
10/7/20 – Unit cost roof repair items being complete.
10/15/20 – Located (2) poor areas of roof installation at RTUs. Imbus to provided a follow up repair of the installation.
10/29/20 – Project update: 40% of surfacing installed and 90% of unit cost repair completed.
11/17/20 – Bulletin No.1 issued for pricing.
11/25/20 – Imbus submitted pricing for bulletin No. 1.
12/01/20 – Bulletin No. 1 pricing approved via email. Change order being processed.
12/04/20 – Change Order No. 1 issued for processing.
12/10/20 – THP received Change Order No. 1 from Imbus. THP forwarded to the County for final execution.
12/10/20 – Project update: 95% of project base bid work complete.
01/12/21 – Project punch list completed. A few small items noted.
01/18/21 – Imbus submitted January pay application (minus retention). THP processed it and sent to Hamilton County.
01/18/21 – Imbus submitted draft project manual.
01/22/21 – Imbus reported all punch list work completed. THP and Tremco to verify final installation.
03/04/21 – Final closeout documents sent to the County. All closeout documentation approved. THP to deliver hard copies to DDS and Facilities.

DDS – Franks Center Roof Restoration Read More »

250 WHT – Booster Pump Replacement

01/22/20 – TEI fieldwork visit and researching equipment options.
01/30/20 – SOSS submitted and original fieldwork completed.
02/24/20 – SOSS submitted awaiting approvals.
03/23/20 – Project ready for review. TTC will send to county for review. New booster pump is 100% redundant but new pumps are 5HP. Barth confirmed conduit and feeders still sized properly for new loads.
04/16/20 – Bids received from Peck, Geiler, Triton and Debra. TEI tabulated and sent to the County for decision.
04/28/20 – TTC released bid tab to bidders. Did not tell bidders who the winning bidder is.
04/30/20 – PO in for approval with County, looking at weekend work for this job.
05/27/20 – Project in for approval with the County for weekend work with PHB as the apparent low bidder.
06/24/20 – PHB sent the submittals in on the project. ThermalTech reviewed and sent back to the vendor including limited comments from the County. PHB working on background checks with BC who is helping get them onsite to the work ASAP. Unfortunately, the lead time on the pump package is 5 weeks at this time because we missed the “on shelf” package they had waiting for us. The hope is to get this installed ASAP.
07/24/20 – PHB has scheduled the pump replacement on August 8 with the backup date of August 9. They have not however received their PO and Contract yet. TEI check with Facilities and it is in place and Tony will send it. PHB will install the pumps and get them working on the weekend BAS interface and local alarms will be picked up the next week by Peck.
08/26/20 – Peck performed the work over the 8/8 weekend. The new booster pump is working and online. TEI issued Punchlist for the project to PHB with remaining work items. Payapp #1 was submitted and approved. Final payapp was submitted but held for closeout documents.
09/16/20 – TTE on-site performing Records Drawing check. Some piping needs to be changed on Record Drawing and CAFM drawing.
09/18/20 – OM’s delivered. Punchlist work complete. TTE to approve the final invoice and send in the final paperwork. Project ready to archive.
10/28/20 – TTC checked in with PHB to ensure all payments have been made and project can be closed.

250 WHT – Booster Pump Replacement Read More »

NFPA 80 Inspection

11/19/19 – SOSS approved for Downtown Fire Rated Door Inspection RFP
11/19/19 – SOSS approved for Auxiliary Buildings Fire-rated Door Inventory
12/18/19 – Champlin sent Fire Rated Door Inspection Bid Documents draft to County
12/31/19 – Champlin began inventory at 250 Taft
01/03/20 – Champlin visited Juvenile Center
01/06/20 – Champlin completes rest of field visits
01/15/20 – Champlin received instructions from Tony Matre to combine both projects into one.
01/21/20 – Champlin receives access to archives for existing drawings of Auxiliary buildings
02/07/20 – Champlin expected to send bid documents to County
02/14/20 – Kru and Sam met with Bert, Tony, Jessica, and Rycca to discuss scope of work to be included in documents. Champlin is waiting for service agreement draft from Bert.
11/20/20 – CA reached out to DHPace in Columbus for a unit price per door. No response after initial call. Reached out again last week and still no response. Looking for new contact to advise.
02/25/21 – No update.

03/25/21 – Preparing Bid package

04/29/21 – Bid package ready for review.

05/27/21 – No Update

06/25/21 – No Update

07/29/21 – No Update

08/26/21 – No Update

10/26/21 – Final bid set completed. Submitted to purchasing.

03/31/22 – Plans marking 0ut doors to be provided to county

04/28/22 – Plans sent to county. TPC Door schedule from GBBN incorrect (Appears to have been entirely copied from Taft Center). Champlin can provide review of TPC if directed.

05/26/22 – Champlin to review TPC friday or monday depending on availability.

08/25/22 – Champlin reviewed reports and door count discrepancy. A&D doors need further discussion.

NFPA 80 Inspection Read More »

TPC – 6th Floor Lighting Upgrades

01/28/20 – TEI authors and submits SOSS for lighting upgrades in the 6th floor board room area to eliminate the large “beam me up” light fixtures per the request of facilities and the Commissioner. TEI has sent facilities an option with costs, lighting calc and a rendering of the space.
02/26/20 – Commissioner rejects initial selection. TEI and HCFD send commissioner lighting selection data sheets and commissioner selects a fixture that is acceptable. ThermalTech sends HCFD revised rendering and lighting calculations for approval. TEI and HCFD discuss benefits/drawbacks of removing wall sconces in the room versus replacing the wall sconces. Pending commissioner approval.
03/26/20 – Project pending review an approval of rendering.
04/30/20 – Project pending review and approval of rendering.
05/27/20 – Project pending review and approval of rendering.
06/23/20 – Project pending review and approval of rendering.
07/29/20 – Project pending review and approval of rendering.
08/21/20 – Project pending review and approval of rendering.
01/28/21 – Archive for now.

TPC – 6th Floor Lighting Upgrades Read More »

Electrical Switchgear PM Specs – 2020

PM – John Nester, Mike Barth

01/28/20 – TEI authors and submits SOSS for approval as requested by facilities.
02/26/20 – TEI receives signed SOSS and PO for the project. TEI to set up kickoff meeting with HCFD.
03/26/20 – Project pending COVID-19 restrictions.
04/30/20 – Project pending COVID-19 restrictions.
05/27/20 – Project pending COVID-19 restrictions.
06/23/20 – Project pending COVID-19 restrictions.
07/29/20 – TEI has kick off meeting with Bryan Collins. TEI and Bryan visit all sites to review gear that is included in the scope of the project. Upon receipt of questionnaires from the building managers, the specifications will be drafted for HCFD to review.
08/21/20 – TEI issues request for information from building managers to include in the specifications. Upon receipt of the information from the building managers, specifications can be completed and issued for bidding, once HCFD says to issue.
09/23/20 – TEI waiting on completed forms from building managers. Upon receipt of the information from the building managers, specifications can be competed and bid package issued.
12/09/20 – Project bids received, CE Power apparent low bidder, and contract sent to Prosecutors office for review and approval. Building priority and schedule TBD once contract is returned and PO cut.
01/26/21 – JN with facilities sends CE Power PO and contract, with instructions for background checks. Upon receipt of approved BGCs, pre-construction meeting to be scheduled. CE Power contacts TEI to request walk through of all facilities prior to evaluate the building and access issues to be prepared to speak intelligently at the pre-construction meeting. TEI instructs CE Power to start the BGC process, and then send request in email.
02/23/21 – Upon notification from JN that CE power has BGC’s completed and passed, a pre-construction meeting will be scheduled to prioritize and develop an anticipated project schedule.
3/24/21 – Background checks are coming back for CE Power staff. HCFD and TEI meet at P&D garage with CE Power to discuss first building to get work completed on. P&D garage work to occur on 03/27/21.
04/28/21 – P&D Garage work completed. 2020 is next – and meetings have occurred at the site to develop plan of execution of work at the 2020 facility.
05/26/21 – TEI and HCFD have meetings with 2020 staff to discuss options with performing the PM. HCJC looking at options to make the PM work. Facilities and HCJC working together with TEI to develop plan.
06/23/21 – work at 2020 facility pending approval of plan from HCJC.
07/28/21 – work at 2020 facility postponed till later in the year (cooler weather). HCFD and TEI walks A&D and 800 Broadway with Bldg managers and CE Power. CE Power to submit outage schedules and durations for both facilities and then PM to be scheduled.
08/26/21 – TEI, HCFD, and CE Power met at A&D to review the project. A solution to make the PM procedures easier in the future was suggested. RT and MB spoke with JFS, and decided to work on the solution to keep the computer room powered (see A&D computer room emergency power). Discussing 800 Broadway now with CE power to keep project moving.
10/26/21 – CE power has sent several of thermal scans for review. 800 Broadway work still to be scheduled. CE power to provide availability.
12/13/21 – CE power reviewed 800 Broadway  for outage plan.  No outage plan submitted from CE Power to date.  CE power receives PO for emergency power and HCFD requests schedule for this work and 800.
01/25/22 – Outage plan received and under review with TEI and HCFD for 800 Broadway.
02/23/22 – Outage plan approved for 800 Broadway – TEI and JN reach out to CEPower for schedule.
04/27/22 – HCFD and TEI pushing CE Power to schedule work.  Pending CE Power Availability.
06/28/22 – 222 cleaning scheduled on 07/09/22.   meetings for balance of buildings to be scheduled the week of 07/11/22.
08/24/22 – CE power to provide proposed schedule for balance of buildings.  CE Power stated that they will be providing load monitoring (proposed dates are 09/01/22 and 09/02/22).  The proposed schedule for the balance of the buildings is due to John Nest and Mike Barth by end of day on 08/25/22.
09/26/22 – A&D building work site work performed.   Duke issues with identifying the location of the emergency feed, caused a re-schedule of the outage.
10/26/22 – Next building (2020) outage plan meeting with users scheduled for 10/31/22.
01/25/23 – 2020 work completed with minimal issues.   Pre-outage walk throughs occurred for the CH and for the TPC.  Outage plans are in development with CE Power and outages will be scheduled upon approval of outage plans.
03/29/23 – CH work completed.   There were issues with one server circuit not backed up and 120 gear maintenance was aborted.   480 gear completed.   TPC gear remains to be PM’ed.
04/27/23 – TEI places to call to Qualus to discuss TPC.  Qualus not returned call to date.
05/23/23 – TEI and HCFD meet with Qualus on site to discuss the project, alternates to the project, and the possibility of moving the Duke Energy bus duct.  Pending quotes from Qualus.
06/28/23 – Pending quotes from Qualus.
10/26/23 – TEI and HCFD working to get Qualus to coordinate and work with Beam repair in basement.   Once the coordination is complete, the work at TPC will be scheduled and project will then be complete.
12/06/23 – HCFD send Qualus CO for additional work.  Upon receipt of CO the final work to be scheduled.
03/27/24 – TPC work to be completed likely in June/July of 2024.  NOTE – add the Emergency generator gear on loading dock to list of gear to be maintained.

05/29/24 – HCFD, TEI and Qualus coordinating dates for final building.  Once scheduled, website will be updated with date scheduled.
08/28/24 – TPC work scheduled for 09/07/24. Project will be complete once TPC work is completed and all reports and closeout documents received for Qualus.
09/25/24 – Switchgear cleaning occurred at TPC. Project complete pending final closeouts.

Electrical Switchgear PM Specs – 2020 Read More »

Comm Center – Electrical Service Upgrade

PM – John Nester, Mike Barth

01/28/20 – TEI authors and submits SOSS for project upon request of Facilities Department.
01/30/20 – This in in the approved projects list.
02/26/20 – TEI receives PO and signed SOSS for project. TEI to schedule kickoff meeting with facilities and building manager to kick off the project.
03/26/20 – TEI, County Facilities, and building manager to kick off the project. Due to the COVID-19 restrictions, design meetings and field work at this facility have been placed on hold until all restrictions are lifted.
04/30/20 – Project pending COVID-19 restrictions.
05/27/20 – Project pending COVID-19 restrictions.
06/23/20 – Project pending COVID-19 restrictions.
07/29/20 – TEI met with Bryan Collins and Ian Zellner to re-kick off the project. TEI contacting Joey Downs at Buckeye Power to re-evaluate the proposed solutions and add any updated recommendations/parts-pieces to develop the drawings and specifications.
08/21/20 – TEI contacts Buckeye Power to follow up on the initial quotation that Buckeye submitted. Design has commenced and coordination with EMI equipment supplier. We will notify HCFD once design review is ready.
09/23/20 – TEI, HCFD, and Ian meet with BPS, review the two options for the HMI replacement that BPS submitted. TEI and HCFD requested Sole Source letter from BPS. TEI developing Construction Documents for permitting and construction.
10/27/20 – TEI receives Sole Source letter from BPS. Working on permitting package – will provide draft of package for HCFD review once funding is released for the project.
12/09/20 – TEI wrapping up permitting package, and will send HCFD a review set prior to holiday break for review and to prepare for a January 2021 issuance.
01/26/21 – TEI sends JN at facilities a review set for the project. Upon facilities department review – TEI to finalize bid package and send to get costs.
02/23/21 – TEI and JN establishing final design review meeting with Ian Zellner and Comm Center Staff (within the next week), and will discuss dates for walkthroughs, etc at the meeting, then the project will be sent out for bidding.
03/24/21 – TEI receives sole source letter (modified as requested by Hamilton County). TEI and HCFD meet with the staff at Comm Center, and can issues the project once the procurement method is determined (sole source or ITB). purchasing approves sole source letter on 3/24/21. TEI and HCFD to conduct final meeting to finalize bidding documents ASAP.
04/28/21 – Per HCFD request – TEI requests a current quote from BPS, that has not expired. BPS confirms on 4/28/21 the latest version that we have recieved. Project to be issued upon receipt of this information from BPS and HCFD approval.

05/26/21 – TEI Submits Package to HCFD – who sent to prosecutors office for review and comments. Will issue to BPS upon prosecutor approval.

06/23/21 – Contracts mailed to BPS for signature and return to HCFD. Upon receipt of signed contracts, project will be approved and PO issued.

07/28/21 – PO issued to BPS for project. TEI and HCFD to schedule meeting with BPS to kick off construction and get leadtimes, etc.

08/26/21 – Construction pending procurement of equipment.

10/26/21 -Construction pending procurement of equipment. Anticipated to be Nov/Dec work.

12/13/21 – BPS on site starting today to install upgrades in the gear.  Anticipate project work completed by end of the week.

01/25/22 – Work completed on the original contract work.  HCFD requests quote from BPS for a replacement breaker to use incase of a breaker failure.  BPS issues the quote and HCFD issues a PO for quote.  BPS to purchase breaker.

02/23/22 – Upon receipt of breaker from BPS, project will be complete.

04/27/22 – Breaker received.  Training completed.  work from BPS completed.   Upon receipt of closeout documents (AIA) from BPS – project complete.

05/26/22 – Upon receipt of closeout documents (AIA) from BPS – project complete.

06/28/22 – Project complete.

Comm Center – Electrical Service Upgrade Read More »

2020 – Fire Alarm System Upgrade

PM – John Nester, Mike Barth

01/28/20 – TEI authors and submits SOSS for the project requested by Facilities.
02/26/20 – TEI receives PO and signed SOSS. TEI and Jessica Powell request design kickoff meeting with 2020 staff. Project kickoff meeting to be scheduled ASAP and design to commence thereafter.
03/26/20 – TEI, County Facilities, and building manager meet to kick off the project. Due to the COVID-19 restrictions, design meetings and field work at this facility have been placed on hold until all restrictions are lifted.
04/30/20 – Project Pending COVID-19 restrictions.
05/27/20 – Project pending COVID -19 restrictions.
06/23/20 – Project Pending COVID-19 restrictions.
07/29/20 – TEI meets with Rycca and Joe Houlihan to re-kick off the project. TEI re-booted the design process. Design fieldwork to be scheduled in the next 2 weeks or so.
08/21/20 – TEI completes field work and is working on completing design. TEI reaching out to Darryl Meadows (CFD) to schedule 85% complete review meeting with CFD and Bldg Department to get buy in on design with the AHJs prior to sending to HCFD for design review.
09/23/20 – TEI meets with Darryl Meadows, at the facility to review the design documents. Darry indicated that there is no BDA in the building presently, and that the City Ordinance requires a 3rd Party company (i.e. MobilCOMM) perform a spectrum analyzation of the building. TEI contacted MobilCOMM to obtain a quotation for the analysis. TEI will schedule a meeting to review design documents with HCFD – discuss option of Mass Notification, and latest Code changes that have been issued by NFPA 72, but that have not been adopted by the City of Cincinnati to date.
10/27/20 – TEI receives quotation from MobilCOMM for spectrum analysis for the building. TEI to schedule the test at a date that is approved by building manager. Upon receipt of the results of the testing – documents will be finalized and a review set will be sent to HCFD once funding for the project is secured.
12/09/20 – Spectrum Analysis scheduled for 12/15/20 with MobilComm. Upon receipt of results of analysis, TEI can send 99% set to HCFD for review in preparation for a January 2021 issuance.
01/26/21 – MobilComm provides spectrum analysis of the building, and a BDA for the project is not required for the building. TEI requests final design review meeting, and upon notification that funding is secured for project, will finalize ITB and issue for bidding.
02/23/21 – Project has been issued for bidding as ITB# 029-21. Pre-bid meeting scheduled for 03/09/21 and bids are due to purchasing on 03/24/21.
03/24/21 – Bids opened on 03/24/21 – and apparent low bidder is DeBra Kuempel, Inc. ThermalTech is vetting bids at 1:30 on 03/25/21 and will make recommendation ASAP to facilities upon completion of vetting process.
04/28/21 – Construction pending approval of contract by BOCC.
05/26/21 – PO and contract sent to DK on 05/25/21 – kickoff meeting to start submittal process requested with DK.
06/23/21 – JCI/Simplex developing submittals for the project. Upon approved submittals, construction will commence.
07/28/21 – TEI rejects (revise/resubmit) original submittals for the project. TEI receives revised submittals on 07/28/21. TEI to re-review and send approved submittals to DK for project. Project construction kickoff meeting can be schedule in next 2 weeks.
08/26/21 – HCFD and TEI host pre-construction meeting at the project site with Bldg Mgr, Brian Bell and Wayne McFarland. DK has PO and permits have been submitted for at are pending review comments from JCI Simplex. Materials from JCI have been released and are pending mid September delivery. DK tentatively scheduling mid/late September mobilization to the project site.
10/26/21 – TEI requests timeframe from DK for mobilization. Accoriding to JCI and DK, nearly all materials have be shipped to DK and work can commence.
01/25/22 – Project is in construction.  Backbone installed and DK has been working to pull second conductor to the notification appliances.  Work continues and in the next couple weeks will be working in the housing areas where residents will need to be temporarily relocated.
02/23/22 – Construction continues.   There are issues with the current Siemens smoke control system that the building manager is working with Siemens to resolve.   by first of next week, will be ready to start cutting over the units to the new system.  Meeting scheduled on 02/28/22 with housing unit staff to discuss and plan for relocation of residents during the installation.
04/28/22 – Met this week on site to do more fieldwork, Project should be complete in June 2022.
05/26/22 – Project nearing completion.  Inspections will be scheduled mid-late June for CFD and building department.
06/28/22 – Pretesting of smoke control system scheduled on 06/29/22.  Upon successful completion of smoke control system, inspections to be scheduled.
07/27/22 – Inspections to start next week.  Smoke control system work completed and tested.
08/24/22 – Inspections going well.  Building Department on site 08/25/22 (during this meeting) finishing inspections.  Will need to return once sampling tubes are replaced with correct tubes.  Then training and closeout can occur.
09/26/22 – All inspections complete and passed!  Finalized.   Upon completion of installation of access panels in the ceiling, project will be complete.
10/26/22 – Project completed.  Project pending close out documentation.
12/15/22 – TEI performs punchlist.  Still pending closeout documents.
01/25/23 – TEI receives close out documents from DK and reviews.   TEI requests minor updates.   Upon receipt of minor updates, Closeout documents will be submitted and project will be complete.
02/23/23 – Project ready to archive next month.

2020 – Fire Alarm System Upgrade Read More »

CH – Plumbing Repairs

08/08/19 – TTE sends SOSS to County as F-119.
10/05/19 – Bert inquires about deadline for bidding documents for this job. TTC sent review set and believes TTE can be done 10/31 with this work.
10/29/19 – Jessica send email about status of project and will be the PM moving forward on this work.
10/30/19 – Coty is onsite during afternoon finalizing access panel locations for bidding.
12/11/19 – Bids were sent out to Triton, Geiler and Debra and came back with two bids and a no bid. ThermalTech discussed the project with Triton, the apparent low bidder who seems to have everything covered. Bid tab and Bids forwarded to County for approval.
01/24/20 – Triton has submitted bid documents to the County and contract and PO paperwork is being drafted.
01/30/20 – Triton sent back signed contracts to County.
02/20/20 – Pre-Const Mtg held with Triton. Meeting notes sent on Monday, need to get Emergency Contact list sent to Jessica. Triton ready to mobilize on Monday afternoon to see the job. Background checks need to be complete before they can come on site.
03/23/20 – Triton has a couple of people with background checks and has been down on the initial field trip. Actual project start may be delayed.
04/29/20 – Triton was supposed to be on site last Monday, TTC to follow up with Brian Day on update.
05/08/20 – Project schedule adjusted for personnel availability, looking towards end of May for work.
05/26/20 – Triton and the County set the additional isolation valve work for Friday May 29,2020. Triton to arrive on our about 3pm and work in the evening for the new access panel and valving. TTC plans to be onsite for questions and answers.
05/29/20 – Met Triton onsite for the work and ran into several issues. (1) the hot water valve was not close enough the access panel to meet the dwg requirements. (2) the cold water valve location was not acceptable given the marble façade that would have to be removed to install it’s access panel. We worked on other acceptable locations with Triton and BC while on site. We all decide that given these two issues, we would call off the shutdown and drain tonight and regroup with a new plan later.
06/12/20 – Triton and BC selected a new location on the second floor for the CW valve, they sent info to TEI for consideration.
06/19/20 – Went to the building twice this week to research new locations for the hot water valve. We didn’t take the Triton suggestion for the second floor but we did find a location on the basement floor where an existing valve is already installed. TEI sent emails and photos to the county for discussion and decisions.
06/22/20 – BW sent an email for an update and TEI followed up with Triton and the County on possible new location. TEI and Triton to meet onsite to discuss. County to decide about two valves in series or remove the gate valve.
06/24/20 – Talked to Triton today about getting a change order for this work and they are reporting they’ve spent $5000 in investigation extras on this job. We are coordinating our next visit down there to finalize this job.
07/17/20 – The new City Water valve was installed on 7/17. The first 4″ valve leaked and Triton had to secure a second valve at a supply house in town. That was installed and the work was complete about 11:30 pm. TTE arrived about noon to survey the piping and prove out the hot water line before Triton arrived for work. After 3 or 4 hours of additional confirming of the water lines using temperatures and more measuring the hot water and hot water recirculation lines were again confirmed to be where we thought they were from the previous fieldwork. After the building shutdown however we found the hot water was still pressurized after the main shutdown. Further investigation showed that the hot water recirc was backfeed the hot water main creating a second path through the PK water heaters (somehow bypassing the check valve, mostly likely stuck open). It as proven in the field that to shut the hot water down to the floors both the DHW and DHWR should be turn off. Ancillary to this work we found the PK heaters powered down, so we closed the valves serving the PK heaters too. We found the PK DHWR pump burned up so we powered that down as well. The new pump installed on the AO Smith heaters will serve as the new DHWR pump. When the water turn back on we tested the new CW isolation valve for the upper floors. Half of the floors were off and some were still running. After some additional field investigation, we found another valve that serve one back of public restrooms in the northeast corner of the courthouse. This valve must be shutoff in conjunction with the new valve to isolate the upper floors from lower floors. In the end there are two hot water and two water valves to shutdown the CH upper floor water systems.
07/28/20 – Triton sent a drafted letter confirming the piping found behind the walls in the 3rd and 4th-floor restrooms was indeed brass not galvanized. A change order request was sent to replace the quarter-turn valve found in the NE corner with a chain operated ball valve.
08/26/20 – Change Order #1 was processed for a deduct to the project. TTC and Bryan going to meet on new valve location tomorrow and we are working on the final schedule to wrap up this project work on the 6th and 7th floors.
09/18/20 – Triton on-site tonight finishing up the project. Jax area completed about 6:30 pm. Basement valve installed by 8:30 pm. Triton had to use one 2.5″ coupling and one 2″ cap from the plumber shop to complete the job. Water back on and everything working – no leaks.
10/28/20 – Work is complete, punchlist is distributed, another payapp was approved. We are waiting on insulation and chain operators to wrap this project up.
11/02/20 – County confirms punchlist is complete, insulation installed and chain operators installed. TEI asked Triton to close the project out ASAP.
12/10/20 – Project is completed. Final paperwork is coming in from Triton for closeout.
12/29/20 – Closeout documents from Triton came in today. TTC will review and begin closeout.

CH – Plumbing Repairs Read More »

800 – Fire Pump Study

10/19/19 – SOSS received and ThermalTech onsite for fire pump testing. We witnessed the fire pump test by SA Comunale and they stated that the fire pumps passed with both city water mains open.
10/30/19 – Terry and Cai met to review the model and report. So far the model is working and matching existing conditions. Cai did a great job interpolating the existing pressure drops from the field data we collected. It is our initial view that both city water mains need to be open for the fire pumps because of the large pressure drop across the BFP’s. WE have to get the mfgr data to confirm this. We also are setting up additional testing with CDFP for more field test.
12/12/19 – No new updates this month.
01/24/20 – This project can be archived in lieu of the City Water Main replacement which has been submitted for Bidding & Construction.

800 – Fire Pump Study Read More »

Animal Shelter – Due Diligence Study

10/28/19 – Champlin, THP, and ThermalTech meet on site at the Hamilton County SPCA for a building tour. We toured the facility to see existing conditions and meet with representatives from the ASPCA and SPCA to discuss requirements for animal shelters. TTE has the existing drawings for scanning.
12/11/19 – The teams revisited the project site last Friday, THP on Monday. We are creating the estimates and report scope this week in advance of turning over the final report and estimates.
12/12/19 – The team discussed what to put in the report for Bert and in current population and code population. This report is supposed to discuss if the County should renovate this space for the new code requirements for canine’s. The county is not actually responsible for the cat population. #1-Renovation Cost, #2-expand to code population needs, #3-New Renovation Cost? We are to send all summaries to Kru at Champlin. BW said he really needs this next week. BOCC terminated SCPA agreement this year and are now looking for keep SCPA services. Provide draft by 12/19 to County.
12/20/19 – All partners have submitted cost and write-ups to the County. The County is working with CA on new building cost estimates and any updates that might be associated with square foot cost. The Renovation/Upgrade of existing facility cost seemed to be within expected ranges.
12/13/19 – THP reviewed budget for reduced repair scope project and discussed with CA.
12/16/19 – THP had conference call with project team to discuss repair scope.
12/18/19 – THP finalized draft of building envelope assessment report and emailed to project team for review.
12/19/19 – THP finalized building envelope assessment report and issued to CA.
01/27/20 – All information submitted to the County in December, will check on any additional updates at this months meeting.
02/20/20 – No updates this month.
03/23/20 – No updates this month.
04/30/20 – No updates this month.
05/27/20 – No updates this month.
06/24/20 – No updates this month.
07/29/20 – Emailed Tony all the scanned drawings we have of the building.
08/26/20 – This project picked up a little bit this month in answering some building questions and discussing adding it to Archibus.
09/18/20 – New Arc Flash project SOSS sent to County, followed up with some additional drawings to Tony from study. This project can probably be archived.
09/24/20 – OK to Archive.

Animal Shelter – Due Diligence Study Read More »

JC – Water Heater Replacement

07/11/19 – ThermalTech sends SOSS to County.
08/21/19 – County Issues SOSS and PO to ThermalTech for Work.
10/21/19 – Project Issued for Bid.
10/28/19 – Prebid is held for project.
12/12/19 – Project is in for contract and approval. County reported contract is with the vendor awaiting signature.
01/17/20 – Pre Const Mtg was held and project notes distributed. Submittals and schedules requested.
02/24/20 – Geiler started putting submittals together but we have not seen the schedule or SOV yet for this project. TTC to check in with Geiler on Schedule. The Water Heater submittals look great.
03/23/20 – Permit drawings sent to Geiler for permitting. Geiler says deliveries are running slow due to governments shutdown, getting updated delivery for this project.
04/27/20 – TTC working with StreamKey on new PK-4 heater because a discrepancy was found between the size that the original engineer had for this HTX and what the factory gave us last year when checked. The steam control pieces can be return for closer equipment. TTC to discuss with Tony.
05/25/20 – Due to a HTX failure on PK-2 the new PK heater was installed in place of PK-2 this month and is up and running (so PK-1 was installed in the PK-2 position). Which is okay because they are the same heaters. The mall gasket leak on PK-1 that can now be fixed at the County’s leisure. The new steam control valve for PK-4 is in stock and will be getting replaced shortly by Geiler. The PK-4 shell is already installed but not operational at this time PK-5 must continue to cover the load. The steam control valve upgrade for PK-7 is complete.
06/23/20 – Geiler finished the insulation last week on the final unit. All system seem to be up and running well. When the buiding reopens to TEI, we can do a final Punchlist. Reports from the bldg staff are good.
07/29/20- Approved all but final of Geiler payapps for this work. TTE awaits access to the building for the punchlist work.
08/26/20 – Punchlist for heaters needs to be distributed. TTC using Coty Groeschen field trip for writing the JC Water Heater Punchlist. I will try to get this out this week.
09/18/20 – Project is complete, ready to archive.

JC – Water Heater Replacement Read More »

JC – Cooling Tower Refurbishment

07/11/19 – ThermalTech Issued SOSS-F-113.
08/21/19 – County issued SOSS and PO to ThermalTech.
10/21/19 – Project Issued for Bidding.
10/28/19 – Prebid held for project.
10/30/19 – TEI working on Addendum 1 questions.
12/12/19 – Project is in for contract and approval. County reports the contract is with the vendor.
01/21/20 – Pre Const held with Andy, TTC and Triton.
01/28/20 – Pre Const meeting notes distributed. CO costing approved by TTC to Marley.
01/29/20 – Triton sent in SOV, project schedule and submittals.
02/24/20 – Triton really pushing for background checks, Tony to check on Monday and let us know. Triton needs to get started very soon to have any chance of getting done even by April 15.
03/24/20 – Triton emailed today that the project has been put on hold for this spring and summer and it will be done in October 2020 due to the government shutdown and delivery orders.
04/27/20 – Material has arrived at Triton. Pictures were sent to ThermalTech for approval for payment of stored materials. Covid-19 has this project on hold for the time being.
05/27/20 – No additional updates this month due to Covid.
06/23/20 – TEI updated the submittals and sent to Triton for the job. Block fill is in the Triton yard and awaiting installation in November 2020. There were a couple of items on the submittal review that Triton will check on with the mfgr. Brent Ernsthausen and Clay are our new PM on this job.
07/29/20 – Triton and Brent back on job, TTE caught up on prep work for these towers with Brent for fall work.
08/26/20 – Discussed paying Triton payapps based on equipment stored in their yard. TTC sent photos along with approved payapp.
09/18/20 – Allowance Usage #1 email out and signed by TTE and Triton, we are awaiting final approval by County.
10/28/20 – Pre Const meeting moved to 11/4/20 1:00 pm.
12/10/20 – CT#2 demo is complete. Crane is scheduled on 12/19 with a street closure anticipated. Triton keeping us up to date with email updates from Clay. The project is proceeding along nicely.
12/28/20 – Verbal approval on extra work for cooling tower C-3 replacements was given. Triton continuing work on the towers and order for new galvanized pans was placed with Stoermer.
01/26/21 – Triton continues to grind out the towers and prepare them for rebuild awaiting the parts from Stoermer for rework on the towers.
02/24/21 – Triton stopped for the cold but now back underway. Tower completion should not be an issue.
02/26/21 – Sealing was completed yesterday. With sealing completed, this has allowed us to install the nozzles and piping back into the towers. We are scheduling the alignment for the gearbox. We will begin the fill next week and should be completed next week as well. We will do the clean off of the roof the following week.
03/25/21 – Triton wrapping up final CT work with the hopes the towers will be ready to fill next week. They are working on the gearbox connections this week.
04/29/21 – Triton complete with all work. ThermalTech issued a punchlist to Triton for this project. There is a low water level alarm reporting back to JCI that is in alarm.
05/26-21 – Allowance #1 & #2 out to Tony for signature for the allowance usages related to the interior pans and repairs. There is a small amount that has to be paid as a change order to the job for extra work on the four pans repair, this will now include the level water floats that monitor the basin water levels. Triton has completed and returned the punchlist for this job minus these final items. Triton will purchase and install the floats in the next few weeks.
06/25/21 – New water level valves installed. Triton fixing final leak on CT. Closeout paperwork started. We need Tony to approve and sign allowances and change order #1.
07/28/21 – Project Complete.

JC – Cooling Tower Refurbishment Read More »

230 – Probate Court Security Upgrade

10/03/19 – Project request made Scott Weikel for glass security panels to be installed at public counters on the 9th and 10th floor of the Taft Building.
11/01/19 – Champlin scheduled for field visit to verify locations and dimensions of work area.
11/18/19 – Cost estimate uploaded to Archibus. SD drawings sent to County.
05/20/20 – Meeting at Taft center to discuss scope. Attended by Sam and Mike from Champlin, Rycca, Jessica, and Bryan from County and Scott from the Taft center.
06/03/20 – additional site visit to verify existing conditions
06/03/20 – Meeting at Taft Center to choose product. Attended by Sam, Mike, and Jose from Champlin. Rycca and Bryan from County and Scott from the Taft Center.
07/02/20 – Draft of ITB sent to County for approval
07/27/20 – final copy of ITB and Plans approved. Prebid meeting set for 08/03/20 at 10 am
08/20/20 – Bids received and apparent low is James Hunt Construction.
09/03/20 – Contract signed by Hunt
09/14/20 – Submittal returned to Hunt
10/29/20 – Construction planned for the weekend of 11/21. Punchlist to be scheduled monday 11/23.
11/21/20 – Project ran into complications. New date of install is the weekend of 12/19-20. Punchlist to follow.
12/26/20 – Installation 12/26-12/27 Champlin performed punchlist 12/27
01/18/21 – Additional punchlist issued.
01/23/21 – Glass and 1 dented post cover replaced. sometime this week 2nd post cover to be replaced.
02/24/21 – Back punch by Sam Hofmann, Danny Rusconi, Rycca Thacker and Scott Weikel. Final touch up items to be completed 2/25 at 4pm
02/25/21 – All punch items completed
03/25/21 – Project essentially complete. Final payment sent. The project can be archived.

230 – Probate Court Security Upgrade Read More »

250 WHT – First Floor Painting

10/16/19 – County made request for get pricing to bid out painting 250 William Howard Taft – first floor only.
10/25/19 – Champlin was at site for field verification.
12/5/19 – Cost Estimate and SD drawings sent to County
12/10/19 – Cost Estimate Revised
01/9/20 – SOSS submitted to county
01/22/20 – Approved SOSS and PO received by Champlin
01/30/20 – Waiting to receive bid schedule approval and list of approved vendors before sending RFP to potential bidders
02/21/20 – bid documents sent to County for approval
03/11/21 – Documents revisions sent to Champlin
03/18/20 – Bid documents sent to county
04/02/20 – Project put on hold due to Covid-19
06/25/20 – County reported that most of this work was completed in house.

250 WHT – First Floor Painting Read More »

A&D – JFS Director’s Office Renovation

08/30/19 – Champlin submits SOSS
09/11/19 – Champlin received approved SOSS & PO.
10/31/19 – Susan is coordinating furniture selection. Project will go to bid after that.
12/02/19 – Bids received from 3 bidders. RCF is apparent low and Purchasing is processing this to move forward.
06/25/20 – Furniture on site but may not be used given retirements and Covid. Project can be archived at this time.

A&D – JFS Director’s Office Renovation Read More »

2020 – City Façade Assessment

08/22/19 – THP provided SOSS.
08/28/19 – County approved SOSS.
09/26/19 – THP schedule to complete work in October.
10/18/19 – THP visited site to perform visual inspection of façade from grade and from roofs.
10/25/19 – THP visited site to rappel façade and perform close-up inspection.
10/30/19 – THP finalized draft of façade review report for Owner’s review.
12/12/19 – THP met AFR at site to confirm façade repair locations.
12/13/19 – THP met AFR at site to confirm completion of façade repairs and document locations.
01/03/20 – THP issued field report #19 for 2020 Auburn Ave. façade repairs.
01/21/20 – THP finalized and emailed letters to city about completion of façade repairs.
02/27/19 – Refer to F117 for status.

2020 – City Façade Assessment Read More »

CH – 6th Floor Office Build Out

08/27/19 – County requests onsite meeting to review scope.
09/10/19 – Champlin received approved SOSS & PO.
09/17/19 – Champlin & ThermalTech site visit.
09/27/19 – Check set given to Hamilton County for approval.
10/03/19 – CDs set given to Hamilton County and issued for permit.
12/03/19 – Bulletin #01 sent to County and Triton Services.

12/31/19 – Door and hardware submittals approved and sent to Triton

01/02/20 – CO #4 signed and sent to County

02/03/20 – Champlin performed Punchlist visit

02/04/20 – Punchlist report sent to County and Triton

02/14/20 – Champlin performed Back Punch visit

02/21/20 – Backpunch report sent to County and Triton

05/15/20 – Pay app signed and returned to Triton

CH – 6th Floor Office Build Out Read More »

A&D – JFS Internal Door Replacement

06/17/19 – County requests JFS Internal Door Replacement Project Scoping Meeting
07/02/19 – Meeting with Facilities (Tony Matre, Steve Sears, Cloude Toulson, Bert, Kru and Jeff)
07/11/19 – Champlin submits SOSS
09/11/19 – Champlin received approved SOSS and PO.
09/13/19 – Champlin performs site visit to verify all office door locations to be included.
10/28/19 – Champlin performs site visit with Hardware Consultant to confirm door hardware. Hardware consulting on going.
12/10/19 – Bid set sent to county
01/07/20 – Addendum #1 sent to County
01/16/20 – 5 bids were submitted to County.
01/22/20 – Champlin met with Megen Construction.
01/27/20 – Champlin sent official recommendation to award bid to Megen Construction.
03/26/20 – Waiting on official Contract to be given to Megen to return their door submittal
04/17/20 – Scope of work reduced to egress and security doors only.
05/04/20 – Megen given contract.
05/13/20 – Zoom meeting between Champlin and Megen to discuss scope changes.
05/28/20 – Waiting on revised estimate from Megen to proceed
06/24/20 – Waiting on revised estimate from Megen to proceed
06/29/20 – Megen provided revised estimate and other pre-construction information necessary.
07/21/20 – Pre-construction meeting attended by Champlin, Megen and County to further discuss the project. still waiting on project schedule and schedule of values from Megen.
07/28/20 – Door and Frame Submittal returned to Megen.
07/31/20 – Site visit scheduled to walk through areas of additional scope.
08/07/20 – Megen sent Safety materials.
08/18/20 – Schedule of Values and Project Schedule received from Megen construction. Megen has provided construction schedule showing NTP of August 3 and completion on December 7. On site work scheduled to start October 9. Mark-up of doors to be added sent to Claude/Steve for review and confirmation prior to creating a bulletin for contractor pricing. Waiting on direction to proceed.
08/24/20 – Change order for decrease in scope sent to Megen.
09/09/20 – Add services for Thermal Tech sent to Rycca.
09/21/20 – Megen workers complete background checks. Megen visits site to confirm existing conditions
10/09/20 – Scheduled start date.
10/29/20 – Construction started. OAC meetings scheduled for every Friday through end of construction projected by Megen to be December 7th.
12/10/20 – Working on new RFI for this project. Work on answer after tomorrow’s meeting.
01/15/21 – Restarted weekly construction progress meetings.
01/25/21 – Megen provided construction completion dates as follows: Basebid 2/23/21 bulletin 2 work. 03/02/21 Bulletin 1 work 3/22/21.
01/26/21 – Champlin returned comments requesting accurate pricing for 2 potential change orders.
02/08/21 – Progress Walk-thru attended by Sam Hofmann, Randy Johnson, John Nester, Steve Terheiden, and Rycca Thacker
02/19/21 – Bulletin #03 issued for replacement of existing closer/holders. RFI approved for supplier change from Interior Supply to LaForce.
03/19/21 – First Punchlist by Sam Hofmann, Mike Murphy, Rycca Thacker, Steve Terheiden, and Steve Kenneda.
03/26/21 – Second punchlist scheduled.
04/29/21 – Final punch scheduled for 4/30.
05/07/21 – Verified operation of closer/holders with fire alarm system. (attendees include, Rycca, Steve T, Mike B, Mike M, Sam)
05/10/21 – Champlin sent Rycca contractual dates and sequence of events as a word document.
05/12/21 – Final punch by Rycca, Steve T, Mike B, Mike M, and Sam.
05/14/21 – Punch list issued to Randy and Steve K.
05/18/21 – Rycca receives invoice from Phazor for replacement of fire alarm relays. Champlin send invoice to Megen. Randy acknowledges receipt and indicates he’ll forward it to accounting for payment.
05/25/21 – Contacted Megen regarding schedule of completion of punch list items.
06/24/21 – Megen notified us remaining materials received. intend to install on June 28th.
07/28/21 – Megen issued completion date of 7/28
08/26/21 – Waiting on Medeco Cores to be delivered.
11/08/21 – Final punchlist with County and Champlin. Still waiting on Medeco Cores from Megen.
11/17/21 – Finished second half of final punchlist
11/30/21 – Sent finalized report to Megen. Gave deadline of December 31. Requested filled out responsibility columns and schedule. Have not received either
01/21/22 – Final punchlist finally received from Megen.
01/25/22 – Backpunch by Sam and Rycca.
02/10/22 – Backpunch items completed. All construction services complete.
03/31/22 – Close out documents to be complete by friday.
04/28/22 – Close out documents received from Megen. Under final review.
05/26/22 – Close out documents to be reviewed.
06/30/22 – O&M manual reviewed and returned comments to Megen. Awaiting corrections
08/25/22 – Still waiting on Payroll information.

12/15/22 – All closeout documents and payroll information received. PROJECT COMPLETE

A&D – JFS Internal Door Replacement Read More »

250 WHT – Egress Door

06/18/19 – Bert emailed regrading a question from the County’s Safety Specialist regarding a egress door and egress path at the 250 WHT Building.
06/18/19 – Bert emailed floorplan and egress door in question to Champlin for review prior to site visit.
06/25/19 – On site meeting with Bert, Tony Matre and Kru to review location of Exit Door in question and review egress path.
07/03/19 – John from THP shared building code notes from 2015 project for replacement of deteriorated concrete bridges.
09/01/19 – Champlin shared memo explaining removing exit door designation at mid-landing.
09/11/19 – Cincinnati Fire Department sent followup questions.
09/17/19 – Champlin reviewed existing hardware and access control with building manager. Champlin to review this with Fire Department.

10/24/19 – Champlin had a code review meeting with Cincinnati Fire Department (Darryl Meadows) and Building Department (Greg Wiles)

250 WHT – Egress Door Read More »

P&D – Office Renovation

PM: John Nester, Sam Hofmann
06/24/19 – Krutarth and Christy from Champlin meet with County Facilities and P&D Garage manager to review scope of work on-site
07/02/19 – Christy from Champlin sends concept sketch and scope of work description to Bert Watts for his review
07/18/19 – Christy from Champlin met with County Facilities and PD Garage manager to refine scope of work in CAB building
07/24/19 – Christy from Champlin sends preliminary SOSS to Bert Watts for his review for SD scope of work and cost estimating
07/25/19 – TTC created category and Champlin drafted SOSS for SD and Cost Estimates.
08/22/19 – Christy from Champlin sends revised SOSS to Bert Watts for his approval for SD scope of work and cost estimating, revised to include THP
08/28/19 – TEI created preliminary HVAC load calcs and HVAC upgrades prior to the job starting to make sure the existing equipment can be reused if this project moves forward. It is our belief that the existing air handler can be reused with a new VAV with Elec RH for this job.
09/20/19 – SOSS is approved via email from Jessica Powell.
09/24/19 – No updates on this project from ThermalTech this month.
10/16/19 – Meeting w/ Jessica Powell, Mohammad Islam, Bruce McClain & Greg Smorey at P&D Garage to review SP-02.
10/21/19 – Champlin issued SP-03 plans in response to meeting comments.
10/23/19 – Greg commented on SP-03 plans.
10/23/19 – Champlin revised SP-03 and reissued based on Greg’s comments.
10/24/19 – Greg approves SP-03 drawing.
12/12/19 – We discussed in detail how to price up the expansion of the storage room with THP recommendations from their fieldwork. Bert suggested we put together the cost to do the storage room work as two alternates for this work. We then discussed how to do that work and what to price up in the Alternate. TTE to give new prices to CA for this change.
12/16/19 – Project is given new job number 19-PDFO-0486-2040
01/24/20 – Champlin Cost Estimate is uploaded.
01/29/20 – THP’s opinion of probable cost uploaded to Archibus. DD drawings to be sent to Champlin by 1/31/20.
01/30/20 – CA, THP and TTC to edit the estimate one more time and potentially upload drawings. TTC and JM to discuss with Jessica after Partner Meeting.
02/26/20 – Alternate estimates added to comment section. Waiting on P&D decision.
03/24/20 – Cost estimate updated to reflect flooring changes.
07/30/20 – On hold.
08/27/20 – On hold.
03/25/21 – Facilities to circle back on renovation with Engineers next month. It has been on Covid hold.
04/29/21 – No Update.
05/27/21 – No Update.
06/25/21 – No Update.
08/26/21 – No Update.
01/27/23 – THP – Champlin requested structural proposal for Garage improvements.
02/02/23 – THP provided draft proposal to Champlin for review.
02/22/23 – SOSS is at P&D approval.
02/20/23 – THP provided final structural proposal to Champlin.
03/30/23 – SOSS returned. Kickoff meeting to be scheduled
04/27/23 – Kickoff meeting held on site. Minor changes in scope. Design development in progress.
05/25/23 – Drawings and re-estimate to build budget in progress.
06/28/23 – CD documents by 6/30/2023.
06/29/23 – Met with users on 6/26 to finalize plans. Estimate and complete set to be sent next week.
07/14/23 – THP sent Opinion of Probable Cost and Owner Review Set of drawings to Champlin. Waiting to hear back on comments and bid date.
07/27/23 – Owner review set and opinion of probable cost to be submitted on friday.
08/23/23 – THP no updates.
08/31/23 – Project to go out to bid 9/5.
09/01/23 – THP sent Bid Set drawings to Champlin.
09/28/23 – Project is out to Bid.
10/25/23 – K&T construction won the bid. Contract phase until further notice.
11/27/23 – No updates from THP.
12/07/23 – Project scheduled to kickoff in March.
02/01/24 – Submittals under review, permits submitted on this project.
02/26/24 – THP – Pre-construction meeting held on site. Preliminary schedule for construction to start 03/19/24. TTE has responses ready for review, TTC to look over.
03/28/24 – Submittals returned. Background checks mostly complete. Waiting Permit approval.
04/22/24 – Building permit has been approved and picked up by the contractor. Tentative mobilization date 04/24/24.
04/25/24 – K&T mobilized Wednesday. They will work Mon-Thur starting at 8:30AM.
05/29/24 – Structural scope of work has been completed. THP to attend Progress Meeting on 6/4 to review work and punchlist with contractor. Still on tract for Phase 1 to move on schedule. Emcor submitted change order cost to move the electric disconnect, controls enclosure and add controls to the duct heaters. TTC discussed with Tony.
06/27/24 – Construction in progress. Phase 2 to be complete in 2 weeks.
07/24/24 – Phase 1 complete and ready to start Phase 2.
08/29/24 – Phase 2 complete. Furniture to be delivered next week. Punch to be scheduled.
09/26/24 – Final punch list provided to K&T. Closeouts received.
10/31/24 – Closeouts under review.
12/12/24 – Closeouts complete and final pay app processed.

P&D – Office Renovation Read More »

Project Cost Estimates 2020

07/24/19 – Bert discussed 2020 project schedules with team today. All partners can edit this project for updates this year.
08/28/19 – ThermalTech has received our SOSS back from Facilities and fieldwork has been started. HVAC and Plumbing have bee updated for Admin air compressors, auto title and vestibule projects. We should discussed a revised completion date for all the partners.
08/22/19 – THP provided SOSS for project cost estimates.
08/28/19 – County approved THP SOSS.
09/01/19 – ThermalTech completed preliminary estimates awaiting schematic design documents for changes.
09/10/19 – County approved Champlin SOSS.
09/26/19 – THP completed loading dock estimate and information loaded into Archibus.
10/07/19 – We met back at the Admin Building on vestibule job and modified the MEP cost a little bit. All ThermalTech projects are updated and ready to go.
10/03/19 – Project request made Scott Weikel for glass security panels to be installed at public counters on the 9th and 10th floor of the Taft Building.
10/07/19 – THP attended kick off meeting for review CAB entry project. Based on current project request, THP will not have a role in this project.
10/31/19 – THP estimate up loaded into Archibus.
11/01/19 – Champlin scheduled for field visit to verify locations and dimensions of work area.
11/05/19 – CA cost estimate for Justice Center Security Barriers uploaded to Archibus.
11/08/19 – CA updated SD plan for Autotitle project.
11/12/19 – CA cost estimate for Autotile uploaded to Archibus
11/18/19 – Cost estimate uploaded to Archibus. SD drawings sent to County.
11/11/19 – Bert Watts provided CA with new contact information for someone to walk the scope of JC Door replacement.
12/02/19 – CA cost estimate for Cab Entry uploaded to Archibus.
12/13/19 – CA visited Justice center to review scope for Justice Center Frame Replacement
12/17/19 – TEI updated plans and cost for 2020 Projects for CAB Auto Title and Vestibule project in Archibus.
01/16/20 – CA received list of doors and frames to be replaced in Justice Center from Sgt. J. McAuliffe.
02/25/20 – CA reached out to vendors for more information. In the process of putting together cost estimate based on vendors information.
02/27/20 – PDF 2020 estimates by Friday 2/28 and share with Bert when complete. No binders required for this year.

03/09/20 – Champlin reached out to Sgt. McAullife for questions regarding Justice Center Door Replacement project. Waiting on Stg. to schedule a meeting with higher ups to discuss scope.

05/01/20 – Stg. McAullife provided answers to questions of scope. Reached back to to clarify scope

06/17/20 – Scope finalized. Estimate uploaded to Archibus.

 

Project Cost Estimates 2020 Read More »

A&D – Movable Wall (F005)

07/01/19 – Hamilton County requested to review and design a movable wall.
07/12/19 – THP provided an SOSS.
07/23/19 – County approved SOSS.
08/29/19 – THP completed initial design. THP to meet with County to review approach and design needs.
02/27/20 – Wall manufacturer went out of business, so project on hold.
06/25/20 – Facilities will touch base with JFS on the viability of this project.

A&D – Movable Wall (F005) Read More »

CH – WiFi System Design

02/26/19 – Facilities requests SOSS for WiFi System Design based upon Study that was completed in May 2016. TEI authors and Submits SOSS.
07/24/19 – TEI completes design. TEI has 100% design review meeting with HCFD, CMSNet, and Bradley Bedacht (Courts) and delivers copies of completed drawings and project manual for review. TEI inquires on 07/23/19 with BB if there are any comments. Upon receipt of comments, TEI will contact purchasing to establish ITB # and bidding dates.
08/27/19 – ThermalTech recieves final comments from the owner. Project was issued for bidding. The pre-bid meeting is scheduled for 09/04/19 at 10:00 AM. final bids will be due through the purchasing department at 11:00 AM on 09/20/19.
09/25/19 – The bids opened on 09/20, Glenwood Electrical Services is the apparent low bidder. ThermalTech is vetting the bid to make recommendations for a contract.
10/30/19 – ThermalTech has vetted the bids, and made recommendations to the HamCo for moving forward. Once contracts are completed, a pre-construction meeting will be scheduled with the contractor and the design team.
12/11/19 – Project executed and the purchase order delivered to Glenwood electric for the project. Glenwood sends TEI submittals for review on 12/10/19. Glenwood developing site specific safety plan and schedule for review. Glenwood submits list of employees for BGCs. upon approval of BGCs, will mobilize to the project. Anticipate mobilization early January 2020.
01/28/20 – ThermalTech rejects the submittals for non compliance – waiting for Glenwood to re-submit. According to Glenwood – the BGCs are in progress. Mobilization date is TBD.
02/26/20 – TEI approves and returns all re-submittals – Glenwood stated that their LV guys have the BGCs completed and returned, but the electrical crew has no BGCs returned yet. Materials have been ordered and Glenwood to contact HCFD to schedule mobilization. Glenwood has not gotten badges yet for any of their crew – I said to look closely at the info from HCFD – as there are only specific hours that badges can be made.
03/26/20 – Construction progressing, through the building. Glenwood began construction in the basement and are working their way up through the building. Glenwood’s Electrical guys will be complete by 04/01/20. Glenwoods low voltage guys are currently working on the 2nd floor.
04/30/20 – Project installation nearing completion. Glenwood schedules heat mapping of new system for May 15. TEI and facilities perform punchlist. TEI issues Punchlist.
05/27/20 – Heat mapping postponed until May 29 due to none communicating ports. Once heat mapping is complete, TEI and HamCo (Facilities and courts) to review and make comments for any final adjustments.
06/23/20 – Heat mapping completed on 05/29. There were multiple areas in the building where the heat mapping company did not scan the areas and marked on the report that the levels were below acceptable/expected levels. Upon review, all parties including Glenwood agreed that the heat mapping in those areas would be re-scanned. The re-scan was scheduled for 06/19, and floors 1 and 2 were re-scanned prior to a failure of the scanning device. The heat mapping company is scheduled to return to the courthouse on Friday 6/26 for floors 3 and 4. New reports will then be issued and reviewed by the team (Courts/Facilities and TEI).
07/29/20 – TEI reviewed revised heat maps with HCFD and Bradley Bedacht from Courts. There are a few minor modifications that need to take place, and the courts have been asked if there are any additional modifications that they would be interested in prior to project closeout. Bradley to coordinate the rollout of the new wifi system with telecom.
08/21/20 – TEI, HCFD, Telecom and Bradley Bedacht meet to roll out new system. New system turned on and running on 08/14/20. Glenwood scheduled to train on 08/24/20, and swap the (7) APs that are on the hcpub SSID to the CHPublic on the same day as training. Courts has published the passwords for the SSIDs and after the change over, the hcpub network will be shut down in the courthouse and demo of old system components can occur.
09/23/20 – Project nearly complete – switched over to new system. TEI issues request for CO pricing to add a WAP in room 415, and relocate (2) WAPs for better coverage. TEI receives email from BB stating that there may be a couple additional adds. Glenwood requests walkthrough to confirm understanding of changes. TEI to schedule the week of 9/28.
10/27/20 – Glenwood electric is scheduled to be on site 10/27/20 at 4:00 PM to make the final connections for the Change Order work. Once completed, as-builts and close-out document will be turned in and project can be closed out.
12/09/20 – Closeout documents and as-builts submitted to HCFD. final Pay applications submitted to HCFD. Project complete.
12/10/20 – Courts said so far so good. Proejct ready to archive.

CH – WiFi System Design Read More »

Electrical Findings Study and Report

06/26/19 – TEI authors and submits SOSS for project. Project pending approval of SOSS and PO.
07/24/19 – TEI receives approved SOSS and PO. TEI to establish kickoff meeting with facilities and begin project.
08/27/19 – TEI to kick off this project once server room project is issued for bidding
09/25/19 – TEI is gathering data from the other projects for this report. TEI to schedule meeting with HCFD for kick off meeting.
10/30/19 – TEI working on report – and is scheduling site visits to the buildings included in the report to visit sites. The report is in process.
12/11/19 – TEI working on report – and is scheduling site visits to the buildings included in the report to visit sites. The report is in process.
01/28/20 – TEI has report well in process and will submit draft upon completion.
02/26/20 – TEI has report near completion – pending one manufacturer (GE) responses. Draft report to be submitted upon receipt and review of GE data.
03/26-20 – TEI to send to Facilities draft of report by 04/01/20.
04/30/20 – TEI send draft report to facilities for review. TEI receives comments from facilities. TEI modifying final report.
05/27/20 – TEI to finalize report for submission to facilities.
06/23/20 – TEI to finalize report for submission to facilities.
07/29/20 – TEI to finalize report for submission to facilities.
08/21/20 – TEI to finalize report for submission to facilities.
04/28/22 – Ready to archive.

Electrical Findings Study and Report Read More »

A&D – Façade Coating Survey

06/10/19 – Hamilton County requested SOSS to survey masonry coated area and remove loose debris.
06/12/19 – THP met with American Façade Restoration to discuss contractor scope and to get a proposal.
06/19/19 – THP submitted an SOSS for design services and AFR proposal to complete the work.
08/29/19 – Work scheduled to start after F117 complete.
10/31/19 – See F117 for project status.
01/24/20 – THP finalized Alms & Doepke window sill repair details and emailed to AFR proposal for change order #6.
01/30/20 – See F117 for project status. Construction work complete. Final paper work closeout in process.
02/27/30 – Refer to F117 for project status.

A&D – Façade Coating Survey Read More »

Millvale – Lease Tenant Fit-Out

06/14/19 – IPM and TTE Met County onsite for kickoff field trip for lease space renovation.
06/21/19 – CHA, IPM and TTE put proposal together and submitted to County for consideration.
06/25/19 – Split proposal up into SD & Estimating and CD & Bidding for consideration.
06/27/19 – Submitted new SD & Estimating SOSS to Facilities for approval. Based on the findings in the SD phase we will update the DD, CD, Bidding & CA SOSS later if the project moves forward.
07/24/19 – SOSS approved. Four week time clock has started. TTE has visiting the site and taken off additional plumbing, HVAC and electrical. Bert gave us the contact to do additional fieldwork at the site. One additional plumbing drawing was found on site.
07/25/19 – County stated today that the all disciplines must have permittable style SD documents to attach as exhibits to the lease.
08/28/19 – The team completed the SD phase and cost estimate and submitted to the owner for review. The cost was higher than expected and a value engineering meeting was held with Facilities and JFS. We removed the HVAC from the project, removed one restroom, changed some of the finishes in the space. We then we updated the floor plans, furniture plans, HVAC, Electric and Plumbing and uploaded the new drawings to Archibus. Finally we updated the cost estimate to match the new scope. We are awaiting review and approval by owner.
09/24/19 – No updates. We are waiting on funding and approval to move to next phase.
10/09/19 – Master lease between CMHA and the city is approved. Project will move forward.
10/23/19 – DD set given to Hamilton County.
10/31/19 – Waiting on lease documents to City, waiting on approval to move forward on bidding.
11/01/19 – CD set scheduled to be given to Hamilton County. Bert gave us the background on using this space now and in the future. This may take some time to work this through the City process for DD drawings.
12/10/19 – CA attended walk through of Space with TTE, County, and Cincinnati to discuss scope of work.
01/30/20 – CHMA approved our proposed plan. The County needs this in writing so they can sublease this space and agree on amount of stay past end of lease. Bert said we are just getting through the administration stuff, the project is good to go in concept.
06/25/20 – Project on hold for now. RT will check on future feasibility.

Millvale – Lease Tenant Fit-Out Read More »

Comm Center – Temp Trailer Due Diligence

05/21/19 – TEI to study feasibility of adding a temporary trailer behind the building for additional office space.
07/25/19 – TTC to submit an SOSS for this work.
08/28/19 – No updates this month.
09/24/19 – No updates this month.
10/30/19 – No updates this month.
01/24/20 – No updates this month but officials are started to ask about starting this study.
02/24/20 – No updates this month.
03/24/20 – No updates this month.
04/30/20 – No updates this month.
05/27/20 – No updates this month.
06/24/20 – No updates this month.
06/25/20 – Archive for now, if the project comes back we will bring it back.

Comm Center – Temp Trailer Due Diligence Read More »

Burlington – HVAC Upgrade

09/14/18 – ThermalTech contacted to provide HVAC study at Burlington Garage.
09/20/18 – ThermalTech has Monnit sensors on site for space and humidity monitoring.
10/05/18 – ThermalTech issues final study of space conditions with recommendations for better space and humidity controls.
11/01/18 – ThermalTech issues Small Project Manual for bidding to local contractors for HVAC work.
11/26/18 – ThermalTech issues Bid Results to County.
12/03/18 – Engineer’s Office issues PO to winning bidder for the project.
01/16/19 – SOV approved for NKYHA and the work should begin shortly.
04/03/19 – Project punchlist issued to contractor for Work.
04/25/19 – Review work with County and NKYHA, final changes and adjustments underway.
05/29/19 – ThermalTech created Temperature Trend worksheet and emailed to Tony and Mike.
06/03/19 – ThermalTech issues weekly summary showing temperature and humidity’s are within limits; confirms that installed equipment appears to be operating correctly. TEI has not been on site to witness the workings of the dehumidifiers and RAWAL valves since the 4/25 field visit.
06/26/19 – ThermalTech issued temperature and humidity trends for the building. Everything looks great and all systems are go. We will continue to monitor until July 31.
07/25/19 – ThermalTech adding Monnit sensors for additional trending. Spaces look okay but discharge temperatures and unit temperatures not matching up.
08/28/19 – NKYHA added refrigerant to the Admin unit and TEI pulled out the Monnit sensors after several weeks of good data. Everything appears to be work okay. Humidistats were set to 65% so the units could do the majority of the dehumidification. When the separate dehumidifiers operate they discharge 100F air into the space as part of the dehumidification cycle making it harder for the split systems to maintain space temperature.
09/12/19 – Mark called to say NKYHA sent a payapp in with no signature. I told Mark to forward it to me for payment, but Rick sent it to me and it was wrong.
09/24/19 – Ready to Archive this project. Rick owes the County one more payapp because I rejected his last payapp because it had the wrong amount on it.

Burlington – HVAC Upgrade Read More »

Records Center – Façade and Roof Repairs

05/16/19 – County requested SOSS for façade and roof repair package.
06/19/19 – THP submitted an SOS for design services.
06/27/19 – Verbally approved. Need to final bids and contract by November.
07/03/19 – SOSS Approved.
07/25/19 – Project update: THP anticipated design review documents being published August 2.
08/29/19 – DD docs to be issued September 13th.
08/29/19 – DD docs to be issued September 13th.
10/18/19 – Bid Documents Published.
10/29/19 – Prebid meeting completed.
10/31/19 – Bids due 11/19/19.
11/06/19 – Addendum no.1 issued
11/04/19 – Addendume no. 2 issued.
11/21/19 – Three bids were received. Imbus was the apparent low bidder.
11/21/19 – THP discussed the bid with Imbus and issued a bid summary letter recommending Imbus complete the work alternates no1 and no3 for $353,130.00.
01/30/20 – THP project summary – Bids approved and County generate contract for execution.
02/14/20 – County Issued fully executed contract.
02/27/20 – Project update: Plan to schedule preconstruction meeting the week of March 2nd. Work is anticipated to start early April.
02/14/20 – County Issued fully executed contract.
02/27/20 – Project update: Plan to schedule preconstruction meeting the week of March 2nd. Work is anticipated to start early April.
03/03/20 – THP issued conform set.
03/04/20 – Preconstruction Meeting occurred. Construction to occur once weather allows.
04/16/20 – Imbus mobilized job site.
04/19/20 – Roofing submittals processed.
04/20/20 – Imbus began roof repairs.
05/04/20 – Pay application No.1 processed.
05/12/20 – Lintel submittal processed.
05/27/20 – Pay application No. 2 processed.
06/15/20 – THP issued updated canopy anchor requirements.
06/17/20 – Imbus subcontractor finished installing the canopy.
06/25/20 – Roof work completed. Team plans to meet and punch the roof 6/26/20.
06/26/20 – Punch list review meeting completed. Two minor items noted.
07/08/20 – Warranties submitted.
07/24/20 – Final pay application submitted.
07/27/20 – Changer order No. 1 approved.
07/30/20 – Punch list work complete. THP processing closeout paper work.
12/09/20 – Final project manual submitted.
12/10/20 – THP plans to drop off project manual and final pay request 12/11/20.
01/28/20 – THP dropped of project manual and final pay application mid December.
02/25/21 – Project can be closed.

Records Center – Façade and Roof Repairs Read More »

Burlington – Building Roof Replacement (F002)

04/10/19 – Engineering office requested a roof replacement project.
04/16/19 – THP visited the site to develop a SOSS.
06/24/19 – THP submitted an SOSS for design services.
07/11/19 – SOSS approved.
07/25/19 – Project update: THP anticipated design review documents being published August 2.
08/29/19 – DD docs to be issued September 13th.
09/26/19 – Meeting with Burlington Engineer 9/27/19
10/18/19 – Bid Documents Published.
10/29/19 – Prebid meeting completed.
10/31/19 – Bids due 11/13/19.
11/13/19 – Three bids were received on 11/13/19. Wm. Kramer and Sons was the apparent low bidder.
11/22/19 – THP discussed the bid with Kramer and issued a bid summary letter recommending Kramer complete the work alternates no1 and no2 for $73,764.00.
01/30/20 – THP project summary – Bids approved and County generate contract for execution.
02/26/20 – County issued executed contract.
02/27/20 – Project update: Plan to schedule preconstruction meeting early March once formal PO is issued. Work requested to start mid-April. Kramer confirmed start date is good.
03/03/12 – Conform documents issued.
03/12/20 – Preconstruction Meeting completed.
03/19/20 – Submittals processed.
03/31/20 – Kramer mobilized.
04/29/20 – Pencil copy of Pay Application No.1 returned for corrections.
05/04/20 – Kramer last day on site.
06/16/20 – Roof installation condition meeting completed.
06/25/20 – Roof needs final top coat installation and punch list completed.
07/20/20 – Punch list review meeting completed.
07/30/20 – Punch list work complete. THP processing closeout paperwork.
11/13/20 – Final project closeout manual submitted and sent County Engineer
11/18/20 – Final pay application approved and processed.

Burlington – Building Roof Replacement (F002) Read More »

Comm Center – Lower Level Quiet Room

05/29/19 – ThermalTech authors an SOSS for the project – pending SOSS approval and PO.
06/26/19 – Project Pending approval of SOSS and PO.
07/24/19 – Project pending approval of SOSS and PO.
08/27/19 – Project pending approval of SOSS and PO.
09/25/19 – Project pending approval of SOSS and PO.
10/30/19 – Project pending approval of SOSS and PO.
12/11/19 – Project pending approval of SOSS and PO.
01/28/20 – Project pending approval of SOSS and PO.
02/26/20 – Project pending approval of SOSS and PO.
03/26/20 – Project pending approval of SOSS and PO.
04/30/20 – Project pending approval of SOSS and PO.
05/27/20 – Project pending approval of SOSS and PO.
06/23/20 – Project pending approval of SOSS and PO.
06/25/20 – Latest discussion was to just archive this project as it is not needed at this time. OK to archive.

Comm Center – Lower Level Quiet Room Read More »

A&D – Access Control System Design

05/29/19 – Hamilton County requests SOSS for the project.
06/26/19 – TEI submits SOSS to facilities. Project pending SOSS approval and PO.
07/24/19 – TEI receives signed SOSS and PO for project. TEI, Facilities and JFS to conduct project kickoff meeting on 07/25/19 to begin project.
08/27/19 – ThermalTech emails Claude T to request 100% review meeting for a time on (or around) 09/11/19. After final review comments, project will be issued for bidding.
09/25/19 – ThermalTech, HCFD, and JFS meet to review 100% documents. HCFD send TEI federal procurement requirements. TEI adds to the project manual and submits to HCFD for review by prosecutors office. Project will be issued for bidding upon receipt of comments from the prosecutors.
10/30/19 – Project will be issued for bidding upon receipt of comments from the prosecutors.
12/11/19 – Project bids received, Glenwood Electric is apparent low bid on the project. TEI vetted bid and submitted recommendation that HamCo proceed with authoring the contract with Glenwood.
01/28/20 – Upon approval of contract and issuance of PO to Glenwood Electric, a pre-construction meeting will be scheduled and the project construction will commence.
02/26/20 – Glenwood’s PO and contract approved. Construction kickoff meeting scheduled for 02/27/20 at 1:00 PM.
03/26/20 – Construction kickoff pending the return of the background checks.
04/30/20 – Construction began – paused due to non-shipment of parts from MFGR. Glenwood clarifying scope and working to get actual ship dates.
05/27/20 – Construction underway. Control cabinets installed in basement through 7th floor on west end of the building. Controllers installed on 6,5, and 4 on the est end of the building. power supplies ordered and pending on time delivery, power supply install anticipated to start on or around June 1. Anticipated project completion is end of June.
06/23/20 – All controllers are installed. All power supplies have been installed and powered. Glenwood and Claude Toulsen are working to develop new badgeing standards (photos, logos, facility codes, etc). Upon completion of the badge standardization process, and all of the JFS data is updated to new standard, the database will be imported to the Kantech system and the system will then be migrated over to the new system.

07/29/20 – JFS is working with Glenwood to transition old database into the new database, and upon completions of the development of the new database, new system pretty much ready for rollout. The door on the southwest corner of the Parkhaus Garage is on the old system, and will not be functional after change over without adding to system. Glenwood provided pricing for changeover. HCFD, JFS, AMB and A&S to determine next steps.

08/21/20 – Glenwood waiting on Pictures from JFS to include in the software before they can transition over to Kantech system. Glenwood working to respond to punchlist information that the installation is not in compliance with the specification.

09/23/20 – JFS completes their preparation work with the new employee photo database. Discussion occurred when Glenwood stated there was no additional expandability in the new system. TEI provided documentation of the basis of design product had substantial expandability built into the system. Glenwood ordered additional cabinets to provide the expandability that was included in the specifications. Glenwood to begin installation of additional cabinets and the associated programming on 9/28. Estimating 2 additional weeks from then for completion of installation. Upon completion of installation, TEI will perform final Punchlist and process closeout documents.

10/27/20 – Glenwood is on site programming all cards and integrating the new database. Additional batteries are on site, however, additional power supplies were back-ordered, and are scheduled to ship 10/30/20. Will be installed upon receipt.

12/09/20 – Glenwood on site doing switchover to new system. All upper floors are on the new Kantech system, and the new doors in the basement and sub-basement are installed and on the new system. Exterior doors are scheduled to be switched over on 12/14/20, and building staff and Sheriff’s office has been notified and is planning for the switchover.

01/26/21 – TEI and Matt Butz performs punchlist for project. Upon completion of Punchlisted items and closeout, project will be complete.

02/23/21 – TEI and Rycca Thacker perform punchlist back-check. TEI requests final closeout documentation from Glenwood to close out the project.

03/24/21 – TEI receives and is reviewing the O&M manuals from Glenwood. Upon approval of O&M Manuals, TEI will deliver to HCFD. TEI and Glenwood working to provide all close out paperwork for the project.

A&D – Access Control System Design Read More »