Hamilton County Facilities

230 – East Exterior Lighting

PM = Rycca Thacker, Mike Barth

07/29/26 – HCFD requests SOSS. DEG submits SOSS.
08/26/26 – DEG sends fixture model number to HCFD to get trades to check pricing and lead times. DEG finalizing the plans for permitting and trades to install.
09/23/26 – DEG submits drawings to IBI for approval and permit.
10/28/26 – Permit and plan review approved. HCFD trades has approved plans and permit. Trades to complete the install. DEG will call for inspections once work is installed.

230 – East Exterior Lighting Read More »

111 – Arc Flash Model and Labeling

PM Rycca Thacker, Mike Barth

06/23/26 – DEG receives PO and signed SOSS. Arc Flash Study initiated.
07/29/26 – DEG has nearly the entire single line from the KZF project modeled in SKM software. Next step is to field verify make/model numbers and serial numbers. DEG to schedule with the building manager.
08/26/26 – Study in progress.
09/23/26 – Study progress continues.
10/28/26 – Study complete. Labels to be printed and be scheduled with building manager to apply.

111 – Arc Flash Model and Labeling Read More »

230 – Plumbing Upgrades

PM: Megan, Terry Cannon,
04/30/26 – Project opened on website. DEG started fieldwork and is working on bid CD documents. Need to check on SOSS approval.
05/27/26 – Need to request meeting with new building manager before proceeding. Meeting June 4 at 9am for design meeting with Jesse.
06/25/26 – First review set probably ready in July.
07/30/26 – Plumbing ready for review, electric will be ready soon then to County for Owner review.
08/26/26 – Review sets sent to County and limited comments received back. Floor plans updated. The project will be ready to bid soon.
09/15/26 – Prebid
09/18/26 – Addendum 1 issued.
09/22/26 – Addendum 2 issued.
09/24/26 – Bid due Friday.
09/25/26 – Bids received. Triton and QCM Mechanical submitted bids. DK and others did not bid the project.
10/22/26 – Facilities notified DEG that the bids are not awarded due to contract technicalities. TTC informed Triton in person.
10/27/26 – TTC & Rycca discussed how to rebid the job with a few small changes and make it suitable for award. DEG will update the bid documents adn send back out for a price refresh from the same vendors.

230 – Plumbing Upgrades Read More »

Comm Center – BE Assessment (F041)

PM: Rycca Thacker / Ian Zellner, John Millar
03/06/26 – HC requested an assessment SOSS.
03/13/26 – THP provided an SOSS for review.
04/09/26 – HC approved SOSS.
04/30/26 – THP working on Assessment. Roof testing/thermal scans 4-6 weeks out from April request. Testing contingent on weather conditions.
06/16/26 – THP completed field survey and roof scans.
08/05/26 – THP published the final report.
08/27/26 – Put into Archibus. THP has full restoration and partial, agreed to enter full cost and in notes put reduced scope.

Comm Center – BE Assessment (F041) Read More »

230 – 11th Flr Training Rm Acoustics

PM: Rycca, Eryn
04/30/26 – SOSS to be submitted shortly.
05/28/26 – SOSS submitted.
06/25/26 – Acoustic testing occurred 06/19. Consultant will provide design recommendations based on report.
07/30/26 – Report provided by testing consultant to HCFD. Elevar to research other panel providers and will provide report in layman’s terms.
08/27/26 – Report and design options provided. Consultant working on final design images based on actual photos of the space.
09/24/26 – Rendering photo and samples provided to COA.
10/29/26 -Costs provided to COA.

230 – 11th Flr Training Rm Acoustics Read More »

Crime Lab – Electrical Coordination Study

PM = Rycca Thacker, Mike Barth

04/29/26 – HCFD requests DEG to visit the site to discuss issues with exterior lighting circuitry. DEG to submit SOSS for partial electrical coordination study for affected circuits.
06/23/26 – DEG receives PO and signed SOSS. Electrical Study commences.
07/29/26 – DEG conducts site visit to document all existing breaker model and serial numbers to perform the analysis. Project Analysis being modeled in easy power program.
08/26/26 – Coordination study and report draft sent to HCFD for review.
09/23/26 – trades electricians to adjust settings. Project complete.
10/28/26 – Project complete. Can this be archived.
10/29/26 – TTC archived.

Crime Lab – Electrical Coordination Study Read More »

111 – Employee Break Shelter (No ITB)

PM: Rycca, Eryn
eeagle@elevar.com;

04/30/26 – SOSS provided for CA.
05/28/26 – Awarded to Tumlin and Elevar receiving initial Div 01 submittals.
06/25/26 – No update.
07/30/26 – Submittals complete and unit moved into production planning. Contractor will provide stamped drawings soon.
08/27/26 – Contractor will provide stamped drawings soon with Elevar to follow up. Anticipated unit installation in Oct.
09/24/26 – Contractor provided stamped drawings. Anticipated unit installation in early Oct. Elevar/HCFD/GC to meet onsite prior to installation.
10/29/26 – Unit installed. Need closeout docs from GC.

111 – Employee Break Shelter (No ITB) Read More »

800 – Tower AHU Replacements

PM: Matt, Terry, Elevar
03/26/26 – Original SOSS rejected, need XBE on this job. DEG got proposal from Elevar last week and resubmitted on 3/25. Robert approved but need LOI for Elevar. DEG to provide and resend SOSS.
04/29/26 – More fieldwork completed last week with Tom and we have selected which units will be replaced. DEG working with Habegger on new unit selections and putting background drawings together. We will have a kickoff meeting in May with Elevar on electrical work for these units.
05/27/26 – Unit selections are made, we will be ready to meet with Elevar for electrical kickoff first week of June. No real surprises with new units other than they are all converted VVT to VAV units now. ALC controls kickoff meeting discovered that they cannot reuse any of the JCI VFD drives on this project.
06/25/26 – HVAC design progressing, Electrical kickoff meeting held with Elevar, more fieldwork next week. Owner planned end of July.
07/30/26 – Met with owner on design scope. Design continues, Owner review set still planned for end of July. Working on coordination with Emcor and Elevar on scope for VFD’s and electrical needs.
08/26/26 – Another field trip and final design concepts updated for several AHU.  We have meeting with Facilities Thursday afternoon to discuss budget, final scope, and asbestos abatement.  Then we are ready to bid.
09/15/26 – Project Issued for Bid. Bid opening scheduled for 11/12/26.
10/26/26 – Addendums issued bid opens on 11/12/26. Addendum 1 issued. No additional questions have been received as of 10/26.

800 – Tower AHU Replacements Read More »

525 – HVAC Retrocommissioning (No ITB)

PM: Rycca, Terry
Closeout Contact: Will Fisher wfisher@davieseg.com


02/24/26 – SOSS submitted for CX work.
03/25/26 – No updates.
04/29/26 – SOSS received last week. Internal kickoff meeting yesterday. Client kickoff meeting scheduled for Friday.
05/13/26 – DEG on site for initial fieldwork and discovery meeting.
05/20/26 – Internal meeting with Emcor & Habegger for RTU retro commissioning at 525. Commissioning is set for 5/28/ and 5/29 with Will Fisher, Emcor and Habegger.
06/25/26 – Bison currently repairing RTU-4, Triton currently upgrading economizers for RTU-2,3. Once complete CX will continue. Graphics updated to match other buildings.
07/30/26 – Bison repaired their units. Parts delayed on Triton units until 8/5. After economizers are programmed CX continues.
08/26/26 – Final parts came in yesterday and Triton is scheduled on site 8/27 to install missing parts for these units, then final commissioning will begin.
09/23/26 – DEG and Emcor met earlier this month and finalized the commissioning for this building and set final report to HC. Outstanding item are the exhaust fans in the main warehouse which are owner items to troubleshoot and repair.
10/26/26 – All work is complete the retro-commissioning is complete, final report sent to the County.

525 – HVAC Retrocommissioning (No ITB) Read More »

Colerain – Animal Shelter – (F037)

PM: John Millar/Emily Phillips
01/30/26 – THP issued SOSS for review.
02/17/26 – Hamilton County approved the SOSS.
02/18/26 – THP completed preliminary field survey.
02/26/26 – THP working on repair documents.
03/25/26 – THP finalizing document review set for review with HC early April.
04/27/26 – THP published Owner review documents.
06/25/26 – THP working on Bid Documents.
08/26/26 – THP working on Bid Documents with included demo walkway.
09/22/26 – THP published DD documents.
09/24/26 – Project plans to publish bid documents 9/28/26.
10/13/26 – Prebid meeting occurred.
10/16/26 – Addendum No. 1 issued (prebid meeting minutes).
10/29/26 – Project update – Bids due 11/23/26.

Colerain – Animal Shelter – (F037) Read More »

Comm Center – Electrical Assessment

PM = Rycca Thacker, Mike Barth

02/25/26 – HCFD requests SOSS. DEG to prepare SOSS for submission.
03/25/26 – No updates. DEG to submit SOSS.
04/29/26 – Pending SOSS approval.
06/23/26 – Pending SOSS approval.
07/29/26 – Pending SOSS approval.
08/26/26 – Pending SOSS approval.
09/23/26 – Pending SOSS approval.
10/28/26 – DEG receives signed SOSS and PO. Assessment underway.

Comm Center – Electrical Assessment Read More »

Comm Center – Electrical Device ID and Arc Flash

PM = Megan, Mike Barth

02/25/26 – HCFD requests SOSS for project. DEG to Provide SOSS.
03/25/26 – No updates. DEG to finalize and submit the SOSS.
04/29/26 – Pending SOSS approval.
06/23/26 – Pending SOSS approval.
07/29/26 – Pending SOSS approval.
08/26/26 – Pending SOSS approval.
09/23/26 – Pending SOSS approval.
10/28/26 – HCFD asked for revised SOSS with Electrical Sub included in price. DEG to receive quote from Edge Electrical Contractor by 10/30/2026 and will then resubmit.

Comm Center – Electrical Device ID and Arc Flash Read More »

TPC 9th Floor JFS and CoC Renovation

County: PM Rycca Thacker – Champlin PM: Sam Hofmann

02/26/26 – SOSS received for JFS portion of work. Design team verified existing conditions. SD plans and estimate in progress.
03/26/26 – SD plans and estimate in progress.
04/30/26 – SD plans and Estimate to be submitted to County next week.
05/28/26 – SD plan and estimate submitted to county for JFS work. CoC work is put on hold until further notice.
06/25/26 – No Update.
07/30/26 – No Update.
08/28/26 – CoC approved. SD plan and estimate to be uploaded to Archibus.
09/24/26 – Re-kick off to be scheduled.
10/29/26 – No Update.

TPC 9th Floor JFS and CoC Renovation Read More »

JC – Kitchen and Laundry Water Heater Upgrade

PM: Matt Butz, Terry Cannon
02/12/26 – DEG kicking project off and setting up fieldwork.
02/25/26 – We’ve confirmed the new heaters are the high temperature laundry and kitchen PK heaters. The SOSS is submitted and DEG is beginning preliminary engineering.
03/25/26 – SOSS submitted, project setup.
04/29/26 – Initial fieldwork started, drawing setup underway. Pat Bemmes will be assisting with this project.
05/27/26 – Drawings are setup, equipment submittals and cost have been requested from vendors.
06/25/26 – Project put on hold. Send final DEG invoice.

JC – Kitchen and Laundry Water Heater Upgrade Read More »

SPHQ – AHU-3 Replacement

PM: Matt Butz, Terry Cannon
02/12/26 – Kickoff meeting being scheduled with HamCo.
02/25/26 – The SOSS has been submitted. Barrett meet Ian on site and review existing conditions. This unit is only five years old, do we really want to replace it.
03/25/26 – Waiting on SOSS and kickoff meeting to determine final scope.
04/26/26 – Internal meeting on project progress. We will scheduled next meeting with Ian after 525 RECX gets underway.
05/27/26 – On hold wafting on direction from County on how to proceed. AHU already replaced five years ago.
06/25/26 – Project put on hold, send final DEG invoice.

SPHQ – AHU-3 Replacement Read More »

230 – Lobby Security Upgrades

PM: Rycca Thacker, Eryn Thamann
02/26/26: Added as new project. Need meeting with COA/Probate/HCFD to review scope.
03/26/26: SOSS provided for concepts/SD phase.
04/30/26 – No update.
05/28/26 – Will wrap into elevator project. Elevar to provide new SOSS and will work on design options.
06/25/26 – SOSSs in process for approval with HCFD now.
07/30/26 – Concepts reviewed at initial meeting and working thru final concept now. Will review with HCFD prior to scheduling full group meeting. 230 Court Admins wanted this work to be completed faster than if combined into 230 Lobby Security project.
08/27/26 – A third option for the rear secure elevator area was discussed with Rycca and will be provided this week. Another meeting with the main group will then be scheduled. Exterior Lighting portion broken back out to separate project.
09/24/26 – A third option was provided to the entire group and another meeting was held. Another revision was sent to entire group for input and potential third meeting.
10/29/26 – Another mtg was just held and option 7 is under design.

230 – Lobby Security Upgrades Read More »

Colerain – Kitty City Electrical Upgrades

PM = Megan, Mike Barth

01/28/26 – HamCo request SOSS for Electrical Upgrades for Kitty City. DEG submits SOSS. DEG receives approved SOSS and PO on 01/28/26. DEG coordinating meeting with Duke.
02/25/26 – DEG meets with Duke to discuss power options. DEG proceeding with load calculations to send to Duke for service sizing.
03/25/26 – DEG develops drawings for electrical upgrades. Final field work scheduled for 03/31 at 7:30 AM to confirm final details.
04/29/26 – DEG submits 100% review drawings and OPCs to HCFD for comment/approval. Upon receipt of comments, ITB will be submitted.
05/27/26 – DEG meets with bldg mgr – adds a couple of alternates for additional outlets and also replace thru wall fans with new with humidistats.
06/23/26 – Drawings sent to HCFD for review.
07/29/26 – Upon receipt of HCFD review comments and/or approval, ITB package will be finalized and issued.
08/26/26 – Meeting scheduled for 08/28/26 with CARES to review and receive approval. Goal setting worksheet submitted (pending approval).
09/23/26 – Project issued for bidding. Prebid meeting occurred on 09/23. Bids are due on 11/12.
10/28/26 – Project in bidding phase. (1) addendum issued.

Colerain – Kitty City Electrical Upgrades Read More »

800 – HVAC Controls Upgrade (STS)

PM: Terry Cannon, Tony Matre
Closeout: Joe Bulach, joe_bulach@emcorgroup.com, Dayna O’Brien, dobrien@davieseg.com

 


08/19/25 – Kickoff discussion with Emcor.
11/18/25 – Emcor running low voltage at the building for new DDC network.
12/09/25 – Const Mtg and meeting minutes distributed.
01/08/26 – Const Mtg. Emcor making progress on equipment in the basement and on the first floor. They need help with access to some rooms that are under HCSO control.
01/20/26 – Const Mtg and new schedule released. Emcor gearing up for Chiller plant programming in March. Joe says they will take care of the 6th floor network cable. AM reports it is still not in the right place. The switches are in place and ready.
01/21/26 – Emcor shared missing submittals with DEG on VFD’s.
02/25/26 – Work continues as Emcor is planning on working on the chiller plant in March.
03/25/26 – Work continues, chiller plant programming in progress. Emcor ready to commission when building starts the chilled water plant for the season.
04/28/26 – Const progress meeting with Emcor held with DEG, Tom and Emcor. Small progress being made on new controls. Emcor asked to start boiler plant this week, it was decided to wait because of cold weekend temperatures. Tom had issues with chiller operation, Emcor found chiller in manual and released it. Emcor did some training with Tom to show him how to use new system but Graphics are not complete yet and the chiller plant is not fully programmed yet. Emcor to work on graphics, updated chiller programs and preparing for heating plant integration.
05/25/26 – Const Meeting held adn Emcor reported they started the boiler plant upgrades and they are making good progress. The communication infrastructure is in place for the future upgrades and the 800 Tower units can be added to it.
06/25/26 – Const meeting held last Tuesday, working out graphics updates and final controls work. Tom requested training.
07/30/26 – Project nearing completion, chiller sequences being updated.
08/26/26 – Project is complete and in commissioning. PCHWP-2 has an issues that DEG will be on site troubleshooting on Thursday.
09/23/26 – DEG met onsite to review chiller operations. DEG recommends to follow DK recommendation to replace thermal overloads on PCHWP-2. Tony said that Craig could perhaps replace these since they are less than $100. That is our recommendation as well. DEG updating the PID to new conditions after replacement of CH-2.

800 – HVAC Controls Upgrade (STS) Read More »

111 – Antenna Power Upgrade

PM: Rycca, Barth
12/05/25 – Met onsite to gather SOSS data for this project. DEG to submit SOSS for this work.
01/28/26 – DEG receives SOSS and PO. Working to schedule a progress meeting with RT availability.
02/25/26 – DEG submits to the City of Springdale for permit for work. Install pending permit approval.
03/25/26 – DEG receives permits from Springdale. HCFD schedules install with MobilComm.
04/29/26 – Work complete. Closeout?

111 – Antenna Power Upgrade Read More »

Winton – New Animal Shelter Building

PM: Rycca Thacker, Mike Murphy, Terry Cannon
12/11/25 – Land purchase is complete. The new building should be online by September 2029-ish.
02/26/26 – SOSS and PO received. Site investigation has begun. Kickoff to be scheduled sometime in March.
03/26/26 – Kick-off held with County, Cares and design partners. Geotech will begin investigation shortly. SPoA to send out programming survey shortly.
04/30/26 – Geotech beginning their scope. Needs assessment confirmation meeting on the calendar for 6/3.
05/28/26 – Data collection teams meeting held on 5/12. CARES needs to confirm some operational questions to prepare for the needs assessment on 6/3.
06/25/26 – Programming verification meetings complete. CARES will review and compare data to existing concept plan.
07/30/26 – SPoA to provide final program report.
08/28/26 – Programming report provided to CARES for review. Add services for Geotech approved. Additional testing scheduled for first week of september.
09/24/26 – Additional clearing needed for geotech. Approval pushed new borings until October. Program verification meeting held and concept plans incoming.
10/29/26 – Concept plan presented. CARES provided comments. SD plan in progress.

Winton – New Animal Shelter Building Read More »

All Buildings – Space Allocation Drawings

PM: Rycca Thacker, Eryn Thamann
12/11/25 – SOSS requested for space allocation drawing updates. Awaiting final building priority list from HCFD to finalize SOSS.
01/29/26 – Elevar working on SOSS.
02/26/26 – Elevar provided SOSSs.
03/26/26 – SOSSs approval pending.
04/30/26 – SOSS approved for three buildings. Need schedule from HCFD for access hours, building priority, and deadlines.
05/28/26 – Waiting for Elevar badging to be finalized.
06/25/26 – Started scanning of 1701 06/22 and will last the week. Drawings will be updated as scans come back and starting with JFS areas for leasing diagrams.
07/30/26 – Working thru 1701 set and met with HC IT Dept to review on 07/23. Scanning complete for 111 Tri-Co. Scanning scheduled at TPC for 08/10-08/14.
08/27/26 – Provided 1701 CAD and pdf files. Just received pdfs files of the parking garage and will bgin on those soon. Scanning completed at TPC and 111 Tri-Co. As staff area vailable, these drawings will be checked against scans.
09/24/26 – CAD files received of 1701 parking garage from Champlin to complete that portion of work. Files for 111 are almost complete and sent to HCFD for indications of tenant spaces. Templates for 138 are complete.
10/29/26 – Working thru TPC now.

All Buildings – Space Allocation Drawings Read More »

CH – B95 Office Suite Renovations

PM: Megan, Sam
10/30/25 – This project went out to bid this week. Sam will send out invites for prebid and bid opening.
12/11/25 – Triton is low bidder. Project in contract phase.
12/12/25 – Furniture and two drawer cabinets can be located close to the hot water radiators, they just have to be moved if we ever need to service the units.
01/28/26 – Contract goes in front of the board today. Bulletin #1 will go out next week with the changes requested from Rycca.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No update.
04/30/26 – Submittals are coming in. Project mobilization to be scheduled by County.
05/28/26 – Project tentative start on 8/10/26.
06/25/26 – No update.
07/30/26 – Submittals are being returned. Project start has adjusted to 8/31.
07/30/26 – RT said we may get new direction on final design for this space. We may need another Bulletin for this project.
08/28/26 – Mobilization on hold until scope changes are settled.
09/24/26 – Scope changes received. Bulletin is being prepared.
10/29/26 – Bulletin will be issued to Triton upon approval

CH – B95 Office Suite Renovations Read More »

Dane – Security System and Exterior Lighting

PM: Matt Butz, Mike Barth
10/30/25 – Project was sent out for bid, DK sent in questions with options. Security lighting prebid also held.
12/10/25 – Project small projects bids received. Glenwood awarded the bid. Contract in finalization phase. Submittals and construction to commence once the contracts are approved.
01/28/26 – Project contracts and PO sent to subs. Meeting dates for KO meeting requested from contractor.
02/25/26 – DEG and HCFD meet with Glenwood on exterior lighting. Installation of drawings pending light fixture procurement (approx mid March).
03/25/26 – Exterior lighting installed. Play yard lighting levels requested to be increased. DEG performs lighting study to increase the lighting levels. DEG sends to HCFD.
04/29/26 – Play yard lights installed last week. All exterior lighting complete. Security cameras work to commence upon the completion of Central Campus work.
05/27/26 – Play yard lights permitted and inspected (final inspection passed). Cameras are kicking off beginning of June.
06/23/26 – DK has mobilized to the project site to install the cameras. installation is underway. Weekly project meetings scheduled.
07/29/26 – Installation underawy. Most of access control installed. Cameras are being installed and cabling installed with the GSA vendor.
08/26/26 – Installation will be finalized when ISWP installed at the location.
09/23/26 – ISWP installed by technical services. Installation finalization and connections scheduled with DK.
10/28/26 – Installation of cameras nearing completion.

Dane – Security System and Exterior Lighting Read More »

All Buildings – Emergency Switchgear PM

PM: Rycca Thacker, Mike Barth
10/30/25 – The project is out for bid, prebid is scheduled for November.
12/10/25 – Bid opening occurred. Zero bids received.
01/28/26 – HamCo asks DEG to re-package and resend out to bid.
02/25/26 – No updates this month. DEG will compile all data and send list of buildings that information is still pending.
06/23/26 – DEG contacts all building managers to confirm that there have been no modifications to the critical load lists for each building. A review set will be sent to HCFD end of June.
07/29/26 – DEG has not received responses from buildings.
08/26/26 – ITB pending the advertised estimate from HCFD and then goal setting worksheet approval.
09/23/26 – Project in bidding phase. Prebid meeting was held on 09/22. Bids are due 11/12/26.
10/28/26 – Project in bidding phase. (2) Addendums Issued.

All Buildings – Emergency Switchgear PM Read More »

TPC – Mechanical Room Door Replacement

PM: Jesse Estes, Sam Hofmann

08/28/25 – Field visit to confirm scope.
09/25/25 – Review set submitted to county. Project will be going out to bid next week.
10/30/25 – Project in Bid phase. Bids open 12/1.
12/11/25 – Triton is low bidder. Project is in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No update.
04/30/26 – Submittals are coming in. County to schedule mobilization.
05/28/26 – Tentative start date of 7/6/2026.
06/25/26 – No Update.
07/30/26 – Tentative start has been pushed back to 9/8.
08/28/26 – No update
09/24/26 – Project has not started yet.
10/29/26 – 16 doors and frames have started. Project ongoing.

TPC – Mechanical Room Door Replacement Read More »

RSC – Regional Safety Complex Phase 2

PM: Rycca, Murphy, Toombs
09/25/25 – Design schedule has been updated such that final CD documents to be completed and bid in November 2025. Design documents are about 60% complete at this time.
10/29/25 – 90% Drawings, specifications, and cost estimates sent to Owner this week.
12/12/25 – Phase 2 drawings are in for owner comments. Bert said that he would get those back later this week. We are shooting for bidding first of January.
01/25/26 – MEP drawings and specification sent to Champlin Issued for Bid. They are stamped and signed. The targeted bid date is 02/02/26, Champlin reviewing all final documents in the set now. DEG is trying to onboard an AV and IT specialist for this job. We have not received his PO yet, Bright Technologies.
1/28/26 – THP submitted Bid & Permit set 1/21/26. will go out 2/3. Construction is expected to start in April.
02/26/26 – Budget has been approved and sent to Robert Bell for approval. Waiting on Cincy approvals to go out to bid. We are shooting for mid March issuance.
03/26/26 – Project is out to bid. Pre-bid scheduled for 4/2.
04/30/26 – Bid opening pushed back to 5/21. Sniper tower scope was pulled out as an alternate.
05/28/26 – Graybach was apparent low bidder. Bid vet to be scheduled in near future.
07/30/26 – A305’s requested from bidders. Waiting on direction from County. Not sure we have received them yet.
08/28/26 – Graybach awarded the project.
09/22/26 – THP – CA on going, reviewing RFI’s/Submittals.
10/29/26 – Permits submitted and almost ready. Dave commented that general waiting on fire inspector. Driveway permit is expiring next month. Plumbing submittals received and returned. Mechanical submittals received and returned.

RSC – Regional Safety Complex Phase 2 Read More »

JC – Cell Door and Frame Replacement (Phase 5)

PM: Matt Butz, Sam Hofmann

08/28/25 – Sheriffs provided scope of doors to be included in phase 5. Review set will be complete shortly.
09/25/25 – Review documents provided to county. Project will go out to bid on monday.
10/30/25 – Alpha is apparent low bidder. Bid vet occured 10/29. Alpha subbing out majority of the work to Cornerstone.
12/11/25 – Cornerstone is awarded the bid after contradictions in Alphas LOIs and Bid Vet statements came to light. Project in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract signed. Kick off to be scheduled in near future.
03/26/26 – Cornerstone has taken field measurements. Submittals incoming.
04/30/26 – No update.
05/28/26 – Submittal received and returned. Schedule needs to be determined by Sheriffs.
06/25/26 – No update. Tentative fall start.
07/30/26 – Delivery scheduled for end of August.
08/28/26 – Mobilization in 2 weeks.
09/24/26 – two phases complete. Work ongoing.
10/29/26 – Project ongoing.

JC – Cell Door and Frame Replacement (Phase 5) Read More »

JC – Polished Concrete – Phase 2

PM: Jesse Estes, Sam Hofmann

09/25/25 – Project kickoff held and scope determined. Review documents will be ready for County next week.
10/30/25 – Project in bid phase. Bids open 12/1.
12/11/25 – Triton is low bidder. Project in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – Bulletin #1 issued to include emergency L31 scope. Triton to provide schedule to begin work asap.
04/30/26 – Submittals approved. Triton to provide schedule.
05/28/26 – Triton mobilized 5/26. Epoxy demo ongoing.
06/25/26 – Half of South 3rd floor pods are complete. 5th floor Hall is next.
07/30/26 – First phase grinding and polishing is complete. Furniture will be installed next week.
08/28/26 – Furniture install ongoing. Backpunch scheduled for next wednesday.
09/24/26 – Phase 2 in progress.
10/29/26 – 2 pods complete in phase 2. Work ongoing.

JC – Polished Concrete – Phase 2 Read More »

CH – Stone Stair Assessment (F033)

PM: Rycca Thacker, John Millar
09/03/25 – County asked THP to review stair condition at Courthouse stairs.
10/03/25 – THP submitted SOSS.
10/17/25 – County approved SOSS.
12/11/25 – THP plans to walk the steps next Monday and provide a report by 12/15/2025.
01/28/26 – THP is currently reviewing existing conditions and discussing internally.
02/17/26 – THP issued a draft report.
02/23/26 – THP issued final report.
02/25/26 – THP updated Archibus project request.
03/26/26 – OK to Archive.

CH – Stone Stair Assessment (F033) Read More »

Crime Lab – Leak Investigation (F032)

PM: Rycca Thacker, John Millar
08/28/25 – County asked THP to review water infiltration at the coroner building.
09/05/25 – THP completed an initial site visit to investigate the conditions.
02/25/26 – THP had follow meetings and discussion with HC. THP published an email with summary of potential leak areas and an opinion /of probable costs.
04/03/26 – Based on THP recommendations, County directed THP to complete water tests of the suspect areas.
04/09/26 – THP and HC staff completed water testing at the louvers and screen wall. Testing found multiple leaks in the screen wall.
06/25/26 – Project Archived.

Crime Lab – Leak Investigation (F032) Read More »

800 – Fire Pump Replacement

PM: Matt, Terry Cannon
Engineers: Coty Groeschen, Wesley O’Hara
08/27/25 – Prebid held today, bids are due in September. Owner furnished equipment includes fire pump, jockey pump, low suction controller and fire pump controller.
08/28/25 – Issued for Bid 8/13 and bids open 9/24.
09/24/25 – Bid Opening today at 11AM.
10/03/25 – Post bid meeting held with Alpha and they are recommended for the project. Base bid no alternates accepted.
12/12/25 – Jesse reported contracts close to being sent to contractor for signature.
01/25/26 – Contract should have went to BOCC on Jan 19, no updates. Sending Permit Drawings Tuesday 2/3. Electrical RFI received and in the process of being answered.
02/12/26 – DEG starting pre-construction work with Alpha and subs.
02/25/26 – Contracts are back. DEG coordinating with Duke and IBI on power installation requirements for the MI cable. Alpha EC vendor being weird about MI cable requirements and cost.
03/25/26 – Alpha arranging EC vendor for this job. DEG working on necessary CFD details before work begins.
04/22/26 – FDC testing complete and 800 passes inspection. DEG checking with Alpha on starting this project and getting permits to begin. A project schedule should be ready to share with the owner in a couple of weeks.
05/27/26 – SOV was approved today. We are ready to set up the Pre-Const meeting. DEG sent mechanical drawings for permitting to Alpha last week adn IBI drawings are already in for permitting.
06/25/26 – Kickoff meeting held with contractors. IBI permit approved, City permit under review. Electric change order under review. Schedule, SOV, Site safety documents received and under review.
07/30/26 – Had meeting with vendors on electric change order. Third meeting scheduled today at 1PM. Prices are coming down but not going away. Met with CFD and received their thoughts on allowing the high rise fire pump to provide temporary service for both low and hi rise, they are amendable provided we provide a letter stating it will work. Griffith sent us that letter.
08/26/26 – CO-1 sent and signed by DEG and Alpha, returned to County for approval. Planning on scheduled work to begin in October after Duke power is stable.
09/23/26 – 9/26 shutdown pushed back to Veterans Day. Alpha agreed to January 2027 startup without the project incurring any additional cost.
10/26/26 – JTL requested site visit to start working on the electrical portion of the job. DEG informed them to coordinate with Facilities on access adn that we wanted to be cc’ed on all visits so we can stop in and check progress.

800 – Fire Pump Replacement Read More »

CH – Parking Lot Repair (F029)

PM: Matt Butz, Paul Bellman
06/03/25 – County, Kleingers and THP had a meeting to discuss scope of asphalt repair work.
07/24/25 – County and THP met to discuss project phasing.
07/30/25 – THP published preliminary opinion of probable cost for the project.
08/08/25 – THP published SOSS.
08/18/25 – County had kick off meeting with Tumlin, Champlin, THP, and Kleingers.
08/20/25 – County approved SOSS.
08/28/25 – Kleingers scheduled to survey the parking lot.
09/08/25 – Kleingers survey received
09/22/25 – Kleingers, THP, HC reviewed Courtyard lot for RFI #03 regarding overlay vs milling.
11/05/25 – THP, HC, and Tumlin reviewed milling conditions and full depth repair options.
11/14/25 – Kleingers provided updated striping plan.
11/18/25 – THP reviewed new asphalt in courtyard during heavy rain. Puddling and improper slope was observed on east portion of lot.
01/28/26 – No updates – weather pending.
02/26/26 – No updates – weather pending.
03/24/26 – No updates – Status of ponding in Courtyard area?
04/30/26 – THP to review on site conditions.
05/28/26 – No updates. Work in adjacent areas ongoing.
06/25/26 – Sink hole and active line was discovered in Courtyard lot. THP, Davies, and HC discussed scoping, filling void, and providing cleanout per supplied detail. Tumlin to get CO cost to repair.
07/30/26 – No updates from THP. Have not heard from Tumlin on the CO costs to repair sink hole in Courtyard Lot.
09/23/26 – No updates.
10/29/26 – No updates. Punchlist coming and cleanout addressed soon.

CH – Parking Lot Repair (F029) Read More »

Alms & Doepke – City Knock Down (F028)

PM: Rycca Thacker, John Millar
05/06/25 – County approved SOSS.
05/23/25 – County and THP had a kick off meeting.
08/28/25 – THP anticipates sending bid documents to contractors on 8/29/25.
09/02/25 – THP issued bid documents to American Façade Restoration, Buckeye Concrete Restoration, Hardig Industrial Services, and ZSR Contracting and Restoration. Kestner was unresponsive.
09/09/25 – Site prebid meeting occurred.
09/17/25 – Bids were received from three contractors. American Façade Restoration was the low bidder.
09/19/25 – THP reviewed the proposal with American Façade Restoration.
09/22/25 – THP published the a recommendation for American Façade Restoration to complete the work for the County to review.
09/24/25 – County requested additional bidders from the Bold list be invited to bid the project.
09/25/25 – THP sent three additional requests out to BSBE and MBE firms.
10/03/25 – THP received one proposal from LRT that was $15,000 over the low bidder.
10/15/25 – County issued a PO for AFR to complete the work.
10/29/25 – AFR is working through background checks. AFR is proposing to complete the work 11/10 to 11/14. Work is weather dependent and second shift.
12/11/25- THP has completed the survey at the building and is working on providing a City report regarding the observation by next week.
01/18/26 – The report has been approved by HC and THP submitted the report to the city.
04/30/26 – OK to archive this project.

Alms & Doepke – City Knock Down (F028) Read More »

2026 Project Cost Estimates

PM: Rycca, Mike, Sam, Eryn, Terry, Mike, John

07/31/25 – We discussed the quantity of 2026 projects coming our way and we think about 20 project are new. The County will self-inflate the refresh cost estimates. Rycca will print and share the original list with us soon.
08/20/25 – ThermalTech received approved SOSS received from County.
08/28/25 – TTE Internal kickoff start, completion matrix created, Champlin assignments accepted and the TEI MBE partner engaged for work this year. Elevar SOSS submitted to HC 08/27.
09/24/25 – ThermalTech DEG working on estimates, most are done. Fieldwork in JC scheduled for this week. Gazelle will start uploading to Archibus this week.
09/25/25 – Elevar estimates ongoing and meetings with tenants scheduled.
10/30/25 – Elevar complete with estimates. ThermalTech complete with estimates.
12/11/25 – Complete. Davies partner creating binder PDF of each estimate before module is closed.

2026 Project Cost Estimates Read More »

230 – Summer Boiler Replacement

PM: Tony Matre, Terry Cannon
07/31/25 – SOSS approved. ThermalTech is conducting fieldwork to see if we can fit a boiler into the elevator and down to the in a size matching the KN boiler 2000 MBH. We did confirm that the boilers intended to be used on the Ameresco will not fit into the elevator, but they are 2500 MBH.
08/20/25- Final review drawings ready to review. TTC will send to County for review.
08/25/25 – Boiler selection is waffling, not sure where guys are going to fit a boiler in the elevator and down to the basement. We decided to have a base bid boiler and an Alternate boiler that matched future boilers.
09/24/25 – Review will be sent to Tony Matre for his review today.
10/29/25 – TTC preliminarily setup prebid meeting but did not get confirmation from bidders except one bidder (Triton) who showed up. TTC to reschedule.
11/14/25 – Prebid meeting with four vendors.
11/26/25 – Bids received, tabulated and sent to County. All bids were overbudget.
12/12/25 – TTC repackaged drawings and sent to DK for State Term pricing.
01/25/26 – County deciding if they want to award this project via State Term to Emcor and Debra Kuempel.  It does sound like it is going that way.
02/25/26 – No update on moving forward on this project yet.
03/25/26 – No update, still awaiting green light from County to move forward with state term work.
04/26/26 – DEG and Ameresco working on new boiler plant, this project can be archived.

230 – Summer Boiler Replacement Read More »

TPC – BOCC Security Upgrades

PM: Matt Butz, Eryn Thamann, Mike Barth
06/26/25 – Fee estimates from Elevar/DEG were provided based on the Sheriff’s risk assessment document. ROM construction estimates were also provided.
07/31/25 – No update. The County commented that all has been submitted, waiting on comments.
08/28/25 – No update.
09/25/25 – No update.
12/11/25 – No update.
01/29/26 – No update.
02/26/26 – No update.
03/26/26 – No update.
04/30/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – No update.
10/29/26 – Submitted SOSS for egress study.

TPC – BOCC Security Upgrades Read More »

TPC – 7th Floor New Sink

PM: Megan, Terry Cannon
05/14/25 – Field trip to site with Rycca.
07/28/25 – Owner review set sent to County.
08/20/25 – Option 1 & 2 sent to owner for review with cost estimates.
08/28/25 – We received prices for SS pans and will update the cost estimate and send back with updates today.
09/24/25 – Project is also on 2026 Project Cost Estimates, we will use same numbers for the estimate.
10/29/25 – Project is updated in Archibus 26-ADM-0138-2485.
12/12/25 – TTC needs to revisit site with Rycca for new scope.
01/25/26 – Ryan and Sam to meeting with Rycca for kickoff meeting – waiting to here back about when this will be. We do need to draft an SOSS for this work and bid it out Small Project.
02/25/26 – Waiting to send SOSS, latest news was that this may be included in a bigger floor renovation?
03/25/26 – Questions out about final scope and expanded floor plan. Revised SOSS not submitted yet.
04/29/26 – Scope questions answered, DEG owes Champlin revised SOSS for final floor plan.
05/27/26 – Project On hold.
06/25/26 – Project on hold.

TPC – 7th Floor New Sink Read More »

TPC – 3rd Floor Auditor Breakroom

PM: Megan, Sam Hofmann, Terry Cannon
05/29/25 – Added as new project.
06/25/25 – Checking dates for meeting.
07/24/25 – Design meeting conducted on site.
08/26/25 – Design continues, updated floor plans received from Champlin today.
09/24/25 – Prices and owner review documents submitted to Champlin. County to review budget and scope to determine if they have enough money to bid as is.
10/30/25 – Scope and Budget confirmed. Project will be issued for bid today.
12/11/25 – Triton is low bidder. Project is in contract phase.
01/28/26 – Contract goes in front of the board today.
02/26/26 – Contract is signed. Triton is to pace projects out to place priority on Bondhill. Submittals and pre-mob items can begin.
03/26/26 – No Update.
04/30/26 – Submittals are in process. County to schedule mobilization.
05/28/26 – Triton mobilized on 5/6. Construction and Bi-weekly meetings ongoing.
06/25/26 – Demo complete. Framing complete. Roughin inspections ongoing.
07/30/26 – Construction ongoing.
08/28/26 – Project nearing completion. Punch scheduled for next week.
09/24/26 – Punch walkthrough completed. Closeouts in progress.
10/29/26 – Backpunch complete. Closeouts received and being reviewed

TPC – 3rd Floor Auditor Breakroom Read More »

All Buildings – Fire Damper Testing & Inspection

PM: Tony Matre, Terry Cannon
05/22/25 – Tony Matre asked for an SOSS to rebid this project in 2025.
06/25/25 – SOSS submitted.
07/30/25 – SOSS approved this month. Internal meeting conducted for kickoff to collect as-builts and setup new drawings.
08/28/25 – Drawings are nearing review status. Coty and Luke made good progress, but we have a lot of as-built items to incorporate from the last bid.
09/24/25 – We are updating the drawings for the new buildings including 525, EMA, and Mercy. Drawings should be ready for review in a couple of weeks for the whole bid package.
09/25/25 – 525 does not have any fire rated walls. CHA answered Coty about Dane.
10/30/25 – Still putting new buildings together.
12/12/25 – Original building drawings updated. New building drawings added, ready for TTC review. We noticed that several fire dampers missed in the Justice Center because of the spline ceiling are open and accessible. TTC worked with NKYHC to get a quote to update the fire dampers in the JC lobby now before the new ceilings go back in. NKYHC working with Triton to use their lift.
01/25/26 – Review sets sent to Tony Matre for distribution and review. After comments are received, we will setup the bid schedule for this project.
02/25/26 – No comments received yet, ttc checked in a couple of times.
03/25/26 – We are waiting on green light from Tony before bidding. Review sets are in for comments.
04/26/26 – Project on hold awaiting green light from Tony.
05/27/26 – DEG needs to add to buildings to the the bid and then we will start putting together the ITB.
06/25/26 – Finalized scope for new buildings, updated and found missing data from previous bid and addendums, final items being added to scope for bid package.
07/30/26 – Talked to Tony and we are removing 1701 and 111 from scope. We don’t have to wait for any additional comments from Facilities, TTC can package this up for bidding.
08/26/26 – Coty reviewed drawings this month and made changes but said he needs to clean up some items from the Coop work and he will get that done this month for my final review.
09/23/26 – Review project with Tony, putting 2026 budget together for Tony, but he also said to get the job out for bidding in October 2027.
10/26/26 – TTC will review drawings before Partner meeting.

All Buildings – Fire Damper Testing & Inspection Read More »

230 – Multipurpose Room Renovation, Prosecutor’s Office

PM: John Nester, Eryn Thamann
05/28/25 – Initial scope meeting held and Elevar to provide SOSS with TEI.
06/26/25 – Need SOSS from DEG for final submission to HCFD.
07/31/25 – Pending SOSS approval. May be combined, hold for now.
08/28/25 – On hold as it may be combined with Mother’s Room project and moved to first floor VA area.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Combined with Mother’s Room. Part of 2026 new project requests and uploaded to Archibus.
12/11/25 – Proposal requested for this as combined with Mother’s Room.
01/29/26 – Need meeting with COA/Probate/HCFD to review scope.

230 – Multipurpose Room Renovation, Prosecutor’s Office Read More »

230 – Mother’s Room Addition, Prosecutor’s Office

PM: John Nester, Eryn Thamann
05/28/25 – Initial scope meeting held and Elevar to provide SOSS with TEI.
06/26/25 – Need SOSS from DEG for final submission to HCFD.
07/31/25 – Pending SOSS approval. May be combined, hold for now.
08/28/25 – On hold as it may be combined with Mother’s Room project and moved to first floor VA area.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Combined with Training Room. Part of 2026 new project requests and uploaded to Archibus.
12/11/25 – Proposal requested for this as combined with MultiPurpose/Training Room.

230 – Mother’s Room Addition, Prosecutor’s Office Read More »

SPHQ – Fall Protection Upgrade (F026)

PM: Matt Butz, Paul Bellman

04/01/25 – County requested SOSS for Fall Protection upgrade to the existing roof.
04/24/25 – THP to publish SOSS for review.
05/21/25 – SOSS approved.
06/25/25 – THP requesting roofing plans to start layout.
07/30/25 – THP working on DD drawings and plan to send draft to HC late next week.
08/27/25 – THP finalizing DD drawings and plan to send to HC at the end of the week.
09/24/25 – THP working towards CD drawings. Need to schedule a review meeting with HC.
10/15/25 – Documents issued for bid on 10/15/25.
10/29/25 – Pre-bid meeting held 10/27/25.
11/19/25 – THP issued summary letter to HC recommending NR Lee Restoration.
12/11/25 – HC finalizing paperwork for Contract approval.
01/14/26 – HC issued fully approved Contract to HR Lee Restoration.
01/27/26 – Preconstruction Meeting held virtual.
01/28/26 – THP issued Preconstruction Meeting Minutes.
02/19/26 – Preconstruction Meeting held On-site.
02/20/26 – THP issued Preconstruction Meeting Minutes.
03/25/26 – HR Lee is scheduled to deliver telehandler forklift 3/26 or 3/27 and material on 3/31. Work scheduled to begin shortly after.
04/08/26 – THP and HC reviewed on site substantial completion by HR Lee.
04/20/26 – HR Lee submitted Change Order for requested additional railing at small roof. THP to review with HC.
05/26/26 – HC issued signed and approved CO for additional railing. HR Lee placed order and updated schedule requested. Closeout documents in progress.
06/25/26 – THP is scheduling a final walk-thru with all parties. Closeout documents in process.
07/14/26 – On site final walk.
08/21/26 – THP sent CO #2 for requested safety line and final punch items to HR Lee for signature. Signed CO#2 returned to HC.
09/22/26 – On site review of final punch list items. HR Lee to schedule remaining work by next week.
10/08/26 – HR Lee completed final punch list items and THP and HC reviewed and approved.
10/15/26 – HR Lee submitted final closeout docs.
10/29/26 – HR Lee submitted paint touch up procedures from manufacturer for warranty work and would like to schedule paint touch up of bases.

SPHQ – Fall Protection Upgrade (F026) Read More »

SPHQ – Parking Lot Repave (F025)

PM: John Nester, Paul Bellman

04/01/25 – County requested SOSS to repaving of the Patrol HQ Parking Lot.
04/02/25 – THP completed a preliminary walk of the site.
04/18/25 – THP coordinated consultant proposals from Kleingers and Terracon.
04/24/25 – THP to publish SOSS for review.
05/07/25 – SOSS approved.
05/19/25 – Design kick off meeting complete.
05/29/25 – Civil survey and underground detective work complete.
06/25/25 – Terracon scheduled for underground exploration. THP coordinating with HC.
07/16/25 – Terracon completed borings and sent Draft report.
08/15/25 – Terracon sent final boring report.
08/28/25 – Meeting scheduled with THP, Kleingers, and Terracon to review boring report to finalize plans. Told Rycca THP can have this out late September.
10/15/25 – Documents issued for bid on 10/15/25.
10/29/25 – Pre-bid meeting held 10/27/25.
12/11/25 – Project on hold till further notice.

SPHQ – Parking Lot Repave (F025) Read More »

230 – Exterior Signage Feasibility Study

PM: John Nester, Eryn Thamann
03/26/25 – SOSS provided and pending approved PO.
04/24/25 – PO provided. HCFD to schedule kick-off mtg.
05/28/25 – Design kick-off meeting held with the Court/Court Admin/HCFD. Elevar to provide timeline for first round of design.
06/26/25 – Elevar to provide zoning code info to HCFD and not signage design options yet.
07/31/05 – Draft code study sent to HCFD for review.
08/28/25 – Renderings provided to HC on 08/25.
09/25/25 – Elevar needs final design and digital seals to proceed with Small Projects bid.
10/30/25 – Part of 2026 new project requests and uploaded to Archibus.
12/11/25 – No update.
01/29/26 – Archive?

230 – Exterior Signage Feasibility Study Read More »

Record Center – Animal Shelter Renovation

PM: John Nester, Sam Hofmann, Terry Cannon

02/27/25 – SOSS returned. Kickoff to be scheduled in near future.
03/25/25 – Preliminary HVAC and plumbing calculations started.
03/27/25 – Kick off meeting held. SD in progress.
04/24/25 – Follow up programing meeting held. SPoA is working on plans to be provided in next couple of weeks.
05/29/25 – Programming meetings in progress.
06/26/25 – Programming meetings still in progress. Finalizing schematic plan with SPoA.
07/24/25 – TTE sent SD cost for MEP work to Champlin for use on this project.
07/31/25 – Schematic design plan finalized. Site and DD developing.
08/28/25 – Last schematic meeting to be scheduled. County needs revised estimate for next steps. Keep Rycca looped in. TTE cost up near $2M so far.
09/25/25 – Estimate provided to county based on finalized SD Plans. County to determine feasibility of moving forward.
10/30/25 – Final schematic design meeting held to determine next steps with 7-9 million dollar budget gap. County to discuss with Cares to determine the minimum amount of renovation they need to use record center.
12/11/25 – Murphy met with Caroline to discuss scope and possible reductions. County to provide direction on funding of the project. No movement until budget is set.
01/28/26 – No Update.
02/26/26 – No Update.
03/26/26 – No Update.
04/30/26 – No Update. OK to Archive.

Record Center – Animal Shelter Renovation Read More »

TPC – NFPA Fire Door Upgrades

PM: Sam Hofmann, Jesse Estes

02/27/25 – SOSS returned. Kick off to be scheduled in near future.
03/27/25 – Drawings have been started. Kick off to be scheduled.
04/24/25 – Drawings in progress. To coordinate with Elevar on format.
05/29/25 – No update.
06/26/25 – Field visit to walk through all buildings to be scheduled.
07/31/25 – Field visit complete. Drawings to be finalized.
08/28/25 – Final review meeting to be scheduled.
09/25/25 – Door Hardware Consultant to visit doors on site to provide feedback and cost.
10/30/25 – Assa Abloy is working on specs and estimate.
12/11/25 – Assa abloy is finalizing scope.
01/28/26 – Finalizing cost estimate and base bid scope
02/26/26 – Completing bid set and project manual.
03/26/26 – No Update.
04/30/26 – No Update.
08/28/26 – County is cleaning paint off labels and will report back which locations will still need to be replaced.
09/24/26 – Confirmation required on labels able to be cleaned.

TPC – NFPA Fire Door Upgrades Read More »

800 – Façade Repair SD (F022)

PM: John Nester, John Millar
01/02/2 – Champlin reached out to THP to provide SD services for the new Animal Shelter.
02/25/25 – THP provided an SOSS for SD Services.
03/26/25 – Elevar pending approved PO. Truescan started scanning the building from the interior.
04/23/25 – Design team had internal kick off meeting. Project update – Scanning complete and THP working on base Revit model for the project.
05/28/25 – Elevar has site walk scheduled for 05/30 to review windows. THP completed initial surveys and plans to rappel 5/29 and 5/30.
06/26/25 – Elevar investigating window replacement vs restoration and window cleaning products.
07/31/25 – Window drawings are progressing and a set will be provided to THP for inclusion in the next checkset to HCFD.
06/30/25 – THP completed aerial platform surveys of the lower section of the building and interior surveys of the façade 6/30 to 7/3.
07/17/25 – Stone stabilization proposals received and AFR is the low bidder.
07/22/25 – THP sent 800 Broadway review set to County. Set included windows and fall protection.
07/30/25 – AFR installing supplemental anchors on north elevations. Anticipate being complete by 7/31/25.
07/30/25 – AFR completed installation of supplemental anchors and THP confirmed the work.
08/27/25 – THP published share file with SD review drawings. Drawing included stone, window, and safety package.
08/28/25 – Summary documents and initial estimate planned for week of September 2.
08/28/25 – Window SD set provided to THP 08/15.
09/25/25 – Elevar provided ROM estimate to THP.
10/30/25 – Review mtg with HCFD scheduled for 11/06.
10/23/25 – THP issued opinion of probable cost for all work.
10/30/25 – County review meeting scheduled for November 6th.
12/11/25 – Review mtg held with HCFD. Revised estimates and design schedule to be provided.
12/01/25 – Schematic Design meeting occurred. Scope, budget and next steps presented.
12/23/25 – HC requested an SOSS – DD through Bidding.
01/19/26 – THP published SD report for County project planning.
01/29/26 – THP/Elevar working on SOSS.
01/31/26 – THP and County working through project scope and design team services.
02/25/26 – THP published SOSS for review.
04/09/26 – HC approved SOSS.
04/30/26 – THP working through initial design phase planning.
05/27/26 – Design Kick off meeting completed.
06/08/26 – Project summary for security meeting published.
06/17/26 – Project placed on hold.
07/29/26 – THP published summary of conditions for use by the County.
09/24/26 – Project on hold.
10/25/26 – Project on hold

800 – Façade Repair SD (F022) Read More »

General Structural Services (F019)

PM: Rycca Thacker, John Millar/Paul Bellman
04/24/25 – THP completed an initial analysis of the Hillcrest storage shed truss/decking for review by the County. Preliminary findings for published via email.
07/30/25 – THP was requested to review Justice Center parking configuration and walked the site with John and Tony.
08/14/25 – THP published two Justice Center parking options for review by the County.
08/28/25 – THP attending monthly meetings, updating website and coordinating structural questions.
09/25/25 – THP attending monthly meetings, updating website and coordinating structural questions.
10/24/25 – THP submitted updated General Service SOSS.
10/29/25 – THP attending monthly meetings, updating website and coordinating structural questions.

General Structural Services (F019) Read More »

Elevar – General Services 2025 (F021)

02/25/25 – PO approved.
08/28/25 – CH fifth floor interior sign code summary provided to HC on 08/27.
12/11/25 – No updates.
01/29/26 – Combine with General Services F015.
03/26/26 – 230 exterior lighting study and 111 Tri-Co smoker’s hut performed under Gen. Services.
04/30/26 – Submitted SOSSs for additional PM and CA time to support HCFD and a Prevailing Wage Coordinator.
05/28/26 – SOSSs not approved for PM and PW Coordinator. Juvenile Assessment Center walkthru occurred and Elevar/DEG to issue report.
06/25/26 – Elevar SOSS not approved yet for Juvenile Assessment. Complete the report under Gen Services?
07/30/26 – 230 Court Admins wanted this work to be completed faster than if combined into 230 Lobby Security project.
07/30/26 – Elevar Juvenile Assessment report complete and need DEG portion to fully integrate.
08/27/26 – 230 Exterior Lighting Project back to DEG for electrical design. Fixture options provided to Rycca.
08/27/26 – Does HCFD want Elevar’s Juvenile Assessment report without DEG’s report?
09/24/26 – Elevar assessment report provided to HCFD without DEG’s portion. Site visit was made to review potential relocation of operable partition but put on hold.
10/29/26 – No update.

Elevar – General Services 2025 (F021) Read More »

JC – Emergency Power Upgrade 2025

PM: Matt Butz, Mike Barth
11/06/24 – THP update – THP provided an email with budget to rebid the project.
01/30/25 – Restart post to track 2025 project for this project.
01/24/25 – THP update – THP provided a formal SOSS.
02/26/25 – Prebid Meeting occurred on 02/26/25. Attendance by DK, Dunn Electric and Driekast. Bids due on 4/10/25.
03/07/25 – Terracon on site for test boring. Preliminary results included sandy dirt findings. Official report coming later this month.
03/25/25 – Terracon invoiced project for work but final report not here yet.
03/26/25 – Project bidding. Lots of questions being submitted by Glenwood. Bids are due 04/10.
04/23/24 – Project bids received. (2) bidders. Glenwood and Alpha. Glenwood apparent low bidder. DEI approves bids. TEI vets bid ln 04/22/25 – TEI to submit letter of recommendation to start the contract phase.
05/28/25 – Project in contract phase.
06/25/25 – Project in contract phase. Contract contacts TEI asking about status.
07/30/25 – DEG, HCFD, Bldg Mgr meet with Glenwood Electric for a pre construction KO meeting. at time of bid, the generators and switchgear quoted Glenwood 6-8 weeks for submittals, and then 40 weeks +/- for shipping of gear. Glenwood released the submittals end of last week. Likely startup of construction summer 2026.
08/27/25 – DEG has not received submittals to date.
09/24/25 – DEG receives equipment submittals. Submittals under review and approval.
10/29/25 – DEG working with contractors to get the permits in order.
01/28/26 – Issues with one switch that contractor and DEG working on.
02/25/26 – CO #001 issued. All gear should be on order. Estimated delivery June/July 2026.
03/25/26 – Glenwood submits several RFIs on the project. DEG reviewing RFIs.
04/29/26 – Glenwood submits pay applications for procured material. DEG to visit the crane yards to certify the equipment.
05/27/26 – Project construction pending material procurement.
06/23/26 – DEG speaks with Glenwood, and the gear manufacturer has production delays, the anticipated mobilization date has slid to 09/01. The existing equipment in the areas where the work is to occur needs to be relocated prior to mobilization.
07/29/26 – Project mobilization pending procurement of equipment.
08/26/26 – DEG meets with Glenwood at FDL and Ohio Cat to certify some of the equipment. Gen sets are on site in Dayton Crane Yard. Glenwood to schedule certifying the equipment trip with DEG.
09/23/26 – Pre-construction meeting occurred. glenwood site super has been on site to get knowledge of the building. Construction to begin around 10/01/2026
11/06/25 – THP issued permit drawings to be submitted with Davies set.
10/01/26 – Triton issued RFI No. 1.
10/05/26 – THP responded to RFI No. 1.
10/28/26 – Construction underway. Multiple meetings and discussions re fitting generator on oversized skid into the basement. Skid to be modified to fit into the building. ATS location for North tower is final coordination item at the time.

JC – Emergency Power Upgrade 2025 Read More »

1916 – Building Assessment

PM: Rycca Thacker, Eryn Thamann
12/12/24 – Project created for tracking.
01/29/25 – Draft copy sent out. Elevar finalizing photo and final cost portions now.
02/25/25 – Final report provided after requested edits.
03/26/05 – Requested revisions have been made. Waiting on a few last elevator assessment items from Wes.
04/24/25 – Elevator evaluated. Final report provided to RT along with bound copies as requested.
05/28/25 – Final report provided in April.
05/29/25 – Archived.

1916 – Building Assessment Read More »

800 – Exit Stair Security Cages

PM: Matt Butz, Eryn Thamann
01/29/25 – Met onsite 01/27 to review scope and SOSS requested.
02/25/25 – SOSS provided for Elevar/TEI. Pending approved PO.
03/26/25 – Pending PO approval. Onsite meeting with City AHJ is scheduled for 03/27 to walk spaces and review for any AHJ concerns.
04/24/25 – Elevar had site visit walk-thru AHJ to review life safety concerns. City concerns sent out in meeting minutes with sketches. HCFD needs to confirm additional scope as indicated by AHJ. Elevar will work on stair scope only for now.
05/28/25 – Elevar provided drawing backup to TEI on 05/28. After MEP design is DD level, a design review meeting will be scheduled with HCFD. Elevar to provide design schedule and will need to meet with HCFD to review Div 01 requirements.
06/26/25 – Design review meeting scheduled for 06/30 to review CD set.
07/31/25 – HCFD has 95% set. Waiting on approval prior to preparing final bid set. Elevar to provide clarification on fee per MB’s request.
08/28/25 – Discussing remaining fee with MB/TEI.
09/25/25 – Part of 2026 new project requests.
10/30/25 – Uploaded to Archibus.
12/11/25 – No update.
01/29/26 – Elevar met with HCFD to review 90% set and provided overview sheet for security committee. Waiting on security committee approval before proceeding with CDs. Project needs to be bid/award in 2026.
02/26/26 – Waiting on security committee approval before proceeding with CDs. Elevar has picked up internal revisions and ready when HCFD obtains approval.
03/26/26 – HCFD to setup security committee approval before proceeding with CDs.
04/30/26 – On hold pending HCFD approval of bidding costs.
05/28/26 – Out to bid now with bids due June 30.
06/25/26 – No update.
07/30/26 – Contractor recommendation provided to HCFD and contracts are in process with Purchasing.
08/27/26 – In final stages of contracts with Purchasing.
09/24/26 – Contract was finalized.
10/29/26 – Procurement starting but no submittals yet.

800 – Exit Stair Security Cages Read More »

All Buildings – Life Safety Drawings

PM: Rycca Thacker, Eryn Thamann
01/29/25 – SOSS requested. JN to confirm what buildings are included in SOSS.
02/25/25 – Pending approved PO.
03/26/25 – First site walk 03/27 at 230. Other buildings shall be scheduled after initial 230 bldg walk.
04/24/25 – 230 Building progressing. Examples with a few questions sent to HCFD for review/approval on 04/22. Elevar is scheduling other buildings with onsite facility managers.
05/28/25 – Example of 230 building was approved by HCFD. Site walks for TPC, 800, CH buildings have also been performed. Need updated drawings for JC care pods and TPC to accurately show floor plans. Need facility manager contacts for remaining locations to schedule site walks.
06/26/25 – JC walk-thru scheduled for 07/02 – 07/03.
07/31/25 – JC walk-thru occurred and Elevar has questions re: JC. Elevar received CH comments from Court Admin and an additional walk-thru is needed to confirm map orientation. Remaining buildings have not been walked yet.
08/28/25 – Evac maps for 230 building provided to HC on 08/27. Other buildings are ongoing.
09/25/25 – All maps will be provided before 11/01. Building 230 has been turned over.
10/30/25 – Evac maps are progressing and on schedule for 11/01 deadline except for a few floor plans where Elevar doesn’t have updated plans and can’t get updated plans.
12/11/25 – All buildings except Hillcrest campus and 6th Floor CH plans have been provided to HCFD with additional JC detainee-area evac plans.
01/29/26 – One floor of CH and Hillcrest to be completed by end of next week. Awaiting Tri-County drawings.
02/26/26 – Elevar working on final 111 Tri-Co drawings now and expect completion in approx. one week.
03/26/26 – Complete with 111 Tri-Co. Portion of Hillcrest remains until further notice.
04/30/26 – Complete. Keep project open for Hillcrest?
05/28/26 – No update.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – SOSS provided to complete 1701.
09/24/26 – No update on SOSS for 1701. CAD/pdfs provided to HCFD for other completed buildings.
10/29/26 – No update.

All Buildings – Life Safety Drawings Read More »

Hillcrest – Campus Repairs Phase 2

PM: Megan, Sam, Hofmann, Terry Cannon

01/27/25 – Create new project for tracking.
02/26/25 – ThermalTech has preliminary started creating the second phase floor plans for MEP.
02/27/25- Because this is tied to Federal Grant money, Phase 2 may not proceed and potentially fall back to Trades to do the work hodgepodge in the future. CCF Grant Funding in summer 2025 at state level and make give us some indication of what we are doing future.
03/25/25 – Project on hold until further notice.
04/23/25 – Project on hold.
05/28/25 – Project on hold.
06/25/25 – Project on hold.
07/30/25 – Project on hold.
08/28/25 – Project on hold.
09/24/25 – Project on hold.
10/30/25 – Project on hold. High level cost was sent to Rycca for grant purposes include the updated cost for design partners. updated Kitchen cost also sent to County.
12/11/25 – No update.
12/12/25 – Some items in Phase 1 being moved to Phase 2 for example school sink solids interceptor, repairs in Maple cottage, dining rec RCP.
01/28/26 – No Update.
02/26/26 – No Update.
03/26/26 – No Update.
04/30/26 – Grant is pending. Scope will be reduced to fit budget of grant. SOSS incoming to right size fee for reduced scope.
05/28/26 – No Update.
06/25/26 – 1.5 million grant awarded. Phase 2 scope meeting held. County to determine budget and design partners to provide updated SOSSs.
07/30/26 – No Update. Remove from list.

Hillcrest – Campus Repairs Phase 2 Read More »

A&D – Water Heater Draft Study

PMs: Tony Matre, Terry Cannon

01/27/25 – Wireless space pressure sensors installed 1/24. Initial pressure readings indicate the water heater room is slightly negative (0-0.025 in WG) compared to both outside and the elevator machine room. The observed airflow showed consistent flow from the elevator machine room into the water heater room and from the water heater room to outside, suggesting the pressure would be elevator machine room > water heater room > outside. The observed draft on the water heater was a slight backdraft from the flue into the water heater room. The thermal camera was used to look for temperature gradients in the flue which could indicate a clog, but none were observed. ThermalTech is continuing to observe pressure readings and look for irregularities.
02/26/25 – Wireless equipment has been installed and we are monitoring the room. We have had one incident where the air seemed to be moving into the elevator room. TTC discussed with Glen cover all transfer openings and continuing to monitor for another 30 days.
03/13/25 – Covers were placed on the VAV duct and the transfer grill between the mechanical room and elevator to isolate the room from draft influences. Another test was conducted when there was little draft by opening the door to provide combustion air, but this did not fix the issue either.
03/25/25 – Draft still an issue. ThermalTech camera the flues and found them to be clear.
TTE brought in a Enervex for a third party review of the installation. They suggested extending the flues another 6ft each and thought the additional elbows added below the heaters might be a problem, they are running flue calcs for us to review.
04/23/25 – Project recommendations sent to Tony and Glenn and some additional conversation was had, but we have not been given direction to where to go next. We recommend new roof penetration and longer flue pipes to eliminate the issues.
05/28/25 – Project on hold.
06/25/25 – Waiting on County direction for next steps.
07/30/25 – Prices came back too high and too much scope. Barrett reached out to DK to realign cost and scope.
08/28/25 – Prices updated and given to Tony and Glen for next steps.
09/24/25 – Archived.

A&D – Water Heater Draft Study Read More »

JC – Condenser Pumps Replacement

PMs: Matt Butz, Terry Cannon
01/17/25 – SOSS Requested.
02/26/25 – SOSS received, TEI starting preliminary engineering.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. Our first design meeting to be in April.
04/23/25 – Project design has begun, we should have preliminary review ready in a couple of weeks, and then we can meet and talk particulars for this project.
05/28/25 – First round of internal reviews complete. We are picking up TTC markups, creating a construction cost estimate, and filling out electrical coordination sheet. We will have the mechanical drawing issued for owner review on 5/30.
06/25/25 – No comments back from anyone that I know of, should we move to bidding?
07/28/25 – We sent drawings back for comment and requested AIA documents for bidding. Ready to bid but ITB not requested until budget is set.
08/28/25 – Budget set at $200,000. Comments and AIA contracts forthcoming from Facilities for this project.
09/24/25 – Prebid held last Friday, it was well attended. Addendum 1 due out this week.
10/29/25 – Pre Award meeting held with Geiler today and they can be recommended for this project.
12/12/25 – In contract approval stage.
01/25/26 – Sent before BOCC on Jan 19 for approval. We are awaiting notice to proceed. We have reviewed submittals already and are waiting on project kickoff to send them back to Geiler.
02/25/26 – Contract and PO are ready. DEG preparing for project kickoff. Pump submittals are approved.
03/25/26 – No kickoff meeting yet, submittals are approved, awaiting go ahead from County to move on this one.
04/29/26 – Kickoff meeting held early this month. Geiler commented that pumps were bid to be replaced when entire chilled water system was down. We are going to get everything in place and start this project in November 2026.
05/27/26 – DEG approved first pay application for $5500 and will send to County. Project on hold until November.
06/25/26 – Payapp received. Equipment in town, DEG to review at Geiler warehouse.
07/30/26 – Equipment approved, waiting on next Payapp from Geiler.
08/26/26 – Hold till November start.
09/23/26 – On hold until November, TTC approved and sent in Payapp 1, Payapp 2 already paid.
10/23/26 – Payapp 1 has cleared at Geiler.
10/26/26 – Pre-const meeting November 5. TTC removed the tentative tag on the meeting and update the invite.

JC – Condenser Pumps Replacement Read More »

800 – 6th Floor Reno & Bsmt Plumbing Repairs

PMs: Sarah, Terry Cannon, Eryn Thamann
01/17/25 – SOSS Requested.
02/25/25 – SOSS submitted to HCFD. Pending approved PO.
02/26/25 – Awaiting approved SOSS.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. We will follow Elevar lead on first design meeting. TEI scope is in the basement and the 6th floor area. Elevar hasn’t received approved PO.
04/24/25 – PO provided and awaiting design kick-off meeting with Court Admin/team.
04/23/25 – Project setup and internal meetings underway. Elevar and ThermalTech setting up kickoff meeting.
05/28/25 – Awaiting kickoff meeting with Elevar and County. TTE ready to mobilize for design.
06/25/25 – Kickoff meeting in July.
07/30/25 – Drawings received from Elevar, ThermalTech working on MEP design, submitted questions about need for MSB in new restroom. Additional fieldwork done last week for basement repairs.
07/31/25 – Drawings are progressing for a bid review set Aug 8 and a bid set to HC Purchasing Aug 15. TTC changed name and assigned to Elevar and merged Plumbing Repairs and 6th Floor Reno.
08/28/25 – Project scheduled for bid advertisement on 08/29.
09/25/25 – Bids due 10/10. Last addendum due out 09/26 with final questions.
10/30/25 – Lowest bid was Triton and under advertised cost. Vetting mtg occurred and Elevar has recommended Triton for award.
12/11/25 – Project awaiting final contract award from purchasing.
01/29/26 – No update.
02/26/26 – Contract was approved but Elevar has seen no submittals or correspondence. Elevar to schedule construction kick-off mtg.
03/26/26 – Contract was approved but Elevar has seen no submittals or correspondence.
04/30/26 – Have reviewed some general trade submittals.
05/28/26 – Possibly complete with submittals but low on Triton’s priority list.
06/25/26 – No update as it’s low on Triton’s priority list. Not received change order pricing for flooring add.
07/30/26 – Construction kickoff meeting held 07/20. Recurring progress meetings scheduled.
08/27/26 – Triton likely back onsite now after ACM removal. Regular progress meetings to resume next Mon. We will keep the floor drain in the project based on today’s conversation.
09/24/26 – Working thru slab change order.
10/29/26 – New pricing is expected soon for slab work.

800 – 6th Floor Reno & Bsmt Plumbing Repairs Read More »

800 – Low Rise AHU Replacements

PM: Matt Butz, Terry Cannon
01/17/25 – SOSS requested.
02/26/25 – TTC still needs to submit this SOSS, this is the last one on my list to submit.
03/25/25 – Internal kickoff meeting held this month. Drawings are being updated with existing conditions for the building. Our first design meeting to be in April.
04/23/25 – Project underway. We have completed our first field trip to the building. TEI running load calculations to verify sizing, setting up existing drawings and working on ventilation calculations. After we get the preliminary design complete, let’s meet and discuss project particulars.
05/28/25 – We held a kickoff meeting with the Facilities in the last month and made another round of field trips to the building for additional information. We are trying to prove HVAC AHU sizing from original job and collect factory information from original install of the low rise units to verify coil sizing, heating and cooling loads and whether or not air side economizers make economic sense during this replacement.
06/25/25 – ThermalTech doing additional fieldwork to lock down actual ductwork in the mechanical rooms. We should be ready for bidding next month.
07/31/25 – Project submitted for Owner Review. Project Manual didn’t make it through TTC review, will be sent later. Look for prebid third week of August.
08/26/25 – Prebid meeting Wednesday 8/27. TTE invited many.
09/24/25 – Addendum 1 previously released. Bid opening today at 11AM.
10/29/25 – Project on hold pending official bid award. TTC answered Nester email inquiry this morning about award status. TEI/DEG has not advised either bidder the project has been awarded yet.
12/12/25 – in contract approval stage. TTC notified contractors that Triton received the bid and Alpha did not.
01/25/26 – Sent before BOCC on Jan 19 for approval. We are awaiting notice to proceed.
02/12/26 – Contracts are back. Pre-Const meeting being set up now.
02/25/26 – Triton has been awarded the project. We are scheduling the project kickoff meeting soon. We do need to discuss what are we going to do with AH-71 and it’s proximity to the parapet wall.
03/25/26 – Submittals coming in, no kickoff meeting scheduled yet.
04/26/26 – DEG working on change order request drawing to relocate AHU-L71 to farther away from parapet wall. Once complete we will get a price from Triton for the change.
05/27/26 – DEG sent revised AHU-L71 location to Triton for pricing to rotate away from parapet to get 10 foot clearance.
06/25/26 – Awaiting project kickoff. AHU-71 change order not received yet.
07/30/26 – Pre Construction meeting held with Triton. Working on submittals, sent permit drawings to Triton, working on getting project n place for January start so unit can be replaced over long County weekend.
08/26/26 – Reviewing submittals preparing for January start.
09/23/26 – Still on track for January start, no new submittals in September from Triton.
10/26/26 – Had meeting with Triton and Emcor on HVAC Controls. We are awaiting the resubmittal of the controls package to DEG for full review. The controls have not been approved for this project yet. AHU submittals including curbs are approved. We are verifying current lead time for equipment.

800 – Low Rise AHU Replacements Read More »

Records Center – Showers, Washers, Dryers

PM: John Nester, Terry Cannon

12/12/24 – Plumbing drawings for dog washing shower area submitted and construction began last Friday.
01/27/25 – Triton has secured permit and is currently installing the dog showers in the facility. The trench drain has been cut, they didn’t like the cover, we are working getting a grated cover instead.
01/28/25 – Field visit reviewed existing conditions. TTC will send some questions to Triton about the install as a follow-up. The trench drain cover has been replaced and is currently curing.
02/26/25 – Showers and trench drain installed. Washer and dryer work is underway as well.
02/27/25 – Ready to Archive. Move all washer and dryer time to new Records Center Animal Shelter.
03/25/25 – The showers, washers and dryers are installed and being used.
04/23/25 – Space is in use this phase can be archived. New work will be picked up on the Records Center Animal Shelter project.
05/28/25 – Archive this project.

Records Center – Showers, Washers, Dryers Read More »

Colerain – Animal Shelter Wood Canopy (F020)

PM: John Nester, John Millar
10/21/24 – HC reached out to THP asking for repair of the Animal Shelter Wood Canopy.
10/31/24 – THP reviewed internal past documents and County email. THP to meet with County to discuss next steps.
12/11/24 – THP working on repair design.
12/16/24 – THP surveyed the site and met with County personnel. Shoring configuration was discussed and direction was given to install preliminary shoring.
12/17/24 – THP sent shoring detail for review.
12/19/24 – HC installed shoring and sent photos of sample shores. Shoring detailing was confirmed.

Colerain – Animal Shelter Wood Canopy (F020) Read More »

A&D – Elevator System PM Agreement

PM Tony Matre, Mike Barth
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre met to establish project schedule. The project in process.
02/26/25 – No updates this month
03/26/25 – No Updates this month.
04/23/25 – Project manual near completed. XBE paperwork to be submitted for approval then ITB will be issued.
05/28/25 – No Updates

A&D – Elevator System PM Agreement Read More »

230/800 – Elevator System PM Agreement

PM = Tony Matre, Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Tony meet and establish project schedule. Project in progress.
02/26/25 – No updates this month
04/23/25 – No updates this month
05/28/25 – No Updates
09/24/25 – DEG and AKM discuss that this goes out to bid mid October. Also discuss 1 year contract with optional 1 year renewals pending the elevator replacement projects.
10/29/25 – Project to be sent to purchasing on 10/31/25 for bidding.
12/10/25 – Prebid occurred on snow event day. A send prebid occurred on 12/08/25 for the bidders that could not attend during snow event. Bids to open on 12/29/25.
01/28/26 – Tony M and Bonita drafted contract and sent to Prosecutor.

230/800 – Elevator System PM Agreement Read More »

TPC – Elevator System PM Agreement

PM = Tony Matre, Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to develop project schedule. Project in process.
02/26/25 – No updates this month
03/26/25 – No updates this month.
04/23/25 – No updates this month.
05/28/25 – No updates

TPC – Elevator System PM Agreement Read More »

All Buildings – Generator Systems Inspections and Testing

PM = Tony Matre, Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to establish project schedule. Project in process.
02/26/25 – No updates this month
03/26/25 – TEI visits all building sites that are new to inventory/coming online this spring/summer. TEI submits DEI paperwork. As soon as approved by DEI – ITB will be issued.
04/23/25 – TEI issues project for bidding. Prebid meeting was on 04/21/25. In bidding phase.
05/28/25 – Bids received. (2) bidders. Project in contract phase.
06/25/25 – Project in contract phase.

All Buildings – Generator Systems Inspections and Testing Read More »

All Buildings – Fire Alarm System Inspections & Testing

PM = Tony Matre, Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives signed SOSS and PO. Per Tony – Project to commence Q1 of 2025
01/29/25 – TEI and Matre meet to establish schedule. Project in progress.
02/26/25 – No updates this month. AKM wants bid out in April ’25
03/26/25 – No updates this month. Work to occur in April 2025.
04/23/25 – Nick (TEI) developing and updating the data sheets for the buildings with newer systems. XBE paperwork in works and ITB to be issued.
05/28/25 – No updates
06/25/25 – No Updates
08/27/25 – DEG going to issue bid package first week of September. Proposed (AKM approved) prebid dates are 9/15 and 9/16.
09/24/25 – DEG issues for bidding. JCI, Siemens and SA Communale indicate interest in project. Prebid dates are 09/23 and 09/24, no bidders attended the prebid walk thrus. bid openings 10/22.
10/29/25 – SA Communale Only bidder. AKM working on Contract.
12/10/25 – Project in contract phase.

All Buildings – Fire Alarm System Inspections & Testing Read More »

2020 – WiFi System Study

PM = John Nester – Mike Barth

10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO.
01/29/25 – TEI and HCFD to conduct study walk thru of building in next 2 weeks.
02/26/25 – TEI requests time with HCFD to perform study walk thru
03/26/25 – TEI and HCFD walk the building to locate/document the existing WiFi system devices. Report is in progress.
04/23/25 – TEI to have draft report for review by HCFD/2020 staff by mid May.
05/28/25 – TEI has a draft review meeting with the HCFD/2020 staff. TEI finalizing a few modifications to the draft and will distribute to team for review/comments.
08/27/25 – DEG sends final report with HCJC comments included.
10/29/25 – DEG addresses C Walsh questions via email
12/10/25 – No updates this month

2020 – WiFi System Study Read More »

JC – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after fist walk of 230 bldg. Need updated drawings from Champlin and door labels from HCFD that match fire door report.
04/24/05 – Walk-thru not scheduled yet.
05/28/25 – Elevar needs building info that matches between original LSS report and building plans. Current plans don’t have door numbers listed and LSS report has inaccurate photos of doors. Walk-thru on hold pending further info.
06/26/25 – JC walk-thru scheduled for 07/02 – 07/03.
07/31/25 – Walk-thru performed but drawings have not been updated yet.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates almost complete but can review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – Paint removal will occur at JC. Elevar reviewed JC with Sheriff’s and a few items will be revised. No updates on progressing project into bidding.
07/30/26 – Elevar had questions regarding anti-ligature closer locations at JC and emailed to HCFD. List of doors needing paint removed sent to HCFD. Need final allowance amount from HCFD to add to bidding docs for door re-certificaiton/replacement if paint removal doesn’t work.
08/27/26 – Questions still remain for JC anti-ligature items but will be confirmed prior to bidding. HCFD to provide allowance figure for re-certification.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

JC – Fire Door Repairs Read More »

CH – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after first walk of 230.
04/24/25 – Walk-thru not scheduled yet.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
06/26/25 – Ready for review with Champlin/HCFD.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

CH – Fire Door Repairs Read More »

800 – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and Elevar will schedule walk-thru after first walk of 230 bldg.
04/24/25 – Walk-thru not scheduled yet but is next in line.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
06/26/25 – Ready for review with Champlin/HCFD.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. No update on whether paint removal from stickers was successful.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

800 – Fire Door Repairs Read More »

230 – Fire Door Repairs

PM: Sarah, Eryn
10/30/24 – SOSS in final review prior to sending.
12/09/24 – Pending approved PO.
01/29/25 – Pending approved PO.
02/25/25 – Pending approved PO.
03/26/25 – PO approved and initial site walk scheduled for 03/27 with JN.
04/24/25 – Walk-thru occurred and drawings have progressed. Elevar to coordinate with Champlin on design in near future.
05/28/25 – DD-level drawings are prepared. Elevar needs to review with Champlin/HCFD for general design intent; need bidding info.
07/31/25 – Ready for review with Champlin/HCFD.
08/28/25 – HC/Champlin/Elevar review meeting scheduled for 09/02 to review current sets and decide on bidding strategy.
09/25/25 – Finalizing cost estimates now. Drawings to be updated with any cost estimate comments. Specs to be completed after final project design review.
10/30/25 – Initial cost estimates complete and ready to review with HCFD. Need mtg scheduled to review estimates and what scope is base bid vs alternates. Also under review by separate hardware consultant.
12/11/25 – 95% review set provided to HCFD with costs. Elevar working on bid breakdowns now for the various buildings, alternates, and unit costs and will review with HCFD once complete.
01/29/26 – On Elevar’s current workload to write bid form breakdown.
02/26/26 – Elevar provided bid form breakdown. Rycca requested summary and Evan/Matt to setup meeting with Sheriff’s to review JC.
03/26/26 – Elevar to hold on design as-is. Evan/Matt to setup meeting with Sheriff’s to review JC in future. Work order in process for removing paint that may impact bid form.
04/30/26 – SOSSs approved for additional CA work. No update on whether paint removal from stickers was successful.
05/28/26 – No update. Need to know if paint removal was successful on stickers.
06/25/26 – No update.
07/30/26 – No update.
08/27/26 – No update.
09/24/26 – Awaiting paint removal status.
10/29/26 – No update.

230 – Fire Door Repairs Read More »

Colerain – Animal Shelter Boiler Replacement

PM: Tony Matre, Terry Cannon

09/26/24 – After SD and pricing efforts, we have decided to bid this project via Small Project bid with one for one like boiler and no recirculation pump replacements in the Base Bid.
10/30/24 – Drawing are modified and ready for bidding. NKY will be but no word back from DK and Geiler on their willingness to give us a price for this work.
12/12/24 – No updates since last meeting. BW said to go ahead and get three prices for the boiler replacement but they are not moving on doing the work this year. One price received so far.
01/28/25 – No updates.
02/26/25 – No updates.
03/25/25 – No updates.
03/26/25 – Tony confirmed this project on hold. No work for TEI at this time.
04/23/25 – Project on hold.
05/28/25 – Archive until further notice.

Colerain – Animal Shelter Boiler Replacement Read More »

All Buildings – Fire Sprinkler Inspection & Testing 2025

PM: Tony Matre, Terry Cannon

09/26/24 – SOSS Requested.
10/30/24 – SOSS submitted. Preliminary project setup has begun. TTE needs to add three buildings to the bid this time around, 111, 525, 4210 Dane, Crime Lab and Coroners Office.
12/12/24 – Approved SOSS and PO not received yet.
01/28/25 – PO received. Preliminary specs assembled by Barrett. We need to scheduled fieldwork to confirm quantities. We heard the first deadline for draft review is end of February.
02/26/25 – Limited updates, we will be working on this one in March.
03/25/25 – No updates. We still plan on bidding this job by end of April.
04/23/25 – Fieldwork is completed. New buildings are added, old buildings are removed. Specs have been updated for 2025 Code references. The Project manual is ready for Tony Matre review.
05/28/25 – TTC compiling proposed bid cost to request the ITB number for this project. Trying to scheduled a two day prebid for this project. Bid will be in June.
06/25/25 – Prebid meetings scheduled for July 9,10.
07/21/25 – Addendum #1 sent to bidders.
08/28/25 – Bids opened and awardable. SA Comunale had only openable bid. Next steps by County.
09/24/25 – Contract being drafted. We answered some questions about the give year testing.
10/29/25 – Archive.

All Buildings – Fire Sprinkler Inspection & Testing 2025 Read More »

JC – Polished Concrete – Phase 1

PM Jesse Estes, Sam Hofmann

09/26/24 – Project to go out to bid next week.
10/31/24 – Project is out to bid. Bid opening is 11/8.
12/12/24 – No bids received. Project went back out to bid and is opening today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future. Permit to be submitted in near future.
2/27/25 – Contract in progress.
03/27/25 – Kick-off scheduled for 4/2.
04/24/25 – Kick-off held. Submittals received. Mobilization to be scheduled.
05/29/25 – No update.
06/26/25 – No update.
07/31/25 – No update.
08/28/25 – Waiting on background checks to clear to begin.
09/25/25 – Concrete grinder sub walked out on project. Alpha is searching for replacement.
10/30/25 – Alpha found replacement grinder sub. Alpha discovered that all furniture on the 5th floor of the north building has been tack welded to the bolts. all furniture in the day space area will be removed and re anchored. All cell furniture will be grinded around as best as possible.
12/11/25 – Pods are complete. Alpha to begin central hallway.
01/28/26 – Scope Complete. Waiting on closeouts.
02/26/26 – Closeouts received and missing items requested.
03/26/26 – Items still outstanding.
04/30/26 – Items returned. Hard copies outstanding.
05/28/26 – No Update.
07/30/26 – Closeouts delivered to County.

JC – Polished Concrete – Phase 1 Read More »

230 – Façade Repairs (F016)

PM: Matt Butz, Fateme Shahiyan

08/29/24 – County request THP rebid Alternate Façade repair package from SOSS F003. SOSS Hamilton County.
09/23/24 – THP published review drawing to County.
09/23/24 – County provided review comments to THP.
09/26/24 – Final bid to be released to purchasing with Advertise to bid scheduled for 9/30/24. Bid opening scheduled for 10/30/24.
10/16/24 – THP issued Addendum No. 1 – (prebid minutes and updated prevailing wages).
10/21/24 – THP issued Addendum No. 2 – (update to sheet metal prevailing wages).
10/30/24 – Bids were received.
10/21/24 – THP issued Addendum No. 2 – (update to sheet metal prevailing wages).
10/30/24 – Bids were received and BCR was the lowest bid.
11/05/24 – THP had a Bid Review with BCR
11/14/24 – THP sent the bid summery and recommendation letter for BCR to Hamilton County.
01/16/25 – Preconstruction meeting completed.
01/29/25 – Progress meeting completed.
01/30/25 – Project status – BCR has rigged and complete the first knock down survey of the north elevation. Work will progress north to west to south.
02/21/25 – Crew moved to the west elevation to do the knock down and have the spots ready to patch when temperature gets better in the next week.
02/24/25 – BCR send out Pay App No.1 for THP review and THP approved that.
03/17/25 – BCR Completed all repairs at TPC. THP did the final site visit and did not observe any problem with repairs.
03/26/25 – BCR start installing the swing stage on roof for the north return wall of the building.
03/31/25 – BCR completed the work and sounded the north return wall. No major sports or damage.
04/04/25 – BCR submitted pay app No.2 and was approved by THP. BCR needs to provide the closeout documents.
05/27/25 – BCR is working on the closeout documents, and they are planning to provide all documents by end of the week.
06/10/25 – BCR has provided all closeout documents, which have been approved by THP. BCR is in the process of sending the notebooks and USB drive containing the documents to the County. Once that is completed, THP will send the signed final pay application to HC.
07/30/25 – Project status: All closeout documents approved. Waiting on project notebooks.
08/26/25 – BCR planning on complete the closeout documents and send it to the county by end of the next week along with the TPC project.
09/15/25 – BCR dropped off the closeouts documents to HC/Matt Butzz. However, the electronic documents, notarized warranties and 2 payrolls for the project were missing. BCR is planning to provide the documents by end of this week.
12/11/25 – All project closeout sent to County and final pay application approved.

230 – Façade Repairs (F016) Read More »

2025 Structural Estimates CIP Resubmittal (F010)

PM: John Nester, John Millar

06/11/24 – THP HC requested SOSS for project estimates broken down by New, Resubmittal and CIP Resubmittal.
06/25/24 – Champlin published draft project lead list.
07/15/24 – Thermal Tech published final edit.
08/28/24 – THP published SOSS.
08/29/24 – THP working on estimates.
09/26/24 – THP finalizing estimates.
12/11/24 – THP completed structural project estimates.

2025 Structural Estimates CIP Resubmittal (F010) Read More »