2025 Structural estimates Resubmittal (F009)
PM: John Nester, John Millar
2025 Structural estimates Resubmittal (F009) Read More »
PM: John Nester, John Millar
2025 Structural estimates Resubmittal (F009) Read More »
PM: John Nester, John Millar
2025 Structural Estimates New (F008) Read More »
PM: Rycca Thacker, Mike Barth
09/25/24 – HamCo requests SOSS for Elevator Modernization project for (4) elevators in 230 East 9th Street Building. TEI and Elevar meet to discuss roles on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar SOSS provided to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
01/29/25 – TEI/Elevar/HC met and TEI has design schedule. Field work is ongoing now.
02/25/25 – Elevar performed field work for all.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting scheduled with HCFD. SD meeting scheduled for 04/02.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team meets with the Courts committee to review security and finishes. DD documents are progressing.
06/25/25 – Team meets with Court Admins. TEI to submit updated schedule.
07/30/25 – Team sends proposed schedule and RFIs to HCFD for direction.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Low bid being vetted by design team.
04/30/26 – Contract in process with HC Purchasing.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027). The contract phase and procurement deposit caused the delay.
230 – Elevator Modernization Read More »
PM: Rycca Thacker, Mike Barth, Lauren Schmitz
09/25/24 – HamCo requests SOSS for Elevator Modernization project for (5) elevators in 800 Broadway. TEI and Elevar meet to discuss rolls on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar provided SOSS to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO. TEI and JE perform initial walkthrough of all of the elevator machine rooms.
01/29/25 – TEI/Elevar/HC met and TEI has design schedule. Field work is ongoing now.
02/25/25 – Elevar performed all field work and work is ongoing.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting was scheduled with HCFD. SD review meeting shceduled for 04/02.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team waiting on HCFD to schedule courts committee for design review.
06/25/25 – Team meets with Court Admins – get direction on security and finishes. TEI to submit updated schedule.
07/23/25 – THP – Davies, Elevar, County and THP met to review possible options for getting the elevators in 800 Broadway.
07/30/25 – Team sends proposed schedule and RFIs to HCFD for direction.
07/29/25 – THP sent a proposed summary of elevator access plan and THP scope of work for review.
08/13/25 – THP sent an SOSS to Davies for review.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/08/26 – THP issued bid documents.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Low bid being vetted by design team.
04/30/26 – THP sent questions for GC post-bid review in March.
04/30/26 – Contract in process with HC Purchasing.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027. The contract phase and procurement deposit caused the delay. Due to the obsolescence of the R-410A refrigerant, the Liebert units for the machine room cooling anticipated ship dates are 52+ weeks. The Skill-Aire alternate ($42k deduct) is 16-18 week ship time.
800 – Elevator Modernization Read More »
PM – Rycca, Mike Barth
09/25/24 – HamCo requests SOSS for Elevator Modernization project for (9) elevators in Courthouse. TEI and Elevar meet to discuss rolls on project. TEI and Elevar developing SOSS.
10/30/24 – Elevar provided SOSS to TEI.
10/30/24 – TEI submits SOSS for approval. Project pending SOSS approval and PO.
12/11/24 – TEI receives Signed SOSS and PO. TEI and JE perform initial walkthrough of all of the elevator machine rooms.
01/29/25 – TEI has design schedule. Field work ongoing.
02/25/25 – Elevar performed field work for all.
02/26/25 – TEI working on developing SD documents with a proposed end of March deadline for SD.
03/26/25 – Elevar provided SD drawings to TEI and SD meeting scheduled with HCFD.
04/24/25 – Team to meet with Court Admin/committee to review project, security, and finishes. Elevar has finish presentation prepared. HCFD to notify team when courts are available.
05/28/25 – Team waiting on HCFD to notify when courts committee are ready for review meeting.
06/25/25 – Team meets with Court Admins – get direction on security and finishes. TEI to submit updated schedule.
07/30/25 – Team sends proposed schedule with RFIs to HCFD for direction.
08/27/25 – Team meets with court admins and gets final sign off on selections. Team submits OPC for HCFD to obtain funding. Once funding approved, project will be sent to ITB.
09/24/25 – Project issuance pending funding approval.
10/30/25 – Project issuance pending funding approval.
12/11/25 – Project submission for 100% review on 12/15. ITB date in Jan 2026.
01/28/26 – Project out to bid. Prebid well attended. Bids due 2/26
02/26/26 – Bid opening today!
03/26/26 – Bids still under review by HC.
04/30/26 – Low bidder vetting meeting occurred. Contract in process with HC Purchasing. Notification of TKE buyout forwarded to HCFD.
05/27/26 – Triton contract approved at the BOCC meeting on 05/21/26. Preconstruction meetings to be scheduled early June.
06/23/26 – Preconstruction meeting conducted on the project with HCFD and court administrators. Contractor in the survey and submittal phase prior to ordering of equipment.
07/29/26 – Project in submittal development phase. Design team has not received submittals to date.
08/26/26 – Project in submittal development phase. Design team has not received submittals to date.
09/23/26 – Design team receives initial submittals.
10/28/26 – Submittals continue to get reviewed and returned. Mobilization anticipated approximately Mid-April 2027 (original schedule was mid-March 2027. The contract phase and procurement deposit caused the delay.
CH – Elevator Modernization Read More »
PM: Matt Butz, John Millar, Eryn Thamann
06/26/24 – THP provided SOSS to Elevar.
07/25/24 – County approved SOSS.
08/14/24 – THP and Elevar completed a kick off meeting and general walk of the roofs.
08/27/24 – SOSS approved. Kick off meeting held with HCFD, THP, Elevar. Building scanning schedule being coordinated for site access.
09/26/24 – Truscan came out two days ago and modeled the building. Elevar will share with the partners, over one billion points scanned, CH and surrounding areas. More fieldwork needed.
10/30/24 – Model shared with THP and SD continues.
12/09/24 – THP working with model and performing site work.
10/30/24 – Model shared with THP and SD continues.
12/11/24 – THP completed initial field work to confirm model accuracy. THP provided review comments and has begun working on model joints.
01/29/25 – THP has performed several facade tests but weather limited site work; surveying still ongoing to document stone/terra cotta joints. Roof plans are developed; THP/Elevar coordinating on roof edge details now.
02/25/25 – Deliverable schedule sent to MB. Work ongoing.
03/26/25 – Met with HCFD to review SD status drawings. THP has additional site investigation to perform but still look on track for May SD deliverable.
04/24/25 – Team is progressing with design. Elevar to get masonry contractor under contract to complete destructive investigation.
04/24/24 – THP field surveying work is wrapping up today (4/24). Any additional site visits will be on an as-needed basis for verifications. Background drawings complete and THP actively transferring field surveying data to drawing set, and tallying repair sizes/quantities.
05/28/25 – Decision on mason expected 05/29. Elevar to schedule work with HCFD.
06/26/25 – Mason under contract and patiently awaiting their onsite schedule. THP/Elevar meeting to coord. designs. Final SD set expected to HCFD end of July.
07/31/25 – Mason walk-thru 07/24 with THP/HCFD and scheduled onsite start for 08/04. Badging will start if crew will be inside but will determine at walk-thru. Deadline pushed back to accommodate mason.
08/28/25 – Waiting for final mason contractor to get badged to start investigative demo.
09/25/25 – Mason onsite in Sept and design team finalizing drawings based on findings.
10/30/25 – Final SD set provided to HCFD along with cost estimate. Review mtg schedule for 11/06 with HCFD/THP.
11/06/25 – THP and Elevar met with HC to review SD set. HC requested updates to OoPC and schedule.
11/21/25 – THP sent final OoPC to Elevar, with requested updates from HC.
12/01/25 – THP reviewed design schedule with Elevar and HC during 800 Broadway meeting.
12/11/25 – Final cost estimate and design schedule will be provided to HCFD this week.
01/29/26 – Elevar/THP working on SOSS.
02/23/26 – THP published fee proposal to Elevar for Phase II of design work.
03/26/26 – SOSS approval pending.
04/24/24 – THP update – THP field surveying work is wrapping up today (4/24). Any additional site visits will be on an as-needed basis for verifications. Background drawings complete and THP actively transferring field surveying data to drawing set, and tallying repair sizes/quantities.
04/30/26 – SOSS approved. Need to schedule kick-off meeting with team and HCFD.
05/28/26 – Design kickoff mtg occurred 05/27. Elevar to send pdf presentation to team for review with Court Admins. Team will provide design schedule very soon.
06/17/26 – Project placed on hold.
06/25/26 – On hold. Design kickoff minutes and presentation provided to HCFD.
07/30/26 – No update. Remains on hold.
08/14/26 – THP provided recommended critical repair scope and budget.
08/27/26 – Priority list provided by THP to HCFD. Could restart after November with very limited scope.
09/24/26 – Project on hold.
10/25/26 – Project on hold
CH – Facade Repairs/Roof Replacement (F005) Read More »
PM: Rycca Thacker, John Millar
06/26/24 – THP provided SOSS for County review.
05/16/24 – Hamilton County approved SOSS.
01/29/24 – No update.
02/27/25 – OK to Archive.
JFS – General Structural Services (F004) Read More »
PM = John Nester, Mike Barth
08/28/24 – ThermalTech Issues SOSS for approval.
09/25/24 – Project pending SOSS approval.
10/30/24 – Project pending SOSS approval.
12/11/24 – Project pending SOSS approval. Work picked up in different project, okay to close this one.
CH – Courtroom 580 Electrical Upgrades Read More »
PM = Matt/ Trades, Mike Barth
08/28/24 – ThermalTech submits SOSS for all sirens in Zone 4.
09/25/24 – TEI receives signed SOSS and PO for project. TEI to schedule kick off meeting with HCFD.
10/30/24 – TEI contacts Duke Energy for available fault at each location. TEI coordinates with HCFD for addresses of each siren. Model in Progress.
12/11/24 – Zone 4 sirens are modeled and the labels are ready for printing. TEI will print and deliver to HCFD.
01/29/25 – TEI to deliver the labels to HCFD.
02/26/25 – TEI delivers Arch Flash Labels for Zone 4 sirens.
03/26/25 – TEI delivers SOSS for zone 5 sirens. TEI receives PO to start the Zone 5 package.
04/23/25 – TEI to start the arc flash study for zone 5 sirens.
06/25/25 – No updates this month.
07/30/25 – DEG receives available fault from Duke for Zone 5 sirens and modelling is in process.
08/27/25 – Modeling of all sirens in progress.
10/29/25 – Modeling complete. Pending MCB and CMI review.
12/10/25 – No updates
01/28/26 – HamCo requests SOSS for next zone (assuming Zone 6).
02/25/26 – DEG submits SOSS for Zone 6.
03/25/26 – DEG receives PO and signed SOSS for Zone 6. DEG gathering data from duke and developing model. Zone 5 arc flash stickers to HamCo Trades.
04/29/26 – DEG completes modeling of zone 6 sirens. On Barth’s desk for review and approval, and then send to CMI for approval prior to printing labels for trades.
05/27/26 – No updates.
06/23/26 – DEG reviews model with CMI (Charlie) and gets CMI approval of model. DEG prints all zone 6 labels and delivers to Trades Electricians.
07/29/26 – Project deliverables complete until next years zone 1 SOSS approved.
EMA – Tornado Sirens Arc Flash Study Read More »
PM = John Nester, Mike Barth
08/28/24 – ThermalTech submits SOSS for approval.
09/25/24 – TEI receives signed SOSS and PO. TEI contacts Bldg Mgr to schedule site eval (tentatively 9/30 or 10/1).
10/30/24 – TEI submits report for review and comments from HCFD.
12/11/24 – TEI develops drawings for County review.
02/26/25 – TEI develops permit documents and HCFD solicits quote from Glenwood (emergency on call electrician), Glenwood submits drawings for permit.
03/26/25 – Plan review complete and approved. Glenwood pulls electrical permit and to schedule install.
04/23/25 – Glenwood proceeding with the removal of the raceway and installation of the new conduit system. HCFD to notify TEI when complete and a punchlist visit will be conducted.
05/28/25 – Project completion pending punchlist.
06/25/25 – HCFD and TEI complete punchlist. No items identified on punchlist. Project complete.
Colerain – Animal Shelter Electrical Investigation Read More »
PM: Eryn Thamann, Matt Butz
08/27/24 – Elevar SOSS approved. TEI to submit SOSS.
09/24/24 – TEI submitted SOSS to HCFD. Elevar requested design kick off meeting with HCFD.
10/30/24 – Drawings are setup and design team need to walk space for FV and finish discussions.
12/09/24 – Need to review finishes with HCFD. Will perform site work 12/12. BW said bring over finishes and he would like to maybe replaced tile in main hallways.
01/02/25 – TEI reached out for update on project progress.
01/27/25 – Kickoff meeting occurred 1/22, SD & Cost Due to John Nester 3-4 weeks after meeting.
02/26/25 – Elevar to gather full SD set for HCFD submission. Archibus project made and SD estimates can be added. ThermalTech will complete SD drawings by Friday 2/28.
02/27/25 – JN will bring in Sheriff Office for final review early March for this job.
03/26/25 – Team met with stakeholders to review SD options. Elevar will provide another round of SD options and storage options based on new info from meeting.
04/24/25 – Elevar provided second round of SD plan options and Sheriff storage options for selection. Upon plan and storage selections, the team can procced with design docs.
05/28/25 – No update.
06/26/25 – Elevar to update Archibus cost estimates.
07/31/25 – Elevar to update Archibus cost estimates.
08/28/25 – Estimates updated and new options uploaded.
09/25/25 – No update.
10/30/25 – No update.
12/11/25 – No update.
01/29/26 – Elevar to submit SOSS. Need final decision on Sheriff’s storage options or no storage included. Confirm no separate interior office for Sheriff’s IT group.
02/26/26 – Elevar has remaining fee and will start on this immediately.
03/26/26 – DEG to finalize MEP drawings and a final HCFD review set will be ready.
04/30/26 – Set is 95% and on hold for final bidding info.
05/28/26 – Need to prep documents for trades work. Elevar to submit building permit and DEG to submit IBI permit.
06/25/26 – Elevar to submit building permit and DEG to submit IBI permit this week.
07/30/26 – Kickoff meeting held 07/22. IBI permit approved. Building permit still under review.
08/27/26 – Kickoff meeting held with trades. IBI review approved and DEG will submit. Building permit paid for and wall bracing engineering change submitted.
09/24/26 – Will postpone construction start until approx. Nov 2026.
10/29/26 – Restart?
CH – 6th Floor Sheriff’s Storage Read More »
PM: Eryn Thamann, John Nester, Jesse Estes
08/27/24 – SOSS approved. JN to send new drape/blind info for review prior to scheduling site visit.
09/24/24 – JN to send info and meeting invite to review mock up.
10/30/24 – Elevar met with Court Admin to review mockups. Drawings started for SD.
12/09/24 – SD review meeting with HCFD/Court Admin scheduled for next week.
01/29/25 – Met with Court Admin and revised drawings based on meeting. SD review package is nearly ready for HCFD final review.
02/26/25 – Drawing package submitted to HCFD for final review.
03/26/25 – No update.
04/24/25 – No update.
05/28/25 – No update.
06/26/25 – No update.
07/31/05 – Elevar to research historic requirements for elevations.
08/28/25 – No historic restrictions on interior window treatments and confirmation sent to HC.
09/25/25 – No update.
10/30/25 – No update.
12/11/25 – No update.
01/29/26 – Archive?
CH – Re-Drape and Blinds Read More »
PM: Eryn Thamann, Bert Watts, John Nester
08/27/24 – Initial meeting held with HCFD, Juvenile Court, Elevar.
09/24/24 – SOSS submitted for strategic planning efforts. Juvenile Courts waiting on larger funding of Hillcrest projects/programs before approving.
09/26/24 – On hold.
10/30/24 – No update.
12/09/24 – No update.
01/29/25 – No update.
02/25/25 – No update.
03/26/25 – No update.
04/24/25 – No update.
05/28/25 – No update.
Hillcrest – Campus Long Term Strategic & Master Planning Read More »
PM: Eryn Thamann, Matt Butz
08/27/24 – SOSS approved. Kick off meeting held with HCFD, THP, Elevar. Building scanning schedule being coordinated for site access.
08/29/24 – Merged with THP project but kept THP project active.
09/24/24 – Exterior building scan performed and point cloud just received 09/24. SD package will proceed.
CH – Roof Replacement and Facade Repairs Read More »
PM: Bert, Mike M, Terry, John Millar
05/30/24 – ThermalTech submitted SOSS to Champlin for SD & Cost.
05/31/24 – Champlin sends TTE background material to start working on this project.
06/26/24 – Design Meeting started, Champlin sent agenda and latest drawings.
07/02/24 – Board Presentation Day.
07/10/24 – Fieldwork at site.
07/17/24 – Fourth Floor layout sent from Champlin to TTE.
07/25/24 – JFS Computer Room fieldwork setup for TTE.
07/31/24 – Bond Hill Due Diligence SOSS request sent.
08/01/24 – SD & Cost sent to Hamilton County for this project.
08/21/24 – Due Diligence SOSS questions came back from Champlin. Be ready to move on due diligence quickly if approved.
09/19/24 – THP update – Champlin/County request THP provide building envelope and garage restoration due diligence assessments.
09/26/24 – Due Diligence kicked off. Architectural, MEP and environmental site visits complete. Survey happening today. Structural and civil scheduled.
10/02/24 – Due Diligence – THP update – THP published proposal to Champlin.
10/03/24 – THP update – Champlin/County request THP provide structural footing design for the garden fencing as part of the larger project.
10/07/24 – Due Diligence – THP update – THP field teams completed building envelope and garage surveys.
10/10/24 – Due Diligence – THP update – THP completed roof thermal scans.
10/11/24 – THP update – THP published proposal to Champlin.
10/23/24 – Met onsite with Facilities, Environmental Services, Ameresco and ThermalTech on Netzero energy opportunities.
10/25/24 – Due Diligence – THP update – THP published building envelope and parking garage due diligence assessment to Champlin.
10/31/24 – Due Diligence draft submitted to county. SOSS for DD-CA submitted. DD review meetings have begun. Documentation ongoing.
12/12/24 – DD to be submitted for review on 12/23. Estimate to be submitted 1/6. Meetings ongoing.
12/23/24 – THP update – THP issued DD fence and moveable wall structural details.
01/27/25 – ThermalTech finalizing fieldwork at the site to continue design for HVAC, Plumbing, Electric, and Fire Protection beyond the DD phase into CD. We have received the server survey from Telecomm and have updated our calculations for each IDF and MDF room, we hope to have floor plans updated by end of this week with proposed rack locations and HVAC needs. We are on pace to make the CD deadline of February 28, 2025.
01/30/25 – Final meetings with each department ongoing. CD’s being developed. Bid review set to be submitted for review on 2/21.
02/27/25 – Review set submitted to county. Tentative bid issuance date is 3/6. DDS has been removed from bid package to be issued as a separate project.
03/27/25 – Drawings are ready for bid. Updated Estimate to be submitted this week.
04/24/25 – Bid phase ongoing. Pre-bid had light attendance. Bids open May 23.
05/29/25 – Graybach is apparent low. Bid vet to be scheduled when bid is determined acceptable.
06/26/25 – Bid vetting in process. A305s provided to county for consideration.
07/31/25 – Graybach will be awarded the bid. bid vet meeting held. contract has been signed and will be going in front of the board next week. Const meetings start week of August 11.4
08/28/25 – Graybach has mobilized and began demolition. Furniture move services bid issuance on 8/26. RFI received on plumbing and HVAC are being answered as they come in. We have officially access controls, but it has been resubmitted as individual components and AV cable, fiber and Cat6 is approved. Now we need to discuss what to do about the security camera system. We reinforced with the field foreman that we are pulling every cable back to the IDF rooms so it landed by floor. TTE to send IDF coordinate drawings to John for ordering and coordination ASAP.
09/23/25 – TTE met with DK yesterday on proposed HVAC changes at Bond Hill. DK has already performed all the work on the first floor, we negotiated changes and discuss field engineering changes methodology with Dustin and Dave. We agree on the material cost but feel strongly that the labor is more than what is needed to make the requested changes (as it was estimate at three additional men for one month). TTE suggested that this change order is enough to cover not only the 1, 2, 3 floors, but the entire building.
10/02/25 – THP – Champlin requested field support for cutting holes in precast panels.
10/23/25 – THP – after site trips and coordination with Champlin, THP issued field sketch for precast hole support.
12/11/25 – Graybach still confident they will get done by mid January with TCO in mid January for Phase 2. TCO expected next week for Phase 1 as most inspections are done for the TCO work. Design team still issuing Bulletins for changes for GC, EC, and low voltage. AT A&D they are getting ready to move to the new building. HC has weekly move meetings for coordination, Veteran Services move being coordinated. Osterman working with HC and Graybach coordinate move items. HC seeking additional funding for extra asks at the building and the low voltage items.
01/28/26 – Punch walk through completed. Exit sign issue has been solved.
02/26/26 – JFS has moved in to the first 3 floors. minor punch work ongoing. Floors 4 and 5 are ongoing. DDS awarded to Triton. Demo is complete for DDS.
03/26/26 – Floors 4 and 5 in progress. Punch tentatively scheduled for 3 weeks from now. Furniture scheduled to be compete 5/1. DDS portion is ongoing.
04/30/26 – Project to be complete in 2 weeks. Punch scheduled for next week. Move in mid may.
05/28/26 – Punch work nearly complete on 1, 2, & 3. Punch walk through on 4 & 5 minus DDS happened last week. Everyone (minus DDS) should be moved in by end of next week.
10/29/26 – Closeouts ongoing.
Central – Office Consolidation Phase 1 & 2 Read More »
PM: Matt/Trades, Terry Cannon
Closeout: Terry Cannon, tcannon@davieseg.com
06/25/24 – Proposal from ANS sent to Bert Watts for review.
07/24/24 – Submitted for 2025 budget. County may know in Q4 about viability.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold.
01/17/25 – SOSS Requested.
02/26/25 – Kickoff meeting on hold while TEI researches additional technologies.
03/19/25 – Preliminary conditions meeting held with EMA on SOSS modifications. TTC submitted revised SOSS with additional scope same day.
04/23/25 – MCP sent a very high proposal in to assist on this project. TTC to follow up with Nester on next steps.
05/28/25 – TTE release PO to ANS for Siren Assessment, scheduling the first kickoff meeting June 30 or July 2, this request out to Mike D at ANS. ANS says they will need about 45 days to perform the onsite analysis. MCP quote came back very high, looking for other specialist contractors to assist with assessment.
06/25/25 – ANS cannot make the July 2 date, TTC to pick another date.
07/18/25 – Kickoff meeting held at 525 with ANS and EMA. Project set to kickoff August 4.
07/27/25 – Nick commented that third party vendor not required for future recommendations of system and we can concentrate on the siren conditions first.
07/30/25 – Additional scheduling taking place, project set to kickoff August 11 onsite at Siren #414. EMA, TEI, HCDF and ANS.
08/28/25 – ANS has made two deployments to the County so far. Zone 4 was completed the first week of August. Zone 5 was addressed this week. We are not sure how far ANS will get this week but shadowing ANS, each siren was about one hours to 90 minutes of work with travel. We have questions out for what constitutes a FAILED siren, especially in regard to test 3.1.4 on the Audit worksheet. The Siren Tracking sheet was created and updated and implemented by ThermalTech and put to use in the OneDrive. The OneDrive folder is available for use on this project. We are on schedule for targeted completion.
09/24/25 – Vendor meetings continue. Zone 6 is complete. 26 audits have been uploaded, no failures for this group. Several sirens were skipped for access and traffic control. Joe is in town for Zone 1&2 at this time.
10/29/25 – ANS has completed their initial visit to all sites in all zones. ANS returning November 3 for Traffic Control sites. The traffic control sites and daily order was released today to all team members. Friday November 7 is a backup day to pick up remaining sites. Facilities has followed behind ANS nicely fixing and putting UNSAT sirens back into service.
12/12/25 – Traffic Control and Access impeded sites have been visited. DEG checks with ANS every day for final audits. We have received 8 of the final 37. TTC must submit 25% Draft Report by Friday.
12/31/25 – Draft report sent to Hamilton County Facilities & EMA for review.
01/12/26 – Received final 17 Audit reports from ANS and incorporated them into the report.
01/15/26 – Reviewed report with EMA and tabulated all siren conditions from ANS and presented these numbers to EMA as well.
01/25/26 – Updated report being sent to the EMA this week for second around of reviews.
02/25/26 – Rev-5 sent to the EMA for comment. This version includes the Acoustic Model from ASC. No comments received from Rev-4 yet.
03/25/26 – No comments received yet.
04/16/26 – Met with the EMA on comments on the report. They are extensive comments. DEG will begin working through the changed.
04/27/26 – DEG continues working on report updates. We’ve gotten though some of the proposed cost changes, most of the editing is complete, inventory changes picked up and now TTC has to contact Federal Signal and get their information for the report.
05/21/26 – Met with EMA and Facilities and sent back next revision of report to EMA for approval and review.
06/25/26 – TTC checked back with Morgan on comments or progress, no update yet.
07/30/26 – No updates on markups to final report.
08/26/26 – No updates, saw Nick at Sharonville Life Safety event, he didn’t mention.
09/23/26 – No updates but we are starting two siren relocations with Ben, Keith, and Zach.
10/26/26 – Waiting on next review meeting with EMA. Project is in closeout.
EMA – Tornado Siren Conditions Assessment (No ITB) Read More »
PM: Matt Butz, Sam Hofmann
03/28/24 – SOSS received. Sheriffs to locate doors included in this project.
04/25/24 – No update.
05/30/24 – Sheriffs provided doors to be included. Work in progress.
06/27/24 – Work in progress.
07/25/24 – No Update.
08/29/24 – Owner review set submitted. project to be bid in next couple weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Cornerstone is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project in contract phase.
01/30/25 – Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff scheduled for 3/31.
04/24/25 – No Update.
05/29/25 – Submittals received.
06/26/25 – Submittals to be returned and a schedule provided by Cornerstone.
07/31/25 – Submittals returned. Cornerstone to schedule mobilization.
08/28/25 – No update.
09/25/25 – No update.
10/30/25 – Cornerstone to mobilize Monday to finish phase 3 work and begin phase 4.
12/11/25 – Phase 1 complete. Moving to phase 2 after the new year.
01/28/26 – Project ongoing.
02/26/26 – Project is ongoing. 2 pods left until completion.
03/26/26 – Project ongoing. second to last phase has been started. Final phase to pause for 1 month until Triton completes phase 2 work.
04/30/26 – No update.
05/28/26 – Cornerstone to complete this project after tritons project is complete.
06/25/26 – No update.
07/30/26 – Final pod is ongoing.
08/28/26 – Work is complete. Closeouts in progress.
09/24/26 – No update
JC – Selective Cell Door Replacement 2024 (Ph. 4) Read More »
PM: Tony Matre, Terry Cannon
05/28/24 – Cooling tower makeup water reviewed and approved by GCWW and should be on bill next billing cycle.
06/27/24 – Irrigation sewer deduct ready to review by County. It’s ready to send to GCWW.
07/24/24 – Second deduct meter sent to County for review. TTC followed up by email.
08/28/24 – Received Tony signatures on final paperwork, ready for submission to GCWW.
09/24/24 – Second application has been given to GCWW and MSD, they confirm they have it but it has not been reviewed or processed yet.
10/30/24 – Additional data requested and sent last week to MSD.
12/12/24 – MSD and GCWW have all the data they need, we are waiting on their approved and meter review. The first meter has been on the bills since June, and we are getting a deduct for it. Meter number S03787, so far, they have saved a little over $1,000 in sewer charges in the first few months with the meter online.
01/02/25 – We have the meter and the transmitter has been located. We are moving towards installation in the near future.
01/27/25 – HC has installed the meter and transmitter. ThermalTech is coordinating the final inspection with MSD.
02/26/25 – Meter has been installed and approved. We will check water bills to see when it shows up on the GCWW bill.
03/25/25 – Sewer deduct meter not on water bill yet.
04/23/25 – March water bill has both sewer deduct meters logged on the bill but the irrigation meter has no usage usage yet. This project is ready to archive.
05/28/25 – Archived.
2020 – Sewer Deduct Meter Read More »
PM: John Nester, Fateme Shahiyan
04/26/24 – THP provided SOSS Hamilton County.
05/09/24 – County approved SOSS.
05/24/24 – THP provided review documents.
05/28/24 – County provided comments to review documents.
05/31/24 – THP provided Economic inclusion work sheet.
06/04/24 – Economic inclusion package returned to THP.
06/07/24 – THP issued bid documents.
06/20/24 – Prebid meeting occurred.
06/21/24 – Addendum no. 1 issued.
06/26/24 – Bid opening scheduled for July 23, 2024.
07/23/24 – The County received one bid from BCR. Base Bid was 8% over the project opinion of probable cost.
07/24/24 – Department of Economic Inclusion noted the bid was responsive.
07/25/24 – THP and the County to review the bid.
08/15/24 – THP published bid summary letter, recommending BCR.
09/26/24 – Earlier, County sent contract to BCR for execution.
10/04/24 – Contract executed and published.
10/15/24 – Preconstruction meeting occurred.
10/21/24 – County published rooftop safety tie inspection report.
10/25/24 – BCR published submittals for review by THP.
10/29/24 – THP returned submittals to BCR.
10/25/24 – BCR published submittals for review by THP.
10/29/24 – THP returned submittals to BCR.
11/08/24 – BCR published the SOV for review by THP.
11/19/24 – BCR published their schedule for the project
12/04/24 – BCR sent the Pay App No.1 to THP
12/10/24 – BCR Resubmit the Change order No.1
12/10/24 – BCR sent revised Pay App No.1 to THP and THP approved it.
12/10/24 – BCR completed about 30% of the work including sounding and opening up the lintel areas on the fifth floor and providing temporary flashing over the top of the ledge angle.
01/30/25 – Project status – BCR completing sounding, concrete and masonry repairs on West Elevation of Todd Portune Center. Remaining work is corner of south elevation of the TPC. Due to low temperatures crews moved to the 230 WHT building to complete knock down survey work. Crews will return after work at 230 WHT is complete.
02/24/25 – Project is still on hold and crew are still working on 230 WHT.
03/17/25 – BCR Completed all repairs at TPC. THP did the final site visit and did not observe any problem with repairs.
03/25/25 – THP send the pay app No.4 from BCR, to HC for the final review.
04/23/25 – Project is completed and BCR needs to provide closeout documents.
05/27/25- BCR is working on the closeout documents, and they are planning to provide all documents by end of the week.
06/25/25 – HC requested Change Order #3 (CO#3) for the emergency concrete repair on the north elevation of the Portune Center. BCR has provided CO#3 to HC, and HC is currently working to get it approved. BCR is planning to send the supporting documentation, including the cost breakdown with any applicable markups, to THP and HC by the end of this week.
07/01/25 – Change order #3 approved.
07/14/25 – BCR started work.
07/24/25 – THP visited the site and reviewed the work. Field report published.
07/25/25 – BCR finished knock down work.
08/26/25- BCR provided the last pay app for the emergency repair to THP for review. BCR planning on complete the closeout documents and send it to the county by end of the next week.
09/15/25- BCR dropped off the closeout documents to HC/Matt Butz. The electronic documents, notarized warranties were missing. BCR planning to provide all documents by end of this week.
12/11/25 – All project closeout sent to County and final pay application approved.
02/26/26 – Ready to archive.
230 – WHT & TPC Critical Façade Repairs [TPC Work Only] (F003) Read More »
PM – John Nester, Sam Hofmann
05/30/24 – Kickoff meeting held. Several options are ready for review. Meeting to be scheduled for mid June.
06/27/24 – Meeting held with Paula to go through options. More direction given. A revised plan is in progress.
07/25/24 – Updated options have been sent to Paula. Waiting on her response to finalize plans. Estimate complete and submitted.
08/29/24 – No Update.
09/26/24 – No Update.
10/31/24 – No Update. OK to Archive.
TPC – Auditors Breakroom Renovation Read More »
PM: John Nester, Mike Barth
05/29/24 – HCFD requests SOSS from TEI on 5/29/24.
06/26/24 – TEI submits SOSS. Project pending SOSS approval and PO.
07/24/24 – TEI receives signed SOSS and PO. Study in development in conjunction with the JC Study.
08/28/24 – TEI meets with vendors to discuss industry trends and current offerings. Report in development.
09/25/24 – TEI finalizing report to send to HCFD for review.
10/30/24 – TEI submits report for review and comments from HCFD.
12/11/24 – HCFD and TEI meet with HCSO to review draft report. Final report to be submitted.
01/29/25 – Final report to be submitted with the JC report. JC report pending 1 item.
02/26/25 – TEI sends final report. HCFD sends additional final comments. TEI to incorporate and resubmit final report.
04/23/25 – TEI receives budgetary numbers from suppliers for additional features. TEI finalizing report and to submit draft.
05/28/25 – TEI Submits finalized reports to HCFD.
06/25/25 – TEI submits final report. HCFD requests cost for engineering (not an official SOSS at this time)
07/30/25 – DEG submits estimated SOSS cost to HCFD for review.
08/27/25 – No updates. County has all closeout documents. Ready to Archive. Put study into Archive Room.
CH – JAX Door Control System PLC Study 2024 Read More »
PM: John Nester, Mike Barth
05/29/24 – TEI submits SOSS for approval. Project pending PO and Signed SOSS.
06/26/24 – TEI receives approved SOSS and PO. Documents in Process. Trades will be doing this work, TE to send final dwgs in for review. It will permitted through City of Blue Ash.
07/24/24 – TEI sends drawings to HCFD for review.
08/28/24 – TEI obtains permit from Blue Ash. TEI delivers permit and approved drawings to Keith Otis. Electricians state that material procurement stage – once materials arrive – will get installed.
09/25/24 – HamCo Trades Electricians to notify TEI when they are ready for inspections.
10/30/24 – TEI coordinates breaker types with trades. TEI to arrange inspections when notified by trades.
12/11/24 – Inspections pending call from trades re completed installation.
01/29/25 – Inspections pending call from trades re completed installation.
02/26/25 – Trades calls TEI and are ready for inspections. TEI to schedule with trades and Blue Ash.
09/24/25 – DEG and trades meet with blue ash and has approved inspection. Blue ash did not have records for final inspections for re-circuiting work. that inspection is scheduled for 10/01
10/29/25 – Revised documents in plan review stage.
12/10/25 – Permit applied for – pending approval for final inspection.
01/28/26 – DEG follow up with the City of Blue Ash.
02/25/26 – DEG and trades gets final inspections. All inspections and work passed with City of Blue Ash. Project complete.
02/26/26 – Give County as-built drawings and archive the project.
Crime Lab – Emergency Power System Upgrades 2024 Read More »
PM: Matt Butz, Mike Barth
05/29/24 – TEI submits SOSS for approval. Project pending PO and Signed SOSS.
06/26/24 – TEI receives signed SOSS and PO for project. Study initiated and TEI is prepared to schedule meetings with the correct stake holders at the HCSO.
07/24/24 – TEI and HCFD discuss scheduling kick off meeting the week of 08/05.
08/28/24 – TEI meets with system suppliers to discuss latest industry trends and current offerings. Report is in development.
09/25/24 – TEI reviewing report and will send to HCFD for comments.
10/30/24 – TEI sends report to HCFD for review and comments.
12/11/24 – HCFD and TEI meet with HCSO to review report. HCSO asks if the Telecor cell intercom system is compatible with a new PLC. The PLC system will accommodate, TEI to investigate any potential modifications to the Telecor system that would be required and the potential cost implications, then the report will be finalized.
01/29/25 – TEI contacts ICS multiple times to get cost schedule implications. ICS not responding. Per Matt – we will issue the final report after 02/01/25 if no response from ICS by then.
02/26/25 – TEI submits final report to HCFD. HCFD sends additional comments to TEI to incorporate. TEI to resubmit upon completion of updates.
03/26/25 – TEI working with suppliers to get budget numbers for alternatives that were included.
04/23/25 – TEI receives budgetary numbers on 04/21/25 from suppliers. Final updates to be completed and returned to HCFD.
05/28/25 – TEI submits finalized reports to HCFD.
06/25/25 – Finalized reports are submitted. HCFD asks for an approx cost for engineering. Not an official SOSS at this point.
07/30/25 – DEG submits estimated design engineering costs to HCFD.
08/27/25 – No updates.
09/24/25 – No updates.
09/25/25 – OK to Archive.
JC – PLC System Replacement SD & Estimate Read More »
PK = Matt Butz, Mike Barth, Eryn Thamann
05/29/24 – TEI submits SOSS for approval. Project pending PO and signed SOSS.
06/05/24 – Elevar submits SOSS for approval. Project pending PO and signed SOSS.
06/26/24 – Project pending PO and signed SOSS.
07/24/24 – TEI, Elevar and HCFD meet on site with end user. Scope changed and SOSS’s to be resubmitted for new revised scope.
08/27/24 – Elevar submitted new SOSS on 07/26 and awaiting approval.
08/28/24 – TEI receives signed SOSS and PO.
09/24/24 – Elevar scheduled a design kick off meeting for 10/01.
10/30/24 – Concepts provided to Probate for review.
12/09/24 – Finalizing concepts this week.
01/27/25 – ThermalTech awaiting schedule from HC/Elevar, HVAC SD level completed. In CD phase with 75% review in next few weeks. Electrical to finalize field confirmation after the partner meeting on 01/30/25.
02/25/25 – 75% review set sent to Probate for review and schedule of onsite meeting. Elevar still owes additional SOSS for lift removal/office add.
03/26/25 – Team met with Probate and has a few revisions. Still need finishes from HCFD. Elevar still owes additional SOSS for lift removal/office.
04/23/25 – Team is awaiting approval of lift/office SOSS to complete CDs.
05/28/25 – Progressing with CD drawings while waiting on final finishes approval.
06/26/25 – CD set was reviewed Probate and approved. Final finishes and systems furniture selected. Waiting for Probate to approved final SOSS for lift removal and additional office at which time they will be added to the drawings.
07/31/25 – Probate set to issue PO for additional work last wee/this week. Elevar to coordinate additional work and provide backgrounds. Need final approval for bidding from HCFD.
08/05/25 – THP received project authorization and signed agreement.
08/22/25 – THP – Elevar, County and THP reviewed field conditions for infill project.
08/28/25 – Additional SOSS approved and THP made site visit to field verify existing lift. Project will be ready to start HC review/bidding prep after this final scope is completed.
09/08/25 – THP issued infill repair detail for review.
09/25/25 – Drawings 95% complete and likely ready for a final review. ROM cost estimate sent to Probate for review.
10/21/25 – THP issued structural bid documents for project package.
10/30/25 – Project out to bid as of 10/22. Pre-bid mtg scheduled with team for 11/05.
12/11/25 – Post-bid vetting meeting scheduled for Alpha on 12/10 with Triton as next lowest.
01/29/26 – Permit/revisions applied for at City. Waiting on final contracts thru Purchasing.
02/26/26 – Contract awarded to Alpha on 02/19. Elevar to schedule construction kick-off mtg.
03/26/26 – Elevar to schedule construction kick-off mtg after Alpha provides construction schedule; expect this soon. HCFD to award special inspections SOSS.
04/30/26 – Construction kick-off meeting scheduled for end of May.
05/28/26 – Construction kickoff mtg occurred 05/27. Eryn to issue mtg mins and setup recurring progress mtgs. Construction to start June 1.
06/25/26 – Construction ongoing.
07/30/26 – Construction ongoing. Approx. carpet delivery is Aug 4. Phase 1 is waiting on carpet install prior to shifting to Phase 2.
08/27/26 – Construction ongoing in phase 2. Working on HVAC duct issue.
09/24/26 – Punch list for Ph. 2 occurred and contractor moved to Ph. 3.
10/29/26 – Approx. 2 weeks from Phase 3 completion. Furniture move is scheduled for 10/28. Closeouts will also remain.
230 – 10th Floor Marriage License Reno 2024 Read More »
PM Watts, Murphy, Cannon, Millar, Barth, Thomas, Thamann
04/25/24 – Project module is open for 2025 projects.
06/27/24 – Murphy has assigned estimate leaders on each estimate, sent to all partners for approval.
06/27/24 – BW suggested that we meet with every requester and get their input on the submitted request. And we coordinate when the walk through will happen. Architectural they always needs to meet with county people. Budgets due on 7/12/24. This project is due end of August.
07/22/24 – Elevar – SOSSs submitted for CIP, New, and Resubmitted 2025 projects.
07/24/24 – ThermalTech – our approved SOSS was received last week, we’ve started the work, our electrical resubmittals are done, Champlin and Elevar are setting up field trips.
07/25/24 – Champlin submitted SOSS and has all the new projects fieldwork scheduled for last week of July and first week of August.
08/27/24 – Elevar: SOSSs approved and estimates ongoing.
08/28/24 – ThermalTech: Almost all field is compete. NEW and CIP estimates are progressing nicely, much of the data has already been entered. RESUBMITTED projects have been updated for Electrical Scope, Mechanical, Plumbing and Fire Scope are being update and reviewed this week. Mike Barth and Terry Cannon should begin QC reviews first of September. MBE currently entering all estimates that TTE has completed and turned over for entry. For New Estimates Completed 62% Elec, 31% Mech, 29% Plumbing, 28% Ready for Final Review.
09/24/24 – ThermalTech is complete with all entries. TTC and MCB are currently reviewing the data entered for the QC process except that TTC has to enter the 800 controls estimates manually. Elevar is complete with all entries.
10/29/24 – ThermalTech: all ThermalTech estimates are entered.
12/12/24 – ThermalTech has printed PDF binder files for its estimates.
12/31/24 – Ready to Archive.
2025 Project Cost Estimates Read More »
PM: Rycca, Terry Cannon
04/24/24 – Kleingers sent preliminary survey to County and ThermalTech for approval. Two items were tagged for review from the survey, the creek crossing and box culvert.
04/25/24 – SOSS approval going in front of the Board on May 2. BW needs all the TE paperwork by Monday for this work.
05/17/24 – Bert checked on status of submission to GCWW for water permit. TEI working on fire calculations for the load. We have the city water demand at 90 GPM.
05/28/24 – Colerain Township asked for the cost to extend the water line past the property. TEI and Kleingers will have to discuss additional cost.
05/29/24 – TEI to have preliminary application ready to discuss at Stated meeting this Thursday and completed by Friday.
06/26/24 – Preliminary application submitted this month. HC asked us to submit a SFHA permit too, which Kleingers is taking care of.
07/24/24 – Kleingers submitted both applications. TTE will check on progress with Doug.
08/28/24 – Update meeting scheduled for next week with County and City.
09/24/24 – Kleingers is currently working updating the drawings and its going well. It’s pretty straight forward except for the creek crossing, that might be tricky.
10/30/24 – Kleingers, ThermalTech and GCWW met onsite two weeks ago. TTE and Kleingers group sent out updates from meeting. The plan is agreed upon, Kleingers continue to design the routing and scope for new water line. GCWW says they will probably run a 12″ main in the street for current and future growth.
12/12/24 – Kleingers spoke with Bert this week and received the okay to proceed with the final construction drawings creating for the new water line.
01/28/25 – Kleingers sent an update to Bert. TTE sent review comments to Kleingers. Doug inquired if there was any progress on easement around bridge for new line.
02/26/25 – We had a progress meeting with GCWW, HamCo, Kleingers, adn ThermalTech and reviewed progress. TKG will follow up on easements and permitting. ThermalTech send load calcs to GCWW for use in their model.
02/27/25 – BW already made call on easements but believes the Engineer Office probably wants a Right of Way enlarge so the utilities can get back to maintain utility in the future. The routing of the line from the tap to down the road may change to meet GCWW needs for taps. TTC to check back with Doug on additional updates.
03/25/25 – Kleingers submitted an updated set of review drawings this week for review.
04/23/25 – Project in for review. Some emails are going around for coordination right now.
05/28/25 – Biweekly design meetings are now being held on Friday afternoons. ThermalTech hosting the meetings on Teams. Current work includes final approvals form GCWW, communication with Colerain Fire Dept about hydrant locations and finalizing HC Engineers Office comments. The Right of Way for the work around the bridge is in HC hands. Kleingers review drawings are up to date and distributed.
06/25/25 – Kleingers sent review drawings to the team yesterday. TTC to review and work on branch application. GCWW said the first shipment of piping will be delivered Friday.
07/11/25 – Design meeting to review County engineer comments
07/18/25 – Design meeting to review comments with GCWW. Kleingers to update and send new drawings for GCWW review to everyone.
07/30/25 – Next meeting is August 1 to comment on revised drawing sets and proposed budget. Bert sent easement requirements to Kleingers for their help with.
08/01/25 – Design Mtg #8 was held. The schedule was coordinated with the latest timeline. Kleingers will pick up latest markups and update the BOM on the dwgs for CWW. We are sending final review set to every for review the week of August 18. The easement work is underway.
08/04/25 – Kleingers sent latest drawings and materials list for final approvals.
08/22/25 – Final review project manual and drawings submitted to Bert Watts for approval. Budget and cost estimate finalized and coordinated with Bert. Comments sent to Kleingers by TTC for updates into final bid package. KEG working on easement with HCEO. Mylars sent to City for approval. New budget around $1.14M and we will publish at one million.
09/24/25 – Final review with City, GCWW and HamCo held on 9/12. We must wait until city/county agreement is signed and funds approved for bidding then TEI can publish the project.
10/29/25 – Kleingers has paid the OEPA bill and sent the City receipt. The project is nearly ready to bid but we await the City/County agreement to move forward with bidding. All the documents are ready to go minus final review and assembly.
12/12/25 – City/County agreement went to Board for Approval on 12/11, assuming that is approved bidding for RSC City Water Line will be in January.
01/21/26 – Received comments back from Bert Watts indicating that the City and County would have final comments back to DEG by Feb 6. Issuance pushed back to Feb 11 and bid date extended.
02/18/26 – Project Issued for Bid to County Purchasing.
02/25/26 – Prebid scheduled for March 4 on site. Bid opening schedule for April 1.
03/25/26 – The project is out for bid. Addendum 1 & Addendum 2 have been issued. Bids open April 1.
04/22/26 – Bids extended to April 22. Bids were opened and read. Four awardable bids.
04/24/26 – The low bidder has pulled his bid because they did not include the full paving requirements.
04/27/26 – The pre-award meeting is scheduled with the next low bidder QCM on Friday at 1:00 PM.
05/27/26 – QCM was recommended for the job. Their contract is in for review with the prosecutor office.
06/25/26 – Contract sent to QCM and signed. DEG met with QCM on SOV and schedule on 6/24. QCM to send SOV in for review and they are okay with schedule extension and August 1 start. They would like to have a pre-const ASAP.
07/30/26 – Early Pre Const and Pre Const meeting held, notes distributed. Next meeting August 4. QCM acquired ROW permit, survey complete, and had begun marking and cutting pavement.
08/26/26 – Const Mtg #1 & #2 held on site. QCM making progress to about 1200 LF of piping installed. FH 13 installed. 50 sticks of piping missing but we’ve tracked it down to a missing shipment. US Pipe working to provide missing lot to the project site for use. Payapp #1 received and approved.
09/23/26 – Payapp #2 approved and submitted. Next Const Mtg is next Tuesday at 8AM not 9AM. QCM working on CO cost for hydrant and culvert, we will have something by the end of the week. Things are going well.
10/19/26 – Project team met on site to review landslide condition at Station 4 where the water line goes down hill to creek. It was decided to bring Terracon out to review existing road conditions.
10/22/26 – Project team met Terracon on site to review existing conditions. Facilities, GCWW, Terracon, QCM, DEG and Kleingers discussed alternate routes and proposed solutions. GCWW is leaning toward keeping the line where design and shoring up the hillside and sharing that cost with HCEO. Facilities and HCEO has afternoon meeting to discuss next steps. Afternoon meeting reviewed original design and field conditions with HCEO, Facilities and DEG. Kleingers not at afternoon meeting. It was decided to do more investigation, look for previous soil boring and to reconvene with another HCEO and Facility meeting on 10/30/26 for updates.
10/26/26 – HCEO working on reviewing existing field conditions at and around original water line path so we can keep water line in original spot. Terracon submitted boring report to Facilities from 1970’s for this area. This report was shared with the project team. Follow up meeting on Friday.
RSC – City Water Main Extension Read More »
PM: Matt Butz, Sam Hofmann
04/25/24 – Project update at Partner Meeting
5/29/24 – Field verification confirmed. CDs in progress.
06/27/24 – Final floor plan given to Matt for confirmation of scope from sheriffs.
07/25/24 – Bid set in progress. scheduled for owner review on 8/9.
08/29/24 – Owner review set submitted. Project to be out to bid in next couple weeks.
09/26/24 – Project is out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Only bid received was non responsive. Project is back out to bid today.
12/12/24 – Bid opening today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future. Permit to be submitted in near future.
2/27/25 – Contract finalized. Kick off to be scheduled in near future.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals returned. Change order #1 processed. Mobilization to be scheduled.
05/29/25 – Project scheduled to begin 6/30.
06/26/25 – Start date delayed due to hollow metal frame manufacturer issue.
07/31/25 – All issues solved. Waiting on Alpha to schedule mobilization.
08/28/25 – Waiting on confirmation for glazing ship date. Alpha has reached out numerous times to McAndrews and has not gotten a firm response.
09/25/25 – Glazing will be delivered by end of november. Alpha will mobilize next week and install temporary glazing until the BR rated glazing comes in. Frames were delivered in one single piece which are too large to fit into any elevator. Frames will be cut in half in the field and welded back together once in place.
10/30/25 – Alpha’s mason walked out on the job. A couple masons reviewed the project before they settled on one. Electrical work is complete. Alpha is convinced that the mid November deadline will still be met.
12/11/25 – Punch walk through tenatively scheduled for week of 12/22. Mason work is almost complete.
01/28/26 – Back punch complete. Waiting on closeouts.
02/26/26 – Waiting on closeouts.
03/26/26 – Closeout items missing sent to Alpha. Awaiting final submission.
04/30/26 – Waiting on hard copies.
05/28/26 – No Update.
06/25/26 – Hard copies delivered. Final pay app approved.
JC – CARE Pod Counseling Rooms Read More »
PM: Matt Butz, Sam Hoffman, Mike Barth
04/25/24 – Champlin has submitted SOSS, ThermalTech submitted SOSS recently.
05/30/24 – SOSS returned. Project kickoff to be scheduled in near future. BW said that this project on the fast track due to a recent incident in the parking lot.06/27/24 – Kickoff to be scheduled.
07/25/24 – Meeting held on site with County, Champlin, and several judges. Champlin is investigating fencing options and guard booth options for review. Plan will be modified based on comments in the field.
08/12/24 – THP completed a cursory field measurements for review of the proposed fencing.
08/12/24 – THP sent proposal to Champlin for review.
08/27/24 – THP sent SOSS to County for review.
08/29/24 – THP working on design with Champlin.
08/29/24 – Second meeting held for more investigation. THP found that additional structure will be needed for fence and guard booth.
09/25/24 – THP issued bid documents 9/20/24.
10/31/24 – Project is out to bid. Opening on 11/8.
01/30/25 – Tumlin was awarded the bid. Kickoff held. Permit submitted 1/29. Pending zoning and historical society approval. Submittals incoming.
02/27/25 – Submittals in progress. Tentative schedule received. Rejection received from the historical society.
03/27/25 – Submittals in progress. Zoning hearing scheduled for 4/2 for historical variance.
04/24/25 – Historical approval provided given some aesthetic changes to the project. Tumlin to provide pricing on the changes.
05/29/25 – Working with guard booth manufacturer to meet energy code requirements.
06/20/25 – THP submitted Bulletin #1. This covers the revisions that resulted from historic review board comments.
06/25/25 – THP received preliminary pricing from KT Holden for resurfacing lots: 250k.
07/31/25 – County approved moving forward with the Resurfacing project.
08/26/25 – THP modified the footing design to accommodate a continues concrete curb. THP preparing final sketch to be published on 8/30 with Bulletin No. 4.
09/24/25 – THP issued bulletin #4 on 8/29/25 to add grade beam for field conditions and new parking lot resurfacing work. Project in CA
10/30/25 – Grade beams installation onging. Guard booth will be lowered into place this weekend. Progress continues.
01/28/26 – Steel for door installed. Work ongoing.
02/26/26 – Cold formed steel going up in the next couple weeks. Fence material delivered. Phase 2 is pushed back slightly to align work.
03/26/26 – Phase 1 nearly complete. Cladding structure to begin weather dependent. Phase 1 fence installed. Phase 2 tentative date is 4/13.
04/30/26 – Phase 1 complete this week. Following for punch and commissioning. Phase 2 to begin 5/11. Parking on e court street and bus stop coordinated with city to prep for phase 2. Rycca, Mike and Derrick met onsite for security plants. SOSS incoming.
05/28/26 – SOSS for security plant beds submitted. Sheriffs have solved their booth connection issue and kicked off phase 2.
06/25/26 – Phase 2 to switch over mid July. Doors and booth to be tested to ensure seamless transition.
07/30/26 – Phase 2 has begun. Demo exposed some underground conditions that are being resolved. Phase 1 issues have been worked out, including new controls after being struck by lightning.
08/28/26 – Issues discovered below grade have been solved. Grade beams almost complete. Steel has been erected.
10/29/26 – Finishing fence this week. Programming second door. Ready for turn over next week.
CH – Parking Lot Security Read More »
PM: Matt Butz, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Field verification complete. Project in progress. ThermalTech has been onsite and updated mechanical drawings for the potential future pans. Sam to setup kickoff project for this job.
06/27/24 – Kickoff to be scheduled in near future. BW asked to add the North Bldg Lobby to be added as an Alternate to this job, lower ceilings etc.
07/25/24 – Meeting held to discuss scope. Field visit to North building will take place soon. Bid set will be ready for owner review by end of August.
08/29/24 – Owner review set submitted. Project will be issued for bid in the next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 10/1.
10/31/24 – Triton is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project is in contract phase.
01/30/25 – Contract is still in process. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract finalized. Kickoff to be scheduled in near future.
03/27/25 – Kickoff held. Submittals in progress.
04/24/25 – Submittals still in progress.
05/29/25 – No update.
06/26/25 – No Update.
07/31/25 – Submittals returned. Triton to schedule mobilization.
08/28/25 – Pre-mobilization meeting to be scheduled. Duration schedule received.
09/25/25 – Background checks approved. Triton mobilized this week. Demo to begin next week.
10/30/25 – Demo complete in both buildings. Installation has started.
12/11/25 – Plumbing and drain pan rework saved cost and simplified the system. Ceiling grid and pads to begin in North Lobby next week.
01/25/26 – Diffuser RFI answered earlier this month, should be an easy install. DEG reminded the county that they were working on Geiler replacing bad p-traps at ceiling before new ceilings are going back in. Fire dampers accessible only through this ceiling should be getting done by NKYHC (see Tony).
01/28/26 – North Building insulation tested for asbestos and came back negative. Triton providing pricing for insulation and mastic removal.
02/26/26 – CO#1 approved to remove insulation and mastic. Work is ongoing. Scheduled to be complete March 5th. Fire damper work is complete. Plumbing repairs being finalized. Fire alarm worker can use Triton lift to facilitate progress.
03/26/26 – Ceiling installation ongoing. CO Trap work to begin next week. Project tentatively to be complete mid april.
04/30/26 – Electric sub never got plan review approval. Issue has been resolved and inspections can be scheduled. Once inspections are passed, padding out ceilings will be final step.
05/28/26 – Final inspection passed. OKI to be on site for pad installation this week. Punch to be scheduled week of 6/8.
06/25/26 – Punch complete and final work to be complete this week.
07/30/26 – Punch work complete. Closeouts ongoing.
08/28/26 – Back punch complete. Closeouts received.
10/29/26 – No Update.
JC – Lobby Ceiling Replacements Read More »
PM: John Nester, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Field verification complete. work in progress.
06/27/24 – CDs in progress.
07/25/24 – No Update.
08/29/24 – Project will be issued for bid in next couple of weeks. Send to JN for review including the base bid and three alternates (bullet glass).
09/26/24 – Project is out to bid. Pre-bid scheduled for 9/30.
10/31/24 – No bids received. Project is back out today.
01/30/25 – Alpha was awarded the bid. Kickoff to be scheduled in near future.
2/27/25 – Contracts finalized. Kick off to be scheduled.
03/27/25 – Kickoff held. Submittals to be submitted.
04/24/25 – Submittals in progress.
05/29/25 – Pricing for frosted glazing received. We need to decide if spandrel glazing is remaining in the project.
06/26/25 – Change order cost to remove spandrel glazing and add frosted glazing to project received. Jesse to confirm.
07/31/25 – Changes confirmed. Scope will potentially be added to make use of deduct funds.
08/28/25 – Provided confirmation of scope change and permission to start. An offical cange order will be settled at the end of the project after any additional scope is added.
09/25/25 – No update
10/30/25 – Work is complete. Scaffolding removal and final cleaning to take place next week.
12/11/25 – Scaffolding removed and punch items addressed. Closeouts in review.
01/28/26 – County to provide scope for additional change order work.
02/26/26 – Field visit to determine additional work attended by Sam and Rycca. Bulletin #1 to be posted shortly.
03/26/26 – Bulletin #1 sent to Alpha to include glazing replacements on floors 5-10 and window cleaning of first floor windows.
04/30/26 – Alpha provided pricing. Waiting on clarification on pricing.
05/28/26 – No update.
06/25/26 – Change order approved. Schedule to be sent after submittals are approved.
07/30/26 – No firm delivery date yet.
08/28/26 – Tentative delivery date of 9/14
10/29/26 – Glazing installed. Windows washed this weekend.
TPC – Atrium Glass Replacement Read More »
PM: John Nester, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in. We need the PO by mid-November and the project must be complete by 11/1/25, they are moving out of the lease space.
05/30/24 – Kickoff held with Thermaltech, County, Reentry and Champlin. Some minor redesign will be explored.
06/27/24 – New options will be provided to Trina this week.
07/25/24 – New options presented. Final plan confirmed. CDs in progress. Owner review scheduled for 8/14.
08/29/24 – Final owner review meeting held. Project will be issued for bid in next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 9/30.
10/31/24 – Triton is low bidder. Bid vet to be scheduled in near future.
12/12/24 – Project is in contract phase.
01/30/25 – Contract still in process. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract finalized. Kick off to be scheduled.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Submittals in progress. Kickoff meeting scheduled for next Wednesday.
06/26/25 – Demo for Phase 1 in progress.
07/31/25 – Demo complete for Phase 1. Re-entry to move to 4th floor space to give Triton full access to project area.
08/28/25 – Phase 2 demo is complete. Triton met with County and Champlin to discuss change orders. Adjusted COs provided. HC reported today that they would like to Triton to be completed in October 2025.
09/25/25 – Project on schedule to finish end of October. All change orders settled. Work continues.
10/30/25 – Project nearing completion. Furniture delivered to site. Triton will most likely get TCO approval early next week. Fire sprinklers are being added in a couple of pockets. We are keeping the window washing sprinklers heads as-is but Preferred will have to update their permit drawings after the TCO is approved.
12/11/25 – Fire protection work took longer than expected. Inspection to be scheduled for next week. Final CO expected before Christmas.
01/28/26 – Inspector will not provide CO until the exterior stair door is fixed. Trades is fixing the door starting on 2/2. Bulletin 2 for window shades and power issued and waiting pricing.
02/26/26 – Bulletin 1 pricing received. Work outstanding.
03/26/26 – Bulletin #2 pricing has been received and approved. Triton to begin electrical work.
04/30/26 – Blinds installation outstanding. All other work complete.
05/28/26 – Closeouts received and returned. Triton to submit outstanding items.
06/25/26 – No update.
07/30/26 – Hardcopies to be delivered to County.
08/28/26 – Hardcopies delivered. Access control programming complete.
10/29/26 – No update.
TPC – Reentry Expansion Read More »
PM: Megan, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Initial field verification complete. We will need a second trip to take dimensions.
06/27/24 – Second trip complete. CDs in progress.
07/25/24 – No Update.
08/29/24 – Owner review set submitted. Project will be issued for bid in next couple of weeks.
09/26/24 – Project out to bid. Pre-bid scheduled for 9/30. ITB sent to multiple stained glass vendors.
10/31/24 – Bids received. One vendor had a bond issue, one bidder did not fill out XBE paperwork properly. Purchasing to provide direction.
12/12/24 – Project is in contract phase.
01/30/25 – Contract is still in progress. Kickoff to be scheduled in near future.
02/27/25 – Contract Finalized. Kickoff to be scheduled.
03/27/25 – Kickoff held. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Phase 1 windows are removed and taken back to the shop for refurbishment.
06/26/25 – Progress meeting at the shop scheduled for mid July.
07/31/25 – Windows still in progress.
08/28/25 – Phase 1 windows to be reinstalled in september. Phase 2 windows will be removed during the same time. Tentive completion date of end of october.
09/25/25 – Reinstallation of phase 1 began this week. Removal of phase 2 in progress.
10/30/25 – All storm windows have been installed. Stain glass installation of phase 1 to begin shortly. Phase 2 to be complete by end of november. County to request change order related to the plaster repair at window jambs.
12/11/25 – One section of stained glass installed. Second half of windows are still under repair. Background checks for installers have been over 90 days. County allowed stain glass to be reinstalled all at once when phase 2 windows are ready.
01/28/26 – No update.
02/26/26 – No update.
03/26/26 – Breilmeyer to mobilize this week. Installing half of glass and taking the other half to their shop.
04/30/26 – Half of stained glass is installed. Tentative completion at end of may.
05/28/26 – Breilmeyer to mobilize 6/8 to install the second half of the glass.
06/25/26 – Second half install ongoing.
08/28/26 – Installation complete. 1 punch item outstanding.
09/24/26 – No Update.
10/29/26 – Punch item complete. closeouts outstanding
CH – Law Library Stained Glass Window Repair Read More »
PM: Matt Butz, Sam Hofmann
04/25/24 – SOSS returned. Project to be scheduled in.
05/30/24 – Project to start once first phase is complete.
06/27/24 – Field verification completed. Drawings in progress.
07/25/24 – No Update.
08/29/24 – Owner review submitted. Investigating one more option for interior vestibule doors. Project will be ready to bid in next couple of weeks.
09/26/24 – Project will go out to bid next week.
10/31/24 – Project is out to bid. Bid opening is 11/8.
12/12/24 – No bids received. Project was put back out to bid and opens on 12/19. Olek intends on bidding.
01/30/25 – Olek was awarded the bid. Contract is still in progress. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff held. Submittals in progress.
04/24/25 – Doors have been removed and refurbishment is in progress.
05/29/25 – No Update.
06/26/25 – No Update.
07/31/25 – Call to discuss potential additional scope scheduled. Doors still in progress.
08/28/25 – Olek to reinstall riot doors in mid september. Electrical work to be complete during this visit. Any items that need to be taken to their shop will be removed and brought back after refurbishment.
09/25/25 – Olek currently onsite prepping for installtion of riot doors and interior doors.
10/30/25 – Door hardware supply issues pushed installation of riot doors back.
12/11/25 – Olek has been back on site. Ran into issues with the thresholds and pivots. Olek will be back mid january to continue work.
01/28/26 – Olek did not come back on site as first promised. Olek not responsive or timely. Champlin gave them a notice to be on site 1/19 or they would be referred to the prosecuter. Olek agreed they were in breach of contract but would not be on site until 1/26. The snow storm pushed that visit back until acceptable weather. County to provide prosecuter with letter.
02/26/26 – Olek to be back on site on March 9th to complete all remaining work.
04/30/26 – All work is complete. Closeouts are nearing completion.
05/28/26 – Closeouts outstanding. DK to complete a couple punch items.
06/25/26 – Close outs reviewed and several items still needed.
07/30/26 – Final punch item to be complete by Olek in August.
08/28/26 – Olek on site to complete punch work.
09/24/26 – Punch work complete. Olek sent official request for multiple change orders. Champlin has recommended denying request.
10/29/26 – Olek sent official request citing the contract. Champlin to provide official response.
CH – North and South Riot Door Refurbishment Read More »
PM = Matt, Barth
04/24/24 – TEI submits SOSS for approval.
05/29/24 – Project Pending SOSS approval.
06/26/24 – TEI receives signed SOSS and PO. TEI has conversed with building manager re existing system and electrical needs.
07/24/24 – Project in progress.
08/28/24 – TEI to meet with building manager to discuss updated model and options.
09/25/24 – TEI meets on site with building manage and Matt Butz. A list of possible upgrades developed. TEI sends schematic dwg and costs to HCFD for review and direction.
10/30/24 – TEI issues project for bidding. Prebid meeting scheduled for 11/12/24 at 11:00 AM.
12/11/24 – Bids open at 11:00 AM on 12/12/24.
01/29/25 – No bids received. HCFD to advise if re-bid funds are available.
02/26/25 – No updates on rebid funding.
03/26/25 – No updates on rebid funding.
04/23/25 – No updates on rebid funding.
05/28/25 – No updates
06/25/25 – No updates
07/30/25 – No updates on rebid funding.
08/27/25 – No updates on rebid funding
09/24/25 – Project pushed to 2026 project.
01/28/26 – DEG to submit SOSS for re-package and rebid for 2026 project.
02/25/26 – DEG submits SOSS for approval.
03/25/26 – Project pending approval of SOSS
04/29/26 – DEG receives signed SOSS and PO. Reaching out to bldg mgr to confirm scope.
05/27/26 – DEG meets with Ian Zellner – confirms scope. Finalizing drawings and OPC for HCFD review.
06/23/26 – DEG to submit 100% review set to HCFD by end of June.
07/29/26 – Per HCFD – Project on HOLD until further notice.
08/26/26 – DEG to update labels and apply then close out the project.
09/23/26 – No updates
10/28/26 – All labels have been applied to the gear on site. Project complete.
SPHQ – Arc Flash Remediation 2024 Read More »
PM: Matt/Trades, Mike Barth
04/24/24 – TEI receives signed SOSS and PO.
05/29/24 – TEI develops Clifton (#81 W Nixon) drawings and submits plans to IBI for permitting. We will notify county trades once permit is approved.
06/26/24 – TEI secures permit for #81 West Nixon. HCFD to notify when the work is completed and ready for inspections.
07/24/24 – No updates this month.
08/28/24 – No new work this month.
09/25/24 – IBI inspection passes and EMA and Duke to connect power. Work on Siren #81 complete.
10/30/24 – No updates this month.
12/11/24 – Ben (EMA) sends Alex GPS coordinates for siren that needs to be permitted. TEI working on the permit documents.
01/29/25 – No Updates this month.
02/26/25 – No updates this month.
03/26/25 – No updates this month.
04/23/25 – Wes and Ben (EMA) coordinate location. Upon approval of location and connections by Duke, permit drawings will be issued.
05/28/25 – TEI finalizes permit drawings and submits to IBI for plan review.
06/25/25 – Plan review passed. Permit applied for on line. Ready to schedule work with trades.
07/30/25 – Permit was delivered to HCFD (Electricians). Inspection pending installation. DEG will call for inspection when notified that the siren has been installed by trades.
08/27/25 – IBI inspection occurred and passed on 08/27/25.
09/24/25 – No updates.
10/29/25 – No updates this month.
12/10/25 – No updates this month. Pending issues with existing poles. etc.
01/28/26 – No updates this month. Pending issues with existing poles. etc.
02/25/26 – No updates this month. Pending issues with existing poles. etc.
03/25/26 – No updates this month. Pending issues with existing poles. etc.
04/29/26 – No updates this month. Pending issues with existing poles. etc.
06/23/26 – No updates this month. Pending issues with existing poles. etc.
07/29/26 – No updates this month. Pending issues with existing poles. etc.
08/26/26 – EMA reaches out to Wes about possible relocation of pole in Wyoming (Chisholm Park).
09/23/26 – EMA and DEG are working on (2) siren locations for 2026, and (1) for 2027.
10/28/26 – (2) Sirens are in for QC review. Then will be issued for installation.
EMA – Tornado Sirens Gen Services 2024 Read More »
PM: Megan, Mike Barth, Mike Murphy
04/24/24 – TEI receives signed SOSS and PO.
5/29/24 – HCFD, TEI and Judge Jenkins Visits Montgomery County CH to see system in action. Champlin and TEI visit all courtrooms to develop plans and take measurements of existing benches for install locations of equipment.
06/26/24 – Weekly meetings are conducted every Wednesday afternoon. The most current EV equipment has been sent from BIS to the team. TEI has Design documents well developed and will be conducting a final walk thru of each of the courtrooms on 06/27/24 as soon as the docket clears.
07/24/24 – TEI will provide HCFD a final review set on 7/26/24. HCFD will review and get comments back to TEI by 8/2/24. Project to be issued for bidding on 8/7/24.
08/28/24 – Project has been issued for bidding. Prebid meeting was held on 08/23 – (2) bidders attended. Bid opening scheduled for 09/19.
09/25/24 – Received (1) bid from DK, (39% over budget). Rejected the bid, repackaged and re-issued for REBID. Rebid Prebid meeting scheduled for 10/18 and Bid opening on 11/06. TEI reaching out to area ECs by phone and notifying of bid opportunity.
10/30/24 – Final addendum issued on 10/30/24. Bid Opening 11/06/24 at 11:00 AM.
12/11/24 – Bids open. DK low bid. TEI vets the DK bid and sends letter or recommendation to HCFD. project pre-const meeting to occur upon contract approval.
01/29/25 – DK, HCMC, HCFD, BIS and TEI are in the pre-construction/procurement phase of the project. DK to provide project schedule.
02/26/25 – DK, HCFD, BIS, TEI and HCCPC have weekly meeting to update status and tracking.
03/26/25 – Work on CR 580 has started. Next CR’s were discussed at the meeting this week. BIS to ship the next 2 rooms equipment week of 4/10.
04/23/25 – Work continues in CR 580. End of this week DK to be ready for carpet install (HCFD covering carpet install). Floor slab xray scheduled for 04/26/25 (Saturday).
05/28/25 – BIS sends technician to CR 580 today for coordination with DK. All DK field issues/concerns addressed. Field visit to fire up the system on 05/30 at 1:00 PM.
06/25/25 – CR 580 complete, pending training on equipment and demo to other Judges.
07/30/25 – CR 580 training completed. CR 580 in use and DK is now working on CR 320. Tweaks are happening as the systems are being placed into service. Rycca asked if we should order the AV equipment and set it back in the Archive room and they can use them out of the boxes on the sixth floor. Punchlist scheduled for 8/5 at 3PM.
08/27/25 – Punchlist for room 580 completed. DEG issues the Punchlist to DK. Installation of BIS equipment installed this week.
09/24/25 – Finalizing CR320. Moving on to CR 380 next. At const meeting, it was discussed to ship all equipment as soon as ample storage space for 16 more rooms equipment. Arpa funds must all be spent by 12/31/2026.
10/29/25 – Programming installed in Room 320. Work starting in rooms 300 and 380.
12/10/25 – Work continues with CR 300 and 380. Punchlist scheduled for 12/10/25 cancelled due to court session running long.
01/28/26 – Project continues.at the meeting today discussed the next 2 rooms to be worked on (340 and 360). This will finish the CRs on the 3rd floor.
02/25/26 – Project continues. Work on 3rd floor progressing. Speakers swapped out in 580 and sound quality substantially improved. DK brings in “sound expert”, Leo Little form ICS, to evaluate rooms. Leo to provide quotation to DEG for sound engineering services.
03/25/26 – Electrician changes necessitated for the project. DK to update situation ASAP. finishing CR 330 and moving to 360 and 340 next.
04/29/26 – Work continues in Rooms 340 and 360. Walk for 485 and 496 scheduled for 5/5.
05/27/26 – work continues in room 340 and 360. Rooms 485 and 495 are next (waiting on floor boxes to be fabricated). Walking locations on the 5th floor 05/27/26.
06/23/26 – Sound Guy (Leo Little) models room 485 and returns proposed layout with the speakers that were purchased from BIS.
07/29/26 – Sound guy visits room 300, modelling the room. HC directs Leo to only use the bill of materials for the rooms, and to not give recommendations for improved sound quality with equipment not in the original BOM.
08/26/26 – Room 300 sound recommendations installed. Sound quality greatly improved. ICS states that next 2 rooms are scheduled to be sent today.
09/23/26 – Work continues on the installation. ICS completes all room sound models and recommendations. There are 2 rooms (320 and 380) that HCFD sent comments back to ICS for tweaks.
10/28/26 – All sound models received on all rooms. Punchlist walk occurred on 10/26/2026. Work starting on Jenkins CR on Monday 11/02.
CH – Common Pleas AV Upgrades Read More »
PM: Matt Butz, Mike Barth
04/24/24 = TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for HCFD to review.
07/24/2024 – HCFD moves location of NWS to 3rd floor data room. TEI updates the drawings.
08/28/24 – Project pending installation from DK.
10/30/24 – DK installs camera.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Finalizing binders.
06/25/25 – DK, DEG and HCFD to me re final closeout
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
A&D – Exterior Camera Upgrades 2024 Read More »
PM: Matt Butz, Mike Barth
04/24/24 – TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for review from HCFD.
07/24/24 – All HCFD comments picked up on drawings.
08/28/24 – Project pending completion of installation from DK.
10/30/24 – Project completion pending punchlist and closeout documents.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
06/25/25 – DK, DEG and HCFD to meet re final closeout.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
230 – Exterior Camera Upgrades 2024 Read More »
PM: Matt Butz, Mike Barth
04/24/24 – TEI receives signed SOSS and PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to review scope of work and locations for equipment. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – All HCFD comments picked up on drawings.
08/28/24 – project pending Historical society review of proposed mounting hardware and installation by DK.
12/11/24 – Historical Society approves installation. Project pending installation by DK.
01/29/25 – Project installation nearly complete. DK states that there is an Injector issue to resolve and project will be ready for punchlist.
02/26/25 – Project complete pending closeout.
03/26/25 – HCFD and TEI perform and issue punch list. Project pending closeout.
04/23/25 – Project pending closeout docs from DK.
05/28/25 – Pending closeout documents.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
CH – Exterior Camera Upgrades 2024 Read More »
PM: Matt Butz, Mike Barth
04/24/24 – TEI receives signed SOSS ands PO.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – All HCFD comments picked up on drawings.
08/28/24 – Cameras installed last week. TEI and HCFD to schedule punchlist and review of camera views on the system.
10/30/24 – Project completion pending punchlist and closeout documents.
12/11/24 – TEI issues Punchlist. DK sends signed off punchlist to HCFD and TEI. Pending Closeout.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
TPC – First Floor Lobby Cameras Read More »
PM: Matt Butz, Mike Barth
04/24/24 – TEI receives approved SOSS and PO. Kick off meeting occurred on site on 04/23/24.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – Project issued for small, projects bid. Prebid meeting occurred. Addendum #1 to be issued by 07/26/24.
08/28/24 – Bids received on project (2 bids Glenwood and DK), DK apparent low bidder. TEI vets the bid from DK.
09/25/24 – Project in contract phase.
10/30/24 – HCFD, HCSO, HCRM, TEI and contractor meet for pre-construction meeting. Anticipated construction to start 11/11/24
12/11/24 – DK states that the installation of the system in the JAX area is approx 90% complete.
02/26/25 – Project complete pending punchlist and closeout.
03/26/25 – HCFD and TEI perform and issue punch list. Pending closeout.
04/23/25 – Project pending closeout.
05/28/25 – Project pending closeout.
07/31/25 – OK to Archive, send final bill.
CH – JAX Camera Upgrades Read More »
PM: Rycca Thacker, Terry Cannon
04/01/24 – JFS Category created to track JFS General Services work.
04/22/24 – 2024 SOSS submitted.
07/24/24 – SOSS not approved yet.
08/28/24 – No updates.
09/24/24 – No updates.
10/30/24 – No updates.
12/12/24 – ThermalTech working on draft issue in the penthouse with Glen on the Water Heaters.
01/28/25 – A&D draft troubleshooting is a JFS general services.
02/26/25 – OK to archive.
JFS – General Services Read More »
PM: Ted Graham, Mike Barth
03/28/24 – Program started, poster created, training held, policies & procedures entered into the record for all to see 🙂

04/24/24 – Barth is still on the fritz, his doctor extended his convalescence another four weeks. After that, they will probably just remove the foot and replace it with another hand so he can do three times as much work as he normally does. One hand for CAD, one hand for the calculator one hand for a cell phone, his other foot will be used to kick the butt of all the coops at the office.
05/09/24 – Program membership has grown by 100%! Welcome to the program Mr. Ted Graham!

06/18/24 – Welcome to the program, Rycca! This month’s safety topic is monitoring for Overexposure to UV Radiation.

07/24/24 – Hopefully no updates this month 🙂
08/28/24 – No updates to report.
09/24/24 – We have lost the tree, crying, grieving, and bemoaning has ensured.
Barth Safety Prorgram Read More »
PM: John Nester, Mike Barth
02/29/24 – Bradley Bedacht contacted TE for new project. Project added to website.
03/27/24 – HamCo requests SOSS for Study of existing system and requested upgrades.
04/24/24 – TEI submits SOSS. JN and TEI discuss scope and HCFD to confirm total scope.
05/29/24 – TEI and JN to confirm scope.
05/30/24 – This project returned to the Courts for their coverage. We can archive this job.
PM: John Nester, Mike Barth
02/29/24 – Project created for tracking. MCB says we have all we need.
03/27/24 – Project docs to be sent to JN ASAP.
04/24/24 – BW and TEI review ODOT documents and submit what we can. Balance of data required from tenant.
05/29/24 – Project pending data from tenant.
06/26/24 – Project pending data from tenant.
07/24/24 – Project pending data from tenant.
08/28/24 – TEI and HCFD develop a package to send to ODOT for review and commentary including bid documents, project manual and OPC. Package sent to ODOT on 08/28/24.
09/25/24 – Project pending ODOT approval.
10/30/24 – Pending ODOT approval
12/11/24 – No Updates from ODOT.
01/29/25 – No updates from ODOT.
02/26/25 – No Updates from ODOT.
04/23/25 – Received Stage 3 approval from ODOT. HCFD investigating funding gap from the grant and the updated costs. Then notify TEI on next steps.
05/28/25 – Next steps to be coordinated with HCFD.
06/25/25 – TEI sends updated opinion of probable cost to HCFD for county to discuss grant funding/cost differential.
07/30/25 – No Updates
10/29/25 – DEG receives email from HCFD that this project is cancelled. OK to Archive.
Comm Center – EV Charging Project Read More »
PM: Bert Watts, John Millar
02/01/24 – Hamilton County requested an SOSS for roof replacement of Skywalk bridges.
02/29/24 – THP reviewed roof approach with Contractor and roofing manufacturers. THP working on proposal.
03/14/24 – THP issued DD review set of roof replacement with the Skywalk Exterior façade repair.
03/28/24 – THP working on bid package.
04/25/24 – Project combined with F077. THP working on documents.
05/30/24 – THP working on documents and targeting a bid set for June.
07/19/24 – THP issued Bid Documents to the County and Arc.
07/22/24 – Bid Documents Released on Bid Sync.
07/25/24 – Prebid meeting scheduled for July 30th and Bids due September 12th.
07/30/24 – Prebid meeting completed.
08/29/24 – Addendum No. 1 to be published.
08/29/24 – Addendum No. 1 published.
09/09/24 – Addendum No. 2 published.
09/19/24 – The bids were received from Browning Chapman and Buckeye Construction and Restoration. Both bids were under budget and within 8% of each other.
09/25/24 – THP and Browning Chapman had bid review meeting. BC appears to have all major scope items covered, including site logistical needs. The group discussed extending the contract to include time this winter to allow for shop drawing and window fabrication. BC is reaching out to the subcontractors to determine feasibility and needs. THP to publish summary letter after BC determines the needs.
10/08/24 – THP published the bid summary letter recommending Browning Chapman based on the bid amount.
10/31/24 – Hamilton County working on the AIA contract.
12/11/24 – Contract before the BOC for execution.
12/11/24 – Contract before the BOC for execution.
12/17/24 – Contract approved and sent to BC.
01/30/24 – Project status – BC finalizing submittals and background checks. Preconstruction meeting scheduled for 2/18/25. Anticipated construction starting end of March.
02/17/25 – Browning Chapman sent submittals for THP’s review.
02/18/25 – Preconstruction meeting completed.
2/27/25 – Browning Chapman finalizing background checks, submittals and permitting. THP working on submittals.
3/11/25 – Progress Construction Meeting.
3/18/25 – Progress Construction Meeting.
3/24/25 – Browning Chapman mobilized.
3/25/25 – Progress Construction Meeting.
3/26/25 – THP finalizing revised submittals and reviewing pencil Pay App #1.
04/01/25 – Progress Construction Meeting.
04/08/25 – Progress Construction Meeting.
04/09/25 – Permit Issued.
04/15/25 – THP finalized all submittals.
04/15/25 – Progress Construction Meeting.
04/21/25 – Roofing demo and window removal on East Skywalk began.
04/22/25 – Progress Construction Meeting.
05/06/25 – Progress Construction Meeting. East Skywalk roofing.
05/13/25 – Progress Construction Meeting. East Skywalk roofing complete. Steel Installation. North Skywalk mobilization.
05/20/25 – Progress Construction Meeting. East Skywalk steel painting, window flashing, painting mock-up. North Skywalk stair scaffold and roofing on east portion.
05/27/25 – Progress Construction Meeting. East Skywalk window installation. North Skywalk roofing and window removal/temp. panels on east portion.
06/03/25 – Progress Construction Meeting. East Skywalk Window install complete. North Skywalk Roofing east half complete and window removal/angle install in progress.
06/10/25 – Progress Construction Meeting. East Skywalk Façade painting in progress and North Skywalk roofing west half in progress.
06/17/25 – Progress Construction Meeting. North Skywalk Roofing west half complete and window removal complete. North Skywalk window install in progress. Punchlist started.
06/24/25 – BC sent Pencil Pay App #4 for review. THP to return shortly.
07/15/25 – Progress Construction Meeting. North Skywalk Façade painting.
07/29/25 – THP issued punch lists for North Bridge roof work and East Bridge. North bridge roof work was completed.
07/29/25 – Progress Construction Meeting. North Skywalk Façade Painting complete. East Skywalk Punch Complete. EJ Work in progress. BC sent Pencil Pay App #5 for review. Final Punch scheduled for 8/14/25 @ 1pm.
08/15/25 – THP investigated reported leak condition on the east end of the north bridge.
08/18/25 – BC, THP, and County completed water test and confirm leak was from roof drain line in the cavity below the bridge slab at the east end of the bridge.
08/19/25 – BC and THP used a camera to scope the drain line and found two breaks in the drain line that corresponded to the leak location.
08/21/25 – BC, THP and County completed punch trip for north bridge.
08/28/25 – THP exploring different plumbing repair options and developing opinion of probable costs.
10/29/25 – BC to begin Roof Drain line repair on 11/03/2025. 2 week schedule.
11/06/25 – THP completed site visit to review completed drain line.
11/14/25 – THP reviewed hatch mockup. Proposed hatch too big for panel. Updated panel size ordered. Weather permitting panel work to start in December.
12/11/25 – BC is installing the access hatch in the panel at the shop. Painter is scheduled to paint the panel in the shop. Once complete, BC to schedule panel installation.
01/28/26 – THP is reviewing BC’s Closeout Documents and should be returned 01/30/26.
01/28/26 – BC is currently estimating repairs for Concrete truck damage to North Skywalk.
02/05/26 – THP returned all Closeout Documents with comments to BC for final submittals to HC.
02/25/26 – THP to reach out to Imbus regarding mental panels and bending 20′ lengths.
03/25/26 – North Skywalk leak – BC indicated they are in contact with Delaware glass.
03/25/26 – Concrete truck panel damage – BC reaching out to metal panel manufacturers to get custom panel pieces and working up pricing. BC would like to coordinate panel repairs with leak.
04/20/26 – BC sent proposal to THP for Metal Panel Repairs. THP to review proposal with HC and schedule the work.
04/28/26 – BC is working with Delaware Glass on the leak at the North Skywallk and is working on scheduling them next week. A lift is required and will need to be delivered.
05/11/26 – Lift Plan submitted for Metal Panel work and glass warranty work.
05/19/26 – BC submitted cost breakdown for skywalk repairs to HC.
06/25/26 – Delaware Glass has completed warranty work for leak in North Skywalk. BC has completed metal panel work at North Skywalk and has processed all requested closeout documents.
07/30/26 – Verify with County if project can be archived.
09/23/26 – THP completed a site visit on 9/16/26 to review paint peeling on exterior skywalk façade. Field report to follow shortly.
10/26/26 – BC scheduling a site visit with Painting Contractor to review paint Issue.
10/28/26 – HC received letter from City of Cincinnati Permit District Inspector regarding open inspections for the project. BC was notified.
JC – Skywalk Roof Replacement & Exterior Repairs (F002) Read More »
PM: Rycca Thacker, Paul Bellman
02/01/24 – Hamilton County requested slab project be rebid based on previous project.
02/12/24 – THP published review documents to the County.
02/16/24 – Hamilton County provided review comments to the documents.
02/16/24 – THP published bid documents to Hamilton County.
02/20/24 – Hamilton County advertised project for bid.
02/27/24 – Prebid meeting occurred.
03/11/24 – Addendum 1 issued to Purchasing.
03/14/24 – Addendum 2 issued to Purchasing.
03/15/24 -Addendum 3 issued to Purchasing.
03/28/24 – Bids due date April 8, 2024.
04/12/24 – Reviewed Bid with Browning Chapman.
04/19/24 – THP issued Bid Summary Letter to Hamilton County.
05/02/24 – Hamiliton County issued Contract Documents to Browning Chapman.
05/10/24 – Browning Chapman returned signed documents.
05/30/24 – Hamilton County Board review on 06/06/24.
07/19/24 – Browning Chapman working on pricing estimates for floor finishes, submittals, and background checks.
07/23/24 – Hamilton County requested to schedule a kick-off meeting.
08/15/24 – Preconstruction meeting completed.
08/19/24 – THP issued meeting minutes.
08/28/24 – Browning Chapman issued revised flooring options estimates. Browning Chapman’s submittals approved. Project to be scheduled.
09/25/24 – Browning Chapman submitted new flooring proposal for polished concrete. Approved and BC will need to develop Change Order.
10/28/24 – THP returned submittals to Browning Chapman.
10/31/24 – Final Pre-Construction meeting scheduled for Friday 11/01/2024.
11/01/24 – Kick-off meeting.
11/04/24 – HC sent Notice to Proceed.
11/07/24 – Progress Construction meeting.
11/14/24 – Progress Construction meeting.
11/20/24 – Progress Construction meeting.
11/20/24 – THP Signed Pay App #1 and sent to HC.
11/27/24 – Progress Construction meeting.
12/05/24 – Progress Construction meeting.
12/10/24 – THP signed Change Order #1.
12/12/24 – Progress Construction meeting.
12/13/24 – THP Signed Pay App #2 and sent to HC.
01/09/25 – Progress Construction meeting.
01/16/25 – Progress Construction meeting.
01/23/25 – Progress Construction meeting.
01/23/25 – THP Signed Pay App #3 and sent to HC.
01/30/25 – Progress Construction meeting.
02/13/25 – Progress Construction meeting.
02/20/25 – Punchlist Walkthrough.
02/26/25 – Browning Chapman finalizing punch list items. Final walkthrough scheduled 03/06/25.
03/06/25 – Final Walkthrough and signoff of completed items.
03/07/25 – THP signed Pay App #4 and sent to HC.
03/26/25 – Email sent to Browning Chapman requesting Closeout documents. BC indicated Closeouts will be ready for review on 3/28/25.
04/11/25 – BC sent closeout documents to THP for review.
04/18/25 – THP sent reviewed closeout documents and comments back to BC.
04/22/25 – THP sent HC signed Pay App #5 – Final Retainage.
04/24/25 – BC sent HC Final Closeout Documents.
05/29/25 – Can THP archive project?
06/25/25 – Project Archived.
2020 – Slab and Masonry Repairs (F001) Read More »
PM: John Nester, Mike Barth
02/28/24 – HCFD requests SOSS for project.
03/27/24 – Project designed, permitted, and installed. IBI inspection passed on 03/27/24. EMA Calling Duke to Energize the Siren.
04/24/24 – TEI has received no updates on this siren.
05/29/24 – TEI has received no updates on this siren. This project can be archived.
EMA – Siren #607 Relocation Read More »
PM: Rycca Thacker, Terry Cannon
02/01/24 – Create project for single upgrade of core area drinking fountain.
02/23/24 – Met onsite to review existing conditions. Champlin putting SOSS together for TTE to use for SOSS to county for one EWC on first floor. Build out into Security space seemed doable.
03/19/24 – SOSS submitted for approval, full scope.
03/22/24 – Fees seemed high for single drinking fountain, second SOSS submitted with reduced scope.
04/24/24 – On hold waiting on direction from County on next steps.
05/29/24 – On hold waiting on further direction from County.
06/26/24 – On hold waiting on further direction from County.
07/24/24 – On hold.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold. Ready to archive.
A&D – First Floor Drinking Fountains Read More »
PM: Megan, Mike Murphy, Terry Cannon
12/20/23 – THP – Champlin request SOSS for incidental structural support work.
12/21/23 – THP submitted SOSS to Champlin for review.
01/30/24 – Kickoff meeting with Facilities, Juv Court, Champlin and ThermalTech.
01/31/24 – Meeting notes distributed, TE started drawings packages for Phase 1.
02/28/24 – Scope for phase 1 finalized. Meeting scheduled for March 13, 10AM to review finishes and answer any remaining questions.
03/22/24 – ThermalTech Phase 1 drawings and cost estimates pretty close for final review. TTC working through individual items with Facilities. TTC requested meeting with Facilities to coordinate final scope of each building to nail down equipment repairs, replacement, upgrades. Verified that the four cottages are Elm, Evergreen, Hickory and now Maple is an Alternate.
03/22/24 – Champlin close to complete with review set as well. Final review meeting set for 4/3. Estimates to follow on 4/12.
04/24/25 – Final review drawings sent this month. Revised estimates were sent to Bert for review. Breakouts were formatted so they can see the assessment vs final design.
05/30/24 – County approved funding. Drawings modified accordingly. User requested a meeting to be scheduled in near future. BW said that the project can go out for bid as soon as we are ready to bid this project. TTC, MCB, and SH said the drawings and specifications are ready. BW and MM discussed the fence alternate around the building. Be ready to bid June 11-13 timeframe.
06/27/24 – Project is out to bid. Pre-bid scheduled for 7/9. Partners to invite local contractors for bidding on July 9.
07/25/24 – Project is still in bid phase. Final addendum to be posted by next Wednesday.
08/29/24 – Bids came in awardable. Accepting different alternates will determine lowest bid. County to decide what they are accepting.
09/26/24 – Project is in contract phase. County still finalizing alternates. Champlin to send recommendation letter for recommended bidder and note we have not finalized the accepted Alternates.
10/31/24 – Contract in process. Variance package for the fence is nearly complete.
12/12/24 – Contract awaiting on PO approval. Submittals incoming. HVAC and Plumbing submittal are done, TTC needs to approve and send along. BW said to go ahead and submit permit and fence variance for this job.
01/02/25 – ThermalTech starting on submittals this week for Phase 1.
01/30/25 – Kick-off held 1/29. Submittals are in progress. Zoning is complete. Permit has been submitted. Zoning application for fence to be submitted this week. Graybach ready to mobilize by mid February.
02/26/25 – We met with Aramark on Tuesday to review kitchen operational needs. TTE has been reviewing and working on HVAC, Plumbing and Electrical submittals on an ongoing basis. We are in good shape. Two AHU’s have delayed ship dates because the manufacturer is not producing R-454B refrigerant yet.
02/27/25 – Submittals in progress. Notice to proceed will be provided to allow Graybach to start on site work. Zoning application for fence to be submitted this week
03/27/25 – Submittals ongoing. Demolition ongoing. Permits approved and picked up. Fence application in HC lawyers hands.
04/24/25 – Bulletin #1 released. Already received a $25,000 add for the window changes. The rest of the pricing is outstanding.
05/21/25 – Met with Graybach, Champlin, Facilities on Change Order log, we do not have EC cost yet. Review deducts and approved a couple of them. Verbally approved Windows change order.
05/28/25 – ThermalTech regularly meeting contractors on site working on RFI and Change Orders for this project. The big items are the R-454B units for School and Dining, Water Closets on new tile walls, ductboard repairs and controls for the Admin building.
05/29/25 – Change order #2 for the windows is approved. Several potential change orders have pricing submitted. Rycca needs to finalize which will be approved or not. Change orders 3 and 4 approved. The remaining items have been priced and submitted to the board for a PO increase. Work may have to pause while this process takes place.
07/31/25 – Request for funding all change orders went before the board. No update on their decision yet. Work is in progress. Rycca reported that LaForce found a control key and it is getting cut and shipped to our site. The hope is to stay with the existing manufacturer. Rycca further said that they need final change order cost for all remaining COR so she can take final numbers to the BOCC. HVAC final cost, plumbing underground cost, electrical final change order needed. Sam is working on the frosted glass specs but must be ligature proof. TTC to confirm if County self performs repair if warranty is intact.
08/26/25 – Construction meetings continue. We agreed on the items to be included in Change Order 5 and now we are working on reconciling the cost associated with them. TTE sent two items for HC plumbers to fix, but while on site they had questions. TTC to meet them on site to review.
08/28/25 – County requested $800k for Phase 1 repairs. Plus CO#5 is approved and sent to Josh for approval.
09/24/25 – TTE sent a long list of field conditions to Graybach after last const meeting for them to address before the project gets to the punchlist phase. Graybach responded with action items and concerns over some of the comments. One item was that the County agreed to allow the return diffusers to remain as installed but they should be changed out before occupancy.
09/25/25 – Change order request goes in front of the board this week.
10/30/25 – Change order request was approved by the Board. Work continues in full force. No word on the fence yet.
12/11/25 – More change order requests came in. Scope removal to cover permit required work is being considered. Project competition is tentatively scheduled for end of February.
12/12/25 – DEG met onsite to review lighting change order and work out several nice compromises with the EE and GC. MCB to send Rycca and proposed update. Parks & Graybach to update and send in revised change orders for review.
01/23/26 – Const Mtg. DEG walked the site, check plumbing, heating, and electric. Chris Hofmeister called us back to the cottages to ask about external conduit adjacent to the receptacles. This turn out to be communication wiring not power wiring. Habegger will be out Tuesday to check temperatures in school, the two wings felt cold, but the core was warm. HVAC and plumbing are released to perform their punchlist.
01/28/26 – Campus is nearing completion. Bulletin to address change in fence scope to be issued in near future and variance submitted.
02/26/26 – Work ongoing. Waiting on approval for change in fence height to issue bulletin. Mechanical punch completed.
03/26/26 – Fence bulletin issued. Waiting on pricing to determine exact scope. Punch of school and admin building complete. Punch for remainder of buildings to be scheduled in near future.
04/30/26 – Punch work in progress. Fence application still in County hands.
05/28/26 – Variance application submitted. Hearing scheduled for 6/16. Owner punch walk through school. The rest of the buildings will be walked on 6/5.
06/25/26 – Variance approved. Survey to be scheduled in near future. Majority of punch work to be complete by mid July.
07/13/26 – TTC on site working on plumbing and HVAC items all week.
07/20/26 – TTC on site working on plumbing and HVAC trends all week.
07/22/26 – DEG on site doing back punchlist work.
07/23/26 – DEG on site doing back punchlist work.
07/24/26 – DEG on site doing back punchlist work.
07/30/26 – Final back punch complete. Minor items outstanding. Fence location needs final approval.
08/28/26 – Punch items have been progressing. Fence location not yet approved.
09/24/26 – 3 items remaining according to Graybach. Fence location has been approved, just waiting on confirmation of supposed easement.
10/29/26 – Back punch complete. Fence work ongoing.
Hillcrest – Campus Repairs Phase 1 Read More »
PM: Jesse, Sam, Terry
02/01/24 – Champlin to send SOSS to TE for this job for Design, Bidding and Construction.
02/29/24 – Kickoff Meeting to be scheduled in near future.
03/28/24 – Kickoff held. Project to be bid in the next month or two.
04/25/24 – Bid Schedule needs to be determined. Project ready to move forward with small project bid. At the Partner Meeting we decide to have Trades do the work, TTE and CHA will assist with permitting. No sprinkler work needed. minimal HVAC. We do need an IBI and General Permit.
05/30/24 – Estimate to be sent to John. CDs in progress.
06/27/24 – Drawings and Estimate sent to John. Permit can be submitted when necessary.
07/25/24 – No Update.
08/29/24 – No Update.
09/26/24 – No Update.
10/31/24 – Permit to be submitted next week.
01/30/24 – Electrical Permit returned. Building and Mechanical Permit in progress.
02/27/25 – Building and Mechanical permit approved.
03/27/25 – No update.
04/24/25 – County to submit trades as a certified contractor in City of Cincinnati.
05/29/25 – No Update. County is getting Trades registered, trying to get fellow government entity set for this work.
06/26/25 – Trades is registered with the city but the HVAC work would not be allowed to be self performed. HVAC scope will be removed and permit revision submitted. ThermalTech updating the HVAC for engineering revision.
07/31/25 – City is not allowing any work that even touches HVAC to be done without a licensed HVAC contractor. We will need to bid out at least the HVAC work. Follow up at meeting was to remove the ceiling from the permit set and any work not associated with the wall and door going in. Resubmit permit without additional work.
08/28/25 – All ceiling work has been removed from the project. Permit approved and ready for pickup.
09/25/25 – No Update.
10/30/25 – Trades have began work. In wall inspection complete and board can be put up.
12/11/25 – No update.
01/28/26 – Work is complete.
2020 – Locker Room Buildout Read More »
PM: Rycca Thacker, Terry Cannon
01/22/24 – Fieldwork rechecked, owner review set by Friday.
01/31/24 – Drawings sent to Rycca for review. We will assist with permitting through the City of Cincinnati and with install as needed by Trades.
02/23/24 – County reviewing drawings.
03/22/24 – Still on hold.
04/24/24 – On hold waiting on direction from the County on next steps.
05/29/24 – On hold waiting on further direction from County.
06/26/24 – On hold waiting on further direction from County.
07/24/24 – On hold.
08/28/24 – On hold.
09/24/24 – On hold.
10/30/24 – On hold.
12/12/24 – On hold.
12/31/24 – HC said to archive this project.
A&D – Mother’s Room Upgrades Read More »
PM: Matt Butz, Terry Cannon
01/24/24 – Project created for tracking any 2024 updates.
02/23/24 – Drawings are created for this year’s bid.
03/22/24 – TTC to create new SOSS in the hopes this job bids again this year.
04/24/24 – TTC has not submitted the SOSS for this job yet. Not sure it needs one, ask on Thursday.
05/29/24 – One of the first steps is to engages Terracon to scan the parking lot around where the new underground tank will be located for anomalies.
06/26/24 – TTC will get Terracon scheduled for July hopefully.
07/24/24 – Terracon has been asked to update their proposal. No SOSS has been submitted for 2024 project yet.
08/28/24 – Revised proposal received today, TTC to review.
09/24/24 – Project will now be rolled up with Emergency Power updates and their next bid.
10/30/24 – Archived.
JC – Underground Fuel Tank Replacement 2024 Read More »
PM: John Nester, Terry Cannon
01/24/24 – Post created for tracking.
01/31/24 – Two punchlist sent to ALC for work on the current job. Training scheduled for Friday with Mike Bowman and Emcor.
02/02/24 – Training went well. Ian, Kendall, Curtis, Terry and Barrett attended. We made a few adjustments while reviewing.
03/22/24 – Project completed, just waiting on some summertime use before we close it out.
04/24/24 – Emcor onsite this week trying to get AHU-1, AHU-4 worked out for dual circuiting. AHU-1 VFD installed on 4/23. NKYHC replacing refrigerant and ambient. Emcor wrapping up they Comm Center and starting the 250 WHT building next week.
05/29/24 – Controls work has been completed and VFD installed. We need to check back with Ian to see if its working better.
06/26/24 – DK currently working at 250, will check on progress.
07/24/24 – 250 WHT is almost complete. 486 next, then Comm Center. TTC checks the graphics and there is work to do before we say they are done.
08/28/24 – Working on final stages of 250 WHT.
09/24/24 – 250 WHT graphics are not complete, points are being programmed now. SPHQ appears that most upgrades are complete. Comm Center graphics are intact but no space temperatures are shown on floor plans, none of the mechanical equipment is shown on a site plan anywhere, found it in the Basement but there is no chiller shown on the plans. Public Works Garage has updated controls on the new work from the renovation has not been programmed and we have no feedback on space temperatures yet. The Records Center has no space temperatures on graphics.
10/30/24 – All buildings are complete except for Records Center according to Emcor. They are waiting on an outdoor enclosure for the outdoor RTU.
12/12/24 – TTC reviewed SPHQ and asked that Emcor put space temperatures on the floor plans with the thermal graphics maps like we did at SPHQ.
01/28/25 – Progress ongoing. All buildings are either done or partially complete. Price received for temps on floors and passed along to Tony for consideration.
02/26/25 – TTC reached out for an update from Mike and Steve yesterday.
02/27/25 – Emcor received final IP address for last building. Mike Bowman will be out to add the last building and then TTC to punchlist.
03/25/25 – ALC should be complete with all buildings. TTC will create a punchlist for each building in the next 30 days.
04/23/25 – TTC working on punchlist right now.
05/28/25 – Archived.
SPHQ – ALC Upgrade BAS Commissioning 2024 Read More »
PM: Matt, Terry Cannon
Closeout: Haeli Johnson, hjohnson@tritonservicesinc.com, Dayna O’Brien, dobrien@davieseg.com
01/24/24 – Post created for tracking.
02/01/24 – TE to submit SOSS for this project.
02/23/24 – Coty will be working on this job.
03/22/24 – Initial fieldwork started this week. SOSS submitted. Electrical review scheduled for next week to ensure fire pump feeders meet current code. Life safety code updates may apply to this upgrade.
04/08/23 – Met with our electrical group this week to discuss the power feeders to the fire pump. We decided the best course of action that saves the County the most money is to let the Emergency Power project go first and update the MCC disconnects to isolate the fire pump disconnect in its tub so that it meets current code. Once that work is complete, we can bid out the replacement of the fire pump with out running into issues with the new NEC requirements for feeders in concrete or the fire pump being fed first before ancillary equipment.
04/24/24 – The preliminary drawings are ready for TTC review.
05/29/24 – TTC marked up drawings for owner review. TEI working with Fire Marshal on component required for replacement versus new NFPA code. This has to be bid this year even though it will be installed after the Emergency Gen update.
06/26/24 – Final drawings are ready for review, changes have been made from our field trip with Andy earlier this month. CFD not willing to provide pumper truck for weekend, we are checking on rental fire pumps and fire watch. SA believes a fire watch can be used.
07/24/24 – We were waiting on the JC Emergency project to be awarded so we could move forward with bidding our design out. The FPC will provide the fire watch as needed to make these piping changes and replace the pump vs using the CFD. I have not seen any CFD response in writing to our design request.
08/28/24 – Final internal review scheduled Friday.
09/24/24 – Project is out for bid. Prebid scheduled for Oct 8 at 9am. Bid Opening is Oct 30.
10/30/24 – Bids opened with four bids under budget, two of which were non-awardable due to a bond issue. TTE to interview KFI on Friday for compliance to bid specs.
12/12/24 – Triton was the low bidder via the base bid and Alternates accepted, we await the contract and PO to have the kickoff meeting.
01/30/25 – Contract going to commissioners tomorrow for approval.
02/26/25 – Contract is back, we are setting up Pre-Const meeting.
03/25/25 – Pre Const meeting was held and meeting notes distributed. Schedule, SOV, and equipment submittals have been requested.
04/23/25 – Construction Meetings started. Stamped permit drawings have been sent to Triton for submissions. Submittals have been requested. Other project startup documents have been requested.
05/28/25 – ThermalTech received written direction on suction valve controller which is not required on this replacement as long as we have the low suction cutoff report as a supervisory back to the FACP. We are approving the Fire Pump Controllers and rejecting the Fire Pump and Jockey pump due to under sizing and rotation issues.
06/25/25 – Equipment ordered and waiting on equipment delivery. The latest ship date is September 18, 2025.
07/30/25 – Pump submittals are finally approved. Bulletin #1 drawings sent for pricing to fix test header.
08/28/25 – Latest update is that the fire pump will arrive 9/19. Triton to coordinate replacement with Owner.
09/24/25 – Work being scheduled now including fire watch requirements.
10/29/25 – The fire pump has arrived. The test header was repaired by SA Comunale, now the wall and patching work needs to be completed. A new test ring needs to be installed on the outside FDC. Quality Fire has two people badged, checking on TJ Williams badged contractors. We need to iron out Fire Watch details with Triton.
12/12/25 – Triton and Quality ready to begin the project. Final fire watch details being negotiated. Inspection test header has been repaired, outdoor placard spacing is loose.
12/22/25 – Construction meeting held, we are working out details of shutdown, fire watch and submittal approvals.
01/12/26 – Const Mtg, finalizing shutdown details, fire watch, and schedule for work. Fire Watch must be provided by Triton for non-secure areas, DEG to issue drawings for scope. Electrical shutdown may require Courthouse to provide steam for Justice Center based on weather.
01/21/25 – Adding additional details and scope to the shutdown and next phase of work. USPA does not have background checks complete for fire watch yet. Electrical changes submitted to IBI. Feb 3 will be electrical emergency crossover and Feb 10 will be the primary crossover. Pump replacement scheduled for Feb 23.
02/25/26 – Emergency power is connected. Normal power has become a power struggle between Duke and IBI and DEG is working through those requirements and obstacles with both parties. the pump install will be coordinated after the power requirements are resolved.
03/25/26 – Normal & Emergency power are connected and ready to go. CFD required paperwork submitted & 3 of 4 FDC did not pass inspection. March 23rd replacement rescheduled until FDC are repaired. SA coming in on Friday to begin repairs and assessment.
04/29/26 – 3 of 4 of the FDC are repaired. The fourth FDC is currently under repair but SA is having trouble sourcing an access panel for the wall opening. TTC asked to open the wall now and repair the FDC which should only take a day, temporarily install a wall covering to keep the fire pump job moving along. The fire pump is currently scheduled to be replaced May 18-22.
05/18/26 – Replacement started on the fire pump today. Triton and DEG providing 24/7 fire watch.
05/19/26 – Repairs and fire watch continues.
05/20/26 – Repairs and fire watch continues. 99% of electrical and mechanical work is complete. Corporate equipment pre-inspected the fire pump installation and it passed. We are trying to move up final inspection to Thursday at 1:00PM.
05/21/26 – Replacement complete. Fire pump tested at 1:00PM with full water test, manual and automatic starts with City of Cincinnati and Cincinnati Fire Department in attendance. All system passed, the new fire pump was put online about 4:00PM and the fire watch was completed.
05/27/26 – DEG provided the punchlist for the project and will distribute later this week.
06/25/26 – Project in closeout.
07/30/26 – Working on latest change orders for this project. COR-1.
08/26/26 – Change Order #2 in the works? Working on other closeout documents.
09/23/26 – Change Order #2 COR #1 data all updated and sent in for approval to County.
10/26/26 – Final change order approved and signed the project is in closeout. TTC reached out to Triton to get all closeout documents by 10/31.
JC – Fire Pump Replacement (085-24) Read More »
PM: John Nester, Mike Barth
12/06/23 – TEI receives approved SOSS and PO. COA to provide TEI with locations of cameras that were discussed with vendor.
01/30/24 – TEI to receive the locations and document on documents.
02/28/24 – TEI will document locations upon receipt.
03/27/24 – TEI, HCFD and DK meet, document locations, and develop drawing. Meeting with all team on 03/26/24 to review and finalize.
04/24/24 – Installation pending material procurement.
05/29/24 – Completion of this project pending punchlist once TEI notified all install work is complete.
06/26/24 – Cameras are installed and the users are working on getting the monitoring functioning (instructions from installer (DK) via email), and Matt Butz helped with Valerus integration to allow end users to utilize the system.
07/24/24 – TEI and HCFD perform punchlist on the project. Tenant confirms views are as desired.
08/28/24 – Project complete pending closeout documents.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
230 – COA Camera System Upgrade 2023 Read More »
PM: Matt Butz, Mike Barth
12/06/23 – TEI receives signed SOSS. Design kickoff to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet to kick off project. Locations and desired coverages discussed. TEI can develop documents based on meeting on 01/30. Roof camera replacements are first priority.
02/28/24 – TEI developing plans based on meeting. Will coordinate the issuances with HCFD.
03/27/24 – Drawings to be completed in April/May.
04/24/24 – Drawings in process.
05/29/24 – No updates
06/26/24 – TEI hand delivers drawings to HCFD for review.
08/28/24 – Project complete pending closeout documents.
12/12/24 – OK to Archive.
JC – Exterior Camera System Upgrade 2023 Part II Read More »
PM: Matt Butz, Mike Barth
12/06/23 – TEI receives approved SOSS. Design Kick off meeting to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet to discuss project objectives and kick off project on 01/30. Options and existing conditions were discussed. Card reader to be connected to the VAX system in the building managed by Risk Management. Door across the hall from Lincoln Base to be added to access control system as an alternate.
02/28/24 – TEI developing plans for this project. Based on kick off meeting for Council Rooms – the VAX controller may be upsized to accommodate additional doors that are desired to be on VAX system.
03/27/24 – TEI Proceeding with documents. Upon VAX confirmation, will complete documents.
04/24/24 – Documents in progress. Review set to be sent to HCFD upon completion.
05/29/24 – no updates.
06/26/24 – Documents near complete. TEI will send HCFD review set in next couple of weeks.
07/24/24 – TEI to deliver review set by end of week of 8/5/24.
08/28/24 – TEI sends documents to HCFD for review. Will issue bid package once review comments received and included in documents.
12/11/24 – HCFD and TEI meets with HCFD to review documents. Final comments to be incorporated and project issued for bidding first of year.
01/29/25 – Documents sent to DK for GSA Pricing.
02/26/25 – DK sends GSA pricing for project to HCFD and TEI. Project pending contract.
03/26/25 – Pending contract approval.
04/23/25 – Pending contract approval.
05/28/25 – Project in contract phase.
06/25/25 – DK, DEG and HCFD have construction KO meeting. Construction to commence approx 06/27.
07/30/25 – DEG reaches out to DK for installation update.
08/27/25 – All equipment installation nearly complete.
09/24/25 – Base bid work complete. Pending CO work (added door).
12/10/25 – Change order issued for additional work. Pending procurement and installation of additional devices.
01/28/26 – Project pending the completion of the CO work.
02/25/26 – No update
03/25/26 – no update.
06/23/26 – Project closeout and final pay apps requested from DK.
07/29/26 – DEG follows up with DK for Closeouts.
08/26/26 – no updates
09/23/26 – Grant extended. Additional security measures drawing by DEG and priced by DK.
10/28/26 – Installation of additional items in progress.
JC – Server Room Access Control Upgrades 2023 Read More »
PM = Matt Butz, Mike Barth
12/06/23 – TEI receives approved SOSS. Project kick off meeting to be scheduled.
01/30/24 – TEI, HCFD and HCSO meet on 01/30 to discuss project objectives and kick off the project. Network switches for the Kiosks and Camera systems shall be put in a lockable rack that will prevent local CO’s from tampering with them. The outlets that serve the overhead rack and the floor mounted Telecor Intercom racks will have lockable covers over them such that they can not be unplugged.
02/28/24 – Project is ongoing.
03/27/24 – Project is ongoing with documentation.
04/24/24 – Review set to be sent to HCFD upon completion.
05/29/24 – no updates
06/26/24 – TEI selects lockable racks. TEI recommends racks with solid doors (versus glass doors), but the glass doors are slightly less costly. ($100-$150 per rack).
07/24/24 – TEI to deliver review set to HCFD end of week of 08/05.
08/28/24 – TEI submits documents to HCFD for review and comments. Project will be issued for bidding upon receipt of comments.
12/11/24 – HCFD and TEI meets with HCFD to review documents. Final comments to be incorporated and project issued for bidding first of year.
01/29/25 – Small projects bid to be issued on 01/31/25
02/26/25 – Project in bidding phase.
03/26/25 – Received (2) bids. Dunn Electric and DK. Dunn apparent low bidder. TEI vets Dunn bid.
04/23/25 – Project in contract phase with prosecutors office.
05/28/25 – Project in contract phase.
06/25/25 – Project in contract phase.
07/30/25 – Const KO to be scheduled with Dunn and HCFD.
08/27/25 – HCFD, HCSO and DEG have const kick off with Dunn Electric. Materials roughly a month out.
09/24/25 – DEG approves submittals. Dunn Electric orders equipment. Dunn sends an email to DEG re equipment cost increase from bid time.
12/10/25 – All LC racks are installed, except G22. Ceiling by rack needs to be raised for the proper NEC clearances for the existing solenoid panels.
01/28/26 – Waiting for HCSO to move their equipment to move ceiling to wrap up the G22.
02/25/26 – Waiting for HCSO to move their equipment to move ceiling to wrap up the G22.
03/25/26 – Triton on site moving ceiling 03/25. Dunn to install new enclosed rack upon completion of ceiling work.
04/29/26 – All work completed. Punchlist completed. Contractor to submit closeouts.
07/29/26 – Project in closeout. DEG discusses with EC closeout docs needed.
08/26/26 – no updates.
09/23/26 – Project complete – pending closeouts.
JC – LC Server Rack Upgrades 2023 Read More »
PM: Matt Butz, Mike Barth
02/28/24 – TEI, HCJC, and HCFD meet on site to discuss the project objectives and locations where coverage is needed. Review set to be sent to HCFD on 3/1/24.
02/29/24 – Jaime will get Mike a set of review drawings EOD today, sent to Matt tomorrow hopefully.
03/27/24 – Documents completed and Dent to HCFD. Meeting with Juv Ct, HCFD, Telecom, and Jason/Todd on site to review and adjust. Documents completed for installation.
04/24/24 – installation pending material procurement.
05/29/24 – TEI has received no updates. BW asked if O’Rourke has provided any of county paperwork yet? Answer, no.
06/26/24 – DK arrives on site to begin installation. Installation ongoing. Risk Mgmt has decided that the NVR will be located on the downtown campus and feed will come back downtown.
07/24/24 – HCFD and TEI to perform punchlist pending HCFD availability.
10/31/24 – Need change order to relocate NVR to Security Bldg.
12/11/24 – Punchlist issued and DK sends back signed completed punchlist.
02/26/25 – project complete pending final closeouts.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – OK to Archive.
Hillcrest – Door Access and Camera System Upgrades Read More »
PM: Matt Butz, Mike Barth
12/06/23 – TEI issues SOSS.
01/30/24 – TEI receives signed SOSS and PO. Project documents to proceed.
02/28/24 – Project is ongoing
03/27/24 – On site investigation and kick off meeting with DK occurred on 03/26/24
04/24/24 – Review set will be sent to HCFD upon completion.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings for HCFD review.
07/24/24 – Construction completed. HCFD and TEI completed punchlist walk.
08/28/24 – Project pending closeout documents.
12/11/24 – No Updates
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – Binders in progress.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – Archive.
230 – Access Control System Upgrades 2023 Read More »
PM: John Nester, Mike Barth
12/06/23 – TEI submits SOSS.
01/30/24 – TEI receives signed SOSS and PO. Project to Proceed.
02/28/24 – TEI and HCFD discuss project schedule based upon system needs (existing system failures and parts unavailability). TEI commits to getting project upon MCB return from medical issues.
03/27/24 – Project in the works. TEI Submits SOSS for Small Projects bid for installation costs
04/24/24 – Project documents in progress. review set to be sent to HCFD upon completion.
05/29/24 – HCFD, Risk Mgmt and TEI meet to discuss scope and locations. TEI developing drawing package.
06/26/24 – TEI hand delivers drawings to HCFD for review.
07/24/24 – Project issued for small bids project bidding. Prebid meeting conducted. Addendum #1 to be issued by 07/26/24.
08/28/24 – Bids received opened for project (2 bids, Glenwood and DK). DK apparent low bid. TEI vets bid on 08/28/24.
09/25/24 – Project in contract phase.
10/30/24 – HCFD, HCSO, HCRM, TEI and contractor meet for preconstruction meeting. Anticipated start date at completion of Jax cameras (Mid December)
12/11/24 – Construction to commence upon completion of the JAX camera Project.
01/29/25 – Project construction kick off occurred on 01/28/25. Construction to commence upon receipt of people to integrate into the system and access levels from Risk Mgmt.
02/26/25 – Construction ongoing on this project.
03/26/25 – Construction complete. HCFD and TEI perform punchlist.
04/23/25 – TEI receives closeout documents from DK this week. Dayna is reviewing and assembling the binders.
05/28/25 – No updates.
07/30/25 – DEG received as builts from DK on 07/28/25. Record drawings are being completed and electronic copies of all will be delivered to HCFD.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.
10/30/25 – OK to Archive.
TPC – Access Control System Upgrades 2023 Read More »
PM – Jesse Estes, Sam Hofmann, Terry Cannon
12/07/23 – Signed SOSS received. Kickoff meeting requested.
01/22/24 – Load calculations are complete, fieldwork is started and mostly complete. Initial findings for AHU and HVAC needs sent to project team. In subsequent discussions it was decide to upgrade the unit for what we need in this space and do not try to “make” existing unit work if its undersized. TTE will design with that in mind.
01/31/24 – Review drawings to be ready in two weeks. TE to finish MEP review for that issuance.
02/29/24 – Final review meeting ready to be scheduled.
03/28/24 – Review meeting to be scheduled for first week of April.
04/25/24 – Review meeting held. Notes from Library received and changes have been made. They need to approve budget.
06/27/24 – Budget is still being worked out. Mothers room to be listed as an alternate. CDs in progress. Pull Mother’s Room out as an alternate. Laura got more money but not all of it. RR Alternate #1, Mother’s Room Alternate #2.
07/25/24 – No Update.
08/29/24 – Voting on new budget today and it should go forward soon.
09/26/24 – Budget was approved. Project to continue in October.
10/31/24 – Project goes out to bid today.
12/12/24 – Bid opens today.
01/30/25 – Alpha was awarded the bid. Contract still in progress. Kickoff to be scheduled in near future. Permit to be submitted in near future.
02/27/25 – Contract in progress.
03/27/25 – Kickoff scheduled for 4/2. Submittals incoming.
04/24/25 – Submittals in progress.
05/29/25 – Pre-mobilization meeting held. Alpha to provide schedule.
06/26/25 – Demo in progress. Freight elevator is down and has stopped work. RTU submittals were returned and we are working on an electrical requirements on the submittal with the vendors now. We have had several meetings trying to lock this down. Lead times range from 6 to 10 weeks.
07/31/25 – Demo is complete. Abatement of flooring to begin this week. Alpha to submit PCO related to plaster repair. AHU submittals have been received and approved with a new manufacturer. It took a long time to get there and there may be a credit to the project when all is said and done (Carrier/CaptivAire to York).
08/28/25 – Abatement will begin 9/2. Work paused during abatement delay. County is requesting more funds for plaster repair CO. Alpha was released to work up to cost of deduct from flooring removal.
09/25/25 – Framing has begun. Bathrooms to be turned over by end of October.
10/30/25 – Bathrooms to be turned over before 11/4. Asbestos concern to be investigated by the county. Work continues.
12/11/25 – Abatement of above ceiling pipe is complete. Alpha to remobilize and continue work.
01/28/26 – Bathroom back punch complete. Several items outstanding. Mid february completion.
02/26/26 – Library punch complete. Punch work outstanding.
03/26/26 – Back punch complete and work verified. Waiting on closeouts.
04/30/26 – Minor additional backpunch items sent to Alpha. Waiting on closeouts.
05/28/26 – No update.
06/25/26 – Closeouts outstanding. Shelf collapsed and new pins are being installed.
07/30/26 – No Update.
08/28/26 – Trades to fix all shelves. Alpha to come fix damaged shelves and adjust doors.
09/24/26 – Alpha to fix damaged shelves and conceal fasteners. Dehumidifier running to remedy door issues.
10/29/26 – Alpha to fix shelves and plaster in conference room.
CH – Law Library Text Room Renovation Read More »
PM: Bert Watts, Paul Bellman
09/28/23 – Hamilton County requested SOSS.
10/30/23 – THP provided SOSS for review.
11/20/23 – County approved SOSS.
12/07/23 – Chris Belcher with Pinnacle coordinate contractor effort to abate the cottage the first week of December. Pinnacle plans to update their NESHAP report once the work is complete.
01/22/23 – THP issued 90% Drawing Owner Review set to Hamilton County.
02/16/24 – THP issued Bid Documents to Hamilton County.
02/20/24 – Hamilton County Purchasing advertised documents to bid.
03/04/24 – Pre-bid meeting held.
03/19/24 – Addendum 1 issued to Purchasing.
03/28/24 – Bid opening scheduled for April 10, 2024.
04/18/24 – THP scheduled Bid review with O’Rourke for 04/25/24.
05/16/24 – Hamilton County requested documents from O’Rourke.
05/30/24 – THP to follow up with requested documents (Schedule of Values, Schedule, Safety plan, general submittals) and schedule pre-construction meeting.
06/05/24 – THP emailed O’Rourke regarding submittals and Pre-construction Meeting.
06/25/24 – THP sent follow-up email to O’Rourke.
06/26/24 – Hamilton County received Asbestos Inspection – Notice of Compliance. O’Rourke to start sending submittals on plumbing material and valves in conjunction with other things.
07/16/24 – Pre-Construction meeting held.
07/17/24 – Pre-Construction meeting notes distributed to all parties. Mobilization scheduled for 7/29/24 (tentative).
07/29/24 – Mobilization and utility work started.
08/16/24 – Demolition complete.
08/23/24 – Final grading complete.
08/28/24 – Seeding and strawing postponed – hold retainage. THP to review pay-app.
09/12/24 – Hamilton County and THP – Final Site walk through.
09/19/24 – THP issued Field Report.
09/25/24 – THP issued closeout list to O’Rourke.
10/09/24 – O’Rourke issued Closeout Documents to THP.
11/27/24 – THP sent pencil copy of Closeout Documents to Hamilton County for approval.
12/10/24 – THP sent final Punch List to be signed and notification for payroll documentation.
12/11/24 – O’Rourke is sending Closeout Documents to Hamilton County.
12/13/25 – Closeout Documents sent to Hamilton County.
01/03/25 – Finalizing Final Pay Application for retainage.
02/26/25 – No updates on Certified Payroll from O’Rourke/Park’s Electric.
Hillcrest – Birch Cottage Removal (F095) Read More »
PM: Bert Watts, John Millar
10/24/23 – Hamilton County requested SOSS.
10/31/23 – THP provide SOSS for review.
11/08/23 – Hamilton County approved SOSS.
THP 2024 Design and Consulting Service (F094) Read More »
PM: Bert Watts, John Millar
10/24/23 – Hamilton County requested SOSS.
10/31/23 – THP provide SOSS for review.
11/08/23 – Hamilton County approved SOSS.
02/29/24 – Record Center roof was noted to be leaking in a number of locations. Roof is under warranty. THP documented the conditions and met with the manufacturer and contractor. Manufacturer’s warranty department has approved a repair approach. Contractor is pricing.
02/29/24 – 800 Broadway tile in NE stair tower had cracking at the first floor level. THP coordinated contractor stabilization, removal and repair. Repair is complete. THP to provide a summary report.
04/25/24 – THP no update.
06/27/24 – Record center roof repair started today and is planned for the next 2-3 weeks. THP scheduled to be on site Friday to review progress.
07/12/24 – Tremco completed warranty repairs and submitted reports for review.
THP 2024 General Services (F093) Read More »
PM: Jesse Estes, Terry Cannon
09/21/23 – Tony requested SOSS for this work. Replace all three he confirmed in a phone call with him.
09/27/23 – Working on SOSS today.
10/25/23 – Review set will be ready Friday for owner review.
12/06/23 – Bids received from DK and Triton. DK is the apparently low bidder. Tony suggested accepting only the Alternates to add heaters to the left and right vestibules. TTC will review the bids with DK and recommend the award for this project.
01/11/24 – DK submitted additional paperwork for this project per request.
02/23/24 – Contract under review.
03/22/24 – Contract under review.
04/24/24 – Contract in for final review.
05/28/24 – Stamped permit drawings sent to DK for permitting.
05/29/24 – Setup kickoff meeting with AJ, Tony, Tyler for starting this project.
06/23/24 – Pre Const meeting held, coredrill complete, team met on door swing issue this morning.
06/26/24 – DK reported that heater was deeper than the door swing and submitted an RFI for resolution.
06/28/24 – A top cap “box” solution was given to DK for pricing. This would move the heater up high enough for the door to open.
06/30/24 – IBI Issued the electrical permit. CIC2402080
07/08/24 – TTE requested factory review of the proposed box solution for the heater depth issue.
07/09/24 -The factory reported that we did not have enough clearance for proper airflow and TTC discovered the maintenance access was blocked by the proposed design.
07/10/24 – A revised solution was sent to the County for comment that moves the heater on top of the panel.
07/24/24 – TTC checked back on the revised design and it was accepted by Tony Matre, TTC forwarded to DK for review. Tyler inquired about still using the box solution.
08/28/24 – Left and Right heaters are installed. Reviewed and approved by TTE and Facilities. DK engaged for change order revision on the center heater in the middle vestibule with the exact same unit the left and right has. DK agreed CO#1 using the allowance monies to pay for the additional heater. Paperwork signed and sent to AJ this week.
09/23/24 – The left and the right heaters are installed, painted, and electrified. The center heater was ordered via change order and should ship 10/2. Once the third heater is installed the electric and controls will be finished for all three heaters.
10/30/24 – All three heaters are installed. Two of them have power and final paint. AJ trying to get electrician on site to power up the final heater. AJ lining up Joe Bulach for DDC integration after third heater is ready.
01/02/25 – Controls are installed, all heaters should be working, punchlist sent, contractor has been asked to start closeout on this project. The heaters are discharging about 110F.
01/27/25 – Still waiting on final closeout documents from contractor.
02/26/25 – Closeout Documents almost complete., they are coming in.
03/25/25 – Closeout documents received and final pay apps being processed.
04/02/25 – Jesse Submitted final pay app today.
04/23/25 – Project can be archived.
CH – Vestibule Air Curtains 2023 Read More »
HC PM: John Nester. CA PM: Christy Dakin
05/08/23 – SOSS approved
08/31/23 – Final furniture plan with additional base feed received yesterday. Last revision required prior to furniture order.
09/22/23 – Design finalized. Furniture ordered.
10/25/23 – No Update.
02/29/24 – Ready to Archive.
TPC – 6th Floor 607 Furniture Renovation Read More »
PM: Bert Watts, Mike Murphy
07/12/27 – SOSS approved, kickoff meetings scheduled.
07/17/23 – Fieldwork started with Architect & MEP. Cottages will be first.
07/27/23 – All fieldwork is completed. Top 10 list has been shared. Champlin working on consolidated list. County will take control of site on 8/1/23 per email.
08/31/23 – Pavement condition report and tree maintenance report have been received. Architectural report nearly complete. MEP system report sample draft of some buildings has been received and acceptable. Other buildings in process. On target for mid September submission.
09/12/23 – Sent final reports to Champlin for Hillcrest including cost estimates for use on final report.
09/28/23 – Final report submitted to County
10/25/23 – Champlin to provide estimate for interior painting of cottages.
02/01/24 – Ready to Archive.
Hillcrest – Conditions Assessment 2023 Read More »
PM: John Nester, All Partners
06/29/23 – SOSS requested and approved for all partners
07/27/23 – Estimates underway. Vendor prices coming in for TTE new projects and estimates are being updated as we get information and quotes in. Re-estimates are also being updated with 2024 pricing. Discuss floor plans need with Champlin for New A/E estimates.
08/28/23 – ThermalTech has 40 of 48 new estimated ready for internal review. We have 68 of 179 re-estimates ready for internal review.
09/25/23 – Project estimates are complete. Champlin, THP and ThermalTech completed last Friday. TTC sent a summary of items for the Re-estimates to the team on Monday.
12/15/213 – Archive project.
2024 Project Cost Estimates Read More »
PM: Rycca, Barth
07/27/23 – County requested SOSS for this project.
08/24/23 – TEI submits SOSS. Project pending SOSS approval.
09/26/23 – Project Pending SOSS Approval.
10/26/23 – Project pending SOSS Approval.
12/06/23 – Project pending SOSS Approval.
01/30/24 – TEI receives signed SOSS and PO. Project proceeding with Documents.
02/24/28 – No updates on this project this month.
03/27/24 – Project waiting on direction from HCFD.
04/24/24 – Project pending direction from HCFD.
05/29/24 – No updates.
06/26/24 – No Updates.
07/24/24 – No Updates.
01/30/25 – Ok to Archive this project.
A&D – Digital Clocks Read More »
PM: Bert Watts, John Millar
06/30/23 – THP provided SOSS for requested proposal.
07/07/23 – Hamilton County approved the SOSS.
08/31/23 – THP working on project estimates.
09/22/23 – THP completed opinion of probable costs and entered data into County Archibus website.
2024 Structural Project Estimates CIP Resubmittal (F088) Read More »
06/30/23 – THP provided SOSS for requested proposal.
07/12/23 – Hamilton County approved the SOSS.
08/31/23 – THP working on project estimates.
09/22/23 – THP completed opinion of probable costs and entered data into County Archibus website.
2024 Structural Project Estimates Resubmittal (F090) Read More »
PM: Bert Watts, John Millar
06/30/23 – THP provided SOSS for requested proposal.
07/07/23 – Hamilton County approved the SOSS.
08/31/23 – THP working on project estimates.
09/22/23 – THP completed opinion of probable costs and entered data into County Archibus website.
2024 Structural Project Estimates New (F089) Read More »
PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 11th.
10/03/23 – Field survey of façade started.
10/11/23 – Rappel of façade completed.
10/26/23 – THP working on report.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
07/25/24 – THP completed assessment and report. No work needed. Final City report due 07/01/27 – Ready to Archive.
JC – Façade Monitoring 2023 (F087) Read More »
PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/06/23 – Rappelling of façades completed.
09/28/23 – THP working on report.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update
08/29/24 – No repairs needed final report due next June.
2020 – City Façade Monitoring 2023 (F086) Read More »
PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/12/23 – Hamilton County approved SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 10th.
10/10/23 – Rappelling survey of Tower completed.
10/17/23 – East wing loose debris survey started.
10/19/23 – East wing loose debris survey completed.
10/26/23 – THP working on summary report updated.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
06/26/24 – Monitoring updated report submitted.
06/27/24 – Budget submitted to County.
08/29/24 – THP scheduling façade knock down survey and inspection for 2024.
09/26/24 – THP to review knock down approach with larger repair package.
10/31/24 – Ready to archive.
12/10/24 – THP closing out the project.
800 – Annual Façade Monitoring 2023 (F085) Read More »
PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
06/06/23 – Hamilton County approved the SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of façade scheduled for October 3rd.
10/03/23 – THP completed rappelling and façade monitoring survey.
02/29/24 – Report complete. THP finalizing project budget.
03/28/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.
06/24/24 – Email status of report and repairs to address both City issues.
06/27/24 – Budget sent to County for City repairs.
08/29/24 – THP working on repair package for City repairs.
12/10/24 – THP closing out the project.
A&D – Annual Facade Monitoring 2023 (F084) Read More »
PM: Jesse Estes, Terry Cannon
04/18/23 – Request for SOSS to replace BFP at CH
05/05/23 – SOSS submitted.
06/21/23 – Fieldwork scheduled.
06/29/23 – We decided to bid this job Small Project given our previous experience with the JC BFP. Project submitted for final review to John.
07/26/23 – Final drawings being prepared, we will add two shutoff valves ahead of the BFP when they are replaced. We should be able to get this bid out within the next month.
08/29/23 – Project is ready for XBE. TTC to prepare for bidding.
09/27/23 – We are putting together front end documents together for this bid now.
10/25/23 – Addendum 1 ready to go out today. Bids are due 10/31.
12/06/23 – Bids received and vetted by ThermalTech. DK was the apparent low bidder and was recommend for award. Contract and PO approval stage.
01/17/24 – Additional paperwork requested by John Nester for this project.
01/24/24 – TTC contacted Bill Roach again for bid documents.
01/31/24 – Nothing received yet.
02/23/24 – Waiting on contract documents from DK.
03/22/24 – Contract under review.
04/24/24 – Contract signed by DK, County waiting on insurance from DK. Submittals were received and sent back for updates. The revised submittals were received today and sent back to the County and put back in the queue for TTE review.
05/28/24 – PO and Contract ready, setup kickoff meeting with DK and County.
06/26/24 – Pre Const held last week. DK has equipment in stock. We need to decide on a couple of valve questions before DK gets started.
07/01/24 – Pre Const meeting minutes distributed to the group. the BFP are in town and the work can be scheduled with HamCo on their schedule. No payapps or SOV has been received or approved yet.
08/28/24 – DK waiting on one more background check to clear and then they will schedule the work.
09/24/24 – Last DK worker did not make it through background checks. DK preparing to do the job with three workers. Bill setting up new schedule.
10/30/24 – Bill ready to do work in November, December time frame with three plumbers over two weekends. He will pick the weekend and give us a scheduled soon.
12/12/24 – The West BFP Replaced last week plus the two isolation valve above the city water booster pump. A small leak was discovered in the West BFP. GCWW does not know where the main city water shutoff is on the east side of the Courthouse so they are doing more fieldwork this week. DK will be after the holidays to do the next BFP. We received work from the city water inspector that the BFP clearances from the floor are acceptable.
01/28/25 – GCWW still searching for east side shutoff valve for east BFP. We are getting conflicting data about the exact location of the existing valve. Regardless it appears as thought GCWW would like to replace this valve when found. One valve found in the street apparently has bad packing, this valve would also be replaced. We will continue to coordinate and get updates from DK and keep the County up to date.
02/26/25 – Still waiting on GCWW to located and fix East Side main shutoff.
03/25/25 – HamCo provided updated from GCWW about locating and find the East shutoff valve for the building. As soon as that is located we will proceed with the next phase.
04/23/25 – GCWWW has scheduled multiple visits to fix or replace the Courthouse isolation valve for the East side of the building. As of this meeting, it is not complete. DK is checking in weekly with GCWW for updates. The DK change order has been submitted for the spool piece leak repair.
05/28/25 – DK meeting GCWW on site Friday to verify the new shutoff valve is holding. Then they will scheduled BFP replacement with County including the new spool piece.
06/01/25 – Will spoke with Justin at DK and have the following update to our never-ending waterworks saga. The isolation valve in the street has been replaced by GCWW. They haven’t patched the road yet so there’s no access to the valve without a backhoe to remove the road plate. DK will wait until the road is patched before performing work(expecting sometime this week or next week for that to take place). At the earliest, DK may replace the backflow preventer next Friday. They’ll be in touch to schedule the work.
06/25/25 – Second BFP replaced last Friday. Spool piece replaced at the same time. Everything seems to be working correctly.
07/28/25 – Both backflow preventers are replaced. TTE needs to do a final punchlist and verify final invoices before closeout.
08/26/25 – Punchlist complete and sent to Debra for signature and updates.
09/24/25 – Checking in with DK weekly for closeout and approvals.
10/29/25 – No closeout paperwork or additional communications from DK have been received. We reached back out for an update. Billy was out 10/6-10/10.
12/12/25 – Ready to Archive. Final documents being delivery to Jesse on 12/13.
CH – Backflow Preventer Replacement Read More »
PM: Bert Watts, Mike Murphy, Terry Cannon
06/29/23 – Opened for tracking.
07/27/23 – Cad plans are ready per request.
08/31/23 – New SOSS requested and will be submitted this week.
09/01/23 – Sent SOSS to Champlin for use on 152 and 157 Kennel options. TTE started working on a zoning and load calc for any future dehumidification unit we may need.
09/28/23 – Small Project flooring replacement ready for bid. Project will be sent out 10/3.
10/25/23 – Bids received for Epoxy Flooring Installation. Bid vetting in progress. Trench drain scope in progress.
10/26/23 – TTE requested design meeting with owner to review HVAC requirements for this space. Temporary vs new conditions, reusing existing equipment, locations of new equipment.
12/07/23 – User meeting held to discuss phase breakdown. Phase 1 = Epoxy Flooring. Phase 2 = Plumbing Improvements. Phase 3 = HVAC Improvements. Phase 3 = All other improvements. Phase 1 has contract signed and flooring installation scheduled for 1/29. Phase 2 to be submitted for owner review 12/15.
01/31/24 – TE submitted Plumbing and HVAC review drawings for this project concerning the trench drains and air conditioning systems for this phase of upgrades. We are still exploring most economical ways to build these trenches at the Dane St. site.
02/29/24 – Request for availability for final phase II meeting sent out. Waiting to hear back from Cares. We can be ready for bid end of March. Wait until next Wednesday and set the meeting with available data.
03/28/24 – Final review meeting held. Cares requested consultant to review the plan. Shelter Planners of America have been brought on and will conduct review.
04/25/24 – Consultant brought on board for industry standard advice. Updated plan presented to CARES. Champlin to incorporate changes and determine new phasing plan.
05/30/24 – Drawings have been updated to reflect plan changes for Phase 2. Final estimate to be submitted this week. BW said to go ahead and include the kennel cost in the Phase 2 work. Phase 3 cost due end of June to County as well. Coordinate with structural for final design and cost.
06/27/24 – Phase 2 and 4 cost submitted to Bert. THP investigated structure options for Phase 3. It was determined that the best option is to put the mechanical units on a platform behind the building that will later serve as the sallyport structure. Goal is to have Phase 2 & 4 ready for bidding by July 17. Phase 3 to be purely HVAC scope and okay to include platform & roof now in this phase. OK to pour slab during this phase. Stairs and ramps can be done later. TE will put power in for Portable HEPA to hold us over until the new units are installed on the new platform in Phase 2.
07/12/24 – Phase 2 & Phase 3 cost submitted to Champlin for rollup to County and Cares.
07/23/24 – Phase 2 + 4 Issued for Bid with additional work included as alternates with latest request from owner and tenant.
08/29/24 – Phase 2 bid opening 9/3. Acoustical vendor bids came in and Universal had the lowest bid for this project.
09/26/24 – Phase 2 bids awardable. Contract returned. First submittals received.
10/31/24 – Contract finalized. Scope may change slightly due to record center work. Holding off on permit submission until changes are finalized. JN said pick a new material for the walls and change them to something less permanent. We discussed phasing for Dane vs Records at this meeting and the fast timeline of preparing space for Phase 2 work for the dogs.
12/12/24 – Bulletin #1 issued addressing scope change requests. Submittals are in process. Kickoff meeting scheduled for next week.
01/30/24 – Bulletin #1 was rescinded. Bulletin #2 issued with minor changes to account for the cancellation of Phase 3. Applying for a change of use in Zoning is ongoing. Application has been sent to examiner for review. Once his comments are received, we can apply for a conditional use review. Permit will be held up until zoning is complete.
02/26/25 – Bulletin #2 and #3 have been issued. Zoning hearing scheduled for March 12. Work ongoing.
02/27/25 – City zoning link was sent to Rycca and Champlin and Nester, not allowed to share, but BW will join with JN. Other witnesses can request access 24 hours in advance.
03/27/25 – Zoning conditional use was approved. Building department has not issued the permit yet and the building department has ordered a halt on all work until a permit is approved.
04/24/25 – Permit has been approved and work resumed. Kennels were delivered on site. We are still on schedule to be complete by end of June.
05/29/25 – Phase 1 punch scheduled for 6/2. Phase 2 work complete by end of June.
06/26/25 – Fire alarm and electrical issues pushed back turn over of phase 1. Phase 2.1 punch complete.
07/31/25 – All punch work is complete. The exterior ramp begins next week. Closeouts to be submitted by Graybach.
08/26/25 – Project is complete. TTC working with Ian and Chris on Wi-Fi thermostats. RTU-7 does have issues but wasn’t part of project. Ian getting . Entrance ramp poured incorrectly. Corrected railing detail to be provided to Graybach.
08/28/25 – Ian getting prices to replace RTU-6,7 given the issues. JN said CVW met with CARES on the security camera, JN to get AIA, TTE to send XBE forms, keep this moving ASAP.
09/25/25 – Multiple issues with all washers. Supplier and plumber met onsite to discuss issues. They are being replaced. Railing work outstanding. Graybach to submit closeouts in next 2 weeks. Security Camera project to be in to John for review by Monday.
10/30/25 – Railings installed. Punch list sent to Graybach and work completed. Back punch to take place in near future. Closeouts received but have not yet been reviewed.
12/11/25 – Railing punch items addressed. Closeouts reviewed. Graybach to provide missing items.
02/26/26 – Closeouts delivered to County.
03/26/26 – No update. County to review closeout documents.
04/30/26 – Final items to be delivered to County.
Dane – Phase 2 Renovations Read More »
PM: Bert Watts, John Millar
05/11/23 – THP provided SOSS for requested proposal.
05/16/23 – Hamilton County approved the SOSS.
08/31/23 – THP plans to complete work from October through November.
09/28/23 – Rappelling of courtyard façade scheduled for October 3rd.
10/03/23 – Rappelling canceled due to additional rappelling needed at A&D building. THP to reschedule.
02/29/24 – Rappelling scheduled for March 20th and March 21st (weather pending).
03/20/24 – Rappelling completed in the courtyard, but cancelled for the exterior of the building due to high winds.
03/28/24 – THP to reschedule rappelling for mid April.
04/25/24 – THP to reschedule final rappelling in mid May.
05/30/24 – THP plans to schedule rappel end of June.
06/24/24 – Email status of report and repairs to address both City issues.
06/27/24 – Budget sent to County for City repairs.
9/26/24 – THP to reach out to the City and determine placing repair package on hold for larger project.
12/10/24 – THP closing out the project.
CH – Annual Façade Monitoring 2023 (F083) Read More »
PM: John Nester, Paul Bellman
04/06/23 – Hamilton County requested SOSS.
04/06/23 – THP, Kleingers, and HC – Site Visit – Review Scope
04/25/23 – Received Kleingers proposal.
05/09/23 – Received Terracon’s proposal.
05/23/23 – THP submitted SOSS to County for Review.
07/12/23 – Hamilton County approved S0SS.
08/21/23 – Terracon on site to mark boring locations.
08/23/23 – OUPs to mark utilities prior to boring.
08/24/23 – Terracon on site for drilling of test bore locations.
09/12/23 – Hamilton County communicated to THP the flipping of Base Bid and Alternate work.
09/18/23 – THP received parking options from Kleingers. Need to review with Hamilton County.
09/26/23 – THP scheduled on site meeting with Kleingers and Hamilton County. Meeting cancelled – Reschedule Teams Mtg.
10/09/23 – THP and County had meeting to review budget and scope of work. Scope of work adjusted to available funds.
10/10/23 – County Issued AIA forms for bid documents.
10/20/23 – Kleingers sent THP review bid drawings and technical specifications.
10/20/23 – THP issued review bid documents – project manual, drawings, and XBE opinion of probable costs.
10/26/23 – Issue of bid documents anticipated for October 31, 2023.
10/30/23- Documents advertised to bid.
11/08/23 – Prebid meeting occurred.
11/09/23 – Addendum No. 1 issued.
12/07/23 – Bid opening scheduled for 12/13/23.
12/13/23 – Bid opening. (3) bids received and under review.
02/23/24 – Hamilton County sent THP Contract Document A101 for review.
02/29/24 – KT Holden low responsive bid. Hamilton County sent AIA contract to KT Holden for review and execution.
03/25/24 – KT Holden returned signed contract to Hamilton County.
03/22/24 – Approved Contract issued to KT Holden by Hamilton County.
05/14/24 – Preconstruction meeting held on site.
05/16/24 – Hamilton County issued notice to proceed to KT Holden.
05/17/24 – Preconstruction meeting minutes issued.
05/20/24 – KT Holden submitted Schedule of Values and submittals.
05/22/24 – KT Holden submitted for permit.
05/28/24 – Kleingers returned submittals. THP to review and return.
05/21/24 – KT Holden picked up approved permit.
06/25/24 – THP returned submittals to KT Holden. Revised submittals returned to THP and sent to Kleingers.
06/25/24 – KT Holden indicated work is scheduled for August.
07/18/24 – THP emailed KT Holden for schedule update.
07/24/24 – KT Holden Scheduled for mobilization on 8/05/24.
08/23/24 – Kleingers conducted a site visit. Utilities and sawcuts were marked.
08/28/24 – KT Holden on site and started construction.
09/03/24 – KT Holden working on asphalt removal and subgrade work.
09/11/24 – KT Holden asphalt work begins.
09/12/24 – KT Holden concrete work begins.
09/25/24 – Hamilton County, THP, and Kleinger met for final site walk through. THP issued Field Report and Punch list.
09/25/24 – KT Holden submitted Pay App #1 and #2 for review.
10/07/24 – THP returned Pay App #1 and #2 to Hamilton County.
10/31/24 – THP will send Closeout requirements to KT Holden.
11/27/24 – Building Inspection passed and Inspector will close permit in system.
12/11/24 – THP Reviewing Closeout documents and submit pencil copy to County for review prior to printing.
01/24/25 – KT Holden sent Closeout documents to Hamilton County – Confirmation received. Final Pay Application needs to be submitted.
02/04/25 – THP sent Hamilton County Final Pay Application #4.
02/27/25 – THP to archive project.
PM: Bert Watts, Paul Bellman
– Hamilton County requested SOSS.
04/26/23 – Pinnacle Enviromental to provide proposal.
05/01/23 – THP submitted SOSS to County for review.
05/10/23 – County approved SOSS.
05/22/23 – THP sent Pinnacle Contract for signature.
07/07/23 – THP received signed Contract from Pinnacle.
07/18/23 – THP forwarded Pinnacle contacts for background checks.
08/21/23 – Pinnacle Environmental on site for NESHAP Hazardous Material Inspection.
09/27/23 – THP Requested proposals from ThermalTech and Pinnacle. Provide SOSS to Hamilton County.
10/19/23 – THP received Pinnacle Pre-Demolition NESHAP report.
10/20/23 – THP published Pinnacle report to the County.
12/07/23 – Chris Belcher with Pinnacle coordinate contractor effort to abate the cottage the first week of December. Pinnacle plans to update their NESHAP report once the work is complete.
01/18/24 – THP reached out to Chris Belcher with Pinnacle for final report.
01/31/24 – THP reached out again to Chris Belcher with Pinnacle for Ffnal report.
Hillcrest Birch Cottage Removal Assessment (F078) Read More »
PM: Bert Watts, Ken Orloff
04/19/23 – THP submitted SOSS for review by Hamilton County.
07/18/23 – Hamilton County approved SOSS.
525 – Civil and Special Inspection (F075) Read More »
PM: John Nester, Mike Barth
03/29/23 – TEI Submits SOSS. Project pending approval of SOSS and PO.
04/27/23 – TEI receives PO and Signed SOSS. TEI finalizing drawings for HCFD review and then will get permits for installation by trades.
05/23/23 – TEI sends review set to HCFD. Will apply for IBI permit upon receipt/implementation of owner’s review comments.
06/28/23 – TEI meets with John Nester, Andrea Hatton, In Zelner and the HC Electricians to review. Minor changes were made and the drawings were submitted to Blue Ash for plan review and permit. Plan review passed and permit is ready for pick up at Blue Ash with a balance of $50 +change. TEI to pick up permit for HC and work can commence.
7/26/23 – TEI picks up permit and delivers to trades. Trades is working on the modifications to the branch circuits.
08/24/23 – Trades to notify TEI when work is completed and TEI will arrange for inspections.
09/26/23 – County electricians reach out to TEI for review of as-built documents. Tentative meeting the week of 10/02.
10/26/23 – TEI and county electricians meet to review as-built documents. TEI incorporates the as-builts onto the CAD files. TEI drawings will be sent to HCFD upon completion of QC review.
12/06/23 – HamCo electricians indicate that there are a few more changes that the facility is wanting to make. Electricians to get modifications to TEI to incorporate in the AS-builts.
01/30/24 -The Sally Port Doors were moved to EM power. Electricians Told TEI circuitry information to include on as-builts.
02/28/24 – TEI updating permit drawings and will submit to Blue Ash for engineering review and final final inspections.
07/24/24 – REFERENCE OTHER STRING FOR UPDATES.
Crime Lab – Emergency Power Upgrades Read More »
PM: Rycca Thacker, Mike Barth
03/29/23 – TEI submits SOSS for project. Project pending Approval and PO.
03/30/23 – SOSS and PO approved, RT will send.
04/27/23 – TEI starting field work and will develop SD/Cost estimates.
05/23/23 – TEI meeting building manager and HCFD to provide field investigation. TEI evaluates (2) options – direct MCC replacement and replacing with PDP since the motors are served with VFDs now. TEI submits SD PDFs and costs for the work. HCFD to provide next steps.
09/26/23 – TEI submits design drawings to HCFD for review. TEI receives review comments. Drawings finalized.
10/26/23 – Upon determination of XBE requirements, this project will be issued as a small projects bid.
12/06/23 – Project issued for small projects bid. Prebid conducted and Addendum published. Bids due to TEI on Friday 12/08/23 at 4:00 PM.
01/30/24 – Project bids received and vetted. Project in contract approval phase. lead time for equipment will be roughly 12 weeks.
02/28/24 – Glenwood electric is sent the PO and signed contract. Submittals yet to be received/approved by TEI.
03/27/24 – TEI receives submittals and approves. Equipment is being procured.
04/24/24 – Construction kickoff scheduled for 4/29.
05/29/24 – Construction kickoff meeting occurred. Glenwood orders electrical equipment (Scheduled ship date = 11/20/24)
06/26/24 – No Updates.
07/24/24 – No Updates.
08/28/24 – No Updates.
12/11/24 – HCFD, TEI and Glenwood meet on site for Pre-construction meeting. Panel in Glenwood shop – Enclosure no with Panel. Glenwood looking at early January for installation.
01/29/25 – HCFD requests installation schedule form Glenwood.
02/26/25 – Installation to begin in next week or so.
04/23/25 – Project installed, complete and punchlist completed. Pending punchlist and closeout.
05/28/25 – Pending closeout documents.
06/25/25 – TEI approves closeout documents. Project completion pending delivery of binders.
07/30/25 – TEI reaches out to Glenwood for binders.
07/31/25 – OK to Archive, all done.
A&D – Chiller Room MCC Replacement Read More »
PM: John Nester. Sam Hofmann
02/15/23 – Signed SOSS received. Painter to be hired by County.
03/30/23 – No Update.
04/27/23 – Meeting with Captain Wilson Scheduled for today.
05/25/23 – Meeting to finalize color selection to be scheduled in near future.
06/29/23 – Drawings will be ready by next week.
07/27/23 – Met with Sheriffs to finalize paint selections. Complete drawings to be given to county next week.
08/31/23 – 5th floor drawings provided. Final set to be complete.
09/28/23 – Final set to be sent next week.
02/29/24 – Final plans sent to County. Executive summary sent to Bert.
03/28/24 – No Update.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – No Update.
07/25/24 – No Update.
08/29/24 – No Update.
09/26/24 – No Update. OK to archive.
PM: John Nester, Matt Rigdon
08/26/22 – Hamilton County requested SOSS.
12/08/23 – THP provided SOSS for review.
12/20/23 – Hamilton County approved SOSS.
03/23/23 – THP anticipate to issue design development documents on 03/28/23.
04/25/23 – THP and Hamilton County met to discuss work. Hamilton County to perform work in-house. THP to provide material list for Hamilton County’s review.
05/24/23 – THP to THP to also send review of material lists of products. Work is still anticipated to be performed in-house.
08/31/23 – THP to send review of the new lapeyre stair at TPC which is to be included in the WHT Railing package.
10/19/23 – THP published review documents for combine 230 WHT rail and TPC stair project.
10/26/23 – THP finalizing documents from County comments.
10/25/23 – THP published gate ordering drawings for Facility department.
11/01/23 – THP published bid documents to ZSR Contracting and Restoration, American Façade Restoration, John P. Tumlin, and Journey Steel.
11/06/23 – Prebid meeting occurred.
11/09/23 – Addendum No. 1 published.
11/17/23 – Bids received from ZSR Contracting and Restoration and American Façade Restoration.
11/21/23 – THP published a bid summary letter for review by the County.
01/23/23 – ZSR Contracting and Restoration was awarded the project at the end of November. Email received from Hamilton County that the contracts are still being processed. Lead time for materials to be 5-6 weeks once contract is received.
2/28/24 – No updates from THP.
3/26/24 – THP received SOV and Project Schedule. Pre-construction meeting to be set closer to delivery time of prefab stair. Prefab stair expected to be delivered first week of May.
04/24/24 – Preconstruction meeting completed.
05/23/24 – THP received revised shop drawings for stair at Portune Center.
09/26/24 – First Progress meeting held on 09/23/24. ZSR to mobilize this week and begin demolition of existing stair at TPC.
12/03/24 – ZSR has addressed outstanding items at the new staircase. THP to begin close out procedures with ZSR.
01/29/25 – Closing out – beginning phase. Doug (ZSR) sent everything over to their office manager last week and he is getting AIA docs together. Doug is hoping to have everything to me this week to review.
3/26/25 – Finalizing Closeout documents. Should be ready to forward to HC soon.
04/24/25 – THP dropped off final closeout documents.
04/24/25 – Archive project.
TPC – Rail and Gate Project (F073) Read More »
PM: Rycca Thacker, John Millar
01/26/23 – Hamilton County requested SOSS for 2023 work.
02/23/23 – THP provided SOSS for County review.
03/07/23 – Hamilton County approved SOSS.
JFS General Structural Services (F079) Read More »
PM: Matt Butz, Paul Bellman/John Millar
12/30/22 – Hamilton County requested SOSS.
02/23/23 – THP Submitted SOSS.
03/22/23 – Hamilton County approved SOSS.
04/27/23 – Design work scheduled to begin 6/1/23 and the project being bid 9/1/23.
07/21/23 – THP needs to schedule a kick-off meeting with the County.
08/21/23 – Kick-off meeting held with Hamilton County and THP.
09/26/23 – THP met with Hamilton County to review site logistics. Preparing Bid Docs for 10/09/2023.
10/04/23 – THP published bid document project manual for final review by the County Facilities.
10/05/23 – THP published bid document drawing for final review by County Facilities.
10/06/23 – County provided comments to the documents.
10/06/23 – THP published final bid documents to Purchasing, Facilities, and Arc.
10/11/23 – Skywalk project advertised to bid.
10/18/23 – Prebid Meeting occurred.
10/23/23 – Addendum No. 1 Issued.
10/26/23 – Bid opening scheduled for 11/15/23.
10/31/23 – Bid questions received by County and forwarded to THP.
11/01/23- Addendum No. 2 issued by THP. Bid opening changed to November 20, 2023.
11/09/23 – Addendum No. 3 issued by THP.
11/20/23 – Bid opening occurred. Browning Chapman and Buckeye Construction submitted bids. One bid was below the advertised budget and the second bid was under the 20% threshold. Purchasing sent bids sent to economic inclusion department for review.
12/07/23 – Bids under review.
12/15/23 – Bids found to be unresponsive.
02/01/24 – THP requested to repackage project for rebid in 2024.
02/29/24 – THP working on DD set.
02/29/24 – THP to issue updated Bid Documents to Hamilton County for Owner review.
03/14/24 – THP issued DD review set with combined roofing project.
03/21/24 – HC Board of Commissioners approved budget for Façade project.
03/21/24 – THP met with Hamilton County to review project DD documents. Based on timing and bid procedure, County requested project bid in early June.
03/28/24 – THP working on documents.
04/25/24 – THP working on documents.
05/30/24 – THP working on documents and targeting a bid set for June.
06/26/24 – THP working on documents and targeting a bid set for July.
07/17/24 – Project is combined with FOO2 – Justice Center Skywalk Roof Replacement.
JC – Skywalk Exterior Repairs (F077) Read More »
PM: Bert Watts, John Millar
11/12/22 – Hamilton County requested SOSS.
12/12/22 – THP provided SOSS.
12/20/22 – County approved SOSS.
Building Envelope Master Plan Ex. Summary (F071) Read More »
11/09/22 – Hamilton County requested SOSS.
11/21/22 – THP provide SOSS for review.
12/12/22 – Hamilton County approved SOSS.
THP Design and Consulting Services (F070) Read More »
11/09/22 – Hamilton County requested SOSS.
11/21/22 – THP provide SOSS for review.
12/12/22 – Hamilton County approved SOSS.
12/29/30 – THP coordinated Courthouse stone knock downs and surveyed southeast corner of the building.
12/30/22 – THP supported Champlin with 2020 Auburn flooring repairs.
01/06/23 – THP and AFR completed knock down work at Courthouse.
01/26/23 – THP updated project status work and attended monthly mtg.
02/23/23 – THP updated project status work and attended monthly mtg.
03/14/23 – THP attend WBE/MBE training meeting for Partners.
03/30/23 – During March, THP hired and coordinated special inspection work for 800 Broadway concrete pour.
04/26/23 – Railing redesign work for 800 Broadway work concrete platform and bulletin was completed.
THP 2023 General Services (F069) Read More »
PM: John Nester, Terry Cannon
02/23/23 – All fieldwork is complete. TTE writing report now and creating cost estimates.
03/29/23 – Report is complete and in for final review with TTC.
04/25/23 – Report sent back as not complete, need pricing and scope updates.
05/21/23 – Phasing drawings completed. Cost estimated updated, final report updated for review. It shoudl be ready by Thursday meeting.
06/28/23 – New version ready to send in for review. This version has the cost estimate, sanitary repairs and drawings included.
07/26/23 – Report is done and priced up. Need to give Facilities the report, drawings and appendices on a thumb drive.
08/29/23 – Coty updated the report this week and cost in the 2024 adn the report were reconciled to some extent. TTC needs to spend time finalizing this work.
09/27/23 – Report is complete, cost estimate is done. I hope to send to JN before the meeting.
10/25/23 – Report is complete, still owe John a final copy.
12/06/23 – OMG I can’t believe this has not been sent to John yet. I HAVE to get this by end of year.
JC – Plumbing Study Read More »
PM: John Nester, Terry Cannon
02/14/23 – Met with John on site to explore options for installing this restroom, Coty, Terry, Sam.
02/23/23 – Champlin to prepare concept drawings, and then we will estimate two options and cost for the job.
03/29/23 – Estimate, dwgs and cost sent to County for consideration.
03/30/23 – OK to archive, HCDF is self-performing the work by swapping the judges chamber and jury room.
CH – Courtroom 380 Restroom Study Read More »
PM: John Nester, Terry Cannon
02/23/23 – Fieldwork completed this week. Report is underway.
03/29/23 – Report is complete and in for final review with TTC.
04/25/23 – Being reviewed now and should be sent to JN before Thursday.
05/21/23 – Final Report should be sent in by Thursday meeting.
06/28/23 – Final Report delivered in hard copy to John.
P&D Plumbing Study Read More »
PM: John Nester, Terry Cannon
02/23/23 – Fieldwork complete. Report has been started. No dissimilar metals were found.
03/15/23 – Additional fieldwork conducted to confirm missing piping.
03/29/23 – Report is being updated.
04/25/23 – Being reviewed now and should be sent to JN before Thursday.
05/21/23 – Final Report sent this evening including final drawings.
06/28/23 – Final Report delivered in hard copy.
250 WHT – Plumbing Study Read More »
PM: Rycca Thacker, Sam Hofmann
02/22/23 – Bid awarded to Alpha. Contracts are in progress.
03/30/23 – Contracts still in progress.
04/27/23 – Pre-construction meeting held. Submittals incoming.
05/25/23 – Some submittals received and returned. Permit approved. Construction is almost ready to begin.
06/29/23 – Construction ready to begin 2 weeks from notice from Rycca.
07/27/23 – Construction began this week. Most submittals complete.
08/31/23 – Construction ongoing. CO#1 in progress to add minor scope. TTE responded to the plumbing change order work with comments.
09/28/23 – Construction ongoing. CO#1 settled. CO#2 has not been agreed on.
10/25/23 – Construction ongoing. Change Order #2 rejected by TTE. Alpha to rework change and send back to us. Lights have been reworked in current ceiling configuration.
12/07/23 – Work is finishing up. Punch list held on 11/27. Back punch to be scheduled.
02/01/24 – Drinking Fountain cover still not acceptable, TE to work on better cover for the plumbing.
02/29/24 – Back punch items still unresolved. Closeouts in review.
03/28/24 – Waiting on hard copies from Alpha.
04/25/24 – Closeouts received. Check to see why its so large. Three hard copies still required with a thumb drive.
05/30/24 – Waiting on release of liens. TTC repaired the water cooler cover to give it more accessibility.
06/27/24 – No Update. TTC modified the EWC wrap so it’s better than it was.
07/23/24 – TTV replaced the pipe wrap again and it looks better than “better than it was”
08/29/24 – All closeouts received. Final pay app released. Ready to archive.
Comm Center – Lobby and Breakroom Renovation Read More »
PM: Matt Butz, Sam Hofmann
02/22/23 – SOSS received. Kickoff to be scheduled soon.
03/30/23 – Kickoff held on site. Sheriffs chose 7 doors for base bid and another 4 as an alternate. They will provide a few more doors to be added into the scope as alternates.
04/27/23 – Still waiting on additional doors from sheriffs.
05/25/23 – No update.
06/29/23 – List of doors and alternates has been provided. Drawings can be complete by end of month.
07/27/23 – Drawings will be complete by end of August.
08/31/23 – Drawings will be complete by end of September.
09/28/23 – Meeting held with Captain Wilson to confirm scope. Project will be out to bid 10/10.
10/25/23 – Project is out to bid.
12/07/23 – Bids returned. Cornerstone is lowest bidder. Bid review meeting held 12/5. Project now in contract phase.
02/29/24 – Cornerstone to send submittals in near future.
03/28/24 – Still waiting on submittals from Cornerstone.
04/25/24 – No Update.
05/30/24 – Submittals received and returned.
06/27/24 – Cornerstone field verification completed this week. Doors to be ordered.
08/29/24 – No Update.
09/26/24 – Cornerstone placed order. Pre-con meeting to be scheduled in near future.
10/31/24 – No Update.
12/12/24 – Cornerstone has material in hand. Coordinating best time with sheriffs and ongoing lock project work.
01/30/25 – Work to be scheduled in line with lock project corrections.
02/27/25 – No update.
03/27/25 – No Update.
04/24/25 – First Pod began. All frames installed but doors did not fit. New doors shipped immediately to finish the first pod. The rest of the doors will ship end of May.
05/29/25 – Pod complete and back punched. Next pod to begin next week.
06/26/25 – Next phase punch scheduled for tomorrow. Final phase to begin in 3 weeks.
07/31/25 – Next set of frames and Phase 4 frames to be manufactured together. 12 week lead time for delivery.
08/28/25 – Frames to be delivered mid september.
09/25/25 – Frames will be delivered next week.
10/30/25 – Cornerstone to remobilize monday.
12/11/25 – Phase 2, 3 and 4 have effectively merged into one project. All material is on site. Scope has been scheduled per unit with phase 2 and 4.
01/28/26 – Work Complete. Closeouts outstanding.
02/26/26 – No update.
03/26/26 – No update.
04/30/26 – No update.
05/28/26 – No update.
06/25/26 – No update.
07/30/26 – Closeouts reviewed and missing items requested.
08/28/26 – No update.
09/24/26 – No update.
10/29/26 – No update.
JC – Selective Cell Door Replacement 2023 (Ph 3 Cornerstone) Read More »
PM: Matt Butz, Sam Hofmann
02/22/23 – SOSS received. Kickoff to be scheduled soon.
03/28/23 – Kickoff held on site. design in progress.
04/27/23 – Overhead doors have been on site to assist with design. Bifold doors to be replaced with new bifold doors. Research needed for physical barrier to stop trucks from hitting garage doors.
05/25/23 – Two bifold door manufacturers are working on quotes. One has been out to site. Drawings in progress.
06/29/23 – Still have not received a quote. Followed up with manufacturers. Drawings in progress.
07/27/23 – Drawings can be complete by end of August.
08/31/23 – Drawings in progress. Nearly complete.
09/28/23 – Project will be out to bid 10/10.
10/25/23 – Project is put on pause until budget information is worked out.
12/07/23 – No update
02/29/24 – Submitted to ODRC for approval.
03/28/24 – State approval received. Final review set to be submitted 4/5.
04/25/24 – Request from the state requires additional design and funding. Waiting for further direction.
05/30/24 – No update.
06/27/24 – State approved the sally port door installation without the mini PLC system. Project to be bid out in near future.
07/25/24 – Project is out to Bid. Pre-bid scheduled for 7/30.
08/29/24 – Bids came in awardable. Robert Bell to review acceptable bids. Bid vet to be scheduled pending ok from Robert.
09/26/24 – Project in contract phase.
10/31/24 – Project still in contract phase. Preliminary site visit held for measurements.
01/30/24 – Submittals returned. Change order to receive hydraulic four-fold doors instead of electrical doors incoming. Kickoff to be scheduled closer to delivery of doors.
02/27/25 – Submittals returned. All doors by 4-fold are ordered and being delivered end of march. Change order #2 approved. Resubmittal for 4-fold door outstanding.
03/27/25 – All doors ordered. Alpha has mobilized to begin electrical work.
04/24/25 – Grant extension was approved. High-speed doors have been installed. North Sallyport doors are next. Trash compactor door has been added to the scope.
05/29/25 – Issue related to door and barrier arm connection has been solved. Overhead door to correct the issue next week. Bifold doors and trash compactor door to be delivered next week.
06/26/25 – North building complete. Change order to paint existing frames approved. Trash compactor door installation ongoing. Bi-fold door control units were delayed. installation to being next week.
07/31/25 – Doors punched yesterday. Multiple change orders requested on small items. Change order frame painting still outstanding.
09/25/25 – Pricing for various items still outstanding. Multiple issues with doors over the last month. Back punch to be scheduled.
10/30/25 – Back punch has yet to occur. Multiple failures this month have been recorded. Closeouts outstanding.
12/11/25 – Change order work outstanding. Meeting with Alpha and Overhead Doors to address continual failure of doors.
02/26/26 – Closeouts outstanding. Doors still having issues.
03/26/26 – No update.
04/30/26 – No update.
06/25/26 – Final closeout review complete. Pay app deadline of this friday.
07/30/26 – Closeouts delivered to County.
JC – Sally Port Door Replacement Read More »