Hamilton County Facilities

2020 – Breakroom to Locker Room Renovation

PM: Sam Hofmann / County: John Nester

02/22/23 – SOSS received. Preliminary plan sent to John. Scope changed by new personnel.

03/30/23 – Kickoff held on site. Estimate in progress.

04/27/23 – Plans complete. Estimate to be complete in near future.

05/25/23 – Plans and estimate have been uploaded to archibus.

06/29/23 – No Update

07/27/23 – No Update

2020 – Breakroom to Locker Room Renovation Read More »

SPHQ – Academy Building Repurpose

PM: Sam Hofmann, Matt Butz
02/22/23 – SOSS received. Kick off to be held soon.
03/30/23 – Kickoff held on site with user. Matt to figure out budget and who pays for furniture. No movement until then.
04/27/23 – Design development on going. We will need one more meeting with users as we finish CDs
05/25/23 – Meeting held on site with users. Drawings in progress.
06/29/23 – Final review meeting held on 6/26. Discussed replacing clerestory windows. Window opening is not a glass block module so aluminum storefront and igu will be specified.
07/27/23 – Final review set submitted to county. Need to redo project manual with updated requirements.
08/31/23 – Project goes out to bid today.
09/28/23 – Bid opens today.
10/25/23 – Project was re-bid due to XBE paperwork not being filled out properly.
12/07/23 – Bids returned. Bid vet to be scheduled for this week.
02/29/24 – Projects kicked off. Submittals received and being returned.
03/28/24 – Construction to begin 4/1.
04/25/24 – Construction ongoing. Romex was found in the building not in conduit. We will get a cost to upgrade the electric to conduit on this job. We have removed the sink from the job and will take a credit for that work.
05/30/24 – Construction ongoing.
06/27/24 – Construction ongoing.
07/23/24 – Const Mtg onsite but little progress from last meeting.
08/29/24 – Progress being made. Tumlin removed wrong water fountain.
09/26/24 – Paint and casework mostly complete. Flooring getting installed next week. New wifi getting installed TTC to follow up.
10/31/24 – Punchlist issues, but additional work is needed. Deteriorated window sills needs to be fixed, EWC question sent today to TTE.
12/12/24 – Punchlist distributed. Sheriff are happy with new space. TTC replaced thermostats and put them on WIFI.
01/30/25 – Project complete. Closeouts to be submitted by Tumlin.
02/27/25 – Tumlin will be onsite for punch items. Closeouts outstanding.
03/27/25 – One punch item outstanding. Closeouts outstanding.
04/24/25 – Closeouts outstanding. Final pay app submitted by Tumlin will be held until closeouts are received.
05/29/25 – Parts missing. Tumlin to complete closeouts.
08/28/25 – No Updates.
09/25/25 – No Updates, we are still waiting on closeout documents.
10/30/25 – Closeout updates have been received from Tumlin. We will review to determine if they are acceptable.
02/26/26 – Closeouts given back to Tumlin to correct and return.
03/26/26 – Closeouts in Countys hands.

SPHQ – Academy Building Repurpose Read More »

230 – Guard Rail – Safety Gate (F068)

PM: John Nester, Matt Rigdon
09/02/22 – Hamilton County requested SOSS.
09/29/22 – THP and Hamilton County walked the sites.
12/08/23 – THP provided SOSS for review.
12/20/23 – Hamilton County approved SOSS.
03/23/23 – THP anticipate to issue design development documents on 03/28/23.
04/25/23 – THP and Hamilton County meeting to discuss work. Hamilton County to perform work in-house. THP to provide material list for Hamilton County’s review.
05/24/23 – THP to send review set of revision drawings that account for existing ductwork interferences. THP to also send review of material lists of products. Work is still anticipated to be performed in-house.
07/17/23 Requested to combine the two safety gate projects for WHT & TPC Buildings into one drawing set. Requested by HamCo to separate Railing at WHT as individual project.
07/26/23 – Documents being finalized and to send July 31.
10/19/23 – THP published review documents for combine 230 WHT rail and TPC stair project.
10/26/23 – THP finalizing documents from County comments.
10/25/23 – THP published gate ordering drawings for Facility department.
11/01/23 – THP published bid documents to ZSR Contracting and Restoration, American Façade Restoration, John P. Tumlin, and Journey Steel.
11/06/23 – Prebid meeting occurred.
11/09/23 – Addendum No. 1 published.
11/17/23 – Bids received from ZSR Contracting and Restoration and American Façade Restoration.
11/21/23 – THP published a bid summary letter for review by the County.
01/31/24 – No updates from THP.
2/23/24 – County sent AIA contracts to ZSR for review and execution.

230 – Guard Rail – Safety Gate (F068) Read More »

525 – EMA/JFS/513 Office Renovations

PM: Bert Watts, Mike Murphy, Paul Bellman, Terry Cannon

01/25/23 – SD and Cost complete.  Created new category and started tracking EMA renovation.  CD documents have been started.  THP and TTE starting overhead door early project.  BW sent information for design.
02/22/23 – User meetings complete. DD in progress from user meeting changes.
03/30/23 – Met with JFS last week. Need to get approval on design from users.
04/27/23 – Meeting on site with JFS scheduled for 5/5. Design development to proceed after that. Update old estimate with new cost for revised design. Cost is due in two weeks. Champlin to send revised plans. Include owner required items in the new cost including blue brick screen wall that is coming down, new sidewalk, plus other owner items.
05/11/23 – Champlin requested updated opinion of probable cost with updated scope of work.
05/17/23 – THP provided updated opinion of probable costs for structural scope of work.
05/17/23 – THP provided SOSS for DD through CA services based on new scope of structural work.
05/21/23 – ThermalTech DD cost updated in Archibus and shared with the team. Drawings are being updated this week.
05/25/23 – Drawings and estimate have been uploaded to Archibus. Landlord improvements have been marked with a (C).
06/12/23 – THP – Champlin returned executed Contract for DD-CA Services.
06/29/23 – No updates from THP.
06/29/23 – Final plans have been approved by users. follow up information to be provided to County this week. CDs in progress.
07/27/23 – 95% Review set submitted to County. Page turn with users to be scheduled.
08/09/23 – THP updated structural work and fees to the Archibus project estimate.
08/31/23 – Updated department breakdown plans and estimate. User page turn to be scheduled in near future.
09/27/23 – THP waiting to hear from Champlin about the page turn meeting with Hamilton County.
09/28/23 – Review meeting held with EMA. minor changes to plans made. JFS and 513 meetings to be scheduled.
10/25/23 – THP sending bid set to Champlin. Meetings held with all users. Final owner review sent to County for landlord approval.
11/22/23 – Building owner has approved the Phase 2 renovation plans. THP to send Bid Set to Champlin once bid date has been set.
12/06/23 – THP to send Bid Set to Champlin for 12/15/23 issuance.
12/07/23 – Received final approval from landlord and County. Bid issuance on 12/15.
01/04/24 – Project advertised to Bid.
01/18/24 – Pre-bid meeting on site.
01/25/24 – Addendum #1 issued.
01/29/24 – THP sent stamped permit set to Champlin.
02/07/24 – THP Addendum #2 issued. Unit prices and details for CMU tuckpointing and CMU replacement were included.
02/22/24 – THP – Bid Opening. 4 bids received (Alpha Construction, John P. Tumlin & Sons, Leo J. Brielmaier, and Triton Services). Champlin to evaluate bids.
03/28/24 – Contract phase ongoing.
04/19/24 – THP – Approved construction contract approved by the Board of County Commissioners and sent to project team.
04/23/24 – THP – County issued PO for the project to the team. Pre-construction meeting tentatively scheduled for 05/03/24 afternoon.
04/25/24 – Contracts finalized. Project kickoff tentatively scheduled for 5/3.
05/03/24 – Pre-construction meeting with full team at project site.
05/30/24 – Kickoff held. Submittals in progress.
06/27/24 – Pre-mobilization meeting scheduled for 7/12. RTU submittals have been rejected, TEI trying to get submittals on approved manufacturers.
07/12/24 – THP reviewed front entry slab drainage issue with Hamilton County.
07/12/24 – Pre-mobilization meeting with full team at project site.
07/25/24 – Construction to begin Monday.
08/28/24 – THP returned structural shop drawings to Champlin.
08/29/24 – Construction ongoing. More abatement to be completed next week. Demo almost complete.
09/26/24 – Construction ongoing. Main sewer line underslab is damaged beyond use. Tumlin to report on extent of damage. CO2 is being discussed and finalized. THP will return approved Masonry Lintel shop drawings to Champlin on 9/26. Water test is complete and Fire Protection calculation underway.
10/29/24 – THP responded to Champlin regarding Masonry repairs. Hamilton County to determine extent of repairs.
10/31/24 – Construction ongoing. Change order 2 and 3 approved for sanitary line work and fire protection changes.
12/06/24 – THP visited the site to coordinate supplemental steel with Thermal Tech and Tumlin to help with the response to RFI 23. THP issued a field report for review by Thermal Tech.
12/12/24 – Work ongoing. Forest Park has provided report stating that any combustible material will need to be removed. We believe the wood studs would be grandfathered in compliance. Champlin to investigate.
01/27/25 – Work progressing, Tumlin stated they would be complete at the end of February. ThermalTech (TTC) trying to schedule a coordination meeting between Emcor, Bison, and KW about final controls scope between project and state term work. Rooftop units not onsite yet but should be arriving soon. Plumbing rough-in mostly complete. Forest part has approved our fire protection permit and Preferred Fire should mobilize soon to the site for sprinkler work. According to Tumlin, we will not have to move all the trucks parked in the warehouse for the sprinkler work (all sprinklers in the Northeast Warehouse must be replaced with 11.2 sprinkler head).
02/26/25 – Work continues in space. GC, MC, EC, FPC are all on site performing work daily. PC coming back soon when the fixtures will be installed. TTE bringing Wi-Fi plan to Friday meeting. Several COR have come in this week, HC asked for the Fire Pit cost too, the permit needs to be amended for the additional inspection. We will get a scheduled update this Friday.
03/11/25 – HVAC Engineering Change drawing sent to Tumlin for their submission to FP for the return air openings on the first floor.
03/23/25 – TTE returned another set of controls submittals to Emcor for the ALC controls. Bison has not confirmed if we can get BACnet thermostats or now. ALC planning on interfacing through the SystemVu controllers in the RTU units.
03/25/25 – Plumbing Engineering change drawing set to Tumlin to give to Carrigan to give to FP for the natural gas adjudication letter received last week. ThermalTech continues to answer questions from the contractors working towards permit approvals.
03/27/25 – Pricing for Bulletin#3 received. Substantial completion date set at May 9th.
04/24/25 – RTUs delivered a month ahead of schedule and have been installed. Fire pit work ongoing. Railings will not be delivered and installed before May 9. Signage quote approved.
05/19/25 – THP visited the site to review supplemental steel.
05/29/25 – Punch list sent last week. Railing scheduled for delivery this week. Tumlin to schedule final inspection. Signage to begin install tomorrow.
06/24/25 – ThermalTech onsite this week working on HVAC issues. We are scheduled to come back for troubleshooting with MC and CC Friday at 7am. Emcor video was sent out from Ben.
06/25/25 – Final inspection complete. CO will be signed when Rafic returns. Ribbon cutting tomorrow.
07/31/25 – Ribbon cutting ceremony held. Several punch items still outstanding. Tumlin to begin closeouts. As-Builts not received yet. Emcor controls out this week for finalizing the new DDC controls..
08/28/25 – Tumlin confirmed all work is complete. Back puch to be scheduled. Closeouts outstanding.
09/25/25 – Backpunch complete. As-builts received. closeouts outstanding.
10/30/25 – Closeouts outstanding. Official CO received.
12/11/25 – No update.
01/28/26 – Closeouts in review.
02/26/26 – Waiting on closeout corrections.
03/26/26 – No update.
04/30/26 – No update.
05/28/26 – No update.
08/28/26 – Tumlin provided update on missing items.
09/24/26 – No Update.
10/29/26 – Closeouts received

525 – EMA/JFS/513 Office Renovations Read More »

525 – Warehouse Doors and Ramp (F072)

PM: Rycca Thacker, Paul Bellman
12/07/22 – THP submitted SOSS to Hamilton County.
01/08/23 – THP spoke with City and have verbal confirmation a new curb cut is allowed.
01/10/23 – THP proposed initial layout to Hamilton County.
01/19/23 – THP and Thermal Tech met Hamilton County and EMA personnel onsite to review site layout and get field measurements.
02/10/23 – THP sent owner review documents to Hamilton County.
02/21/23 – Owner has approved the warehouse improvements. Hamilton County getting funding put in place.
02/24/23 – THP and Kleingers meeting with Hamilton County and EMA personnel to measure vehicles for final ramp layout and design.
03/16/23 – THP sent bid documents to Hamilton County Purchasing Department.
03/20/23 – Bid Documents released by Hamilton County Purchasing Department.
03/29/23 – Prebid meeting completed.
03/30/23 – Project opening scheduled for 4/13/23.
04/13/23 – Bid opening occurred with John P. Tumlin & Sons being the apparent low bidder and under budget.
04/21/23 – THP published a bid summary letter, recommending the County proceed with Tumlin.
05/21/23 – Permit drawings created and sent last week.
04/21/2023 – THP published a bid summary letter, recommending the County proceed with John P. Tumlin & Sons.
05/15/23 – HC sent contract to John P. Tumlin & Sons and requested their insurance certificates.
05/31/23 – HC waiting on Board of Commissioners for contract approval.
05/31/23 – John P. Tumlin & Sons working on schedule of values, schedule, site specific safety plan, material submittals, background checks, etc.
06/29/23 – THP receiving submittals from John P. Tumlin & Sons.
07/12/23 – HC notified THP that the construction contract will be presented to the Commissioners at their public meeting on 07/27/23.
07/27/23 – TTE returned the PTAC submittals again (second time) for changes.
07/28/23 – HC sent approved contract, PO, and Notice to Proceed to THP and Tumlin.
08/22/23 – Pre-Construction meeting set for Wednesday, August 30.
08/30/23 – Pre-construction meeting with THP, Hamilton County, Tumlin, ThermalTech Engineering, and Kleingers.
09/27/23 – Tumlin submitted construction schedule. Tentative date for mobilization set for October 2.
10/02/23 – Tumlin mobilized to site to begin construction.
10/25/23 – Interior overhead doors installed, masonry repaired at office, PTAC installed in office, interior slab on grade has been removed and replaced, interior man door has been installed, steel framing and masonry work at exterior door openings has started. Gas line has been relocated and additional gas line repairs have been approved via change order.
11/27/23 – Steel framing and masonry work for exterior openings has been completed. Both exterior overhead doors have been installed. Electric work and painting continuing inside. All mechanical/gas line repairs associated with this project have been completed. Exterior ramp (grading, forming, rebar/mesh, etc.) has been started. Concrete ramp pour scheduled for the week of 11/27/23.
12/06/23 – Electric work continuing inside. First two concrete ramp pours completed on 11/30/23 and 12/06/23.
01/02/24 – Last concrete pour for ramp completed.
01/24/24 – THP, ThermalTech, Hamilton County, and Forest Park met onsite to walk through and discuss required life safety items to get temporary certificate of occupancy for Phase 1. Team to address issues.
01/26/24 – Punchlist Walk Through with Bert Watts. Sent list to Tumlin.
01/30/24 – Additional Overhead Doors in back of warehouse started to get installed.
02/26/24 – THP, ThermalTech, and Champlin met onsite to review the vehicle layout. Champlin and ThermalTech to update Life Safety drawings and Electrical drawings, respectively, for in place vehicle layout with egress, emergency and exit lighting, etc to address issues that were discussed with Forest Park Building Department and Fire Department.
04/18/24 – THP received updated electrical drawings with emergency/exit lighting from ThermalTech. Request for change order pricing and updated drawings sent to Tumlin for installation.
04/24/24 – THP waiting to receive change order pricing from Tumlin. Installation of emergency/exit lighting required to close out phase 1 and building permit.
05/10/24 – Change Order for Emergency/Exit Lighting approved.
05/14/24 – Fully executed Change Order sent to all parties.
05/21/24 – Emergency/Exit Lighting submittal received. Waiting on review from ThermalTech to send approval. Installation to follow after submittal approval.
06/26/24 – ThermalTech reviewed Lighting submittal – Approved as Noted.
08/29/24 – Safety electrical items being installed.
09/26/24 – Pay Application #7 received for review.
10/11/24 – THP returned Pay Application #7 to Hamilton County.
10/31/24 – Closeout Process needs to be initiated.
12/11/24 – Closeout Process needs to be initiated.
01/23/25 – Closeout Process initiated with Tumlin.
02/26/25 – Closeout Process in progress by Tumlin.
03/26/25 – THP to follow-up with Tumlin on Closeout.
04/08/25 – THP sent Tumlin email on Closeout documents.
04/22/25 – Tumlin responded to email and indicated another request was sent out to subcontractors for closeout documents.
05/16/25 – Fire Alarm testing caused a short in the new fire alarm control panel. A fire watch was required for this weekend and was provided by a third party firm. TTE helped HamCo on first session until fire watch company arrived.
05/20/25 – Cin-Day installed the new FACP and replaced one address module, tested the existing system and found it to be working with no Trouble. We still need to work out warranty requirements.
05/19/25 – THP received close-out documents from Tumlin.
05/28/25 – THP started review of close-out documents.
06/25/25 – THP to return comments on close-out documents to Tumlin.
07/30/25 – THP reviewed close-out documents and sent Tumlin final comments/documents.
08/27/25 – Tumlin is sending final closeout documents to Hamilton County.
02/20/26 – Preconstruction Meeting held for Generator Plug-In Relocation.
02/23/26 – THP issued Preconstruction Meeting Minutes.
03/11/26 – On-site meeting held to review logistics of panel relocation.
03/24/26 – THP verified panel had been removed from the existing Blue Ash location. Status of permit drawings, IBI Inspection, closeout?
04/28/26 – Tumlin is working on final PW info for HC for Closeout Documents.
05/27/26 – County said do not archive until we get all closeout documents.
06/25/26 – Tumlin submitted requested Closeout Documents.
07/30/26 – Need IBI Inspection report for Closeout Documentation for Plug-in Electrical relocation. Davies to submit.
08/20/26 – THP sent project Meeting Minutes to HC.
08/27/26 – Rycca believes they have paid out this project.

525 – Warehouse Doors and Ramp (F072) Read More »

JC – Arc Flash Mitigation 2023

PM: Matt Butz, Mike Barth
01/25/23 – TEI Submits SOSS.   Project pending SOSS approval and PO.
02/23/23 – TEI receives signed SOSS and PO.  Project Kick off to be scheduled with HCFD.
03/29/23 = TEI and HCFD to schedule project kick off.
04/27/23 – TEI performs preliminary review of existing model.   TEI and HCFD to meet to discus next steps.
05/23/23 – TEI and HCFD to set up meeting to discuss next steps.  Proposed time of 9:00 AM on  6/2/23.
06/28/23 – June 2 meeting did not occur.  TEI requested availably from building manager.
7/26/23 – TEI, Matt Butz and building manager meet to discuss building electrical issues.  biggest issue is with breakers for floor machines tripping regularly.  TEI looking for ways to mitigate this issue.
08/24/23 – TEI determines that there are 2 options for moving forward.   The existing gear has built in transformers in the panels.  The cost to replace the is approximately 2 times the cost of sperate equipment.   The transformers are at the end of the  manufacturers standard life expectancy.  The transformers are not problematic at this time.   An option would be to install sub panels and pick up the added circuits from them and address the transformers as they become an issue.
09/26/23 – TEI developed drawings with the sub-panel option.  Review drawings to be  sent to HCFD by 09/29.
10/26/23 – TEI issues project for bids.  Prebid meeting for project occurred on 10/25/23.  Bids scheduled to open on 11/22.
12/06/23 – Bids received and Stem Electric is apparent low bidder.  TEI vets the bid and sends recommendation letter.   Contracts at prosecutors office for approval.
01/30/24 – Project waiting BOCC approval.
02/28/24 – Stem Electric receives signed contract and PO.  Preconstruction kick off to be scheduled in next 2 weeks and TEI awaiting submittals.
03/27/24 – Pre construction meeting scheduled for 04/15/24
04/24/24 – Preconstruction meeting occurred.  Project pending material procurement.
05/29/24 – Stem electric has mobilized to project site and construction has commenced.  working on floor to floor core drills and initial installation .
06/26/24 – Stem mobilized on site and work in progress. Vertical raceways installed through buildings. Wiring to begin with anticipated completion of installation end of July.
07/24/24 – Stem anticipates completion of base bid work by 08/02/2024. HCFD asked for CO pricing to add electric for equipment per the request of the HCSO.
08/28/24 – Stem complete with work pending closeout documents. TEI to print out new Arc Flash Labels and label the building.
09/25/24 – Waiting on Closeouts from Stem.
10/30/24 – Project completion pending closeouts from STEM. TEI provides new AF labels in both towers.
12/11/24 – TEI delivers (3) copies of Arc Flash report to HCFD with tables and single lines in the report.
02/26/25 – Project complete pending closeout.
03/26/25 – Project complete pending circuit breaker that was ordered with allowance $$. Can not close until breaker is delivered.
04/23/25 – Project waiting on breaker delivery.
05/28/25 – Project back punchlist walk scheduled for 5/30.
06/25/25 – Project backpunch completed. Stem completes items and sends pics to TEI and HCFD of completed items. Pending Closeout documents.
07/30/25 – Closeout documents submitted and provided to HCFD. (3) hard copies and (3) Thumb drives.
08/28/25 – Ready to Archive.

JC – Arc Flash Mitigation 2023 Read More »

800 – Arc Flash Mitigation 2023

PM: Matt, Mike Barth

01/25/23 – TEI Submits SOSS.  Project pending SOSS approval and PO.
02/23/23 – Project pending SOSS approval and PO.
03/29/23 – TEI receives signed SOSS and PO.  Project kickoff to be scheduled with TEI and HCFD.
04/27/23 – TEI performs preliminary review of existing model.  TEI and HCFD to meet to discuss next steps.
05/23/23 – TEI to set up meeting with HCFD to discuss next steps.  Proposed time of 9:00 AM, on 6/8.
06/08/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC.
07/26/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC.
08/24/23 – TEI discusses results of upgrades with HCFD PM, and are developing corrective action steps with OPC
09/26/23 – TEI develops drawings and submits to HCFD for review.
10/26/23 – TEI issues project for bids.  Prebid meeting occurred on 10/25/23.  Bids are scheduled to open on 11/22.
12/06/23 – Bids received and opened on schedule.  Stem Electrical is apparent low bid.  TEI vets bid and submits letter of recommendation.  Contracts are at prosecutors office for approval.
01/30/24 – Project awaiting BOCC approval
02/28/24 – Stem Electric receives signed contract and PO.  Preconstruction meeting to be scheduled in the next couple of weeks.
03/27/24 – Pre-construction meeting scheduled for 04/15/24
04/24/24 – Pre construction meeting occurred.  submittals receieved , and approved.  Project pending procurement of materials (approx 12 month ship date).  Stem electric to confirm shipping schedule.
05/29/24 – Project pending material procurement.  TEI requests Stem Electric to send in Ship date.
06/26/24 – No Updates. Project pending material procurement.
07/24/24 – No Updates.
08/28/24 – No Updates, project pending procurement of materials.
09/25/24 – Project pending material procurement.
12/11/24 – Project installation pending material delivery.
02/26/25 – Project installation pending material delivery.
04/23/25 – Project installation pending material delivery.
05/28/25 – No updates.
05/25/25 – No updates.
07/30/25 – Stem electric and DEG and HCFD meet to KO project. Gear has arrived and DEG certifies at Crane yard.
08/27/25 – Stem to begin the construction phase of this in first week or two of September.
09/24/25 – Gear is rigged into place. Outage/tie in to be coordinated.
10/30/25 – MCB to call Stem to schedule a shutdown meeting.
12/10/25 – DEG to follow up with Stem again to schedule the shutdown.
01/28/26 – Stem ready for the outage. John Nester requested pricing on refurbish breaker in the main gear. Stem is sending email of availability to DEG for meeting to discuss/schedule outages.
02/25/26 – Stem to send in proposed schedule and timelines.
02/25/26 – Stem sends in multiple proposed dates in May for tie in schedule. DEG, HCFD, Tech Svrcs, and Juv Courts to meet to discuss outage plans and select date.
04/29/26 – DEG and HCFD meet with all building tenants and discusses power outage plans. Tentative dates for outages are 5/30 for the 2nd floor and 6/19 for the sub-basement gear.
05/27/26 – 5/30 outage cancelled due to the contractor not having BGC staff. 6/19 outage still on the schedule.
06/23/26 – Second floor switch tied in on 06/19. TJW Electric provided staff that had current BGC and badge to perform the work. Basement level work to be scheduled.
07/29/26 – DEG has a virtual meeting with HCFD and Stem Electric. A list of possible Saturdays was emailed to HCFD and Stem to coordinate the next outage. HCFD to confirm the procurement of bad breaker for the distribution panel serving the computer room to be replaced by trades during the outage.
08/26/26 – HCFD states that the replacement breaker has been purchased by trades. Stem has confirmed 09/26/26 date with ESI, still pending confirmation from TJW. DEG states lets work towards making outage #2 happen on 09/26/26 so not to delay other projects. Stem to confirm with TJW and finalize the date.
09/23/26 – 9/26 date was postponed due to staffing issues with Stem Electric. New Date is 11/11/26 – starting at 07:00 AM. Pre-outage conference call scheduled for 10/28/2026.
10/28/26 – Outage is scheduled for 11/11/26. Meeting held with courts, HCSO and HCFD to discuss outage on 10/28/26.

800 – Arc Flash Mitigation 2023 Read More »

A&D – South Entrance Access Control

PM = Rycca Thacker, Mike Barth

01/25/23 – TEI Submits SOSS.  Project pending SOSS approval and PO.
02/23/23 – TEI receives approved SOSS and PO.   Project kickoff to occur and work to be completed.
04/27/23 – TEI to submit review set to HCFD by 05/03/23
05/23/23 – TEI submits drawings to HCFD for review.  TEI receives comments from HCFD.  TEI to update the drawings from the comments and develop bidding documents.
06/28/23 – TEI and HCFD PM finalized small projects bid package and issues to selected XBE companies for bidding.  Bids due back to TEI on 07/13/23.
07/26/23 – TEI invites 8 XBE and 1 non-XBE bidders to give costs on project.  Recieved (1) bid.  bids came in higher than expected.  TEI sends bid information to project manager and waiting for further decisions.
8/24/23 – TEI vets bid from Glenwood electric, and makes recommendations to HCFD.  Project pending contract approval.
09/26/23 – TEI approves submittals.  Installation pending product procurement.
10/26/23 – Glenwood electric has equipment ordered and scheduled to ship beginning of November.   Upon receipt of all materials, installation will be schedules.
12/06/23 – Glenwood working on install schedule.
01/30/24 – Project install complete.  TEI and HCFD perform punchlist.  Upon completion of all punchlist items, and receipt of closeout documents, project will be complete.

02/28/24 – The Original bid portion of the project punchlisted.  CO work waiting on material procurement and scheduled install date.

03/27/24 – The Air Curtian Fan is installed.  Final punch items be completed this week.  Then project can be closed.

A&D – South Entrance Access Control Read More »

JC – Exterior Camera System Upgrade

PM: Matt Butz, Mike Barth

01/25/23 – TEI submits SOSS.  Project Pending SOSS approval and PO.
02/23/23 – TEI receives approved SOSS and PO.  DK to procure equipment and project in commencement phase.
03/29/23 – DK has initiated the installation.   TEI and HCFD to provide punchlist upon Notice of substantial completion.
04/27/23 – DK working on project.  Const progress meeting scheduled for 05/03/23.
05/23/23 – TEI, DK, HCSO and HCFD provide punchlist.  TEI documents locations of cameras and network switches for record drawings.  TEI to submit the record drawing to HCFD upon completion.
06/28/23 – upon receipt of all close out documentation from DK, project will be closed out.
10/26/23 – TEI reached out to DK (Electrical division at DK under major changes – several EEs have transitioned out of DK) for final closeout documents so project can be closed and archived.
12/06/23 – TEI to document the as-built conditions for this project with the Exterior Camera project II.
02/29/24 – Ready to archive.

JC – Exterior Camera System Upgrade Read More »

Crime Lab – Emergency Power Study

PM: John Nester, Mike Barth
12/15/22 – ThermalTech submitted SOSS and it’s approved. TEI to schedule fieldwork next week.
01/06/23 – TEI met Ian on site for kickoff meeting.  MCB, Alex, TTC onsite to review.
01/25/23 – Bert said to concentrate on immediate needs first.
02/23/23 – TEI submits immediate needs draft report to HCFD.
03/29/23 – TEI to develop schedule for Phase II of report.  TEI submits SOSS for implementation of Phase I study results.
04/27/23 – See Emergency Power upgrades for Phase 1 updates.   TEI and HCFD to develop schedule for phase 2 study.
10/26/23 – TEI and HCFD develop schedule (preliminary with options focusing on emergency heat in winter) to be sent to Bert on 10/27/23, and final draft sent to Bert on 11/10/23

Crime Lab – Emergency Power Study Read More »

230 – Magistrate & Mediation Construction

PM: Matt Butz, Sam Hofmann
09/29/22 – Two projects combined into one Construction project. Some furniture will be reused.
10/21/22 – Contracts finalized and Pre-construction meeting held. Kick-off meeting to be scheduled when submittals are returned.
12/15/22 – Kick-off meeting to be scheduled
01/26/23 – Kick-off meeting held. Construction to start in near future. Waiting on all background checks to return.
02/01/23 – Notice to proceed issued.
02/22/23 – Construction on going. First progress meeting held.
03/30/23 – Construction ongoing.
04/26/23 – ThermalTech reviewed the HVAC and Fire RFI’s and discussed final design for these services.
04/27/23 – Construction on going. Will move onto 9th floor this month.
05/25/23 – Punch completed for 11th and 12th floor. Construction started on 9.
06/29/23 – 11 and 12th floor punched. Work is underway on 9th. Everything to be complete by end of month. HVAC and Electric change orders approved, TTE to cover these cost.
07/27/23 – 11 and 12th floor nearly complete. 9th floor to be complete mid august. Waiting on Alpha to provide pricing for potential flooring change order TTE provided a 10″ neck diffuser for Alpha to get installed. Trades will help clean up the 11th floor inefficiencies. Inspections are complete for MEP on 9, 11, 12 floors. 9th floor punchlist coming up soon. Barth talked to Delta and they may be able to provide two can lights for the Reception area from leftover stock.
08/31/23 – Added flooring on order. Install at end of September. Work on 9 is finishing up. a pre-punch list has been submitted to Alpha for less than satisfactory work.
09/28/23 – Alpha has not completed contract work yet. New flooring to begin on 10/3.
10/25/23 – Contract work is still not complete. Flooring has been pushed back until the space can be occupied. No firm install date scheduled.
12/07/23 – All work is complete. Minor punch list items outstanding.
01/31/24 – Closeout documents received. TEI noted there were not redline markups for as-built drawings received for this job.
02/29/24 – Punch list items complete. closeouts in review.
03/28/24 – Hardcopies from Alpha outstanding.
04/25/24 – Closeouts received.
05/30/24 – Waiting on release of liens.
06/27/24 – Closeouts still outstanding.
07/25/24 – No Update.
08/29/24 – No Update.
09/26/24 – Final pay app returned.
09/26/24 – Flooring still not great but ready to Archive.

230 – Magistrate & Mediation Construction Read More »

250 WHT – Façade Repairs and Window Replacement (F067)

PM: Matt Butz, Paul Bellman
09/15/22 – Hamilton County requested SOSS.
09/29/22 – THP to publish SOSS on 9/30/22.
09/30/22 – THP published SOSS. (8 years ahead of schedule).
03/27/23 – THP Revit Model in progress.
04/25/23 – Revit Model 95% complete.
05/23/23 – No updates from THP.
07/20/23 – Hamilton County on site meeting with THP to review scoping.
08/23/23 – County placed project on hold.
09/27/23 – THP to provide Hamilton County with status drawings the first week of October.
10/23/23 – THP provided review documents (drawings and project manual), plus economic inclusion opinion of probable costs.
01/31/24 – No updates from THP.
02/29/24 – No updates. On hold.
03/27/24 – On hold.
04/25/24 – On hold.
05/30/24 – No updates. On hold.
06/26/24 – No updates. On hold.
07/24/24 – No updates. On hold.
08/29/24 – No updates. On hold.
09/26/24 – No updates. On hold.
10/31/24 – No updates. On hold.
12/11/24 – No updates. On hold.
12/12/24 – Champlin to check on const 2B vs 5B and maybe we submit an engineering change to modify it to 5B.

250 WHT – Façade Repairs and Window Replacement (F067) Read More »

2020 – Security Camera System Upgrade

PM = Matt Butz, Mike Barth

09/26/22 – HCFD requests SOSS for the Project.  TEI Submits SOSS.
10/26/22 – TEI receives signed SOSS and PO for Project.   TEI meets with Matt Butz to discuss project.  Kick off meeting with building staff to discuss scope and project details.
12/15/22 – TEI progressing in design.  Will schedule a 75% design review with HCFD and 2020 staff after the holiday break.
01/25/23 – TEI, HCFD and HCJC meet to review project design.   TEI schedules working “Mock up” with Vicon rep on 02/01/23 so the staff at 2020 can see the views that will be provided with new system.   Design will be finalized after Mock up meeting.
02/23/23 – TEI, HCFD and HCJC meet with rep for mock up.  Camera types selected.  TEI has documents 90+% complete for issuance.  All new camera locations have the view area inserted on plans.  Upon final review with HCJC, Project will be issued for ITB.
03/29/23 – Project will be sent to purchasing on 03/31/23 for a 04/03/23 Out to bid issuance.  Prebid meeting is scheduled for 04/20/23 at 2:00 PM.  Bids will be due on 05/04/23.
04/27/23 – Project in bidding phase.  Prebid meeting was 04/20/23.   Well attended prebid.   Addendum 1 already issued.   Addendum 2 to be issued 04/28/23.
05/23/23 – Bids received for project.  (2) bids, DK and Glenwood.  Glenwood Electric Apparent low bidder.  TEI vets the bid, and recommends contract with Glenwood.  Project is in contract approval phase.  Upon contract approval and PO issuance, the project construction can commence.
06/28/23 – Project was approved at the BOCC meeting on June 15.  Glenwood recieves PO and is now working on submittals for approval.  Upon submittal approval, construction schedule will be developed and mobilization will be scheduled pending product procurement.
07/26/23 – Project construction kickoff meeting to be scheduled week of 8/7.  Construction schedule to be issued from Glenwood at kickoff meeting.
08/24/23 – Glenwood electric scheduled to mobilize to project site on 8/28/23.  Construction to commence.
09/26/23 – Construction commenced on project.   Multiple meetings with IT to discuss the network configuration.   Glenwood continuing installation of backbone of system.
10/26/23 – Construction under way.   4th Floor New Cameras are installed, as well as POD 203.  Juv Crt IT has not confirmed Network architecture.  Meeting schedule for 10/30/23 with all parties to finalize decision.
12/06/23 – Construction ongoing.  Network architecture finalized and programmed.  Glenwood has been working in non-housing areas first so that building staff can learn and get used to new VMS system.
01/31/24 – Working on floors. They have a computer in the room and are working on parallel system now, testing on two systems including the Valerus system for training.
02/28/24 – Construction continues on project.  Training occurred on 02/28/24 on site with building staff.  Ready to work on the PODs and move the residents.
03/27/24 – Work continues.  Most of exterior cameras switched over.  Close to working on 3rd floor (final housing units).   Anticipated completion in next 30-60 days.
04/24/24 – Project nearing completion of original scope.  CO cameras being installed.
05/29/24 – Glenwood has a hand full of interior cameras that remain to be installed, and then a few on the exterior.
06/26/24 – Glenwood ready for punchlist on all remaining areas. All main project cameras installed. CO cameras being installed. Demo complete and painted. Encoders being removed now.
07/24/24 – TEI and HCFD to finalize punch and issues on site in August.
08/28/24 – Glenwood has Cornerstone update the PLC system on site with new cameras to endure call ups are correct and working. TEI and HCFD will perform final walk thru once notified by Glenwood that everything complete.
09/25/24 – No Updates. Glenwood and Cornerstone working on scheduling modifications to the PLC.
12/11/24 – Glenwood notifies HCFD and TEI that PLC integration is complete. TEI and HCFD to perform final punchlist.
01/29/25 – Final punchlist completed and issued. Project complete pending closeouts.
02/26/25 – Project complete pending closeout.
04/23/25 – Project complete pending closeout.
05/28/25 – No updates.
05/29/25 – Barth has redlines, updating as-built drawings
06/25/25 – Record drawings complete. Project ready to close out.
09/24/25 – DEG delivers hard copies and thumb drive to HCFD. project complete.

2020 – Security Camera System Upgrade Read More »

JC – Emergency Power System Replacement

PM: Matt Butz, Mike Barth, Ken Orloff
09/26/22 – HCFD requests SOSS for project.  TEI submits SOSS.
10/26/22 – TEI receives signed SOSS and PO for Project.   TEI meets with Matt Butz to discuss project.  Kick off meeting with building staff to discuss scope and project details.
12/15/22 – TEI progressing with design.  Coordinating with Vendors and developing solutions to present to HCFD upon receipt of data from suppliers.
01/25/23 – TEI in receipt of product data from manufacturers.  TEi meeting with rigging company on 02/01/23 to review scope of removing the egens and installing new in existing locations, and determine if any additional modifications are required to move the equipment in/out of the building.
02/23/23 – TEI meets with Rigging company, equipment vendors, and THP on site to confirm constructability of design.   Design documents are progressing to a point where a review set will be sent to HCFD.
03/29/23 – TEI finalizing the coordination with multiple vendors for the equipment associated with this project.   80% complete project review meeting to be scheduled with HCFD.
04/27/23 – TEI has project ready to meet with HCFD and discuss final design direction.   Meeting to be scheduled first week of May.
05/16/23 – TEI and THP discussed increasing scope of work for this project. Adding CMU partition walls and second means of egress in the existing gears rooms in both north and south buildings.
05/17/23 – TEI and THP met onsite to review the existing conditions at gears rooms in both the north and south buildings.
05/23/23 – TEI working on code required upgrades for this project.  We are coordinating with IBI and THP on the redesign.
06/14/23 – THP sent Owner Review documents to ThermalTech.
06/28/23 – TEI submits review set of bid package to HCFD PM for review.  TEI and PM review comments on 06/28/23.  TEI to incorporate the review comments and develop final bid package for issuance after the 4th of July holiday.
07/10/23 – THP waiting to hear back from ThermalTech about Owner Review Comments, ITB #, and bid date in order to issue bid set.
07/26/23 – TEI holds issuance for updated XBE ITB package information.  TEI to develop spreadsheet and work thru issuing with XBE requirements .
08/23/23 – THP has not heard any update on this project.
08/24/23 – TEI issues XBE package and gets approval.  TEI finalizing project manual for HCFDF review and project issuance.
08/31/23 – Go ahead and get pre bid coordinated and final XBE items. Get out for bid.
09/27/23 – THP – Project tentatively out to bid on October 4th.
09/26/23 – TEI submits project manual to HCFD for final approval.  will issue for bidding once manual is approved.
10/04/23 – Project advertised to bid.
10/18/23 – Pre-bid meeting occurred at the Justice Center.
10/26/23 – TEI issues project for bidding.   Prebid meeting occurred on 10/18/23.  Bids are scheduled to open on 11/09.
11/02/23 – Addendum #1 issued.
11/22/23 – Bid Opening.
12/06/23 – (1) bid received, in awardable budget range, but DEI determined XBE submission was not in accordance with requirements and recommended for rejection.  Pending BOCC decision.
01/31/24 – No new updates from THP.
02/28/24 – THP no new updates from THP.
02/28/24 – Project to be re-bid with the fuel tank work bid as a separate project.
03/27/24 – TEI repackages project and will send to HCFD in next 2 weeks for review prior to ITB.
04/24/24 – No new updates from THP.
04/24/24 – TEI sends HCFD re-packaged documents for review.   Upon receipt of review comments, and approval of GSWS from DEI – project to be re-issued.
05/13/24 – THP sent updated drawings and specs to ThermalTech for rebid on 05/15/24.
05/29/24 – Project issued for rebid.  Project prebid meeting occurred on 05/29/24.  Bids Due on 07/11/24.
06/26/24 – Project bidding.
07/24/24 – Project bid opening on 07/24/24. NO BIDS received. TEI contacts electricals to see why no bids.
08/29/24 – No new updates from THP.
08/28/24 – No Updates.
09/25/24 – No Updates.
09/26/24 – No new updates from THP. County requested new SOSS and include the underground tank with the scope again as an Alternate. Bring Terracon in for the Geotech in this SOSS.
12/11/24 – TEI submits SOSS and receives signed SOSS and PO for re-bid. Project to be re-packaged for re-bid starting in January.
01/29/25 – TEI repackaging the documents – send to Purchasing on on 2/10, available for bidding 2/11.
01/30/25 – Ready to Archive, start new Project file.

JC – Emergency Power System Replacement Read More »

TPC – Hydraulic Elevators Modernization

PM: Matt Butz, Mike Barth
09/26/22 – HCFD requests SOSS for Upgrading the Hydraulic Elevators at the TPC.  TEI submits SOSS.
10/26/22 – TEI receives signed SOSS and PO for Project.   TEI meets with Matt Butz to discuss project.  Kick off meeting with building staff to discuss scope and project details.
12/15/22 – TEI progressing with design.  Working towards submitting owner review set to HCFD on or before 12/23/22.
01/25/23 – TEI issues project for bidding.   Prebid Meeting scheduled for 02/09/23.  Bids scheduled to open on 02/22/23.
02/23/23 – a single bid was received (graybach) and it was double the advertised estimate (nearly triple the cost bid 6 months ago as an alternate to the original elevator project).  Bids were rejected.
03/29/23 – Project pending revised scope and/or revised budget discussions with HCFD.
04/27/23 – Project pending revised scope and/or revised budget discussions with HCFD.
05/23/23 – project has been re-designed with the scope of base bid being the aesthetic upgrades to match the traction elevators, and the mechanicals of the upgrades being bid as alternates.   TEI sends drawing to HCFD for review.  HCFD to update the AIA’s, and TEI to send project manual for final review.  By June 1, issue dates, and ITB to be received from purchasing and project to be re-issued for re-bid.
06/28/23 – Project issued for bidding.  Prebid meeting scheduled for 07/06/23 and bids are due on 07/19/23.
07/26/23 – Project bids received.  (2) awardable bidders submitted bids (Alpha Const and Graybach).  Alpha was apparent low bid, had clerical errors in bid and submitted a retraction letter for retract bid.  TEI and Champlin  vetted the Graybach bid and are recommending acceptance of the Graybach bid.
08/24/23 – Project in submittal phase and product procurement phase.
09/26/23 – BOCC approves project.  Project to commence upon PO and kickoff with Graybach.
10/26/23 – project is in submittal approval phase.   Once all submittals are approved, equipment will be procured.  Upon receipt of equipment, installation schedule will be developed.
12/06/23 – All submittals have been returned.  equipment in procurement phase.
01/30/24 – First Hydro unit (elevator #5) scheduled to begin the refresh work in mid February.  To allow new Traction to be run (open to public) for 4-5 weeks prior to taking the second traction out of service for modernization.
02/28/24 – Schedule of elevator #5 pushed until after the second tractor elevator is completed.  Materials received at American elevator, and ThermalTech to certify materials upon confirmation that Graybach and American have confirmed that the materials are the correct equipment.
03/27/24 – TEI certifies material.  HCFD requests CO pricing for additional scope.  Graybach pricing up the changes.
04/24/24 – Project progressing.   Schedule pending inspections of Elev #2
05/29/24 – Hydro units scheduled to start Modernization upon completion of Freight elevator (approx Beginning of Aug)
06/26/24 – No Updates.
07/24/24 – The first Hydro elevator to be taken out of service for the modernization in next week or two (pending no issues with Freight Elevator inspections.
08/28/24 – Elevator #5 out of service being worked on. Graybach indicates that they are on schedule.
09/25/24 – Elevator #5 passes elevator inspection. Generator test completed during building power outage for switchgear cleaning.
10/30/24 – Final elevator nearly complete. Graybach requesting punchlist mid week of 11/04.
12/11/24 – Fianl elevator inspection passed and complete. Punchlist complete. Project pending final closeout documents.
01/29/25 – Graybach sends closeout docs to TEI for review. Pending MCB review.
03/26/25 – TEI reviews and submits closeout docs to HCFD.
04/23/25 – Project can be closed out.

TPC – Hydraulic Elevators Modernization Read More »

Animal Shelter – Dane St Renovations

Project Managers: Mike Murphy, Bert Watts
05/26/22 – SOSS requested to move forward with design. BW provided updated scope for access to the Animal Shelter buildings.
06/30/22 – SOSS approved for Northside building to be converted to animal shelter. Preliminary schedule provided to County. Site visit to be scheduled.
08/25/22 – Site visit performed. Held user meetings to define scope. Work in progress.
09/25/22 – ThermalTech directed to submit their own SOSS’s for this project for regular and small scopes.
09/29/22 – Conceptual plan and estimate to be submitted 9/30
09/29/22 – TEI SOSS has been submitted to BW for approval.
09/30/22 – Conceptual plan and estimate submitted to County.
10/27/22 – ThermalTech electrical & mechanical cost estimates are done. We are working on drawings and plumbing estimates now.

12/15/22 – SD plans and estimates complete

01/26/23 –  No Update

02/22/23 – No Update

03/30/23 – No Update

04/27/23 – No Update

05/25/23 – No Update

Animal Shelter – Dane St Renovations Read More »

TPC – Data Center Decommissioning (9th Floor)

PM: John Nester Butz, Terry Cannon
09/19/22 – Submitted SOSS.
09/23/22 – SOSS approved.
10/26/22 – Drawing created for rebid.
12/15/22 – Champlin has head start on this job, ThermalTech planning on having this ready for review in January 2023.
01/24/23 – Ready to re-kickoff this job and get this out to bid early in 2023.
02/16/23 – Sent Review set to Matt, got ITB, estimate and dates all set. Issue 2/27, prebid 3/8, Bid Opening 4/3.
03/27/23 – Addendum 1 is issued.
03/29/23 – No additional questions received, bid opening Monday, April 3. TTC confirmed two bidders are planning on bidding.
04/25/23 – Bids were opened and Alpha is the apparent low bidder on this job. We have had an online post-bid meeting with Alpha and we followed up with a review of the proposed SOV for the project which was sent back with comments to Alpha. A follow-up phone call with Alpha discussed discrepancies between the budget and bid prices. A final recommendation is being made to he County.
05/21/23 – Pre-Award minutes shared with the team. Contract in approval stages.
06/28/23 – Contracts approved, we are seeting up the Pre-Const Mtg second week of July.
07/26/23 – Pre-Const meeting scheduled for August 18.
08/29/30 – Holding for startup.
09/27/23 – Holding for Startup, should I tell Alpha March 2024 or stick with January 2024.
10/25/23 – Talked to new Alpha PM and will setup meeting to discuss schedule and background check requirements with him. Brandon Winsted.
12/06/23 – Alpha in holding pattern awaiting kickoff of project on our schedule.
01/09/24 – Coordination Meeting #2 held between City and County. PO has been issued by the County to the City for the new fiber line. CAGIS ready to move servers by the end of January. Next meeting to have CLEAR in attendance.
01/30/24 – Coordination Meeting #3 held between City and County. City ready to execute PO to Thayer for fiber run between buildings. TE issued an updated drawing showing the fiber to terminated in CH 2nd Floor in Rack #17. City stated a new Integration Router will be installed in the new County server room in Rack #17 to reduce downtime of the cutover for the Integration router. We need to find a router for the Heroin task force when we demo the 9th floor. 9th Floor demo scheduled for April/May. Next meeting in four weeks.
02/23/24 – Updated Alpha on project progress. Assumed start date May 2024.
03/22/24 – Met with Alpha last week in the room. Pre Const Mtg mid April to be scheduled.
04/24/24 – TTC advised Alpha that our demolition start date will probably be June/July timeframe and that the service elevator will probably be worked on in May, June and July this year. CMSNet is currently getting a quote to move the database server out of the 9th floor over to the CH Server Room.
05/28/24 – Contacted Alpha and pushed back start date to August 2024.
06/26/24 – Admin CH fiber is installed, ttc to get photos today of server room progress. Another City/County meeting was held on Tuesday, ttc sent minutes out for review. July 21 6am is tentative date for Integration router relocation to Admin basement.
07/24/24 – Project walk through scheduled with Alpha for starting to mark existing equipment and demo.
08/20/24 – TTE contact Risk Mgmt and the final server was moved out of the 9th floor room.
08/19/24 – Alpha Construction started in the room. This week they removed ceiling pads and inspected the area. Asbestos contractor coming next week.
08/26/24 – Asbestos contractor began working in the space this week. An exhaust duct was routed across the 9th floor to the nearest window for ventilation. The Ante Room is under remediation now. The main room will be started next week. The floor demo to begin the third week of September.
09/24/24 – Building permit was submitted on 9/18. Fire permit was submitted on 9/18. 2024P08366 but permit is not ready for issuance yet. asbestos remediation has been completed in the ante room and server room, all clear has been issued. Demolition for the raised floor and ceiling is underway. Alpha asked about the status of the E-Waste products in the space and several pieces of equipment are still powered up. County coming on Thursday to remove products.
10/30/24 – Demolition nearly complete in the space. Alpha submitted COR for interior Liebert demo. Fire protection permit is approved and Preferred will be onsite next week to start their work. As soon as the wet
fire system is pulled into room, Alpha will start remaining demo and asbestos remediation.
12/12/24 – Fire protection is complete and the Halon tanks are removed from the building. Asbestos abatement is ongoing at this time and supposed to be done by the end of this week.
12/31/24 – Alpha sent and email outlining the delays in completion due to Testing agency staffing issues and told us completion will not be until early 2025. Testing actually completed their work today and Alpha will be back on Friday to wrap up their work. This job will be ready to punchlist next week Jan 6 – Jan 10. TTC advised all team members.
01/15/25 – Punchlist visit by ThermalTech and Champlin, Jesse and John G were in attendance.
01/28/25 – Punchlist distributed to contractor.
02/26/25 – Project is complete, punchlist has been issued and completed, now Alpha Const is working on back punchlist options. Alpha said they would have closeout documents sent to use by Friday.
03/25/25 – Alpha working on closeout documents for this project including finalizing punchlist, final payapp, and sending closeout documents.
04/21/25 – Punchlist #2 has been submitted to the contractor for completion which includes repairs to two broken windows on the 9th floor and additional electric items.
05/28/25 – Everything completed on second punchlist except windows which are coming in in two weeks.
06/25/25 – Alpha replacing broken windows Thursday to complete punchlist.
07/30/25 – All work is complete including the windows, waiting on owner approval for window repairs.
08/26/25 – All work is complete and approved. TTC will drop off closeout documents on Thursday.
08/28/25 – Closeout documents turned over to County this morning.
09/24/25 – Archived.

TPC – Data Center Decommissioning (9th Floor) Read More »

CH – Critical Façade Repairs (F064)

08/15/22 – Hamilton County requested SOSS.
09/29/22 – THP to publish SOSS on 9/30/22.
10/20/22 – Hamilton County approved the SOSS.
01/26/23 – THP developing design documents.
02/23/23 – THP is continuing to develop design documents. We have partially surveyed the façade for specific damage, and are developing repair/stabilization details. THP will return this week to finish survey.
03/23/23 – THP is developing design documents and plans to have owner review set ready by week of 3/27. We have some remaining survey work from within the courtyard to complete
04/27/23 – THP plans to issue bid review documents May 2nd.
04/27/23 – THP plans to issue bid review documents.
07/13/23 – THP published updated bid review documents to the County.
08/10/23 – THP published bid documents. Bid documents included new XBE program requirements.
08/22/23 – Prebid meeting occurred.
08/23/23 – Addendum No. 1 issued.
08/30/23 – Addendum No 2 issued.
09/07/23 – Bid opening occurred. One bidder over budget. Bid rejected.
09/13/23 – THP issued a bid summary email.

CH – Critical Façade Repairs (F064) Read More »

A&D – Façade and Foundation Repair (F063)

PM: Rycca Thacker, John Millar
08/15/22 – Hamilton County requested SOSS.
09/29/22 – THP anticipates publishing the SOSS 10/4/22. Working with Tru Scan and Thermal Tech.
10/17/22 – THP published SOSS.
01/25/23 – Model created, design ready to start.
02/23/23 – Civil surveys and field surveys in process. Surveys include roof and site work.
04/27/23 – Project updates: Civil survey complete, fall arrest SD complete, and field survey of attic completed. THP coordinating with potential contractors and geotechnical testing company to develop foundation repair package.
07/27/23 – THP anticipates issuing an complete SD set on 8/3/23.
09/28/23 – THP working on SD documents.
10/26/23 – THP scheduled to publish review set October 31.
12/06/23 – THP issued review set.
01/31/24 – THP needs to schedule review meeting with Hamilton County.
02/07/24 – THP met with County to review design development documents.
02/28/24 – THP working on bid documents.
03/28/24 – THP working on bid package.
04/25/24 – THP working on bid package.
05/30/24 – THP working on bid package. Bert said he wants to get it packaged to the point to where it can be bid ready, even if it is shelved.
06/27/24 – Rycca said to go ahead and bid out safety repairs from report.
07/25/24 – THP working on safety package for City Repairs.
08/29/24 – Safety package anticipated for issued 9/4/24.
09/26/24 – Safety review package anticipated for issued 10/09/4/24.
12/10/24 – THP closing out project.
01/24/25 – THP submitted closeout DD package.
02/26/24 – THP published City Façade repair letter.

A&D – Façade and Foundation Repair (F063) Read More »

JC – Security System PM Agreement

PM = Matt Butz, Mike Barth

08/24/22 – TEI authors SOSS for project.   TEI receives Signed SOSS and PO on 08/23/22.  TEI to develop project manual for bidding to have new agreement in place by 01/01/2023.

09/26/22 –  TEI finalizing bid package, to submit for review and then will coordinate ITB with Purchasing department.

12/15/22 – TEI to submit to HCFD for final review on or before 12/23/22

01/25/23 – TEI issues for bidding.   Bids received on 01/18/23.  Service agreement bids turned over to HCSO.

JC – Security System PM Agreement Read More »

230 – Sewage Ejector Replacement

PM: John Nester, Terry Cannon

03/31/22 – County reaches out for SOSS for this job.
04/02/22 – ThermalTech reached out to Derek Koogler to get a submittal and quote for the job.
05/24/22 – ThermalTech on site for fieldwork.
05/27/22 – First set of plans created for job.
06/02/22 – Markups complete, given back to TTC.
07/20/22 – Markups returned to TTC again.
07/26/22 – TTC returned dwgs with additional markups. New lid information requested, use the same style as A&D.
08/05/22 – Page created and back-filled with project data. Progress drawing sent to County. We need preferred floor drains for replacement from John or Ernie.
08/22/22 – Met with John and Ernie on site and finalized scope. One new
08/24/22 – Final markups sent in for Cad. Bid in September, maybe August.
09/22/22 – Bid opened, DK apparent low bidder. Pre-Award meeting scheduled for next Tuesday. We have the budget to take all the Alternates on this job.
10/26/22 – Waiting on final contract and PO to begin work.
12/15/22 – Submittals returned for correction, new submittals should be here any day. Pre const meeting was held with Debra and everything went well.
01/24/23 – Pushing the manufacture hard to update submittals with the correct voltage. Other than that the submittal looks great.
02/20/23 – New submittals were returned FAC so the equipment should be on order this week. We still need external disconnects and transducer submittals. DK getting new delivery schedule.
03/29/23 – Pumps are ordered, assembled scheduled to be complete by the end of April. Tigerflow ship date not confirmed.
04/25/23 – Weekly check-ins with the vendor and contractor has not gotten us a firm date when the package will ship from Tigerpaw.
05/12/23 – Schedule of Values submitted, reviewed, and returned for changes.
06/28/23 – Schedule of value resubmitted for approval. Equipment scheduled to arrive at Tigerflow second or third week of July.
07/26/23 – Pump package will be here in August. Pre-Const meeting will be scheduled in August.
08/07/23 – Pre Construction Mtg #2 was held with Debra and the County. Meeting minutes will be distributed later this month. DK supposed to start in August.
09/27/23 – DK will send Dirk to do this job after they wrap up PBS Ice Machines which will be complete by the end of MNF week (this week). They should be mobilizing in next two weeks. I will check on paperwork again.
10/23/23 – Met Dirk onsite for project kickoff. Mobilization and tools today. DK started disassembly of sewage ejector system. Water filled sump about noon from fire pump test, but was pumped out before DK left for the day.
10/24/23 – Work continued on pump replacement no more water issues.
10/25/23 – Pumps are installed and operating. DK jet cleaning floor drains but finding clogs. Floor was hand scanned before saw cutting. DK used jack hammer to install new floor drain near blow down tank. New line and floor drain installed, concrete poured back into placed. We will meet on Friday for punchlist. Corporate equipment coming Friday for startup.
12/06/23 – Work is complete. Punchlist was issued. Backpunch and training completed. The system is up and running. DK to label each pump in field. DK to provide all closeout paperwork for this job.
01/31/24 – Project is complete. Discuss contractor and allowance with John Nester before accepting final payapps ($5k vs $12k).
02/23/24 – Review closeout documents with John.
03/22/24 – Ready to Archive this job but DK has not provided all closeout documents yet.
06/01/24 – Working with DK on closeout.
09/01/24 – Working with DK on closeout.
12/01/24 – Working with DK on closeout.
01/25/25 – Received Consent of Surety for final closeout today, sent that and final payapp to Hamilton County for closeout and processing.

230 – Sewage Ejector Replacement Read More »

JC – Courtrooms A&B Upgrades

PM: John Nester, Derrick King
07/27/22 – Project created. SOSS is approved. Fieldwork started with Champlin and TEI. Champlin has updated & sent Revit model to TEI for design purposes. The ceiling in one of the rooms will be lowered 24″ in one Courtroom and will stay the same in the other Courtroom. We may need more fieldwork for the non-lowered ceiling for spacing below utilities.
08/22/22 – Review set sent to county
09/29/22 – Project out to Bid
10/27/22 – Triton awarded bid. Contracts in progress.
12/15/22 – Submitted for permit. Still waiting on contract.
01/26/23 – Contract finalized. Background checks submitted.
02/22/23 – Kick-off meeting scheduled for next week.
03/30/23 – Schedule updated, Triton to start next week on this job. Some submittals have been received and returned.
04/25/23 – ThermalTech met Triton onsite for plumbing routes and final connections in closet.
04/27/23 – Construction on going.
05/25/23 – Construction on going. Triton working on getting the steel sub on site.
06/29/23 – Drip pans are on site but not installed, we are waiting on sealing to be completed and reviewed. Construction is ongoing.
07/12/23 – Pans arrived, TTE rejected them due to size and configuration. Triton is taking back to fabricator for reforming. TTE suggested Triton go pick one up for immediate installation.
07/26/23 – Meeting cancelled and moved back one week.
07/27/23 – Construction ongoing.
08/31/23 – Construction ongoing. Courtroom B finishing up. Construction on A started.
09/28/23 – Punchlist for B to be scheduled soon. Drip pans to be installed in A next week.
10/25/23 – Drain pans installed. Finish work ongoing.
10/26/23 – Sprinkler contractor should be onsite this week to start moving and reworking sprinkler heads and systems. JW checking on final sealant for pipe penetrations from second to first floor for us (below and above). Drain pipe in hallway not complete as of last meeting.
01/31/24 – Both courtrooms at punchlist stage. Triton working on final details. New change order submitted for new pans for additional leaks discovered during first use. TE and JN agree new price is better than original submission. Bench refinishing change order work still ongoing. New anchors are being installed on benches when they are reinstalled. New bullet proof glass has been installed but needs to be cleaned by Triton for the full height of the glass. Need change order for back hallways.
02/29/24 – Change order approved for pans above magistrate benches. Triton needs to insulate domestic water piping repair and provide change order for work above ceiling tiles. John asked for construction meeting before demolition. TTC to check on electrical work.
04/25/24 – New leak found. Punch items in progress.
05/28/24 – Ceiling tile fell in Courtroom B. JN, Triton and TTE responded to see and cleanup the damage. An Acorn valve failed up on the third floor.
05/30/24 – Change order work wrapping up.
06/27/24 – Work to be completed this week. Closeouts in progress.
07/02/24 – Triton submitted air balance report today and it was rejected by TTC. Airflows were fine, project data was wrong and AHU data are missing.
07/08/24 – Balance report submitted and accepted by ThermalTech.
07/18/24 – Triton reported all the work in the back hallways was complete
07/19/24 – Nick reported that the plumbers will be back third shift to install the final plastic pan above the ceiling next week.
07/25/24 – Work complete. Closeouts received. Need to be reviewed.
08/29/24 – No update.
09/26/24 – No update.
02/27/25 – Final closeouts received. Need to be confirmed complete.
03/27/25 – No update.
04/24/25 – No update.
05/29/25 – No update. We need Triton subs Release of Liens and certified payrolls affidavit.
07/31/25 – John says closeout documents look good but they need final payment for this job.
08/28/25 – Ready to Archive.

JC – Courtrooms A&B Upgrades Read More »

125 – Public Defender Relo 3,4,5,8,9

PM: Mike Murphy, Rycca
07/20/22 – SOSS Approved. Site visit to be scheduled.
07/27/22 – TEI to send 230 PD from original renocation.
08/19/22 – Preliminary plans sent to HC for review.
09/7/22 – Kickoff meeting held with Users. Program survey sent out.
09/29/22 – Program sent to county. Scheduling next round of planning meetings in progress.
10/18/22 – Meeting held to confirm Program. One department remaining to confirm. Conceptual planning to begin.
12/15/22 – Work on pause until further notice
01/26/23 – No Update.
02/22/23 – 2 options of test fit plans sent to Rycca. One with Guardian Ad Litem in building, one with Guardian Ad Litem moved to another facility.
03/23/23 – ThermalTech performed fieldwork on the 5th floor this week for HVAC, electrical, fire protection and plumbing.
03/30/23 – Meeting with users. Plans as developed are generally ok. however, the building has signed a 2 year lease with a tenant on the 6th and 7th floor. Meeting scheduled for next week to re-phase the department renovations.
04/27/23 – Site visit to verify all existing conditions. SD development ongoing.
05/21/23 – ThermalTech SD Cost and markups uploaded to Archibus for mechanical systems.
05/25/23 – Champlin plans complete. Estimate will be uploaded to Archibus next week.
05/29/23 – Plans and estimate uploaded to Archibus.
06/29/23 – No Update. In meeting we found out the 8th floor won’t be early occupied. Cost seems high per square foot.
07/27/23 – Provided answers to minor questions and broke down cost estimate further.
08/31/23 – County provided some VE changes. Drawings and estimate to be revised by 9/8.
09/28/23 – Archibus estimate and drawings have been updated with the requested changes.
12/07/23 – No Update.
01/24/24 – Partners responded to Cushman email on lower build-out cost with a review of the design build estimate. Count to use as needed.
02/29/24 – No Update.
03/28/24 – No Update.
04/25/24 – No Update.
06/27/24 – No Update.
06/27/24 – OK to archive, they will use the 8th floor with minimal renovation. Next steps leasing options.

125 – Public Defender Relo 3,4,5,8,9 Read More »

2023 Project Cost Estimates

PM: Bert Watts, All Partners
05/25/22 – All estimates sent to Partners for SOSS
06/29/22 – ThermalTech has started updating estimates in the Archibus module. Several reestimates are complete. We are gathering information on the new projects but we need them set to estimating and we have to give them updates on scope and equipment for estimating before they start entering new ones in earnest. We have started requesting prices from vendors as well. We will send the County list for access. It would be helpful to have a coordination meeting on who is leading and who is working on the combined estimates.
05/31/22- THP Issues SOSS for review by the County.
06/10/22 – THP SOSS approved.
06/30/22 – THP developed internal spread sheet for projects. Initial draft complete. THP will publish for possible use by other partners.
07/27/22 – THERMALTECH UPDATE. Most electric cost estimates are complete and ready for Barth review. Limited mechanical estimates are complete at this time. Architectural and Structural coordinated has started for the “new” estimate. Once we get the proposed floor plans, we will update the MEP estimates.
08/24/22 – ThermalTech Update – We are working on these estimates every day to meeting Sept 1 deadline. Champlin has provided SD drawings for almost ever project for our use on the “New” estimates. We are coordinating on individual estimates on a case by case basis. Electrically, all resestimates are complete. Mechanically we have about 25 estimates remaining. We have completed several new estimates and will spend the bulk of our time next week completing the new estimates with the new drawings we’ve received.
09/04/22 – ThermalTech projects are complete for both reestimated and new estimates. TTC will review as time permits.
01/22/23 – Met with John and Ben and reviewed details that would make the Cost Estimating module better for the partners.
01/24/23 – Ready to Archive

2023 Project Cost Estimates Read More »

EMA Sirens PM Schedules

PM: Nester, Cannon
05/26/22 – SOSS has been submitted for this work.
06/30/22 – No updates.
07/27/22 – PM will be entered in 2023.
04/25/23 – No updates this month.
05/21/23 – No Updates.
06/28/23 – Met with guys on starting the PM’s. They found equipment but have questions on existing PM’s for them.
07/26/23 – Will start on these after we get Ameresco PM squared away.
08/29/23 – County has started performing PM’s on the sires. the SOSS was approved in June, we can use new siren PM worksheet to enter the PM’s.
09/27/23 – Kicked off working internally on collecting equipment ID’s. Need to get an update from the guys.
10/25/23 – No updates this week.
12/06/23 – Siren locations reviewed. PM written and submitted for TTC approval. There are about 10 sires in the Archibus Module that do not match where we had Sirens place. This probably not a big deal as long as HamCo electricians know where the sirens are. I pulled my people off of verifying every single address, there were too many small discrepancies with the final address names. We will continue with the PM assignment after my review.
01/31/24 – Siren worksheet submitted and reviewed by County. Discussion with John indicated we can look at PM previously entered and massage the start dates to Ben’s latest request.
02/23/24 – Review PM already entered in Archibus, reset schedule to match EMA zoning.
03/22/24 – New SOSS written for repairs, the PM work is good to go.

EMA Sirens PM Schedules Read More »

264/2611 – ADA Assessments

PM: John Nester, Mike Murphy
05/26/22 – Schedule site visit.

06/30/22 – Site visit complete. Report in progress

08/23/22 – Finalizing report.

09/29/22 – Report to be submitted by end of next week

10/27/22 – Adding cost estimate into report. To be finalized and submitted in near future.

12/15/22 – Report to be submitted soon.

01/26/23 – Report submitted county with final pricing.
02/23/23 – Ready to Archive.

264/2611 – ADA Assessments Read More »

TPC – Arc Flash Remediation Upgrades

PM: John Nester, Mike Barth
05/26/22 –  TEI submits SOSS for work.   TEI receives signed SOSS and PO for project.
06/28/22 – TEI, John Nester, Jesse Estes and John Gilbert conduct project kick-off meeting.  TEI to provide review sets and recommendations to CMI and Hamilton County by the end of July for review and comments.
07/27/22 – TEI has reviewed existing model and contacted Duke Energy for updated available fault information.  TEI to schedule meeting in next week or so with John Nester to review options and recommendations.
08/24/22 – TEI receives updated information from Duke for available Fault.  Current version of SKM software allows additional information regarding gear (Circuit breakers, etc) that the 2010 version did not allow, and actual data utilized in lieu of infinite bus (worst case) data.  With new version of software, incident energy levels are less than threshold of 40 cal.  TEI discusses with John Nester, a complete re-label of the building.
09/26/22 – TEI develops ITB package for the proposed upgrades to the electrical systems in the buildings per conversations with HCFD.  TEI submits review set to HCFD.  Upon receipt of comments, ITB number and bidding dates will be established.
10/26/22 – ITB has been issued, Prebid meeting conducted, (2) addenda issued.   Bids open Friday 10/28/22.
12/15/22 – DK low bidder.  TEI vets DK bid and sends recommendation to Hamilton County.  Hamilton County drafts contract and sends to DK for signature.   DK returns signed Contract.
01/25/23 – DK receives PO and signed contract.   TEI and HCFD working to schedule pre-construction meeting with DK to kick off the construction.
02/23/23 – Pre construction meeting completed.  DK has sent submittals to TEI for review.  Submittals to be returned by end of week and equipment can be ordered.
03/29/23 – Materials have been ordered.   Project to commence upon receipt of materials.
04/27/23 – Construction to commence upon receipt of materials.
05/23/23 – Construction to commence upon receipt of materials.  Material for TPC are at DK office, TEI to set up a meeting end of next week to talk install schedule, etc (pre-const).
06/28/23 – Pre construction meeting occurred.  DK scheduling mobilization with other county projects and will coordinate with HCFD, Bldg Mgr, and TEI.
08/24/23 – DK to be on site next week to work on the gear modifications to expose the adjustable trip settings on the gear.  door modifications are 1-day turn around.  gate shall be locked out/tagged out with no admittance to the electrical swgr room while the covers are removed from the gear.
09/26/23 – Gear modifications are complete.   grounding modifications are complete.   VFD  replacement and then re-labeling of building and project will be complete.
10/26/23 – TEI reaches out to DK to Schedule the installation of the VFD, now that the pneumatic controls were removed from the existing VFD.  Installation schedule to be received early November.
12/06/23 – VFD installed, connect and programmed.   Work associated in TPC is complete and ready to be punchlisted.  Work at CH is not complete, so project can not be closed.
05/29/24 – No Updates.
06/26/24 – No Updates.
07/24/24 – No updates.
08/28/24 – New Arc Flash labels applied in the building.
09/25/24 – no updates.
10/30/24 – no updates.
12/11/24 – TEI delivers final AF reports to HCFD including tables and single lines from the model.
04/23/25 – Updates tied to CH Arc Flash project.
05/28/25 – No updates
07/30/25 – No updates, waiting on CH breaker to close out.
04/26/26 – Ch breaker received and delivered to HC. Ready to closeout. OK to Archive.

TPC – Arc Flash Remediation Upgrades Read More »

CH – Arc Flash Remediation Upgrades

PM: John Nester, Mike Barth
05/26/22 –  TEI submits SOSS for work.  TEI receives signed SOSS and PO for project.
06/28/22 – TEI, John Nester, Jesse Estes and John Gilbert conduct project kick-off meeting.  TEI to provide review sets and recommendations to CMI and Hamilton County by the end of July for review and comments.
07/27/22 – TEI has reviewed existing model and contacted Duke Energy for updated available fault information.  TEI to schedule meeting in next week or so with John Nester to review options and recommendations.
08/24/22 – TEI receives updated information from Duke for available Fault.  Current version of SKM software allows additional information regarding gear (Circuit breakers, etc) that the 2010 version did not allow, and actual data utilized in lieu of infinite bus (worst case) data.  With new version of software, incident energy levels are less than threshold of 40 cal.  TEI discusses with John Nester, a complete re-label of the building.
09/26/22 – TEI develops ITB package for the proposed upgrades to the electrical systems in the buildings per conversations with HCFD.  TEI submits review set to HCFD.  Upon receipt of comments, ITB number and bidding dates will be established.
10/26/22 – ITB has been issued, Prebid meeting conducted, (2) addenda issued.   Bids open Friday 10/28/22.
12/15/22 – DK low bidder.  TEI vets DK bid and sends recommendation to Hamilton County.  Hamilton County drafts contract and sends to DK for signature.   DK returns signed Contract.
01/25/23 – DK receives PO and signed contract from HCFD.   HCFD and TEI working to schedule preconstruction meeting to kickoff the construction.
02/23/23 – Preconstruction meeting completed.  DK sends submittals to TEI for review.  Submittals will be returned by the end of the week and equipment can be ordered.
03/29/23 – Materials have been ordered.   Construction will commence upon receipt of materials.
04/27/23 – Construction to commence upon receipt of materials.
05/23/23 – Construction to commence upon receipt of materials.  DK has the VFDs in their shop.  Scheduled ship date for the replacement MCC bucket is mid to late June.  Scheduled ship date for the replacement MCC is mid to late October 2023.  DK may install VFDs on wall sooner than MCC.  Will schedule pre-const meeting next week to discuss options.
06/28/23 – Pre construction meeting was conducted.  Once Bldg Mgr notifies that the compressed air lines that are in the location that the VFDs are scheduled to be installed have been relocated, DK will install the VFDs on the wall.  Anticipate that all Chiller shutdowns will occur once the MCC arrives (November ish) when the CH is not in cooling mode.
08/24/23 – work pending equipment procurement.
09/26/23 – work pending equipment procurement.
10/26/23 – TEI requests status update from DK on the reciept of MCC.  Upon receipt of MCC – the installation will be scheduled ASAP while not in cooling mode since the MCC serves chillers.
12/06/23 – DK indicates that ship date for MCC pushed by manufacturer from 11/1/23 to 03/14/24.  TEI questions when it was ordered, and DK indicates the PO was issued on 03/17/23.  DK questioned why the ship date delay?  No response.  TEI requests a meeting with DK, to develop an alternate plan for installation since it will now likely occur in cooling season.
01/30/24 – Waiting for equipment to arrive on site to schedule the installation (scheduled ship date = Mid March 2024).
02/28/24 – TEI has DK confirm ship date (=03/14/24) for equipment.  HCFD and TEI schedule pre-const meeting with DK on 03/08/24.
03/27/24 – DK confirms receipt of MCC.  VFDs are powered and the other MCC bucket already replaced.  DK to schedule an outage to install the new MCC over a weekend and to coordinate with weather and CH schedules.
04/24/24 – MCC scheduled for installation on 05/04/24.  Bucket to be swapped out during the same outage.
05/29/24 – MCC install did not occur.  New date being coordinated (tentatively 06/22/24).
06/26/24 – Install of MCC occurred on 6/22. No issues reported back.
07/24/24 – TEI prints off the arc flash stickers for the CH. Planning to install starting Aug 1 – pending availability of HCFD to escort/open doors.
08/28/24 – Upon review – labels were not correct that were printed. TEI reprints labels and will install pending coordination with building manager.
09/25/24 – TEI scheduling applying labels with bldg mgr and will apply all labels in the building.
10/30/24 – TEI applies labels throughout the building
12/11/24 – TEI delivers final AF report to HCFD with the AF tables and the model single lines in the reports.
02/26/25 – HCFD reports issues with MCC replaced. DK indicates additional bucket requested by HCFD ship date of 08/2025.
04/23/25 – Project pending additional equipment shipping 08/2025.
05/28/25 – No updates
06/25/25 – No updates
07/30/25 – No Updates. Breaker scheduled to ship next month.
08/27/25 – Breaker has arrived. DK working with HCFD to schedule the installation.
09/24/25 – Breaker is installed. Waiting on final phenolic labels to come in and be installed and then project will be complete after DEG and HCFD do a final final punchlist.
12/10/25 – DEG conducts final walkthrough. All work complete. Project complete pending closeout.
01/28/26 – Project in Closeout
04/29/26 – Breaker received and delivered to trades. Project can be closed out.

CH – Arc Flash Remediation Upgrades Read More »

264 – HVAC & Electric Conditions Assessment

PM: John Nester, Terry Cannon
04/28/22 – SOSS received and approved.
05/25/22 – It’s on the radar but not started yet.
06/30/22 – No updates.
07/27/22 – We visited the building for our first field trip. We’ve researched HVAC solutions for the space and will probably recommend splitting the existing HVAC unit into two systems one for the first floor and one of the second floor, adding a thermostat for better control, modifying basement ductwork to create two zones and adding one condensing unit for split system control.
08/24/22 – No significant progress this month.
09/25/22 – Draft reports should be done in early October.
10/26/22 – Electric reporting has been started, mechanical items are not so much. Soon…soon.
11/30/22 – Final report was turned over for final review and use. A few edits were made and the final report was resent to County amid several email blunders by TTC.
01/25/23 – No updates.
02/23/23 – Ready to Archive

264 – HVAC & Electric Conditions Assessment Read More »

JC – Underground Fuel Tank Replacement

PM: Matt Butz, Terry Cannon
04/26/22 – SOSS has been received. TTE met with County on kickoff meeting earlier this month. We met with the Fire Marshal and discussed scope of replacement, FM requested double containment piping on both the FOS/FOR piping. TTE on site with Duke to get into the vault and verify pipe routing and type. FOS/R is all double wall contained so we should meet code and fire marshal request for this project. THP not required on this project yet.
05/25/22 – CAD drawings and backgrounds are mostly updated, we are working on specifications and awaiting TTC markups for next step.
06/30/22 – CAD markups are back to designers. This job should be out for bidding by end of July.
07/27/22 – Review drawings are ready. We will submit them for review next week.
08/24/22 – Final markups in for updating. Bid in September.
09/25/22 – JN has provided contracts, TTC putting together bid documents. The project should bid end of Sept/early Oct timeframe.
10/26/22 – Out for Bid. Prebid complete, Addendum 1 ready for issuance. Bid Opening on Nov 4.
12/15/22 – No bids were submitted after extending the bid for local contractors. The job was repackaged as a Rebid and a new prebid was held last week. The local contractor still is not comfortable bidding the work, we have an Alternate design to send out for Addendum today for consideration. Job set to bid on 12/21/22.
01/24/23 – No bids submitted on rebid either. We will try to roll this scope into the Emergency Generator upgrades.
02/23/23 – Project combined with JC Emer Gen project in 2023. Archive this report.

JC – Underground Fuel Tank Replacement Read More »

JC – Germicidal Unit Upgrade

PM: John Nester, Terry Cannon
04/27/22 – SOSS received and approved. TEI to schedule project kickoff.
05/25/22 – Field trip for design kickoff on June 2, 10:30am.
06/02/22 – Design Mtg #1 complete. TEI to research options for whole system UV versus wall mount units.
06/30/22 – Schematic design ideas sent to several manufacturers and pricing has started coming back. We are compiling the study results now. I like the whole unit option.
07/27/22 – Review drawings are ready. We will submit HVAC drawings next week.
08/24/22 – UV design in existing ductwork at AC-D5 being drafted now. TTC did additional fieldwork earlier this month. Bid in September.
09/25/22 – JN has provided contracts, TTC is putting together bid documents. Project should bid end of Sept/early Oct timeframe.
10/26/22 – Out for Bid. Prebid complete, Addendum 1 ready for issuance. Bid Opening on Nov 4.
12/15/22 – Bid was opened, Debra was the apparent low bidder. Pre-award meeting went well and DK was recommended for the job. Contracts and insurance are getting finalized prior to starting work.
01/24/23 – Contracts and PO are in place. We are ready to have the preconst meeting. The first submittal is ready to be reviewed.
02/21/23 – Checked in with DK and they told me they need their submittal back for this job so we reviewed and sent that back this week.
03/10/23 – Equipment ordered and confirmed with the right voltage. Shipping date to be confirmed.
03/30/23 – Permit drawings have been sent to Debra for permitting.
04/25/23 – No update on permit approval yet on city website. TTC checking with DK.
04/26/23 – Parts on in town and at DK office. Permit will be applied for this week. DK ready to start working. Time to have a Pre Const meeting.
05/21/23 – Debra permitting the project now and waiting for badged employee to be available to work on this project.
06/28/23 – TTE sent back permitting responses. Ball is in DK court to get city permit then IBI permit. Dave is trying to get Installation Manual from vendor to submit to the city.
07/26/23 – Permitting not in place yet. Need to check on DK progress. “No detailed information available for the approval of Contractor Registration (This approval is reviewed upon the completion of all other required approvals)”
08/29/23 – Checked with DK a week ago and they had no update. The permit not approved, still in contractor registration phase.
09/27/23 – Talked to Dave at length about this project and its a resource issue for DK. He has not resolved the permit issue yet which he admits they need to get done. DK is currently trying to fix the JC boiler flue before winter and as soon as they are done with that, they will start the this project. DK will get a guy on the Permit this week. I believe they also need EC help for this job and I think that is one of the holdups to get started. All the equipment is in and approved.
10/25/23 – John contact DK this month and demanded a start to this project. Dave Gleason to get people started on this job and coordinate with Andy on access.
12/06/23 – Permit it approved. County reached out earlier this week and asked for an update on progress. TTE reached out to DK several times but also no updates from them at this time. I am thinking we ask Dave for a new project manager for this job so we get someone with more time to help.
01/31/24 – Multiple check ins with Dave Gleason and even Andy, not sure if electricians have started demo, but that is what was supposed to have happened.
02/23/24 – Met DK last week on lighting installation locations. DK has lights installed, need to have electric installed next and start demo.
03/22/24 – Mechanical work is done, need update from DK on electrical demo of existing UV and power for new UV lights.
04/24/24 – DK Electrical has visited the site to start to sort out the electrical scope. John told them to coordinate with the HCSO and Andy for schedule and to be onsite. DK report the new UV lights are powered up, TTE cannot confirm that yet.
05/28/24 – Met with DK today and discussed schedule and first demo of existing units. Sheriff will move inmates around one pod at a time while the units are demolished.
06/26/24 – We had a const meeting earlier this month, one cell will be used first to see how demo goes and Sheriff will move detainees to another cell while DK removes and patches one cell. AJ reported today that he believes the last unit was demolished yesterday and DK should be wrapping up demo very soon.
07/24/24 – Work is complete according to AJ, TTE waiting to punchlist this job.
08/28/24 – Punchlist to be performed 8/29 at 2pm.
09/24/24 – DK onsite patching up existing units, masonry, paint, and patch work on the punchlist. I talked to them today and they will be back down this week and next to wrap this job up.
10/30/24 – TTE checking on final punchlist progress.
12/12/24 – Dave Gleason says that we will have all the closeout paperwork by this Friday.
01/28/25 – Closeout paperwork received. We are working on the closeout process.
02/26/25 – We have received about half of the closeout documents for this project. See new Closeout page.
03/25/25 – Final closeout pages received, we are proceeding to full closeout.
04/23/25 – Project ready to archive.

JC – Germicidal Unit Upgrade Read More »

800 – Sub Basement Storage Floor Repair (F058)

12/14/22 – Hamilton County published a project list for 2022. Project to be complete by Fall of 2022.
03/08/22 – THP completed an initial site visit for scope of work.
03/25/22 – THP submitted a SOSS for review by the County.
04/13/22 – SOSS approved.
06/30/22 – THP working on staff background check. Plan to start mid June.
07/27/22 – THP visited site and needs to get a fire rating from the floor which would require a concrete solution. Looking at potential solutions now.
08/19/22 – THP issued review drawings for County review.
08/25/22 – THP working on option pricing for proposed design and removal of the fill.
09/21/22 – THP issued review Bid Set to John Nester for comments.
09/24/22 – THP issued Bid Set drawings and project manual to the county. Scheduled Pre-bid conference for 10/5/22, last day for questions 10/11/22, last day for answers 10/13/22, and a bid opening date for 10/19/22.
10/19/22 – Bid opening for the project. Four bids received all below or within the project published budget. SSRG the apparent low bidder.
10/26/22 – THP conducted bid review phone call with SSRG.
01/03/23 – SSRG sent Workers Comp. Insurance & CGL Insurance to HC
01/06/23 – HC Signed contract and PO
01/09/23 – HC Approved contract and PO and sent it to SSRG
01/13/23 – THP sent sealed conformance documents to HC and SSRG
01/17/23 – SSRG sent preliminary SOV and Schedule
01/18/23 – HC and THP sent comments back for revisions to SOV and Schedule due to long lead times for railings and the background checks.
01/24/23 – SSRG begun background check process
01/24/23 – SSRG sent submittals for steel rebar, steel railing, and anchorage.
02/27/23 – SSRG asked about the removal of existing piping that is in the way of the slab formwork.
03/01/23 – THP visited the site and, along with verification from the county, noted that the pipe was an abandoned fuel line and that it is acceptable to move/remove pipe as necessary for form work. SSRG will do so with no additional cost.
03/01/23 – SSRG noted they need to use permanent forms instead of digging pea gravel trenches for formwork. THP noted this as acceptable.
03/02/23 – Terracon was contracted to be the special inspector for this project for steel reinforcement and concrete.
03/06/23 – Progress meeting attended by SSRG, THP, and Hamilton County was held. It was requested by the county to draft a pump plan for the concrete pour day to notify parking inhabitants before the pour date. This was supplied that same day.
03/06/23 – Fuel tanks were noted to be buried under the pea gravel. This was deemed to not affect our design since the slab is designed to be structural.
03/06/23 – Concrete mix design was sent to Terracon for reference
03/06/23 – THP supplied SSRG with design loads for permit.
03/07/23 – Special inspections were scheduled
03/09/23 – Stamped special inspection form was sent to SSRG for permit.
03/13/23 – Progress meeting 1 meeting notes were distributed to the team.
03/13/23 – Progress meeting attended by SSRG, THP, and Hamilton County was held. Steel inspection and concrete pour scheduled for 03/13 and 03/14 respectively.
03/13/23 – Steel inspection was performed by Terracon, and steel reinforcement was reviewed by THP for consistency with design drawings. No comments were noted.
03/14/23 – Concrete pour was performed. THP on site from 7:45 AM until about 12:00 PM. Concrete pumping, finishing, and the site cleanup was observed by THP as required.
03/16/23 – Terracon sent reinforcing steel observations report.
03/17/23 – THP sent an elevation for SSRG & steel fabricator use for guardrail modifications.
03/17/23 – SSRG sent pricing for stairway move and rebuilding, and excess pea gravel removal.
03/17/23 – Progress meeting 2 meeting notes were distributed to the team.
03/17/23 – Field Report 02 for concrete pour was distributed to the team.
03/21/23 – SSRG sent Pay App #2 for approval.
04/21/23 – Bulletin No. 1 issued for review by the County.
04/25/23 – Bulletin No. 1 issued for pricing.
05/25/23 – Project summary. SSRG provided pricing for Bulletin No. 1 and Hamilton County declined the modifications. SSRG scheduling the final railing install. April pay application placed on hold, because work is for railing and closeout.
05/30/2023 – SSRG sent May Pay App for review
06/01/2023 – SSRG installed the guardrail per original drawings after Bulletin 01 option was rejected by County.
06/08/23 – THP sent the approved May Pay App to the County
06/12/23 – THP sent email to SSRG outlining the documents required for project closeout.
06/15/23 – THP performed a final punch visit, accompanied by John Nester.
06/15/23 – THP sent the final punch report to SSRG.
07/07/23 – SSRG completed punch list items on site.
07/12/23 – THP reviewed, approved, and sent previously-held April Pay App to County.
07/24/23 – THP reviewed SSRG’s completed punch list work and sent out a field report indicating these items were complete.
07/24/23 – THP compiled and sent As-Built drawings to SSRG for closeout documents. Waiting for SSRG to send closeout docs.
07/26/23 – THP published as-built drawings and completed punch list field report.
08/15/23 – THP contacted SSRG regarding an update to the progress of their closeout documents.
08/18/23 – THP received closeout binder electronic documents from SSRG. Documents included are: General 1 year warranty, As-built drawings (provided by THP), and THP’s Field Report 001. SSRG indicated they are still awaiting their front ends team to compile and send forms G706, G706a, G707, and the affidavits. THP reviewing.
09/26/23 – THP delivered approved project binders to the County.
09/26/23 – THP forwarded approved final pay application to the County.

800 – Sub Basement Storage Floor Repair (F058) Read More »

Comm Center – Asphalt Resurfacing (F056)

PM: Matt Butz, John Millar/Matt Rigdon
12/14/22 – Hamilton County published a project list for 2022. Project to be complete by Fall of 2022.
02/25/22 – THP and County met to discuss scope.
04/04/22 – THP submitted a SOSS for review by the County.
04/25/22 – County approved SOSS.
06/10/22 – THP issued design development documents.
06/21/22 – THP received contractor opinion of probable cost. Within project budget.
06/22/22 – County published AIA forms for final bid documents.
06/30/22 – THP documents ready for bid. THP coordinating bid dates. Anticipates bidding in July.
07/11/22 – THP issued “For Bidding” submittal with drawings and project manual.
07/19/22 – THP hosted pre-bid meeting at HC Comm Center Visitor Lot
07/21/22 – THP issued Addendum #1.
08/03/22 – Bid opening scheduled.
08/03/22 – No bids received at opening. THP contacted over 12 contractors during the bid period. Contractors noted extremely busy for 2022.
08/25/22 – Project documents updated and work rescheduled for spring of 2023. New bidding period advertise 8/26/30, prebid 9/6/22 and bids due 9/13/22.
08/26/22 – THP issued “For Bidding” submittal with new schedule for 2023.
09/06/22 – THP hosted pre-bid meeting at HC Comm Center Visitor Lot.
09/14/22 – Bids are due.
09/14/22 – Bids from Rack7, Prus and JK Meurer were received. All base bid within budget. Rack7 was the apparent low bidder.
09/21/22 – THP and Rack7 completed an initial bid review meeting. Rack7 did not include unit cost work in the base bid and has withdrawn from the bid.
09/28/22 – THP and Prus will complete an initial bid review meeting.
09/29/22 – THP and Prus completed an initial bid review meeting. Prus did not include unit cost work in the base bid and has withdrawn from the bid
10/05/22 – THP and JK Muerer completed an initial bid review meeting.
10/11/22 – THP issued a Bid Summary Letter recommending JK Meurer for the contract.
11/21/22 – J.K. Meurer was approved contract and corresponding PO. Kick-Off meeting sometime after the first of the year. Anticipate work after Winter/start of Spring.
01/04/23 – HC sent CO 001.
01/05/23 – THP signed and returned CO 001.
01/06/23 – J.K. Meurer signed and returned CO 001.
01/10/23 – J.K. Meurer to update THP/HC on background checks, expected submittal process date, and intended work completion date. THP proposed date for Pre-construction for March 15, 2023.
01/26/23 – J.K. Meurer to update THP/HC on background checks, expected submittal process date, and intended work completion date. THP proposed date for Pre-construction for March 15, 2023.
02/23/23 – Background checks to begin this month. Anticipating Preconstruction Meeting for March 15, 2023.
03/15/23 – Preconstruction Meeting
03/23/23 – Anticipating work schedule is May 1st-22nd. The following still needs to be submitted by J.K. Meurer: SOV, emergency contacts, and official schedule. No submittals have been submitted; Anticipating Mix Design Submittal.
04/25/23 – No updates for April. Work to start on May 1st (weather pending). Anticipating on-site visit with J.K. Meurer and Hamilton County on May 2nd (weather pending).
05/01/23 – J.K. Meurer provided mix design submittals. Asphalt resurfacing work began at Visitor Lot.
05/02/23 – THP site visit performed. Revisions were made to full depth repair quantities. Approx. 50% less area than original after observation of base course. Revisions by HamCo were made to ADA space to allow for access aisle to be at west side rather than east side of parking space.
05/05/23 – J.K. Meurer completed work at Visitor Lot and THP performed site visit. Work appeared to conform to drawings and revisions.
05/08/23 – J.K. Meurer began work at Secured Lot.
05/09/23 – THP site visit performed. Revisions were made to full depth repair quantities. Approx. 50% less area than original after observation of base course. Revisions by HamCo were made to the berm at the loading dock ramp.
05/15/23 – J.K. Meurer completed work at Secured Lot and THP performed site visit. Work appeared to conform to drawings and revisions.
07/26/23 – Bulletin being prepared and to be sent for review July 31.
08/09/23 – THP met with Ian to review drive repair needs.
09/26/23 – County request gate repair as part of drive work. Motor details sent to THP.
09/28/23 – THP forward JK Meurer quote for drive and gates.
10/06/23 – County approved quote for drive and gate. THP notified JK Meurer to proceed.
10/11/23 – JK Meurer proposed full slab replacement. THP provided slab requirements for the new ramp. JK Meurer provided updated proposal.
10/17/23 – Project budgetary numbers sent to County for review. JK Meurer proposal using cash allowance funds. Work is below total project budget.
10/17/23 – County sent draft Change Order No. 2 for authorization of new drive and gate motor.
10/25/23 – County published executed Change Order No. 2.
10/26/23 – JK Meurer schedule to begin drive work the middle of November.
11/03/23 – Drive repair work rescheduled to accommodate interior renovation project.
12/04/23 – Demolition of the ramp started.
12/06/23 – Lower section of ramp subgrade and steel prepared. Bottom half of ramp poured and concrete tested. THP inspected steel and Terracon tested concrete.
12/07/23 – Upper section of ramp schedule for completion.
01/15/23 – Concrete replacement at ramp was completed mid-December. Email received from contractor that installation of new gate operator is expected to be installed at the end of January.
01/30/23 – Gate contractor notified THP that the operator is now expected for production on 01-31-24. Production is backed up for LiftMaster and the ship date keeps changing. Installation is TBD in February.
0002/28/24 – Gate contractor is to notify THP and County once the vendor is contacted. Delivery has been delayed for approximately two months.
03/13/24 – Gate operator was delivered and installed on site. Overhead Door did not put the operator in service due to the condition of the gate.
03/18/24 – THP, HamCo Facility Manager, and Overhead Door met on site to review condition of inoperable gate.
03/27/24 – THP received quote from Mills Fence Co to replace existing gate. HamCo has approved. CO to be made up next week.
04/25/24 – JK Meurer planning on complete repair to top of drive on 4/26/24.
05/1/24 – JK Meurer and subcontractor has revised their project close out documents and sent to County. Project is closed. No more updates.
05/18/24 – JK Meurer to revise their pay app 2.
05/23/24 – Mills Fence Co checked gate to ensure it is working. JK Meurer and THP to start the project close out process.
09/26/24 – Awaiting final Change Order deduct from Hamilton County and Mills Fence lien waiver for close out documents.
12/11/24 – THP to review close out documents following updated close out procedures.
01/29/25 – Closing out – last phase. All documents are in and reviewed by THP. (3) As-built Hard Copies, (1) copy of final pay app & AIA docs, (3) copies in notebooks of O&M, and (1) USB flash drive. Will hand in at Thursday’s meeting.
02/24/25 – Final pay application approved.
02/25/25 – Final pay application prevailing wage documentation sent to County.

Comm Center – Asphalt Resurfacing (F056) Read More »

230 – City Façade Assessment (F054)

12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/06/22 – THP Submitted SOSS for review by the County.
04/22/22 – County Approved the SOSS.
04/27/22 – THP Completed a majority of the rappelling survey of the façade.
04/28/22 – Final rappels anticipated first week of June and report to be published in June.
06/30/22 – City Report due 7/1/23. THP to combine final rappel with Portune Center and complete in August.
7/28/22 – THP schedule rappelling 9/7/22.
10/27/22 – THP completed field work. THP to publish reports and budget 11/10/22.
12/15/22 – THP issued draft report.

230 – City Façade Assessment (F054) Read More »

TPC – Center Beam Repair (F053)

PM: Matt Butz, Matt Rigdon
12/14/21 – Hamilton County published a project list for 2022. Project to be complete by Fall of 2022.
02/24/22 – THP submitted a SOSS for review by the County.
03/11/22 – SOSS approved.
03/25/22 – THP completed a survey of the beam repair area.
04/28/22 – THP is developing documents.
05/17/22 – THP published review documents.
05/27/22 – County published review comments to DD documents.
06/30/22 – THP – Issue with Concrete repair around building electrical feeds determined. Repair needs in electrical feed area minor and can wait until electrical area needs service and come off line. THP documents ready. THP coordinating bid dates. Anticipates bidding in July.
07/11/22 – THP issued “For Bidding” submittal with drawings and project manual.
07/19/22 – THP hosted pre-bid meeting at HC Portune Center Lobby.
07/21/22 – THP issued Addendum #1.
07/22/22 – THP issued Addendum #2.
08/03/22 – Bids are due.
08/03/22 – Bids from LRT, Buckeye and ZSR were received. All base bid within budget.
08/18/22 – THP and LRT completed an initial bid review meeting.
08/22/22 – THP issued a follow up sketch for field clarification.
08/24/22 – LRT reviewed sketch and bid, and provided an updated price to their bid.
09/01/22 – Site visit and developed a design change to accommodate existing MEP.
09/16/22 – THP issued new “For Bidding” submittal with design change.
09/27/22 – THP hosted pre-bid meeting at HC Portune Center Lobby. Bids are due 10/7/22.
10/06/22 – THP issued Addendum #1 with new Bid Opening Date for October 13.
10/13/22 – Bids are due.
10/13/22 – Bids from ZSR, LRT, Buckeye, and SSRG were received.
10/14/22 – THP and ZSR completed an initial bid review meeting. THP sent a follow up letter to the County recommending they proceed with ZSR for the based bid and all four alternates.
12/12/22 – ZSR was approved contract and corresponding PO. ZSR has signed and returned COI. Kick-Off meeting sometime after the first of the year. Anticipate work in February 2023 depending on background checks.
01/12/23 – ZSR has begun submittal process.
01/18/23 – HC approved contract and corresponding PO. ZSR has yet to complete background check process. Once completed, pre-construction meeting will be held the following week. Anticipated start of work in February 2023.
01/26/23 – HC approved contract and corresponding PO. ZSR has yet to complete background check process. Once completed, pre-construction meeting will be held the following week. Anticipated start of work in February 2023.
02/14/23 – Preconstruction Meeting
02/23/23 – All submittals are in. Anticipating work to start February 27.
03/23/23 – Drilled holes for rebar on 3/20/23. Permit completed by end of this week. Anticipating deck supporting steel to be installed week of 3/27. Special inspections to be completed following the steel installation.
04/20/23 – On-site visit with Hamilton County to observe completed work. No comments on work from Hamilton County. THP to send close out report.
07/26/23 – Bulletin being prepared and to be sent July 31.
09/28/23 – THP forwarded pricing from ZSR for the beam repair. County coordinating possible repair of beam with electricians.
10/19/23 – County moving forward with electrical and beam repair. County requested ZSR beam repair proposal to develop an AIA Change Order.
10/26/23 – County developing AIA Change order for ZSR.
01/12/24 – Change order for additional beam repair cancelled due to electrical conflicts.
01/31/24 – Project is in the process of closing out. Awaiting final close out docs.
02/28/24 – THP received project close out documents and is reviewing.
03/14/24 – THP received revised project close out documents and is reviewing.
04/25/24 – THP approved draft closeout package. ZSR to send hard copies and USB drive.
05/01/24 – ZSR revised their project close out documents and sent to County. Project is closed. No more updates.
08/29/24 – All final work closeout documents completed. Waiting on final pay application.
12/09/24 – THP reached out to Terracon to provide special inspector stamp for close out to Permit. Terracon to provide this week.
01/29/25 – THP Closedout Procedure – January 3 – City of Cincinnati is currently closing out the permit (Jeffery Hinkle).
03/26/25 – Project Archived.

TPC – Center Beam Repair (F053) Read More »

TPC – City Façade Assessment (F052)

12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/06/22 – THP Submitted SOSS for review by the County.
04/22/22 – County Approved the SOSS.
04/28/22- Rappelling anticipated first week of June. Report to be published in June.
6/30/22 – City Report due 7/1/2023. THP completed review of new cellular towers. THP to schedule rappelling late July. Report to be complete by end of August.
7/28/22 – THP schedule rappelling 9/7/22.
10/27/22 – THP completed field work. THP to publish reports and budget 11/10/22.
12/15/22 – THP issued draft report.

TPC – City Façade Assessment (F052) Read More »

CH – Annual Façade Monitoring (F051)

12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/06/22 – THP Submitted SOSS for review by the County.
04/22/22 – County Approved the SOSS.
04/27/22 – THP Completed rappelling survey of the façade.
04/28/22 – Report to be published in June.
06/29/22 – THP issued reports and City form.
06/30/22 – THP Scheduled to submit form to City.
08/25/22 – Project complete.

CH – Annual Façade Monitoring (F051) Read More »

800 – Annual Façade Monitoring 2022 (F050)

PM: Bert Watts, John Millar
12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/07/22 – THP Submitted SOSS for review by the County.
04/21/22 – County Approved the SOSS.
04/27/22 – THP Completed rappelling survey of the façade.
04/28/22 – Base survey anticipated end of May and report in June.
06/30/22 – City report due 7/1/2023. THP plans to issue draft report for review 7/8/22.
08/25/22 – THP working on findings presentation.
09/28/23 – THP completed new cost data with project estimates. THP working on final presentation.
02/29/24 – THP no update.
03/27/24 – THP no update.
04/25/24 – THP no update.
05/30/24 – THP no update.

800 – Annual Façade Monitoring 2022 (F050) Read More »

A&D – Annual Façade Monitoring (F049)

12/14/22 – Hamilton County published a project list for 2022. City Inspection to be completed by June 30.
04/06/22 – THP Submitted SOSS for review by the County.
04/12/22 – County Approved the SOSS.
04/14/22 – THP Completed rappelling survey of the façade.
06/29/22 – THP issued reports and City form.
06/30/22 – THP Scheduled to submit form to City.
08/25/22 – Project complete.
10/27/22 – Ready to Archive.

A&D – Annual Façade Monitoring (F049) Read More »

230 – Magistrates Lobby Security Upgrade

02/08/22 – Signed SOSS Received.
03/29/22 – DD Kickoff meeting.
04/15/22 – Comments received from Scott and plans adjusted accordingly. 100% review meeting mid may.
05/17/22 – Review meeting with With Scott. Plans adjusted according to his comments.
05/26/22 – Project combined with Mediation. Review set due June 2 Arch and MEP.
06/30/22 – Project in bidding phase.
07/28/22 – bidder recommendation letter sent.
08/25/22 – Building Permit applied. Contracts in progress
09/29/22 – Contracts finalized. kick off meeting to be scheduled in the near future. Construction Project move to a combined construction project.

230 – Magistrates Lobby Security Upgrade Read More »

JC – 2022 Cell Door Replacement (Ph 2 Triton)

PM: Matt Butz, Sam Hofmann
01/21/22 – Signed SOSS Received.
03/23/22 – Meeting with Sheriffs to define scope. Number of doors defined. Hold pending door lock replacement project scope.
06/30/22 – Scope to be defined at project kickoff meeting for current set of doors.
07/28/22 – Scope to be defined at project kickoff meeting for current set of doors.
08/23/22 – Scope finalized. Plans to be sent and confirmed with sheriffs.
09/29/22 – Project out to Bid
10/27/22 – Triton won bid.
12/15/22 – Contracts signed and returned.
01/26/23 – No update.
02/25/23 – No update.
03/30/23 – Triton has subbed Jails Products again. Submittals to arrive shortly.
04/27/23 – No Update.
05/25/23 – No Update.
06/29/23 – No Update.
07/27/23 – No Update.
08/31/23 – Submittals received. Changes noted. Meeting to discuss with Sheriffs to be scheduled in near future.
09/28/23 – Meeting held with Captain Wilson. Submittals to be returned with changes as required.
10/25/23 – No update.
12/07/23 – No update.
07/27/23 – No Update.
08/31/23 – Submittals received. Changes noted. Meeting to discuss with Sheriffs to be scheduled in near future.
09/28/23 – Meeting held with Captain Wilson. Submittals to be returned with changes as required.
10/25/23 – No update.
12/07/23 – No update.
02/29/24 – Kick off to be scheduled close to delivery.
03/28/24 – Triton asked question. Site visit to confirm to be scheduled for next week.
04/25/24 – Waiting on sheriffs to answer keying questions.
05/30/24 – Questions sent to Triton. Triton has not responded.
06/27/24 – New project manager assigned to project. Doors to ordered in near future.
02/27/25 – Doors are ordered and scheduled for delivery the last week of April.
03/27/25 – No update.
04/24/25 – Mobilization scheduled for early May.
05/29/25 – Delivery was delayed. mobilization scheduled for mid June.
06/26/25 – Mobilization scheduled for Monday.
07/31/25 – Frames came in with incorrect dimensions. They will all be modified by Triton and remobilized in a couple weeks.
08/28/25 – Modified frames were manufactured for thicker wall dimension. Triton to provide correct frames as soon as possible.
09/25/25 – Corrected frames will arrive with Cornerstones delivery.
10/30/25 – Frames to be delivered monday. Triton to mobilize and complete their scope.
12/11/25 – Triton discovered that the doors were the wrong thickness. Cornerstone doors can be used to cover all but one of their doors. The one door has been ordered and will be delivered shortly.
01/28/26 – Door delivery date has been pushed back. Work has been paused.
02/26/26 – Door still not delivered. Door suppossedly will be delivered tomorrow. two more doors in this project once the door delivered is completed.
03/26/26 – Final phase to begin next week.
04/30/26 – Frames came in the wrong size. Frames to be delivered next week. Project to be complete end of May.
05/28/26 – Cornerstone to complete final pod for Triton. 6/24 install date.
06/25/26 – Demo revealed damage to block walls. Change order accepted. Cornerstone to complete work. Mobilized this week.
07/30/26 – Work is complete. Closeouts ongoing.
08/28/26 – No Update.
09/24/26 – Change order to order new millenium pac units submitted. No update on closeouts.

JC – 2022 Cell Door Replacement (Ph 2 Triton) Read More »

TPC – Risk Management Renovation

PM: John Nester, Sam Hoffman, Mike Murphy, Terry Cannon
04/29/21 – TEI and Champlin on board with providing programming for this work for the current SOSS in place. Discuss with John and Bert after partner meeting.
05/19/21 – Kick-off meeting held to review scope.
05/20/21 – Champlin sent County preliminary layout of Scenario 1
05/25/21 – User meeting with Rodney Lofland. Review his stated program needs.
06/16/21 – Met with Risk Mgmt and reviewed Champlin proposed floor plans. Got input from the department and discussed needs for space from the Architectural Review. We also started the MEP needs of the space and settled on some basic requirements for HVAC zoning, plumbing use, and security requirements. They do want a kitchenette for a sink, coffee pot, microwave, and refrigerator.
06/25/21 – Sent updated floor plan to County.
07/29/21 – Two estimates will be done. One with 900 SF, one for 2500 SF. County will open the Archiubs estimate for us to put our numbers in. Put the small estimate in as a line item change in the larger estimate. Get number and get schedule.
10/18/21 – SD and Estimate uploaded to Archibus. Provided plans and estimate for a base, upsize and downsize option. ThermalTech drawings, cost and archibus updates also complete.
01/27/22 – Should have a decision on budget and option on Tuesday.
02/22/22 – DD-CA SOSS submitted.
03/31/22 – Signed SOSS received. Deadline of end of April to be Bid ready.
02/25/22 – Signed SOSS Received.
04/06/22 – Kickoff meeting scheduled, to be complete by the end of April.
04/28/22 – Requested Plan review confirmation meeting mid-May. TTC combined our version with Champlin version, we will continue with the Champlin version from here on out.
5/12/22 – Review meeting held. Revised layout approved. TTE to get started on design and Champlin to finalize finishes.
06/30/22 – Project issued for bid.
07/28/22 – Bids received. bid review 7/26
08/23/22 – Building Permit applied for. Contracts in Progress.
09/29/22 – Contracts finalized. Kickoff meeting to be scheduled in the near future.
10/13/22 – Pre-construction meeting held. Kickoff meeting to be scheduled once submittals are returned.
12/15/22 – Construction ongoing.
01/26/23 – Construction on going. Schedule pushed back to be substantially complete on 2/20/23.
02/22/23 – Construction not complete. Will need a couple more weeks.
03/30/23 – Punch list completed 3/29.
04/27/23 – Still waiting on various punch list items to be complete.
05/25/23 – Furniture installed. Triton to send signed off punchlist.
06/29/23 – Waiting on closeout documents
07/27/23 – Extra permit withdrawal paperwork sent to Triton Jeff to give to city. Check and make sure they done.
08/31/23 – No update.
09/28/23 – No Update.
10/25/23 – No Update.
12/07/23 – No Update.
02/29/24 – Closeouts received
03/28/24 – Hardcopies outstanding.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – No Update.
07/24/24 – Additional request sent to Triton for closeout documents.
08/29/24 – No Update.
09/26/24 – No Update.
12/12/24 – Requested updates last month. No update.
01/30/25 – Meeting held with Triton and County to go over outstanding items for several projects.
02/27/25 – Final Pay app processed.

TPC – Risk Management Renovation Read More »

CH – HVAC Control System Replacement (081-22)

PM: Matt Butz, Terry Cannon, Will Fisher
Closeout: Joe Bulach, joe_bulach@emcorgroup.com, Dayna O’Brien, dobrien@davieseg.com


02/19/22 – ThermalTech submitted SOSS for the project.
03/04/22 – Met with Emcor on Ameresco pricing and scope exercise.
03/09/22 – Met with SBS on new technology and ALC interfacing capabilities
03/10/22 – TEI has created all the background drawings and base specifications for the project in the new CSI format.
03/11/22 – SOSS received and work begins. TTC setting up kickoff meeting on this project.
03/15/22 – Met with Honeywell onsite today and reviewed scope of Chiller controls and scope of this project in more detail. Two new corporate guys met us onsite and review past history and what they plan going forward.
03/22/22 – TTE met and review the action item list for bidding this out in 2022. We need to get background checks complete, BDS coming down tomorrow for BGC, Fisher has his badge, Constable BGC is complete and needs his badge. We’ve agreed to meet with Honeywell and JCI as the additional manufacturer’s for this project. We also want some time to sit with the con
03/23/22 – Started specs in new CSI format. Set up meeting with Honeywell for April 8 and JCI for April 11. We are trying to meet with Barth to review acceptable communication paths in the CH. We will schedule fieldwork soon.
03/31/22 – Meeting updated with JCI for 4/7. The badge process is started for 3 guys.
04/15/22 – Final controls meeting with vendors held this day. All said they can bid this job and meet the requirements.
04/28/22 – Project design schedules distributed. Fieldwork and design in April, May, June, July. Bidding in August, September. Award and contracts are October, November. Fieldwork started last Tuesday with Bracken and Matt. Basement, sub-basement, and roof equipment was verified.
05/25/22 – ThermalTech has been on the building finalizing equipment locations and needs for the last month. Our review drawings for all the equipment including VAV boxes will be out the County on June 3. We are also developing airflow diagrams for the control sequences based on our findings and Honeywell existing information. We are on schedule to bid in August.
06/30/22 – This month we finished up equipment takeoffs and sent them back to the County for review. Comments came back in a day and we have scheduled another field trip to check out additional equipment. JN asked for us to check our equipment against the archibus database, however, I cannot see the equipment database in archibus yet. Ask HC for help at meeting.
07/27/22 – A full equipment set of drawings was submitted to the County for review. TEI scheduling another field trip for final equipment information next week. We want to be on site with Randy so we can finalize sequences on standalone equipment and missing equipment in the sequences.
10/26/22 – Out for Bid. Prebid complete, Addendum 1 & 2 issued. Bid was extended to Nov 15. At least one more addendum before bid opening.
12/15/22 – Bids were opened on schedule and the apparent low bidder is Debra Kuempel. A full pre award meeting was held and the recommendation sent to the County for Base Bid and several Alternates for this job that were still under the published estimate. Project is moving forward, Emcor called for an update yesterday.
12/20/22 – County sent the contract to Emcor for signature.
01/24/23 – Contract was sent, not sure if the PO is back yet. Ready for kickoff.
01/30/23 – John checked back with Steve on contract status.
02/23/23 – Project is in front of the board for approval. DK putting together their project team and was instructed to run all communications through the County PM.
03/29/23 – All contracts are in place and we are ready to have pre-const kickoff meeting. TTC to schedule and reach out to ZH commissioning for their background checks.
04/25/23 – The Pre-Const meeting was help and Emcor was introduced to the project team. After the meeting, we walked one AHU and DK spent time on site surveying the existing building and equipment. We are in submittal and background check phases.
05/21/23 – It Meeting was help this month. DK putting together proposed network locations for our review. The County is working on ordering 7 network switches for the new Control VLAN inside the Courthouse.
06/28/23 – DK continues to work on background checks. Initial network switch location rejected, looking for new locations. TTC & MCB to suggest locations, then will give to DK to review, we may need additional network switches.
07/26/23 – Emcor still working on getting staff background checked for this job. Net network locations reviewed and sent to County for their review. We may potentially meet and go over them at Partner Meeting on Thursday. TTC invited IT and Telecom.
08/16/23 – Met with DK and have new prices for the fiber backbone change order. Steve Yockey sent them to TTC who will review and send to County.
09/27/23 – We are very close to finalizing the change order for the fiber infrastructure for this job. TTE will create a final room location drawing for DK after we receive comments from Jack, Steve and the County. Any issues with what is on the our change order markups for VE options? Controls Submittals have arrived for TTE review.
10/25/23 – Background and LEAD checks underway. DK working with JN. Network location finalized with County and Debra and Change Order #1 for network infrastructure sent to DK for signatures, we are accepting the Value Engineering proposal for this work. Controls submittals returned to DK Revise and Resubmit. We’ve incorporated ZH commissioning comments, WF, BDS and TTC comments into specifications. DK and TTE have coordination meeting on Thursday to review in details to ensure resubmittal is correct.
11/03/23 – Bi-Weekly Construction meetings begin. Emcor working on schedule. TE working on submittal review. Team working on network infrastructure. Jack can’t make Friday meetings until 2024.
11/17/24 – Const Meeting. Working on Background Checks and LEAD checks. Emcor low voltage working on cable runs.
12/01/23 – Const Meeting. Start working on deficiency report format, LEADS checks, low voltage routes.
12/15/23 – Const Meeting. Continue with Submittals work, background check and low voltage routes.
12/20/23 – Submittals returned for equipment and sequences. We still have a couple of outstanding items.
01/05/24 – Const Meeting. Work continues and is making progress.
01/19/24 – Const Meeting #6. Emcor and DK working on after hours progress, TE working on missing piece of equipment and getting ZH in Leads checks program.
01/26/24 – Deficiency List and Honeywell Scope meeting in Room 608.
02/23/24 – Const Mtgs continue. DK running new fiber continues. Deficiency list is begin worked and updated. Honeywell contacted for their portions. Emcor pricing up actuator replacements from deficiency report. Submittals are being updated, penthouse controls are being updated.
03/22/24 – Biweekly meetings continue. This month Honeywell got the chiller plant online, the secondary chilled water pumps VFD’s are online and working, Bacnet has been added to three of the four chillers. DK submitted change orders for four pneumatic upgrades to four units. TTE reached out to Honeywell for pricing on these same four units plus their deficiency list items. Emcor has many of the fibers ran to the server room, they need to repair the walls where they brought items into the room and finishing punching down the cabling. The DDC server is installed in the Rack.
04/24/24 – Next Const Mtg tomorrow is this Friday. Will is out this week and Bracken will cover the meeting. Emcor is being pushed to provide a best guess schedule. AH-52 has been submitted. TTE is reviewing sequences for the new equipment, we will have a design meeting with Emcor to go over sequences and make sure they can do what we have asked for in the Project Manual.
04/25/24 – Biweekly meetings continue. The fiber and CAT6 installation is scheduled to be finished by April 30th. The new network and front end are scheduled to be online during May and equipment changeover to the new controls system shall begin immediately afterwards. Emcor will begin with changing smaller equipment in the basement that is less disruptive to everyday operations. Emcor is beginning to work on replacing the approved pneumatic valve actuators that were deficient.
05/28/24 – Biweekly meetings continue. Low voltage wiring will be completed in the next 2 weeks, only the fourth floor remains incomplete. The new ALC controls database will be uploaded to the old server by Emcor this week. The database will then be transferred over to the new server once HAMCO brings the new server online. Emcor will be starting the first equipment change overs next week, once the database is uploaded. Emcor will begin with the smaller equipment in the basement that is less disruptive to everyday operations. CO#3 has been approved to add AHU-52 to the scope of the project, changing that unit to ALC controls. Emcor and ThermalTech have reviewed the controls sequences and are working to finalize the sequences.
06/24/24 – Biweekly meetings continue. Low voltage wiring on the fourth floor will be completed this week and the new network switch will be installed. Emcor has uploaded the new ALC controls database to the new server. Emcor has begun bringing materials to the site and are planning to begin work in the next 2 weeks to change over equipment in the basement. ThermalTech, Emcor, and ZH are working to finalize the controls sequences based on the latest comments provided by ThermalTech.
07/22/24 – Biweekly meetings continue. Emcor has begun to change over equipment in the basement to ALC controls. Emcors graphics department has begun work on the graphics for the front end. CO-01 is nearing completion, ThermalTech will be creating a punchlist to close out the work. Emcor and ZH Commissioning are coordinating to commission the equipment that’s been changed over. ThermalTech is coordinating a controls sequence meeting with ZH and Emcor. ThermalTech is also coordinating a deficiency list review meeting to close/address any open deficiency list items.
07/24/24 – Met with Dale and Ben today on sequences, they should be finalized before end of next week. Met with ZH commissioning today and ALC not ready with graphics for them to star CX, so we are pushing them back a week.
08/26/24 – Biweekly meetings continue. Emcor continues to change over equipment in the sub-basement and basement to ALC controls. Emcor has changed over the south central VAV’s on the first floor, further work on the first and second floor will begin in the next 2 weeks. Emcor continues to develop the graphics, expecting to complete them by the end of August. A preliminary BAS training took place this month to get Tyler Laws and his team familiar with the new system; another training will be scheduled once the graphics are complete. Commissioning by ZH Commissioning will take place once the graphics are completed. Controls sequences have been finalized by ThermalTech and Emcor, the sequence submittal is expected to be submitted by Emcor within August. Work for CO-01 is almost complete, Emcor will provide a punchlist and ThermalTech will verify it. The deficiency list is nearing completion, with a few items being addressed by HAMCO and a few items still to be investigated by Emcor.
09/23/24 – Biweekly meetings continue. Emcor continues to change over equipment in the basement and first floor to ALC controls and has begun work on the second floor. Emcor continues to develop graphics with an expected completion at the end of October. A BAS training session will take place on October 1st to review the graphics in more detail with Tyler Laws and his team. Commissioning by ZH Commissioning has begun starting with the basement equipment. The fiber and CAT6 installation is nearly complete; Emcor has turned over a punchlist that ThermalTech has started to review. The deficiency list is nearing completion with a few items being addressed by HamCo and some items requiring Honeywell assistance.
10/28/24 – Biweekly meetings continue. Emcor continues to change over equipment on the second and third floors to ALC controls. Emcor continues to develop graphics with an expected completion at the end of October. A BAS training session has taken place on October 1st to review the graphics in more detail with Tyler Laws and his team. Commissioning by ZH Commissioning is ongoing and currently focused on the basement equipment. The fiber and CAT6 installation are complete. Once the record network submittal drawings are received, ThermalTech and HAMCO will review and walk down the punch list items. The deficiency list is nearing completion with the last few items being addressed by HAMCO once the steam system is turned on for the winter.
10/29/24 – ThermalTech scheduling change order review meeting with HamCo. We need to work out some scope issues on the drawings vs reality of what is in the space.
12/12/24 – Emcor is mostly complete with the basement and moving up through the building to floors 1 thru 4 as well. They are onsite every day and working towards the April deadline. ZH commissioning has started creating an CX list that Emcor will have to help correct the CX issues as we move forward and complete the work. VPN seems to be working.
12/23/24 – Biweekly meetings continue. Emcor has completed all changeovers on the second floor and third floor. Emcor continues to change over equipment on the fourth and fifth floors to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement, basement, and first floor. Emcor has a few small items to update in the BAS per HAMCO preference. Commissioning by ZH Commissioning is ongoing and currently focused on the first and second floor equipment. The fiber and CAT6 installation are complete. Record network drawings have been received from Emcor. ThermalTech and HAMCO will review and walk down any network related punch list items. The deficiency list will be checked again in January, no deficiencies have been checked on in December. Change order #2 work for AHU-21, AHU-22, OAHU-1, and AHU-B2 has begun. All of the AHU’s mentioned previously have new valves installed per CO#2, only the damper work remains to be completed.
01/27/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, and third floor. Emcor continues to change over equipment on the fourth and fifth floors to ALC controls; these floors should be completed in January. Emcor will begin the sixth floor in early February. There is a small amount of equipment left to be changed over in the sub-basement and basement. Commissioning by ZH Commissioning is ongoing and currently focused on the first and second floor equipment. Most equipment in the basement that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network related punch list items. The few remaining items on the deficiency list should be closed out in February. Change order #2 damper actuator replacement work for AHU-21, AHU-22, OAHU-1, and AHU-B2 should be completed in January, closing out CO#2 work. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 82, 85) have been changed over.
02/24/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, and fourth floor. Emcor continues to change over equipment on the fifth and sixth floors to ALC controls. The fifth floor should be completed in February. There is a small amount of equipment left to be changed over in the sub-basement and basement. Chiller plant changeover will begin in February. Commissioning by ZH Commissioning is ongoing and currently focused on the third and fourth floor equipment. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network related punch list items. The one remaining item on the deficiency list should be closed out in February. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going and should be completed in February, closing out CO#2 work. AHU-52 has been changed over, closing out CO#3. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 82, 85) have been changed over.
03/24/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to change over equipment on the sixth floor as well as wrapping up the equipment in the basement and beginning on the chilled water system and large AHU’s. AHU-82 is the first large AHU that has been changed over to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement and basement. Chiller plant changeover is on-going. Commissioning by ZH Commissioning is ongoing and currently focused on the third and fourth floor equipment. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going. AHU-52 has been changed over, closing out CO#3. A schedule extension due to the additional work of 4 change orders will be discussed once the large AHU’s (68, 75, 85) have been changed over. March will focus on the large systems in the courthouse, the chilled water system and the remaining large AHU’s.
04/23/25 – Work is progressing with about about 84% of the project complete. Emcor has asked for a two month extension for completion. ZH is following behind Emcor and catching up on commissioning. The County has some decent request for front end modifications that Emcor needs to work through. The large AHU’s are being converted now. The Chilled Water plant is current under integration and Emcor has been asked to provide a boiler plant integration cost outside of the scope of this project (see TTC & AKM).
04/28/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to work on the sixth floor, seventh floor, and the chilled water system. All large AHU’s (AHU-68, 75, 82,85) have been changed over to ALC controls. There is a small amount of equipment left to be changed over in the sub-basement and basement (Pending deficiency item repairs). Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning will be next. Most equipment in the basement, first, and second floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for OAHU-1, and AHU-B2 have been completed. AHU-21 and AHU-22 damper actuator replacement is on-going. A schedule extension change order is in progress. May will focus on completing changeover of the remaining items and resolving any commissioning deficiencies identified by ZH Commissioning.
05/27/25 – Biweekly meetings continue. Emcor has completed all changeovers on the first floor, second floor, third floor, fourth floor, and fifth floor. Emcor continues to work on the few remaining items and the chilled water system. The following are the remaining items to be changed to ALC controls for the project: Chilled water system, AHU-B, AHU-B16, EF-71, and misc. (4) condensing units. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HAMCO and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network related punch list items. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is on-going. Change order #4 is closed. Change order #5 has been signed, extending the schedule to June 13 and adding in the changeover of FCU-8 and AHU-B to full ALC controls. June will focus on completing changeover of the remaining items and resolving any commissioning deficiencies identified by ZH Commissioning.
05/28/25 – Emcor did not submit a payapp for January. Payapps 12, 13 and 14 are wrong. We are working on corrections. We received corrected copies of 13 & 14 today but 12 is still wrong.
06/23/25 – Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. Emcor has completed all changeovers except for the chilled water system and (4) misc. condensing units, which are on-going. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HamCo and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network (CO#1) related punch list items. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is on-going. Emcor is back checking all of their work, currently expecting to be done and ready for ThermalTech to punchlist on August 1. Basement, first, and second floors are largely complete and functioning correctly. HamCo is coordinating directly with Emcor to resolve any issues that are identified in the day to day building operations. July will focus on checking all equipment and resolving any commissioning deficiencies identified by ZH Commissioning to prepare for August 1 punchlist.
07/25/25 – Const Mtg held with HamCo, TTE, and Emcor. ZH not present.
07/28/25 – Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. Emcor has completed all changeovers except for (4) misc. condensing units in the basement, which are on-going. The chilled water plant is now changed over and running in automatic mode. Emcor is focusing the majority of their time back-checking the commissioning items found by ZH and resolving any issues with the large AHU’s (85R has some pressure sensor issues being worked on). All change order work is completed. CO#6 is being drafted to give credit to HAMCO for systems that have been removed from scope and to extend the schedule. Change order #2 damper actuator replacement work for AHU-21 and AHU-22 is completed. State contract work is on-going for misc. repairs. Commissioning by ZH is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HAMCO and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HAMCO will review and walk down any network (CO#1) related punch list items. Emcor is back checking all of their work, revised date for ThermalTech to begin punchlist is now August 15. Basement, first, and second floors are largely complete and functioning correctly. HAMCO is coordinating directly with Emcor to resolve any issues that are identified in the day to day building operations. County wants to make sure that DK is doing the t-stat touch up plates. Make sure the County knows when.
08/25/25 – The project has entered the punchlist phase. Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. The chilled water plant is continuing to run in automatic mode. Emcor is focusing the majority of their time backchecking the commissioning items found by ZH and resolving any issues with the large AHU’s. All change order work is completed. CO#6 is being drafted to give credit to HamCo for systems that have been removed from scope and to extend the schedule. State contract work is on-going for misc. repairs. Commissioning by ZH Commissioning is ongoing and most VAV boxes have been commissioned, large AHU commissioning is on-going. ZH is coordinating with HC and Emcor to resolve any issues found. Most equipment in the basement, first, second, third, fourth, and fifth floors that has been changed over to ALC has also been commissioned by ZH. ThermalTech and HamCo will review and walk down any network (CO#1) related punch list items. Punchlist walk with ThermalTech and HC is scheduled for early September.
08/26/25 – We are having a hard time narrowing down the graphics for the generators in the Courthouse. EGEN is the emergency generator in the basement. GEN-1 is the standby generator on the platform.
09/22/25 – The project is in the punchlist phase. Punchlist was developed during a one-day site walk with HAMCO and ThermalTech. Draft punchlist was supplied to Emcor, punchlist will be submitted to Emcor as final once ZH’s commissioning is completed. Biweekly meetings have ended. Meetings are now being scheduled on an as-needed basis. The chilled water plant is continuing to run in automatic mode. Emcor is focusing on completing items on the punchlist or checking the commissioning items found by ZH and resolving any issues. All change order work is completed. State contract work is on-going for misc. repairs. Commissioning by ZH Commissioning is nearing completion. All equipment (except for heating equipment) has been commissioned. ZH has commissioned the chilled water plant. ZH is coordinating with HamCo and Emcor to resolve any issues found. The Punchlist has been issued, and we are ready to enter the closeout documents phase.
10/29/25 – The second training session was held earlier this month with the operators. I think it started our rough but was better received by the end of Training. More use will make the end user more comfortable with the new product. The Project punchlist still being completed. ZH Commissioning has a few days left to complete their work on the deficiency list for this project. We found that the free cooling HTX was not on the graphics yet, DK fixed yesterday and the heating plant is not working correctly yet, DK to assist Tyler in making this right.
12/12/25 – Functional testing deficiencies list meeting held today to review progress from Dec 3-5. Some items complete, many are not. DK needs to devote resources and technician to site to complete the CX work. DEG will have to setup owner internal review meeting later this week to review our outstanding resolution items. TTC pushing for 02/28/26 drop dead date for all the outstanding work, requested basic progress scheduled for DK too address final items.
12/22/25 – Punchlist completion is on-going. Site visits in December discovered that there are numerous open items on the resolution tracking form to be resolved. Resolution tracking form items are planned to be resolved by the end of February. HAMCO has given a PO to Emcor to replace HX-1 and HX-3 steam valves to DDC on state contract terms. Weekly meetings have been scheduled to check on the progress of the resolution tracking form items.
12/23/25 – HTX-4 Meeting scheduled for Jan 7 with County, DK and Davies.
01/25/26 – Emcor and DK making good progress, we are hopeful that this project will complete by the end of February. Ethan making good progress knocking out all final items and coordinating with HamCo and ZH Commissioning. VPN access requested for Will Fisher, Anthony said they will send him application. Smell and temperature on sixth floor better but not gone all the way that I know of. Weekly meeting continue with DEG, Emcor, DK and Facilities.
02/25/26 – Weekly Const meetings continue. Emcor has completed the TE punchlist and ZH resolution tracker except for the chiller plant which they are working on this and next week. The HTX will be taken apart and tested in March or April. TTC reached out to Emcor for a full PW download directory as requested.
03/25/26 – Emcor working on Chiller and Cooling tower plant controls. Emcor commissioning ready to start as soon as chillers are started. DEG and ZH met on commissioning deficiencies. DEG issued Punchlist #2, ZH working on revised resolution tracker worksheet. We are scheduled to inspect the HTX next month.
04/20/26 – Emcor, DEG and ZH reported for final commissioning and worked through the final punchlist and functional testing markups this week.
04/28/26 – Checked in with Tyler and everything seems to be working well.
04/29/26 – Tyler reported this morning at the cooling tower overflowed with water this morning and the penthouse was flooded. Investigation showed that some equipment was commanded off and a second condenser water pump started causing the overflow condition. DEG asked Emcor for an additional logic step to prevent this from happening in the future. Emcor also asked that equipment be release to operated in automatic mode so this does not happen.
05/27/26 – All punchlist and resolution tracker work is reported as complete. DEG requested closeout documents from Emcor for project closeout.
06/25/26 – Project in closeout.
07/30/26 – Working on closeout documents. Emcor collecting OM’s and paperwork. We check back every Friday.
08/26/26 – Almost all closeout documents received including releases. We are working on full closeout.
09/23/26 – After months of work, coordination, and emailing Emcor, we have the final closeout documents and TTC will hand delivery to Ted and Mat ton 9/24. We have requested final payapp for processing.
10/26/26 – Project is in Closeout.

CH – HVAC Control System Replacement (081-22) Read More »

OMJ Accessibility Entrance Study

02/08/22 – Signed SOSS Received. Scope reduced to exterior entrance only.

03/31/22 – Field verification complete. Plan and estimate in progress.

04/28/22 – Work in progress.

5/26/22 – Civil Engineer to provide Champlin with drawings end of day friday 5/27. Final set can be ready to review the following week.

6/30/22 – Bid set and project manual submitted to County for final release.

07/28/22 – One bid came in above 50,000. Bid review to be completed to determine ITB advertised estimate.

08/23/22 – Project out to bid. Pre-bid meeting scheduled for 8/31.

09/27/22 – Bid awarded to Prus. Contracts in progress.

10/27/22 – Pre-construction meeting scheduled for 11/4

12/15/22 – Construction complete.  Punchlist by county and champlin complete. Punchlist by Kleingers to be scheduled.

01/26/22 – Punchlist sent to Prus. They are to fix items that need correcting and confirm slope conforms to code requirements.

02/22/23 – Punchlist completed. Waiting on closeout documents.

03/30/23 – Waiting on closeout documents.

04/27/23 – Close out documents received.

05/25/23 – Waiting on Prus to send final pay app.

06/29/23 – Close outs and final pay app received.

OMJ Accessibility Entrance Study Read More »

A&D – JFS Furniture Redesign DD-CA

02/08/22 – Signed SOSS Received. Kickoff meeting scheduled for 03/22
03/22/22 – DD Kickoff meeting held. Weekly meetings scheduled for friday mornings for duration of DD phase.
04/13/22 – THP requested to review proposed cabinet layout on the fifth floor on the west side of the building.
04/14/22 – THP – Champlin approved THP proposal.
04/22/22 – Weekly DD meetings in progress.
04/26/22 – THP reviewed the cabinet location and analyzing the conditions.
04/28/22 – Kevin asked about dehumidification in the basement. ThermalTech to look at existing conditions and trending this area. Three months DD and three months CD; inclusion meeting during CD phase.
05/27/22 – Weekly DD meetings in progress.
06/30/22 – Weekly meetings complete. DD drawings to be submitted 7/1, DD estimate 7/8.
07/28/22 – Weekly CD User group meeting to start end of august.
08/23/22 – First weekly meeting scheduled for 8/26.
09/29/22 – CD ongoing. Last progress meeting scheduled for 9/30.
10/17/22 – ThermalTech conducted several field trips back to the building for final design
10/26/22 – LEED Checklist returned to Champlin from ThermalTech with comments and suggestions. Drawings, titleblocks, spec headers all being coordinated wth Champlin.
10/26/22 – Final Owner Review meeting scheduled for 10/28/22.
10/27/22 – Friday final owner review will be electronic review. Print three 11×17
12/15/22 – Project out to bid.
01/26/23 – Project still in bid phase. final addendum to be sent out next thursday. Bid opens 2/9.
02/14/23 – Bid opening – Universal is apparent low bidder
02/22/23 – Bid Review is scheduled for 3/3. Meeting rescheduled to two weeks from now. Furniture package is currently under review. Champlin has requested additional information from furniture vendor.
03/30/23 – Champlin sent Letter of Recommendation for Universal. County still deciding whether to move forward with contract with Universal.
04/27/23 – Universal answered several follow up questions. County is proceeding with awarding the bid to Universal. Contract is in progress.
05/25/23 – Monthly meetings with users scheduled.
06/29/23 – No update.
07/27/23 – No update.
08/31/23 – No update.
09/28/23 – No update.
10/25/23 – No update.
12/07/23 – No update.
02/29/24 – No update.
03/28/24 – No update.
04/25/24 – No update.
06/27/24 – No update.
08/29/24 – No update.
09/26/24 – No update.
10/30/24 – No update.
12/12/24 – No update.
01/30/24 – No update.
02/27/25 – OK to Archive.

A&D – JFS Furniture Redesign DD-CA Read More »

CH – Bronze Door Repair

PM: Matt

02/15/22 – Signed SOSS received.
03/31/22 – Field investigation completed. Preliminary drawings completed. We have been in contact with several historic door restoration companies.
04/28/22 – Drawings at 75% complete. Need to schedule a review meeting.
05/10/22 – Review meeting with Rycca. Determined more documentation per door is needed.
06/30/22 – Bid package to be finalized and submitted for final review.
07/28/22 – Additional site visit performed. detailed scope photographs added to drawing set.
08/24/22 – 95% check set sent to HC.
09/29/22 – Project out to Bid
10/27/22 – Olek won bid. West doors and Cleaning awarded. Contracts in progress.
12/15/22 – Contracts signed and returned. Kickoff meeting to be scheduled
01/26/23 – Call with Olek, County and Champlin to discuss details of kickoff meeting. kickoff meeting to be scheduled by end of February.
02/22/23 – Kickoff meeting to be scheduled in near future. Champlin has reached out to Olek twice for dates.
03/30/23 – Kickoff held on site. Preliminary schedule received. Olek to provide firm dates as we near demolition.
04/27/23 – Doors have been removed and sent to New Jersey for refurbishment.
05/25/23 – Doors have been taken apart and analyzed. Doors are in better shape than anticipated. Submittals to come soon.
06/29/23 – Photographs received. Work in progress.
07/27/23 – Restoration ongoing. restoration revealed that the door pulls were originally nickel plated. Change order to nickel plate the door pulls in progress.
08/31/23 – Olek to return to site 9/11. Test fit of closer complete.
09/28/23 – Olek cleaned existing bronze and prepped hardware installation. No crocs in sight.
10/25/23 – Construction ongoing. County requested pricing for additional bonze cleaning.
12/07/23 – Installation scheduled tentatively for march. Olek returned pricing for all items requested.
02/29/24 – Change orders approved. Several doors are complete. Still on schedule for late March Install.
03/28/24 – Doors to be installed first week of April. Site and prep work will continue into the following week.
04/25/24 – Doors to be installed in may. Firm dates to be determined.
05/30/24 – Olek is on site. Two doors are in. One Torchiere was blown over in a storm. Olek is shipping damaged parts to their shop.
06/27/24 – Work on site complete. Olek will need to come back for punchlist work. Matt ask Murphy to review final retainage payment submit.
08/29/24 – Olek needs to come back out to complete punchlist.
09/26/24 – No Update.
10/31/24 – Olek was back on site for the punch work. They did not complete the list and will need to come back.
12/12/24 – Olek came back for the back punch work but did not complete their work. They will be back for the punch and for a closer warranty issue.
01/30/24 – Olek still has punch work to complete. close outs to be submitted.
2/27/25 – Scott reached out to olek to request closeouts and a timeline for punch work. The closeouts are in progress. The punch work will be done in tandem with the first phase of the north and south doors.
03/27/25 – No Update.
04/24/25 – No Update.
05/29/25 – No Update.
06/26/25 – No Update.
10/30/25 – No Update.
12/11/25 – No Update.
01/28/26 – Olek to complete punch work when on site next.
02/26/26 – Olek onsite March 9th to finish punch work.
03/26/26 – Olek is onsite. Punch work is in progress.
04/30/26 – Work is complete. Closeouts nearly complete.
06/25/26 – No update.
07/30/26 – No update.
08/28/26 – No update.
09/24/26 – No update.

CH – Bronze Door Repair Read More »

CH – 1st & 2nd Floor Security Cameras Upgrade

PM = Matt Butz, Mike Barth

02/23/2022 – HCFD requests SOSS from TEI.   TEI submits SOSS, and receives signed SOSS and PO.   Project pending kickoff with HCRM and HCFD.
04/27/22 – Matt Butz and TEI meet with RM, and determine locations for adding the security cameras.  Design documents are getting started now that Barth has returned from medical LOA.  Will have review set for MButz upon his return form medical LOA.
05/26/22 – TEi and Matt to review the design documents for the camera locations.  DK indicates that the materials are in inventory at their facility.  TEI to certify equipment prior to approving the billing.
06/28/22 – HCFD, HCSO, HCRM and TEI meet with DK re status and DK provides tentative schedule.  DK starts installation of cabling on the second floor.
07/27/22 – Installation continues with cabling and camera installation.
08/24/22 – Installation completed.   TEI and Matt Butz perform punchlist.   TEI issues punchlist to DK.
09/26/22 –  HCFD issues DK change order for work associated access control on the second floor.  Upon material procurement, and installation of access control equipment, TEI and HCFD will punchlist those items.
10/26/22 – Installation of access control pending procurement of materials.
12/15/22 – Installation of access control pending procurement of materials.
01/25/23 – Installation of access control pending procurement of materials.
02/23/23 – Installation of access control pending procurement of materials.
03/29/23 – DK indicates that the materials are in their shop and that the installation will be complete by 03/31/23.
04/27/23 – DK having issues with the double doors near the freight elevator.  Working on solutions.
05/23/23 – DK having issues with the double doors near the freight elevator.  Working on solutions.
06/28/23 – DK having issues with the double doors near the freight elevator.  Working on solutions.
08/31/23 – Work is complete, ready to close out the project.
12/06/23 – Pending final closeout documents from DK.
01/30/24 – TEI waiting on warranty letter from DK.

CH – 1st & 2nd Floor Security Cameras Upgrade Read More »

CH – Rooftop Patio Renovation (F042)

PM: , John Millar
10/07/21 – Hamilton County requested SOSS to repair the roof of one of the old “Bear Dens”.
10/14/21 – Hamilton County and design partners met to review design needs.
10/28/21 – THP Submitted a SOSS for review.
05/26/22 – Save the Tree.
04/27/23 – Save the Tree.

04/25/24 – FOOORRRRRRRRKKKK!!

06/27/24 – DUUUUUUCCCCCKKKKK!!
09/26/24 – The tree has unfortunately left this world and we are saddened by its departure.

CH – Rooftop Patio Renovation (F042) Read More »

Hillcrest – Birch Cottage Storm Damage Investigation (F033)

06/23/21 – During storm tree fell on Birch Cottage at Hillcrest causing significant roof damage.
06/25/21 – THP provided SOSS to investigate storm damage.
07/01/21 – County approved SOSS.
07/06/21 – THP visited the site and confirmed initial damage. Cottage unoccupied.
08/16/21 – THP published opinion of probable cost to rebuild cottage or demolish it. OPC included support cost from Champlin Architecture and Thermal Tech Engineering.
10/20/21 – THP issued final report.

Hillcrest – Birch Cottage Storm Damage Investigation (F033) Read More »

Hillcrest – Birch Cottage Storm Damage Repair (F044)

PM: Bert Watts, John Millar

11/03/21 – Hamilton County requested SOSS to repair Birch Cottage.
12/01/21 – THP, Champlin and Thermal Tech met at Birch Cottage to review scope.
01/27/22 – THP submitted SD proposal. Bert has updated on scope of work on the work for the project for coverage of the damage.
04/22/22 – County reached out to Champlin to restructure the approach with Champlin leading the full effort. Champlin requested an updated proposal.
04/26/22 – THP send an updated proposal to Champlin.
01/25/23 – SOSS requested for Birch Cottage demolition.
02/23/23 – THP following up with contractors for environmental study prior to demo for spoils remediation.

Hillcrest – Birch Cottage Storm Damage Repair (F044) Read More »

JC – Cell Window Screen Project

PM: Bert Watts, Mike Murphy
12/06/21 – Signed SOSS received.
01/25/22 – Preliminary plans and schedule created. Will be discussed at JC Door replacement Kick-off.
02/24/22 – Product research completed. Price Estimate in progress.
03/31/22 – Estimate and summary provided to County.
04/28/22 – Waiting on PO.
05/26/22 – Documentation in progress
06/30/22 – Documentation in progress
07/28/22 – Documentation in progress
08/25/22 – Documentation being finalized.
09/29/22 – Final Review to be submitted to County 9/30
10/27/22 – Some corrections submitted. Hard copies to be delivered today for sheriff review.
12/15/22 – ODRC approval. Project to go out to bid 12/22
01/26/23 – Bid opening is 1/30.
02/22/23 – Triton was apparent low bidder but their product did not meet specs. They are saying that they can provide the correct product for 1.6 million.
03/30/23 – Triton pulled their bid. Fabcor was the next lowest bidder. Contracts in progress.
04/27/23 – Contracts returned. Fabcor is starting the submittal process.
05/25/23 – Kickoff meeting held on site. Fabcor to finalize submittals for ORDC review. Fabcor to schedule site visit to field verify all dimensions.
06/29/23 – 4 Screens to be installed prior to the rest as a trial. submittal returned. Jails yet to schedule installation.
07/27/23 – Windows are on order. Jails has been on site to measure the remaining window sizes.
08/31/23 – 4 test screens to be installed next week. County to get approval from state for the rest of the screens.
09/28/23 – Test screens installed and reviewed. List of items from Champlin and Jails sent to Kane for review before the large install. Still waiting on State approval to return submittals.
10/25/23 –  State approved submittals. Sample from Kane that fixed mock up issues received. Review meeting scheduled with Captain Wilson 10/26.
12/07/23 – Comments from mockup returned to Jails. Jails to follow up with a schedule.
02/29/24 – Schedule provided by Jails. Install to begin in April.
03/28/24 – Install to begin 4/1.
04/25/24 – Installation ongoing. North 5th floor to be complete next week.
05/30/24 – Installation ongoing. South 5th floor to be complete next week.
06/27/24 – Installation ongoing.
08/29/24 – Installation ongoing.
09/26/24 – Installation ongoing. Lexan CO approved. Day space CO in progress.
10/31/24 – Installation ongoing.
12/12/24 – Installation ongoing. Day space CO approved. Quote to add Lexan to previously installed screens incoming.
01/30/25 – Installation ongoing. Lexan install in psych unit ongoing. Dayspace screens to be installed next.
02/27/25 – Original contract work complete. Dayspace area is ongoing. Second round of Lexan install ongoing.
03/27/25 – Dayspace mock up rejected. Revised submittal returned. Correct mockup to be installed prior to manufacturing of the remaining dayspace screens.
04/24/25 – Revised mock up also rejected. Kane to provide solution to prevent mesh damage.
05/29/25 – Kane provided solution. Mock up revision #2 to be installed.
06/26/25 – Mock up approved. Manufacturing of dayspace windows to begin.
07/31/25 – Delay from steel mesh manufacturer pushes install into October/November.
08/28/25 – No update.
09/25/25 – No update.
10/30/25 – Jails will remobilize end of november.
12/11/25 – Day space installation ongoing.
01/28/26 – Scope to be complete by end of 2/6. Closeouts requested.
02/26/26 – CO work is complete. Additional screens in Med unit is requested. Awaiting pricing from Jails.
03/26/26 – CO approved for Med unit screens. Delivery date to be provided by Jails.
04/30/26 – No update.
05/28/26 – No update.
06/25/26 – Closeouts in progress. final change order screen installed.
07/30/26 – Closeouts reviewed. Missing items requested. OK to close out the project.

JC – Cell Window Screen Project Read More »

JC – Cell Door Lock Replacement (Cornerstone)

PM: Bert Watts, Mike Murphy
12/06/21 – Signed SOSS received
01/26/22 – Plans and Schedule created. Will be discussed at JC Door Replacement Kickoff.
02/24/22 – Product research completed. Price Estimate in progress.
03/31/22 – Estimate and summary provided to County.
04/28/22 – Waiting on PO.
05/26/22 – Documentation in progress.
06/30/22 – Documentation in progress.
07/28/22 – Documentation in progress
08/25/22 – Documentation being finalized.
09/29/22 – Final Review to be submitted to County 9/30
10/27/22 – Some corrections submitted. Hard copies to be delivered today for sheriff review.
12/15/22 – ODRC approval. Project to go out to bid 12/22
01/26/23 – Bid opening is 1/30.
02/22/23 – Bid opening is pushed to 3/3. Final addendum to be issued before 2/28.
03/30/23 – The bid has been cancelled. An invitation for manufacturers to demo their products has been put out for 4/5.
04/05/23 – Manufacturer presentations held. Willo, Airteq, and Habersham displayed their products to the county and sheriffs.
04/27/23 – Revised bid sent to the prosecutors office for review. Once approved, the project will be ready to rebid.
05/25/23 – Project has been rebid. Pre-bid meeting is 6/2.
06/29/23 – Bids received. Project is awardable.
07/27/23 – Lowest Bidder – Jails – bid is under review with prosecutor to determine if bid is awardable. Second lowest bidder – cornerstone – vetted.
08/31/23 – PO is approved and contract has been sent. Kickoff meeting to be held in the near future.
09/28/23 – Kickoff meeting held. Site visit to measure existing conditions scheduled for week of 10/9. 4 cell mock up to be scheduled at site visit.
10/25/23 – Site visit occurred. Mock up submittal returned. Mock up installation to be scheduled in near future.
12/07/23 – Mock ups to be installed 1/9.
02/29/24 – Mock ups ran into trouble connecting with the PLC. Cornerstone could not figure it out onsite. They sent locks to be tested by Stanley. Locks have not been successfully programmed yet.
03/28/24 – Stanley determined that the locks can be used with modification to the PLC system. Cost of the upgrade is around $500,000. Conversation of next steps ongoing.
04/25/24 – Working mock-ups installed. Schedule to be determined for Securitas to be on site for upgrading power.
05/30/24 – Work to begin 6/17. Work is expected to take 2-3 weeks per floor.
06/27/24 – Locks delivery was delayed. The locks had to be re-programed. Cornerstone to overnight one re-programed lock to ensure functionality. Prep work on George 51 is complete.
07/24/24 – Matt punchlisted project last Sunday. They met the State on Monday. One door hitting the wall, so we need to add a new bumper.
08/29/24 – Installation ongoing. Cornerstone getting to a unit per 2 weeks.
10/31/24 – Installation ongoing. No issues have been resolved by airteq regarding quality control. Meeting to discuss issues with Cornerstone and Airteq will take place next week.
12/12/24 – Installation ongoing. Power upgrade is complete. Rewiring lock power is in progress. New switches to be installed at end of January.
01/30/24 – Last unit work ongoing. Cornerstone and Airteq VPs to attend a meeting in February to work out warranty issues.
02/27/25 – Meeting held with VPs of Airteq and Cornerstone to finalize warranty discussion. 5 year warranty agreed upon. Medical unit to be complete this week. outstanding work will be repairing damaged locks.
03/27/25 – All contract work complete. Closeouts to be submitted and correction work to be done.
04/24/25 – Replacement housing and attic stock to be delivered in near future. Cornerstone will begin correcting outstanding punch items.
05/29/25 – No Update.
06/26/25 – No Update.
07/31/25 – No Update.
08/28/25 – No Update.
09/25/25 – Attic stock and corrected housings delivered and replacement process has began. Closeouts outstanding.
10/30/25 – Still have a couple of things left to do. We need a list of lock boxes left to do.
12/11/25 – List of outstanding punch items provided. Closeouts under review.
01/28/26 – Punch work complete. Attic stock is outstanding. Closeout corrections requested.
02/26/26 – Closeouts will be delivered next week. Attic stock needs to be replenished from warranty work orders.
03/26/26 – Still waiting on closeout docs. Attic stock is still not on site. Warranty period has not began.
05/28/26 – No update.
06/25/26 – No update.
08/28/26 – Phillip onsite to review rust damage. Champlin to provide report.
09/24/26 – Report submitted. No update on solution.
10/29/26 – Roller bolts have been discovered missing on several doors. Sheriffs to provide report.

JC – Cell Door Lock Replacement (Cornerstone) Read More »

A&D – Accessible Employee Entrance

12/03/21 – Signed SOSS Received.
01/25/22 – Product research and preliminary brainstorming started. Field survey to verify existing conditions.
02/24/22 – Field verification complete. Products research complete.
03/31/22 – Options sent to County for review. Waiting on scope decision to price.
04/28/22 – Kevin Holt confirmed this project will not be moving forward. OK to Archive.

A&D – Accessible Employee Entrance Read More »

A&D – Access Control Maintenance Agreement

PM = Rycca Thacker, Mike Barth
12/13/21 – JFS issues RFQ and bids come in significantly higher than expected.  TEI and HCFD to develop an ITB with a clearly defined scope for rebidding purposes.
01/25/22 – TEI working on RFQ – will submit to RT for review and comment.
02/23/22 – TEI and Rycca to finalize requirements of scope and develop bidding schedule for the ITB.
04/27/22 – TEI and Rycca to finalize requirements of scope and develop bidding schedule for the ITB.
05/26/22 – TEI and Rycca discuss scope items and TEI is finalizing the ITB for HCFD review and approval.  TEI to submit to HCFD by June 10.
06/28/22 – TEI submits the final draft of RFP to HCFD for review.   Issuance of ITB pending review comments and direction from HCFD.
07/27/22 – The project is currently in the bidding phase.  Bids are due 8/26/22.  Prebid meeting scheduled on 08/03/22.
08/24/22 – Prebid meeting conducted and addenda issued.  Bids are due Friday 08/26/22.
09/26/22 – Bids received.  Glenwood apparent low bid.  TEI vets bid.  Recommends Glenwood for the project.  In contract phase.
09/29/22 – Archive next month.

A&D – Access Control Maintenance Agreement Read More »

Comm Center – Cell Tower AC Replacements

PM: Rycca Thacker, Terry Cannon
10/20/21 – SOSS approved.
10/21/21 – Draft project manual distributed for review.
10/28/21 – Project prebid tomorrow 10/29. 12 sites. One base bid Blue Ash, 11 alternates.
11/08/21 – Bid received by TEI.  JCI and DK bid the work and Trane declined to submit a bid.  Bids were tabulated and sent to County for award.
12/13/21 –  This month we worked on getting the contract in place with Debra Kuempel for the Bid Bid and seven Alternates.  We continue to work on paperwork and contract.  Terry talked to Kerry last Friday about the intent of the specifications and verified with DK that the bids include all the labor and materials for the work.  Kerry preparing to write a non-AIA contract for use on this project and warned that an STD contract ADA contract protects the county less than a full ADA contract.
01/25/22 – Contract in signing stages at DK
02/24/22 – Still in contract stages, goes to BOCC this Wednesday and PO after that.
03/31/22 – PreConst next week.
04/28/22 – Pre-const meeting was held. Debra is preparing to start the work and call Scott. Submittals have been sent in for the Marvair unit, DK working on the Indian Hill split system.
05/25/22 – DK is scheduling kickoff meeting and fieldwork with Comm Center. I check in a couple of times with Dave. We also reached out to Mobilcom on alarm monitoring and set up a field meeting with DK and Comm Center to all visit a site to see how the alarms are connected to the AC units so we order them correctly. Submittals are still in my inbox pending this field finding.
06/30/22 – All submittals returned and approved. Equipment is on order DK starting at Indian Hill, however the installed equipment is different than planned, DK taking care of it. Payapps should start this month.
07/27/22 – DK started the Indian Hill site this month and is trying to get three Marvair units for the other sites this summer.
08/24/22 – Indian Hill #1 is complete, #2 is being done this week. Payapp #1 submitted with corrections for payment.
09/25/22 – Payapp #1 submitted, Rycca working with DK on some PW issues. No update on the Marvair units for delivery date, checked in with Dave 2 or 3 times.
10/26/22 – Equipment scheduled to arrive Nov 16.
12/15/22 – About 6 sites are complete and Debra is working on the additional sites daily. They hope to be done by the end of the year if the weather holds up.
01/24/23 – All sites are done and DK has billed for all the material. Scott says as soon as he gets time, he will coordinate a punchlist visit for us.
02/17/23 – Scott, Rycca, Terry performed an punchlist at three sites. TTC to prepare punchlist for DK to use on this project. TTC spoke to Dave about some issues we found in the first few locations and DK will take care of them.
03/29/23 – Closeout documents are under review for this project. Final payapps have also arrived. TTE making three binders for closeout.
04/25/23 – Punchlist sent to DK, O&M printed and will be delivered this week to Rycca. DK to check Eden Park for status.
05/21/23 – Working on closeout and punchlist with DK. Eden Park site was checked for issues.
06/28/23 – Punchlist complete, DK working on closeout documents.
07/26/23 – Signed punchlist sent to County for approval. Final payapps sent in for processing. Ready to archive.

Comm Center – Cell Tower AC Replacements Read More »

A&D – Plumbing Modifications

PM: Rycca Thacker, Terry Cannon
10/28/21 – TTC provided update on low flow plumbing issues at the A&D Building. In the past month, we had a major leak at the main sanitary leaving the building. Plumbers called Underground Detective to survey the pipe from the building to the street. TTC to get a test kit for testing in Fifth Floor East.
12/13/21 – TTC in contact with RC Frey & Associates to order the part for testing purposes.  A new SOSS was created for this part of th Study.  Once I get the part in town, i can coordinate with Danny on the installation needs of this part of the test.
01/25/22 – TTC needs to coordinate and pick this part up or have it ordered by County.
02/24/22 – TTC has to get this done this week. I will talk to Danny about getting this ordered.
03/31/22 – TTC stopped at Ferguson earlier this week and the part is special order, order into “inside sales” and as soon as they confirm, we will put on order through TTS.
04/28/22 – TP-4 is here and TTC picked it up and will drop it off today at the meeting. The next step is to coordinate with Danny and Steve on installation.
05/25/22 – Plumbing fixes relocated to the Furniture design job. I spoke to Danny about piping changes inside the chase when we open it open. I plan to discuss at Friday Champlin meeting on a Furniture project. I have also searched out what may be an even easier fix with a new Zurn product but I don’t have the specifics quite yet.
06/30/22 – Need to schedule 5E wall opening with County. Ask at the meeting.
07/27/22 – I was able to get into the chase with three existing chases on the 6th floor and found what I needed for plumbing design.
08/24/22 – Setting up a field trip with Danny, hopefully on Friday at 8:30 am to go over installation.
09/22/22 – Found the flush timers online and there is some discussion to try the flush timers first instead of installing the trap primers first.
09/29/22 – TTC to provide equipment selection to Danny to purchase and install.
10/26/22 – Working out final order details with GenieFlush from California. We should be able to order the equipment by Friday.
12/15/22 – Parts are in, TTC needs to meet with Danny to install and test.
01/24/23 – Two auto flushers were installed two weeks ago and set to two hours intervals. WE will monitor and keep track of clogging.
02/21/23 – One flusher is on 4E and one is on 5E. The fifth floor is working just fine, the fourth floor has a sticky flush rod, TTC to reach out to the vendor for a replacement part.
03/29/23 – We reached out to the vendor for a replacement part and he would like pictures of the bad module.
04/26/23 – No updates.
05/21/23 – No updates.
06/28/23 – Archive.

A&D – Plumbing Modifications Read More »

A&D – Sewage Ejector Pumps

PM: Terry Cannon, Tony Matre

10/28/21 – Sewage ejectors not working correctly. Tony called for replacement work on them. Prebid set for today 2pm today.
11/30/21 – Bids received, QCM apparent low bidder. Pre Award meeting held virtually and QCM recommend for work.
12/14/21 – Tony getting PO for work to QCM for job. TTC to setup a pre const meeting late Dec 2021.
01/18/22 – Pre Const Mtg with QCM. Equipment approved and on order. The meeting went well, Drew and his foreman looked the job over. We are shooting for a Feb or March start date.
02/24/22 – No update on equipment delivery yet. QCM talking to Corporate Equipment every day to finalize a delivery date.
03/31/22 – Changed to submersible pumps, approved new submittals, created new dwgs and sent to vendor, should be installed mid-April.
04/18/22 – New pumps were installed and completed. MC and EC are done, and controls are coming to hook up the alarm points.
04/28/22 – The system is working well, pump #2 is going out on overload. EC dispatched to look at on Wednesday, they called Streamkey to look at the issue on Thursday. ALC controls are not hooked up yet, need additional wiring for the interface.
05/25/22 – Project complete and punchlist distributed to QCM. Emcor ALC waiting on badged low voltage electrician to run their alarm wiring before we close out. I sent all closeout docs to QCM. The system is working well.
06/30/22 – Just waiting on controls to finish DDC work, closeout documents from QCM.
07/27/22 – Controls work is complete. TEI requested O&M and Closeout documents from QCM.
08/24/22 – Project complete, we’ve requested closeout documents.
08/26/22 – All closeout and final payaps received. Project ready to closeout.

A&D – Sewage Ejector Pumps Read More »

250 WHT – First & Second Floor Construction

PM: John Nester, Lead: Sam Hofmann

10/28/21 – Create project for tracking construction progress.
12/14/21 – Project waiting on contract finalization. Permit filed.
01/25/22 –  Construction Kick-off meeting held.
02/24/22 – Notice to proceed issued. CA in progress. RFI submitted on t-stat and answered to leave where is. HVAC submittals received and returned.
03/31/22 – CA on going. Demolition complete, framing in progress.
04/28/22 – CA on going.
05/26/22 – CA on going. Still on target to complete on schedule.
06/30/22 – CA on going. IBI inspections this week. City TCO next week. Move 2nd floor into new space in time for meeting.
07/28/22 – Second floor punchlist scheduled for 8/4. Door delivery for first floor is delayed. Triton to install temporary doors to receive occupancy.
08/04/22 – Second floor Punch list completed.
08/24/22 – First floor punch list completed.
09/29/22 – Second Floor punchlist completed. First floor backpunch to be scheduled.
10/27/22 – Back punches complete. waiting on confirmation that items have be12/15/22 – en completed.
12/15/22 – Second floor sign off received. Still waiting for cores for the first floor doors. PO being held open for TPC 6th floor ceiling work.
01/26/23 – Cores completed. Cypher lock had to be reordered. should be installed in next couple days which is the last item. Close out documents requested.
02/22/23 – Closeout documents and final pay app received.
03/30/23 – Still need physical binders from triton.
04/27/23 – No update.
05/25/23 – Have reached out to Triton several times regarding binders and final pay app, still have not received them.
06/29/23 – Closeouts and final pay apps received.

08/31/23 – No update.

09/28/23 – No update.

250 WHT – First & Second Floor Construction Read More »

CH – Gas Booster Pumps

PM Tony Matre, Terry Cannon
10/28/21 – Project is issued for bidding. Bids received and are awardable. Queen City Mechanical (QCM) is the apparent low bid. TEI conducts the pre-award meeting and provides recommendations to award. AKM indicates that he has PO and the project is moving forward.
12/13/21 – Bids received.  QCM is the apparent low bidder.  Post bid interview went well.  TTC setting up pre const meeting and reviewing submittals for the job.  Trying to coordinate electric with CH shutdown for the Server room which is the MCC in the boiler room where the booster is also fed from.
01/25/22 – Gas pumps are on order. Electrical permit drawings sent to QCM for permitting last Friday. We are trying to get the transfer switch in place during the CH Server shutdown.
02/24/22 – No major updates yet, QCM says the delivery date has been pushed back to April 2022.
03/31/22 – Electric submittals are reviewed, EE permit next. Booster will be here late April or mid-May.
04/28/22 – Stoermer stated the gas booster will be here mid-May to June now. The electrical submittals are returned with limited comments. IBI permit drawings were sent to QCM. They will schedule the work as soon as the equipment this in town.
05/25/22 – QCM and Stoermer have updated the equipment delivery date to be mid to late June. When the equipment gets here, the project will be started.
06/30/22 – Equipment not here, waiting on an update from Stoermer. Gas booster delivery delayed until end of July.
07/27/22 – Gas Booster pump delayed to mid-August. TEI reached out for an updated delivery date.
08/24/22 – Gas booster delayed until the end of August. All other facets of the job are read to go.
09/22/22 – Gas booster delayed until the end of September per Stoermer.
09/28/22 – Gas booster is here. Pad being poured this week, booster will be mounted next week then piping can begin.
10/26/22 – QCM submitted RFI for new piping arrangement with pump rotated 90 degrees to provide clearance around new disconnect in basement.
12/15/22 – Work is complete. First testing was not successful, we are waiting for a warm afternoon day to verify rotation of the new booster before we try again. QCM bringing extra fuses down to replace blow fuse during testing.
01/10/23 – Field rotation was verified and the gas booster started up with factory support. The backup gas booster is ready to go. There is a question about secondary gas pipe heat sensor.
01/24/23 – No closeout paperwork has been received yet on this job.
02/23/23 – No closeout paperwork has been received yet on this job. TTC checked back with QCM as certified PW keep coming in.
03/29/23 – Reached back you to QCM for all closeout documents.
04/26/23 – Closeout documents received.
05/21/23 – Closeout documents reviewed and approved. TTE processing final pay application.
06/28/23 – Final closeout documents delivered to County with Final Payapp. Ready to Archive.

CH – Gas Booster Pumps Read More »

EV Charging Stations RFP

PM John Nester, Mike Barth

10/26/21 – ThermalTech receives signed SOSS and PO for project. RFP in development.
13/13/21 – HamCo advises TEI to hold on the RFP development until a time when the county develops policy on the use/locations etc. of the EV Charging stations.   TEI on hold until directed otherwise from county.
01/25/22 – TEI receives notice from JN that the project will move forward as originally discussed.  TEI and JN to schedule kick off meeting the beginning of February
02/23/22 –  TEI submits list of questions for RFQ to HCFD.   Kick off meeting with HCES scheduled for 03/01/22 at 3:00 PM.  Upon receipt of direction from the HCES, RFQ will be finalized.
04/27/22 – HCFD determines that the Infrastructure needs to be bid separately from the service contract.  TEI develops infrastructure plan (SD level), includes power for the mobile coach, and has review meeting with HCES, HCPH, and HCFD on 04/26/22.  CD phase and implementation pending funding approval from County.
05/26/22 – TEI finalizes the SD package after review with the end users (drawings and revised opinion of probable cost).  TEI submits SOSS for CD thru CA phase of the work.  Work pending SOSS approval and PO.
06/28/22 – Work pending SOSS approval and PO.
07/27/22 – Work pending SOSS approval and PO.
08/24/22 – TEI receives Signed SOSS and PO.   JN states that funding for the install will be in 2023, and to work towards a first of 2023 issuance date for the project.
09/26/22 – TEI working towards an issuance at the end of the year for the infrastructure ITB for now. We can draft the RFP now but it has to be open for future stations.
10/26/22 – TEI working towards an issuance at the end of the year for the infrastructure ITB for now. We can draft the RFP now but it has to be open for future stations.
12/15/22 – Project documents in QC phase at TEI.  Will be sent to HCFD once QC review complete for review and then issued for bidding.
01/25/23 – TEI to send final review set to HCFD for review by 02/10/23.  Project bidding pending HC policy and procedures implementation decisions.
02/23/23 – Project bidding pending HC Policy and procedures implementation decisions.
03/29/23 – Project bidding pending HC Policy and procedures implementation decisions.
04/27/23 – Project bidding pending HC Policy and procedures implementation decisions.
06/28/23 – HC policy has been worked on by ES.   Location for the EV charging stations has been moved from 250 WHT to Civic Center  Drive (Comm  Center), and also to include the Regional Crime Lab in Blue Ash (common provider).  TEI and JN to discuss modifications to existing SOSS.
08/24/23 – TEI visits the site with the building manager and determines path/routing of power feeds for the EV charging equipment.  Discusses with JN, and will modify new SOSS for new location.
09/26/23 – TEI develops plan for drawings and sends to HCFD for review/approval.
10/26/23 – TEI has Underground detective locate existing utilities on site,  TEI shows on plan and HCFD submits to ODOT for approval.
12/06/23 – TEI submits documents to HCFD to submit to ODOT for approval.  Pending ODOT approval.
03/27/24 – Tracking this on other project.

EV Charging Stations RFP Read More »

A&D – 7th Floor Access Control Modifications

PM – Rycca Thacker, Mike Barth

10/26/21 – ThermalTech receives signed SOSS and PO. HCFD asking for design to be complete by 11/05/21.

12/13/21 – TEI submits drawings to TEI with to HCFD for review.   RT returns drawings to TEI with additional scope changes.  TEI to finalize drawings for issuance by EOY.

01/25/22 – TEI sends drawings to HCFD for review and final comments, to be issued upon receipt of comments.

02/23/22 – TEI sends drawings to Glenwood Electric to obtain quote (since Glenwood is under warranty for system).  Upon receipt of quote from Glenwood, TEI and HCFD will determine next steps.

04/27/22 – TEI reviews quote with RT and Glenwood.  Recommendations forwarded to JFS.  Next steps pending approval from JFS.

05/26/22 – JFS approves the Glenwood quotation.   HCFD executes CO for project and Glenwood is procuring materials.   Install to occur upon receipt of materials.

06/28/22 – Install to occur pending material procurement.

07/27/22 – Install to occur pending material procurement.

08/24/22 – Install to occur pending material procurement.  As of 8:00 PM on 8/24/22, Glenwood received materials at their shop on 08/24/22.   Glenwood is coordinating resources and will contact Rycca Thacker in the next few days to schedule installation.

09/26/22 – Project in construction phase.  Upon notification from Glenwood that install is complete, TEI and HCFD will perform punchlist.

10/26/22 – TEI and HCFD to perform punchlist.

12/15/22 – TEI and HCFD to perform punchlist.

01/25/23 – There were hardware issues on the stair tower doors.   Glenwood ordered replacement hardware and tentative ship date is approx 3 weeks.  TEI will finalize punchlist upon installation of pending hardware.

02/23/23 – Project completion pending installation of hardware.

04/27/23 – Project completed.  RT and TEI perform punchlist walk through.  Upon receipt of all close out materials, can be archived.

05/23/23 -Waiting on  receipt of all close out materials.

A&D – 7th Floor Access Control Modifications Read More »

EMA/Comm Center – SD & Cost

09/20/21 – Kick-off meeting with County, Champlin, Thermaltech, THP, and Cushman & Wakefield.
09/27/21 – Building Tour.
09/30/21 – SOSS received from County
10/13/21 – Programming Meeting held with Comm Center, County, Cushman & Wakefield.
10/15/21 – Programming Meeting held with EMA, Champlin, County, and Cushman & Wakefield.
10/20/21 – Draft Program sent to User groups for comments.
12/03/21 – Signed SOSS received for SD.
12/13/21 – SD Kickoff meeting held with Champlin. EMA and 911. SD to be finished by 1/7.
12/22/21 – progress meeting with Users.
01/06/22 – 90% review meeting with Users
01/07/22 – SD set and estimate submitted to County.
02/24/22 – The building purchased is moving forward. 4 teams made the short list, interview will be held in March 2022.
04/28/22 – Revised plans and estimate sent to County. Project is complete, ready to archive.

EMA/Comm Center – SD & Cost Read More »

TPC – Autotitle and BMV Combined Renovation

PM: Matt Butz, Mike Murphy
09/28/21 – SOSS received from County
10/27/21 – Champlin reached out to BMV contact to schedule programming meeting.
11/12/21 – Programming Meeting held with County, Champlin and BMV.
12/14/21 – Narrowed down potential layouts to two options. sending to BMV for comments.
12/22/21 – Met with BMV to finalize design. BMV to submit design to State. No response yet.
02/09/22 – Met with Greg Brush and Shawna Derencamp. Plan approved with small changes. SD and Estimate to be submitted by 3/4.
03/31/22 – SD plan and estimate submitted to County
04/28/22 – Estimate combined with Re-entry and sent to County.
05/26/22 – No update.
06/30/22 – No update.
08/25/22 – No Update.
09/29/22 – SOSS for DD-CA to be submitted in the near future.
10/27/22 – SOSS approved. DD meeting to be scheduled for week of 11/7.
12/15/22 – Final owner approval scheduled for 12/20
01/26/23 – Project will be posted for bid today
02/22/23 – Bid opening on 2/24.
03/29/23 – Graybach awarded the bid.
04/27/23 – RCF has met on site to provide furniture quote.
05/25/23 – Contracts finalized. Quote received from RCF. Kickoff meeting to be scheduled in the near future.
06/29/23 – Two separate kick off meetings will be held with each department. Design team to provide meeting options for next two weeks.
07/27/23 – Mid august start date. Meeting held with Autotitle. Meeting with BMV scheduled for next week. Plumbing and HVAC submittals have been received. TTE will send back this week.
08/31/23 – Construction began 8/14. Demo almost complete.
09/28/23 – Construction ongoing. Bulletin #1 issued for minor deduct work. Furniture for phase 1 ordered.
10/25/23 – Construction ongoing. Coordination between state and county data + telephone ongoing. State has been onsite to drop their data lines.
10/26/23 – The two large VAV boxes ductwork configuration has been modified to fit final wall construction installation. TTC met with NKYHC last week. Plumbing pilot holes reported to be filled, not verified by TTC yet. Drain pan in basement is being fabricated and should be here soon.
12/07/23 – Construction ongoing. phase 1 to be complete 12/22. Punchlist scheduled 12/21.
02/01/24 – Phase 1 is complete, Autotitle has moved into their temporary space. Toilets and restrooms are being installed now. City water tie-in next week. Triton begins demo of old Autotitle space and continues to work on Phase 2 work.
02/29/24 – Phase 2 began. Demo almost complete.
03/28/24 – Construction ongoing. Punchlist scheduled for 4/9.
04/25/24 – Punchlist items in progress. Autotitle moved into their space. BMV to be moved in two weeks after we make some additional changes in network infrastructure. Nick setting up meeting with Sonitrol to finalize new detail on how the new system is going to be monitored.
05/30/24 – Final punch items are in progress.
06/27/24 – Change order pricing outstanding.
08/29/24 – Pricing received. Waiting on materials for Triton to mobilize.
09/26/24 – Materials are in hand or arriving in near future. Triton to be on site this month.
10/31/24 – Triton back on site this week to finish last items.
12/12/24 – Triton has completed some punch items. Subs will be onsite to finish casework next week.
01/30/25 – Triton still has a couple items to complete on site.
02/27/25 – Punch work ongoing. Working on final connections to doors and get fire alarm tie-ins for FA system.
03/27/25 – Punch work still ongoing.
04/24/25 – Repair conducted on the auto operator. Fire tie in still outstanding.
05/29/25 – Access control have been on site a couple times. Problems are still not resolved.
06/26/25 – All items are not complete. Closeouts in progress.
08/28/25 – Closeout received. Ready to Archive.

TPC – Autotitle and BMV Combined Renovation Read More »

2020 – Roof Replacement (F034) and Davit Upgrade (F027)

PM: Rycca Thacker, John Millar
07/29/21 – THP Submitted SOSS to County.
08/23/21 – SOSS approved.
02/2321 – THP completed roof cuts and assessments. THP scheduling masonry survey for repairs, anticipated week of 2/28.
03/07/22 – Week of March 7th, THP Surveyed interior for masonry distress and slab settlement.
03/24/22 – THP and County reviewed field findings from THP survey.
04/27/22 – THP developing DD documents.
06/30/22 – THP developing DD documents. Plan to bid mid August.
07/28/22 – THP proposed design schedule update DD issue 8/30/22 and CD issue 9/15/22
10/27/22 – THP to publish 90% drawings 10/28/22.
01/10/23 – County provide review comments.
01/26/23 – THP anticipates CD documents issued 2/3/23.
02/23/23 – Finalizing documents. Plan to issue bid documents week of 2/26.
03/24/23 – Bid documents anticipated the week of 4/3/23.
05/31/23 – Documents advertised for bid.
06/07/23 – Prebid mtg occurred.
06/16/23 – Addendum No. 1 issued.
06/27/23 – Bid opening occurred. Two submitted bids received with low bid 16% above advertised budget. THP to review with County next steps.
08/31/23 – June bids rejected. County requested roof and masonry project be separated and bid this fall. THP published review documents 8/31/23.
10/06/23 – Roof Repair project approved for KEE system. AIA documents issued to THP. Slab and Masonry Repair project approved. AIA documents issued to THP.
10/0923 – County comments to the review documents published to THP.
10/09/23 – Inclusion goals published.
10/12/23 – Review Bid Documents published for both the Roof and Slab Lifting Projects.
10/13/23 – Final Bid documents published for both the Roof ITB 116-23 and the Slab Lifting and Masonry Repairs ITB 117-23 projects.
10/16/23 – Roof and Slab projects advertised for bid.
10/25/23 – Prebid meeting occurred for both projects.
10/26/23 – Bid opening scheduled for November 30, 2023.
11/09/23 – Slab and Masonry Repairs Addendum No. 1 issued.
11/13/23 – Roof Repairs Addendum No. 1 issued.
11/14/23 – Slab and Masonry Repairs Addendum No. 2 issued.
11/17/23 – Roof Repairs Addendum No. 2 issued.
11/20/23 – Roof Repairs Addendum No. 3 issued.
11/30/23 – Slab and Masonry Repairs Bid opening. No submissions.
11/30/23 – Roof Repairs Bid opening. Five contractors submitted bids with a range of $1,761,452 to $2,103,895. One bid was below advertised bid amount and the remaining bidders were within 10%. Bids sent to the economic inclusion department for review.
12/23/23 – Kelly Brothers Roofing found responsive and THP notified to review the bid.
01/08/24 – THP and Kelly Brother’s reviewed the bids.
01/15/24 – THP published bid summary recommending Hamilton County contract with Kelly Brothers for the roof project.
02/06/24 – Hamilton County sent AIA contract to Kelly Brothers Roofing.
03/02/24 – Kelly Brothers returned contracts to Hamilton County.
03/25/24 – THP published conform and permit drawings to Kelly Brothers and Hamilton County. Drawings updated with 2024 code review and requirements.
03/27/24 – Project contract goes before the board on April 4th for final approval.
04/11/24 – Executed contract sent to KBR.
04/29/24 – Preconstruction meeting completed.
05/30/24 – Project update – THP processing submittals and shop drawings.
05/31/24 – Initial scaffolding installation for roof access to start.
04/29/24 – Preconstruction meeting occurred.
05/31/24 – Project mobilization occurred.
06/27/24 – Contractor working on Roof D, E, and F. Existing roofing removed, repairs started and installation of the complete system started on roof D south end. Roof work on hold until July 1.
07/25/24 – KBR working on Roof D installing system south to north. Temporary scaffolding stair tower at roof F extended to roof D. Temporary stair tower and bridge installed to Roof C.
08/16/24 – THP published Bulletin No. 1.
08/29/24 – KBR completed main installation of Roof D and working on detailing. Preparation for Roof E installation has started.
08/29/24 – KBR completed main installation of Roof D and working on detailing. Preparation for Roof E installation has started.
09/12/24 – THP published walk mat layout review drawing.
09/16/25 – THP sent SOSS for additional services for Roof Safety Design.
09/19/24 – KBR completed main installation on roof D and E and working on detailing on both. Preparation for Roof F has started.
09/19/24 – THP published roof safety review drawings.
09/24/24 – THP published roof safety review drawings, Rev. 1.
09/25/24 – Hamilton County, CMI and THP had a MS Teams meeting to review the roof safety drawings and proposed approaches.
09/26/24 – KBR completed main installation of Roof F.
10/25/24 – THP released initial safety package for pricing by KBR. THP working on platform design to finalize complete package.
10/31/24 – KBR completed Roof D,E, &F including initial punch work. Roof A,B, & C and punch trip review complete. All lightning protection work scheduled to start early November.
10/30/24- KBR completed the work on lower roofs A,B and C and THP completed the initial punch review with KBR and HC for these roofs. THP needs to review the final fibertite’s punch review for the final confirmation.
11/06/24- HP approved pay App No.4 from KBR and send it to HC for the final review
11/07/24- THP send out the Bulletin No.2 to KBR for Pricing.
11/15/24- THP had a visit to KBR’s warehouse to confirm the walk mat materials purchased by KBR.
12/03/24- KBR send the Pricing for Bulletin No.2 to THP for review.
12/05/24- THP requested the breakdown of cost and resubmitting the CO No.2 from KBR.
12/09/24- HP approved pay App No.5 from KBR and send it to HC for the final review.
12/10/24- KBR sent the breakdown of costs for CO#1 for THP’s review.
12/11/24 – THP forwarded breakdown of cost and backup review to Hamilton County.
12/18/24 – County and THP approved KBR pricing. Final change order to be coordinated with safety upgrade work.
01/29/25 – County sent KBR AIA Change Order No. 2 for signature.
01/30/25 – Project status – Roof installed. Change order No. 2 waiting for execution and weather to install new safety platforms, RTU removal, and roof reconfiguration.
02/04/25 – Change Order No. 2 executed.
03/06/25 – Lightning protection work is complete, KBR is still waiting on the certification letter from Maxwell.
03/21/25 – THP reviewed the shop drawings for the platform and sent it back with comments to KBR. KBR Believed it should be roughly 7-8 weeks from getting them on-site for install.
03/26/25 – THP/LJB’s proposal for roof in progress.
04/24/25 – LJB provided updated proposal on 4/17/25. THP sent final proposal to County for review.
05/21/25- KBR confirmed that fabrication for the ladder and platforms is completed and they are at their site ready for deliver and install. KBR are getting themselves put on the schedule and will follow up with THP once they have a date.
06/18/25 – KBR will begin roof work on 07/07, including installation of ladders, platforms, and fall arrest systems on the ladders. Remaining work includes installing walk mats, replacing drain rings and cages on all roofs, and capping abandoned curbs on Roof C. KBR anticipates completing the Change Order #2 (CO#2) work within approximately two weeks from the start date.
06/24/25 – KBR submitted the lightning protection certification for THP’s review.
07/11/25- KBR completed 90% of the CO#2 works including installing walk mat on roofs, platform installation on both roof C and E, installing drain ring & strainers and caping abounded curb.
07/30/25 – KBR will provide CO#3 and CO#4 for remaining work including safety railing on roof D and E, Hatch guard, stair tower rental and all the work regarding removing old davits and installing new fall protection system. (the fall protection system work will be based on LJB design)

HC Juvenile Justice Center Davit Upgrade (F027):
THP PM: Rycca Thacker, John Millar
03/27/25 – County identified a number of safety concerns with roof operations. THP and the County had follow up meetings.
04/17/25 – THP received proposal from LJB for design of the safety davit system.
04/18/25 – THP published SOSS for County review.
05/07/25 – SOSS approved.
05/29/25 – THP coordinating design with LJB. Initial design discussions/meetings complete and formal SD to be submitted mid-June.
06/23/25 – LJB sent the preliminary drawings for the fall arrest system upgrade to THP. The design will be discussed with HC on 06/26. If there are no major changes, the final design is expected to be completed by the end of July.
07/11/25 – LJB sent the 90% drawings set and it was approved by THP and HC. LJB planning to provide the final design by August first.
08/22/25 – KBR completed remaining work on the ladder at roof F.
08/27/25- THP requested an updated cost estimate from KBR for CO#4 with a labor and material breakdown on the few Items including ( Safety Railing Roof D and Roof E, Hatch Guard, Flash New Davits and New Fall Protection) per county’s request and deducting the Terrecon cost from the list since that will be through THP.
08/27/25 – LJB send final review documents to THP. THP to review then forward to the team.
09/10/25- Terracon conducted a site survey to inspect the platform and ladder on roofs. They have noted that (2) attachments bolts on the top of the ladder at Roof E were loose. THP has reached out to KBR regarding this matter, and they are planning to have the steel crew back on site to complete the work.
09/19/25- LJB adjusted few items in their drawings per THP request and THP has sent the final drawings to KBR and HC for their review. KBR is waiting on CO#4 approval to start the rest of the work.
09/26/25 – County requested a breakdown of CO #4 work to be completed with railing material costs provided by the County.
10/09/25 – KBR provided updated pricing for CO #4 with the County providing the railings.
10/10/25 – THP reviewed pricing and noted one item to update.
10/16/25 – KBR provided an updated CO #4 breakdown pricing.
10/16/25 – THP approved pricing.
10/20/25 – County sent fully executed CO #4 to all parties.
10/26/25 – County received pricing for railings for CO #4 work with KBR. THP to review once cut sheets and product information is provided.
12/10/25 – KBR had the crane on site for delivering the roof railing on Friday 12/5 and were planning to complete the work the week of 12/8 weather depending. The work will include the installation of the railing at the roof edge on roof D and E and railing around the hatch at roof D.
01/08/26 – The railing installation on both roof has been completed and installed safety railing at roof hatch needs to be replaced. KBR and LJB will begin the installation of the new fall arrest system at the beginning of march and all remaining work and miscellaneous items will be completed at that time. THP will schedule a meeting before starting the work on March to go over all items with KBR and LJB.
02/23/26: KBR has installed the new railing around the roof hatch and planning to start the work on March 2nd with LJB for installation new fall arrest system. The Crane will be on site on 03/2/26 and contractors are estimating the work will be completed by end of the March.
03/18/26: THP has reviewed the new design layout with LJB, KBR and HC and approved the layout for Roof E, and then the partial section of roof D on 3/20. The rest will be reviewed by THP on the first week of April.
04/30/26: Project summary – LJB and KBR have installed 95% of the fall arrest system. At roof D an assembly needed to be adjusted and fall arrest for the ladder system has a back ordered component. Contractor anticipates finishing end of May.
09/24/26 – Work reported to be complete. THP and KBR coordinating final punch review by Fibertite and Terracon.
10/07/26 – THP completed formal punch trip with KBR. Missing gates noted.
10/29/26 – KBR ordered gates.

2020 – Roof Replacement (F034) and Davit Upgrade (F027) Read More »

JFS – General Services

PM: Bert Watts, John Millar
06/10/21 – County requested a general structural service proposal.
06/11/21 – THP sent SOSS.
07/12/21 – County approved SOSS for TEI, THP, and CHA.
10/28/21 – TTC provided an update on low flow plumbing issues at the A&D building. In the past month, we had a major leak at the main sanitary leaving the building. Plumbers called an underground detective to survey the pipe from the building to the street. TTC to get a test kit for testing in Fifth Floor East.
04/28/22 – Loading dock upgrades and striping and loading sign.

JFS – General Services Read More »

TPC – Electrical PM Procedures.

PM: John Nester, Mike Barth
08/26/21 – HCFD provides TEI with signed SOSS and PO for project.
02/23/22 – TEI reviewing current IEEE standards as they relate to the existing county procedure 7.0.  Once all current standards are incorporated and approved by HCFD and CMI – the PMs in Archibus will be updated.
04/27/22 – No updates.  Will move forward now that Barth has returned from medical LOA.
05/26/22 – No Updates this month.
06/28/22 – No Updates.
07/27/22 – TEI developing list of equipment for Nathan to put the procedures in Archibus.
08/24/22 – No updates this month.
09/26/22 – No Updates this month.
10/26/22 – No Updates this month.

TPC – Electrical PM Procedures. Read More »

JC – Fire Alarm System Upgrades

PM: Matt Butz, Mike Barth
08/26/21 – HCFD send signed PO and SOSS to TEI. TEI contacts HCFD PM to set up design kick off meeting, date is pending.
10/26/21 – TEI has began the design process, setting up drawings and using archive drawings to show on demolition plans. Once kickoff meeting occurs, the field verification process will occur and the project will proceed.
12/13/21 – TEI develops demolition drawings from existing building plans from archives, and conducts design kick-off meeting with HCFD and building manager.  Next step is to schedule field work to document/confirm existing conditions.  TEI to work with building manager on schedule.
01/25/22 – TEI fieldwork pending return of background checks for James Smiddy and Alex Woods.
02/23/22 – Background checks returned and employees badges approved.  TEI and HCFD to schedule the field work with building managers.
04/27/22 – TEI hires MobilComm to provide survey of signal strength for FF radios (per CFD requirements).   Upon receipt of report from MobilComm, recommendations for BDA may be included in design specifications.  TEI fieldwork complete.   Existing conditions  documented and moving forward with new work drawings.
05/26/22 – MobilComm reports back that the building has a non compliant system.  New BDA system will be installed.  TEI Meeting with Fire Marshall on 06/07/22 with 90% complete documents for review/input.
06/28/22 – Project deign near complete – Pending Barth review, documents will be sent to HCFD Week of 07/04/22 for review and comments.   ITB will be issued upon receipt of review comments.
07/27/22 – TEI sends drawings to Hamilton County facilities for review.  Upon receipt of review comments, the package will be issued for bidding.
08/24/22 – Project being sent to purchasing on 08/26/22 for bidding.  Available to bidders on 08/30/22.  Prebid scheduled for 09/14/22 and bid opening scheduled for 09/28/22.  ITB # 075-22.
09/26/22 – Project out for bids.  Bids open 09/28/22.
10/26/22 – Bids received and opened.  DK apparent low bidder.  JCI/Simplex vender in bid.  TEI vets bid and makes recommendation for award.   Project to commence upon contract approval and PO to DK.
12/15/22 – DK signs and returns contract to HCFD.  Once PO is issued, pre-construction meeting to be scheduled.
01/25/23 – DK receives approved contract and PO.  HCFD and TEI working to schedule preconstruction meeting to kick off the construction.
02/23/23 – Pre construction meeting completed.  JCI developing submittal documents.
03/29/23 – TEI speaks with JCI about status of Submittal Package.  JCI states that the submittals are tracking about 2-3 weeks behind the 800 Broadway submittals (anticipated receipt of submittals = late April to Mid-May).
04/27/23 – JCI indicates that the submittals for the JC shall be sent to DK by mid May.  Still tracking same as indicated last month.  TEI to review and turn around upon receipt of submittals.
05/23/23 – JCI indicated that the submittals will be sent to DK this week.   DK has not received to date.
06/28/23 – DK has not sent submittals to TEI for review to date.  Submittals will be reviewed by TEI upon receipt.
07/26/23 – TEI receives submittals for project.   Reviewing and will return.  Pre construction meeting (along with 800) is scheduled for 7/28.
08/24/23 – TEI, HCFD and DK meet (at 800) to discuss project.  work in JC to mobilize late Q1/early Q2 of 2024.  Matt Butz asks about the BDA equipment at the JC, and how quickly it can be installed (issues with the existing system).  TEI reaches out to DK to request data about schedule.
09/26/23 – TEI reaches out to DK for CO cost to install the ERRS (BDA) ASAP versus waiting until the new JCI system is in the building.  MobilCOMM states no issues with the plan.   DK sending electrician to site to confirm existing system is compatible and will issue CO accordingly.  TEI stresses with Gleason that time is of the essence.
10/26/23 – MobilCOMM has ordered to BDA for the JC and will schedule the installation upon receipt of the equipment.  DK still on schedule to mobilize as previously identified.
12/06/23 – TEI asks DK to find status of BDA – should be at MobilCom per previous schedule.  TEI will follow up with DK.
01/30/24 – Installation of BDA pending the background checks from MobileComm
02/28/24 – MobileCOMM cleared to work in building.  TEI contacts DK and tells them that the install must be scheduled and we need to have install date by beginning of February partner meeting.
03/27/24 – MobilComm and DK to mobilize 4/1/24 to install and get the BDA installed ASAP.
04/24/24 – Work has began on the BDA upgrades,  most work in basement complete and 1st floor is next.   All areas with minimal/no coverage were addressed first.
05/29/24 – BDA installed and turned on in the lower levels of both buildings.   Finalizing the install of the BDA in the next week or two.  Started the install of the backbone for the JCI fire alarm system.
06/26/24 – BDA installed and complete. DK and Biederman working out PO issues to get permitted. Panels installed and backbone conduits being routed through the building. DK facing additional staffing issues.
07/24/24 – Staffing issues continue. Permits for BDA applied for – pending City approval. Work continues on backbone. DK developing means and methods and durations of timing needed in all inmate areas to coordinate with HCSO. JCI finalizing CO pricing for deluge system, but Jay at JCI tells TEI that the relays needed for the CO are currently on backorder and the scheduled ship date is 01/31/2038 (and this is NOT a typo!). TEI states this is NOT acceptable!
08/28/24 – Project in construction. Permits for BDA obtained, inspections completed (passed) and MobilComm to send approval paperwork to HamCo once received.
09/25/24 – Construction progressing in the building.
10/30/24 – Construction progressing in the building following behind the cell lock project.
12/11/24 – DK indicates that the backbone installation is nearly complete and that they will need to have JCI and Notifier at the next const meeting (01/08/25) for coordination of cross trip.
01/29/25 – Cross trip installed and working. DK to have JCI at next project meeting to review schedule and Deluge system (controlled on all floors).
02/26/25 – JCI, HCFD, and TEI meet to discuss deluge system on site. TEI sent JCI record dwgs of sprinkler system in building. Construction on-going.
03/26/25 – JCI has all parts for Deluge upgrade to DK. The Deluge upgrade to begin early April.
04/23/25 – Deluge work has started. Working in unit 1 of north tower, all floors. Then Unit 2 North, and so on.
05/28/25 – Side 2 of the north building to be completed in the next 2 weeks.
06/25/25 – Issues with the Deluge valves and water leaks. TTC attends FA meeting and evaluates the valves and to send in recommendations.
07/30/25 – Construction on the project progressing with availability of spaces. DEG submits memo with recommendations.
07/31/25 – TTC issued memo on the deluge valve issue in the North building. We will talk more about this after the meeting today.
08/27/25 – Construction progressing. Moving to south tower beginning of September.
09/24/25 – Construction progress continues. DK following the other projects as pods are made available.
10/29/25 – Construction progress ongoing. Anticipated completion April/May of 2026
12/10/25 – Construction progress ongoing. Change order issued at the OEC meeting today. JCI finalizing engineering change for the building department.
01/28/26 – All work (original Scope) in North tower near complete. JCI to submit documents to city by end of Janaury. Project ongoing. Anticipated completion Late April/Early May 2026.
02/25/26 – Project ongoing. Deluge work is being completed this week and next.
03/25/26 – Project ongoing.
04/29/26 – Pretest completed on 04/28 throughout both buildings. Consult with inspector to be scheduled to outline inspection process.
07/29/26 – 2 months of inspections completed and the CFD and CBD have approved all of the installations. DEG has assembled the punchlist for the project and issued to the EC. Most items were discussed at time of inspection and punchlist walk – and we anticipate that they have been completed. Training for building staff was 07/28/26.
07/30/26 – Electric issues at panel and distribution at fire pit shorted out. Wire ran in lighting conduit and DK has to do an emergency repair for the job. MB to investigate and report back.
08/26/26 – Project complete pending final IBI and Elevator inspections for JCI to sign off on permit. Scheduled for Week of 08/31. Closeouts requested from DK.
09/23/26 – All inspections except IBI complete. IBI pending renewal paperwork. Project pending final closeout.
10/28/26 – IBI final inspection passed and complete. Project pending closeout documents.

JC – Fire Alarm System Upgrades Read More »

800 – Fire Alarm System Upgrade

PM: Matt Butz, Mike Barth
08/26/21 – HCFD sends TEI signed PO and SOSS. TEI contacts HCFD PM to schedule design kick off meeting. Date pending.
10/26/21 – TEI has begun the design process by setting up the CAD file drawings and using archive data to begin the demolition drawings. Once kick off meeting occurs, the field investigation will be scheduled and the design will proceed.
12/13/21 – TEI has taken the as-build documents to create demolition drawings.  Next step is to field verify/document the existing conditions.  Field work to be scheduled with building manager.  design kick off meeting occurred with HCFD and building manager.
01/25/22 – TEI fieldwork pending return of background checks for James Smiddy and Alex Woods.
02/23/22 – Background checks approved and badges approved.   TEI and HCFD to schedule field work with building manager.  Note – there was an issues with the existing Simplex FA System panel (dialer power supply) and JCI sent a quote for a complete panel replacement.   TEI and JCI investigating a more cost effective fix until a time when the system is replaced.
04/27/22 – TEI hires MobilComm to provide survey of signal strength for FF radios (per CFD requirements).   Upon receipt of report from MobilComm, recommendations for BDA may be included in design specifications.  TEI fieldwork complete.   Existing conditions  documented and moving forward with new work drawings.
05/26/22 – MobilComm reports back that the building has a non compliant system.  New BDA system will be installed.  TEI Meeting with Fire Marshall on 06/07/22 with 90% complete documents for review/input.
06/28/22 – Project deign near complete – Pending Barth review, documents will be sent to HCFD Week of 7/4/22 for review and comments.   ITB will be issued upon receipt of review comments.
07/27/22 – TEI sends drawings to Hamilton County facilities for review.  Upon receipt of review comments, the package will be issued for bidding.
08/24/22 – Project being sent to purchasing on 08/26/22 for bidding.  Available to bidders on 08/30/22.  Prebid scheduled for 09/14/22 and bid opening scheduled for 09/28/22.  ITB # 075-22.
09/26/22 – Project bidding.   Bids Due 9/28/22.
10/26/22 – Bids received and opened.  DK apparent low bidder.  JCI/Simplex vender in bid.  TEI vets bid and makes recommendation for award.   Project to commence upon contract approval and PO to DK.
12/15/22 – DK signs and returns contract to HCFD.  Once PO is issued, pre-construction meeting to be scheduled.
01/25/23 – DK receives contract and PO.  HCFD and TEI working to schedule preconstruction meeting to kick of construction.
02/23/23 – Preconstruction meeting completed.  JCI developing submittals.
03/29/23 – TEI speaks with JCI about submittal package.   JCI estimates that the submittals for the 800 building will be completed and turned over to DK in the next 2-3 weeks (Mid April-ish).
04/27/23 – TEI follows up with JCI, submittals nearly complete.   JCI indicated that the submittal package should be sent to DK on or before 05/01/23.  TEI to review upon receipt.
05/23/23 – TEI receives, reviews, and returns submittals with minimal marks, asks for schedule from DK for commencement of work.  JC sends photo of material that was shipped to DK for project.  TEI to schedule pre-construction meeting first week in June.
06/28/23 – TEI requests schedule again from DK.  Upon receipt of schedule, construction to commence pending procurement of materials.
07/26/23 – construction kickoff meeting scheduled for 7/28.
08/24/23 – DK to mobilize to project site and start construction on 9/5/23.  Josh Querry from DK to PM/site Super the project.
09/26/23 – Construction has began.  DK installing backbone of the system.
10/26/23 – Backbone installation complete.  DK has started on upper floors and at the construction meeting on 10/25/23 stated that 18, 17, 16 and part of 15 is complete.  DK also working in basement and installing devices there.   Rooms are being identified that require either  LEADs clearance or special access.  DK to schedule work in these areas during day shift.
12/06/23 – Construction progressing.  Working on installs in LB, B 1,2,3,3M.  LB and B ready for change over.  2 will be by Christmas.  1, 3 and 3M will be nearly complete if not complete by Jan 1.
01/30/24 – DK submits CO request for portion of work changes.  The beam detector CO still pending.
02/28/24 – Beam detector CO still pending.
03/27/24 – Beam detector for 3 beam detectors received ($41k).  HCFD to determine if it is accepted or not.  Smoke purge CO under review.
04/24/24 – Smoke purge CO verbally approved to DK at const meeting.  Beam detector CO not approved at the meeting.  Work continues through the building.
05/29/24 – The smoke purge CO has been approved and sent to DK.  DK and JCI working on Drawing updates and will progress to install as soon as the revised install drawings from JCI complete.  JCI indicated that all parts are readily available.
06/26/24 – No updates from JCI on this project.
07/24/24 – DK same staffing issues – staff being moved from 800 to JC and back. CO verbally approved (HCFD waiting on PO increase) for formal approval.
08/28/24 – JCI submits revised drawings wot city for approval. JCI states that there is no way (on existing system) to repair the amplifier card for the upper floors. TEI and HCFD directed JCI that the New system shall be turned on immediately and use the new devices for audio on the upper floors.
09/25/24 – TEI, DK and HCFD meet with inspector (Jeff Hinkel) to discuss inspection process and 3 and 3M. Inspections will proceed similar to CH and TPC, where we will have multiple teams and multiple inspections. Looking at options for the 3 and 3M area – inspector sympathized with the task and we developed possible workable solutions.
10/30/24 – The switchover of floors to the new system in the tower (top down) has commenced. Anticipate tower work to be completed in approx 2-3 weeks. then move to low rise floors. TEI recommends scheduling inspection of tower floors once tower complete.
12/11/24 – HCFD, CFD, CBD, JCI, DK and TEI participate in the first acceptance inspection at the building. Floors 7-18 were inspected and accepted, with minor tweaks. Construction continues, with the crews starting on 5th floor week of 12/16.
01/29/25 – Crews working on 2 right now. Next inspection scheduled for 02/12/25 at 5:00 PM. Planning for inspections of floors 2-6.
02/26/25 – Inspections for 2-6 went well. First floor complete and working in basement. Will be ready for next inspection in about a month. Then there will be the Flow/Tamper inspections, then AHU/smoke control inspections, then Elevators. Need resolution of elevator issues for the non-functioning elevators.
03/26/25 – Inspection for SB, B and 1 scheduled for 04/16/25. The tamper/flow inspection to be scheduled 2-3 weeks after the inspection on the 16th.
04/23/25 – All floors inspected for smokes, pulls, heats and AVs. Door holders were inspected. Tamper/flows inspection next – to be scheduled TBD.
05/28/25 – Tamper flow inspection occured and passed. Next is air handlers. Inspector allows the magna-helic results from the pre-test to be written on the covers for the inspection night.
06/25/25 – Installation nearing completion. Elevtor and Air Handler inspections scheduled for 07/16/2025
07/30/25 – Freight elevator and final air handler inspections scheduled for 07/31/25 at 0700. This is final building and fire and elevator inspections pending no issues during the inspections.
07/31/25 – Early morning inspection went well this morning. Three small electrical items are required to be updated to get the AHU-45 and Smoke Fans 14 & 15 did not start. The elevators are approved and the Chief Inspector approved the current smoke detector layout.
08/27/25 – follow up visits with CFD and CBD to inspect and approve the repairs made by HC. All inspections completed (other than IBI). IBI to be scheduled once the Bldg Dept and FD upload all their paperwork.
09/24/25 – All inspections passed. HCFD and DEG to schedule final punchlist for project.
10/29/25 – Punchlist completed and issued punchlist to DK.
12/10/25 – project tied to Justice Center PO. Closeout pending completion of JC FA project.
01/28/26 – Project tied to the JC FA PO, Closeout pending completion of JC FA project. Anticipated completion April/May of 2026.
02/25/26 – No Updates.
03/25/26 – No Updates.
04/29/26 – No Updates.
06/23/26 – DEG directs DK to assemble and submit closeout documents for 800 building.
07/29/26 – Project completion pending closeout documents.
08/26/26 – Project complete pending closeout documents.
09/23/26 – Project complete pending closeout documents.
10/28/26 – Project complete pending closeout documents.

800 – Fire Alarm System Upgrade Read More »

A&D – Computer Room Emergency Power Connections

PM – Rycca Thacker, Mike Barth
08/26/21 – HCFD sends signed PO and SOSS to TEI. TEI to start immediately, as the switchgear cleaning work is contingent on the this work.
10/26/21 – TEI submits preliminary plans and opinion of probable cost to HamCo for review. Project pending project funding.
12/13/21 – TEI and HCFD gets quotation from CE Power to provide the install of the work.  HCFD drafts and issues a PO for the work to be installed, and requests schedule from CE Power.
02/23/22 – All equipment has been ordered and anticipated delivery was end of February, early March.   CE Power to notify TEI and HCFD upon receipt of all equipment and schedule installation and cleaning.
04/27/22 – Equipment is installed in the building. HCFD and TEI requesting dates from CE Power to perform Switchgear PM and Tie ins during same outage.   Tie in pending CE Power availability.
05/26/22 – Tie in date tentatively scheduled for June 20 (Juneteenth Holiday).  Pending approval from HCFD and JFS personnel.   JFS requested that it move to as Saturday in case there were issues and needed the Sunday for repairs.   Final date TBD.
06/28/22 – Date of tie in moved to 07/09/22.  Tie in to be competed concurrently with switchgear cleaning (same power outage).
07/27/22 – Power outage cancelled by Duke energy due to tornados in the area, and unavailability of Duke crews.   CE Power, HCFD, JFS and Duke to reschedule.
08/24/22 – Reschedule date is 09/10/22 pending no storms etc. in area.
09/26/22 – Installation complete.  testing, training and punchlist to be scheduled.
09/29/22 – Work on SOSS for putting CRAC and Condenser on backup power.
10/26/22 – TEI submits SOSS for placing CRAC unit condensers on the backup power.   project pending SOSS approval.
12/15/22 – TEI receives approved SOSS and PO.   Project Design in progress.
01/25/23 – CE power punchlist incomplete.  TEI sends follow up email to request that the work completed ASAP.    Alex on site on 01/25/23 to confirm the existing power feeds to the condensing units, and a review set will be send to HCFD prior to bidding.
02/23/23 – TEI to submit to HCFD bid set for final review.
03/29/23 – TEI to submit review set to HCFD by 05/03/23.
05/23/23 – TEI submits review set to HCFD for comments.   Upon receipt of owner review comments, project will be issued for bids (small projects method).
06/28/23 – TEI, RT and Kleeman meet on site and discuss project.   Trades electricians to provide installation of the circuits.  TEI to procure the permit from IBI for trades.
08/24/23 – Drawings are submitted to IBI for permit.  Comments received and answered from IBI.  Permit expected in next day or two.
09/26/23 – Plan review complete and permits ready to be picked up at IBI.  TEI will deliver to HCFD for work to be completed by trades.
10/26/23 – TEI procures the permit for the work and sends to HCFD.  Trades to install work.
12/06/23 – Trades to notify TEI when they are ready for inspections.
01/30/24 – Trades completes work.   TEI and Trades have IBI inspect work and passed inspections on 1/30/24.
02/29/24 – Project complete, need as-builts to close out.

A&D – Computer Room Emergency Power Connections Read More »

TPC – Air Compressor Upgrade

PM: Terry Cannon, John Nester
07/29/21 – Remaining air compressor items after Ameresco work is complete. Is there any way to convert the final remaining devices to electronic? TTC to check on smoke purge control with fire alarm
08/26/21 – Met with Ameresco on scoping remaining pneumatic devices 3 times in the last two weeks. FA testing at Admin on Thursday night to verify existing sequences but the latest thought is that we will have to keep a pneumatic air compressor at the building. We will put a small project bid together for that work and get that out for bid ASAP.
10/19/21 – Final bids were submitted. ThermalTech created a bid tab and sent to the County.
10/22/21 – Talked to Bert about updated bid tabulation and waiting for final approval to move forward.
12/13/21 – Spoke to all vendors about the job and to be ready to start this job as soon as the Admin Fire Alarm.  We are set to begin this project and can schedule a kickoff with the county as soon as convenient.
01/25/22- Construction Work is scheduled to begin late February or early March. We are asking for submittals now.
02/24/22 – Submittals are in, will start right after Fire Alarm.
03/31/22 – Admin FA testing happening now, this project will be started after the FA is approved in April.
04/28/22 – Final FA test was completed and final meeting is coming up soon. TTC to send controls submittals back to Emcor ASAP. JCI submittal not received yet. This project is ready to get going in earnest.
05/25/22 – TTC needs to finish submittals and get Emcor scheduled for the next phase, will move this up to the front burner.
06/30/22 – Submittals are partially reviewed. TTC will setup kickoff meeting with Brian & Katie first week of July.
07/27/22 – The Pre-Const meeting was help with DK and a project schedule was submitted for work to begin in August through October. TEI starting to schedule contractors and vendors for a November final test.
08/09/22- Const Mtg #2 held with contractors. Things are going well DK is on schedule. We addressed several questions after the meeting on the walk through. TTE to work on FA final inspection schedule at end of job. EF-1,3,4,6, SF-8 complete.
08/23/22 – Const Mtg #3 and things are going even better. No major questions. EF-6,10,7, SF-1 Penthouse UH complete. Programming being updated as equipment is brought online. Graphics and controls look good.
09/22/22 – Const Mtgs continue, the job is about half done. DK is on schedule and continues converting pneumatic devices in the building. We have decided to submit a permit for this work and have it tested wit the city one final time. November 10 & 12.
10/26/22 – The project is complete from the DK scope. Pretesting went well and after some programming updates by Emcor during pretesting, the system is probably ready to test with the City. We spoke to Ameresco trying to use their existing permit to retest the system but that permit is closed. We will need to submit a new permit to the city.
12/15/22 – Work is complete, functional testing is complete, all systems are online and ready to go. AC has been turned off. TTC to issues cleanup punchlist to Debra. Project ready to start closeout.
01/24/23 – Work is complete and we talked to DK about cleaning up the rest of the job. AHU-1E is experiencing some issues probably note related to this job but also some issue that are related to this job. Two pneumatic dampers were found that need to be upgraded, but these dampers are already scheduled for demo in the Auto Title project so we instructed DK to lock them open and we have turned off the Air Compressor. Closeout documents started on this job.
02/21/23 – Project is complete, no closeout documents yet.
04/26/23 – Closeout documents requested.
06/28/23 – TTC will check with Steve on closeout documents.

TPC – Air Compressor Upgrade Read More »

JC – Loading Dock Upgrade

PM: John Nester, John Millar,
07/29/21 – Creating SOSS.
08/03/21 – SOSS submitted to Hamilton County for review.
08/09/21 – Hamilton County accepted SOSS.
08/25/21 – THP met at Justice Center with John Nester (Hamilton County) and Mike Barth (Thermal Tech Engineering.
08/25/21 – THP met at Justice Center with John Nester (Hamilton County) and Mike Barth (Thermal Tech Engineering) to review project and begin putting bidding documents together.
9/16/21 – THP sends project manual and drawings to Hamilton County for review. THP revises bidding documents based on County review and sends bidding documents to Triton, KFI, and Schrudde-Zimmerman.
9/22/21 – KFI notifies THP they will not be bidding on the project. THP sends bidding documents to Diversified Facility Solutions and Leo Brielmaier.
9/27/21 – THP holds pre-bid meeting at HC Justice Center. Triton and Leo Brielmaier are the only contractors to attend.
10/5/21 – THP issues addendum No. 1
10/11/21 – Bid due date. THP receives only one bid from Triton.
10/14/21 – THP calls Triton to discuss/review bid.
10/15/21 – THP sends Hamilton County bid review/award recommendation letter for Triton.
11/15/21 – Signed contract and PO issued. Triton to have contractors receive background checks as needed and start submittal process. Pre-construction meeting and NTP to follow in near future.
2/23/22 – Waiting for lead time on new loading dock. Will schedule Pre-Con meeting with Hamilton County and Triton when we have updated lead time/schedule.
3/16/22 – Triton informs Hamilton County and THP that the loading dock lift supplier has received the new lift.
3/14/22 and 3/30/22 – Hamilton County and THP has reached out to Thermal Tech for review of the submittal and to see if an electrical permit is necessary for this project. No response from Thermal Tech.
3/30/22 – Need to confirm with John Nester, Hamilton County the time frame for the project and schedule a pre-construction meeting.
4/20/22 – Triton submitted site specific safety plan.
4/27/22 – Thermal Tech reviewing electrical permit needs of the lift.
6/30/22 – Thermal Tech reviewed the electrical connection and no permit is needed. Contractor working on background checks.
5/26/22 – Thermal Tech reviewed submittal and confirmed a new electrical permit is not required.
06/10/22 – Finalizing and confirming background checks have been performed for necessary crew members for Triton and Sub-Contractors.
07/26/22 – Pre-Construction Meeting has been scheduled for August 2.
08/02/22 – Pre-Construction Meeting at Justice Center with Hamilton County, Sheriffs Department, Thermal Tech, and Triton.
08/10/22 – Field site visit with Triton and sub-contractors.
08/25/22 – Work is scheduled to be performed overnight. Expected to be completed in 1-night.
08/25/22 – New loading dock lift was installed on 08/25/22.
08/26/22 – THP and John Nester visited the site. THP sent field report to Triton for punch list items.
08/30/22 – Issue with loading dock motor. Motor has seized up/burned up. Triton to coordinate with Equipment Depot to get new motor and fix the issue.
09/15/22 – Repairs to the loading dock lift are completed and it is up and running.
09/19/22 – Sheriffs Department informed THP and John Nester that a sizable gap exists between the loading dock edge and the platform edge. THP notified Triton and Triton is working on getting Equipment Depot back on site to review the issue and complete the punch list items.
09/30/22 – The sizable gap between the loading dock edge and the platform edge has been corrected and the other punch list items have been completed.
10/13/22 – Triton, Hamilton County, and THP met onsite to review the loading dock lift and completion of punch list items. Equipment Depot to complete paint touch ups on a final follow up visit.
10/21/22 – Triton working on finalized pay app and all required documents for project closeout.
12/07/22 – Required close out paperwork and final pay app submitted to Hamilton County.

JC – Loading Dock Upgrade Read More »

Animal Shelter – Master Planning

PM: Mike Murphy, Bert Watts
07/29/21 – Master Planning meeting being scheduled for scope and SOSS creation.
08/23/21 – Meeting held with County and Animal Shelter representatives
08/25/21 – Animal Shelter CEO puts Champlin in touch with Animal Arts.
10/17/21 – SOSS submitted to County. Waiting Approval.
11/08/21 – Approved SOSS received.
11/29/21 – Kickoff meeting held. attended by Champlin, County and Cares.
12/06/21 – Programming meeting held. Attended by Champlin, County and Cares. Finalized schedule and future meeting.
01/17/22 – Concept plan approved.
01/26/22 – Bi-weekly meetings in progress. Floor plan and renderings begun.
02/24/22 – Final user meeting to confirm/present interior and exterior renderings
04/11/22 – Final deliverable submitted to County.
04/13/22 – SOSS submitted for analysis of two existing buildings.
04/21/22 – CH and County Meeting to review commissioner feedback.

01/26/23 – Fair grounds site evaluated for animal shelter location. Fit plans in progress.

02/22/23 – SOSS approved to review Winton road site for test fit.

03/30/23 – No update.

04/27/23 – No update.

05/25/23 – No update.

06/29/23 – No update.

Animal Shelter – Master Planning Read More »

125 – 8th Floor Public Defender Expansion

07/28/21 – Submitted SOSS to County.
08/02/21 – SOSS Received.
09/27/21 – Site visit to confirm existing conditions.
10/14/21 – Preliminary plans sent to County for comment.
10/26/21 – Review meeting requested
11/04/21 – Review meeting held. Attended by Champlin, Public Defenders and County
11/29/21 – New layout options sent to County and Public Defenders.
12/23/21 – User meeting to finalize plan.
02/04/22 – SD plan and estimate sent to County.
03/31/22 – No Update
04/28/22 – No Update
05/26/22 – No Update. New information at Partner meeting on project status, still in development.

06/30/22 – Site visit to discuss scope of increased expansion

08/25/22 – Work to be reported in the new project.

125 – 8th Floor Public Defender Expansion Read More »

230 – Court of Appeals Mediation Renovation

07/28/21 – Signed SOSS received by Champlin.
08/26/21 – No update.
11/04/21 – Meeting with County and User to review Mediation Renovation scope reduction.
11/15/21 – SOSS submitted for DD-CA work.
11/17/21 – SD Set and Estimate uploaded to Archibus.
12/14/21 – Signed SOSS received for DD thru CA.
01/12/22 – Design review meeting with new administrative judge. No design changes. waiting for wall covering scope of work to be finalized.
02/24/22 – Waiting on official confirmation of wall covering scope. (our understanding is that there will not be any)
03/31/22 – Scope confirmed. DD in progress. Deadline of 3rd week of April to be bid ready.
04/27/22 – Final review meeting to approve final bid issuance.
05/26/22 – Finalizing bid package will be combined with Magistrates now. Final review set due June 2.
06/30/22 – Project in Bidding phase.
07/28/22 – Bidder recommendation letter sent to county.
08/25/22 – Building permit submitted. Contract in progress.
09/29/22 – Contract Finalized. Kickoff to be scheduled in near future. Construction moved to combined project.

230 – Court of Appeals Mediation Renovation Read More »

JC – Card Access Control

PM – Matt Butz, Mike Barth

7/27/21 – TEI authors and submits SOSS. TEI receives signed SOSS and PO from HCFD. Design kick off meeting to be scheduled early August.

08/26/21 – Field work, pre construction meeting scheduled with DK at 1:30 PM on 08/26/21. Construction to commence thereafter.

10/26/21 – Project in construction. Issues with installation in process of developing repair plan.

12/13/21 – Project complete with the exception of wall path and painting.  O&M manuals delivered to HCFD.

01/25/22 – Project complete  pending receipt of closeout documents from DK.

JC – Card Access Control Read More »

CH/JC/TPC/800 – Panic Button System Upgrade

PM – Matt Butz, Mike Barth

07/28/21 – Thermal authors and submits SOSS. TEI receives signed SOSS and PO from Hamilton County. TEI and HCFD to schedule design kick off meeting first week or two of August.

08/26/21 – HCFD PM and TEI schedule field work at all (4) buildings the afternoon of 09/02/21. TEI has coordinated with SecureTech and project is progressing.

10/26/21 – Project in contract phase. Construction to be completed once contract/PO is BOCC approved.

12/13/21 – Contracts sent to SecureTech.  Pre-install training meeting with HCSO conducted last week.  Parts are ordered and the will be available early January 2022.  Install Scheduled to occur beginning MLK weekend 2022.

01/25/22 – Installation was completed on the weekend of 01/17/22.  Securetech is working on getting closeout information to submit.  TEI and HCFD to provide punchlist the beginning of February.

02/23/22 – All close out documents complete.   Final pay application received.   HCFD to provide TEI with mark ups of button locations to show on CAD drawings.   Upon completion of the as-built conditions, project will be archived.

04/27/22 – TEI receives the mark ups for the CH for As-built documents 04/21/22.  Upon completion of the as-builts (drawings complete, MCB to review final drawings), O&M manuals will be delivered to project can be closed out.

05/26/22 – TEI to provide HCFD with (2) full size sets to deliver to HCSO.   Project complete upon turn over of full size drawings.

06/28/22 – Project complete.

07/27/22 – TEI Delivers thumb drive with electronic version of the drawings per HCSO request to Matt Butz.

CH/JC/TPC/800 – Panic Button System Upgrade Read More »

Crime Lab – PM Schedules

06/25/21 – ThermalTech has been working on project over the last few weeks. New equipment was added to the worksheet, TTC to review final list.
07/29/21 – Susan contacted me about completion and I suggested that we could get these done by August 13. She reviewed our test work in DEV and had some questions. Ryan and Nathan will help me complete this work.
08/12/21 – Discussed progress with Susan and committed to a 8/31 completion for 9/1 PM’s. TE has updated Coroner’s Equipment list to check one more time before completion. We are verifying no duplicates exist.
08/25/21 – TTC sent in final list for equipment creation with 3 or 4 questions. Talked to Susan, Steve and Bert about process to finish. I received codes and values back from Facilities to use on our equipment creation list.
10/01/21 – Final equipment list sent to County for upload to Archibus.
10/08/21 – Needed to add asset column for equipment list and warranty item needs to be added.
10/19/21 – Revised worksheet and equipment list sent back to County. I still have to create warranty information for equipment when we enter the PM’s.
12/01/21 – Crime Lab PM’s entered minus a couple of extraneous electrical PM that TTC is checking the needs on.
12/13/21 –  Electrical PM not needed for exit signs, security gate, or power conditioner.  Steve checked in on warranty items and TTC reported that TTE can enter these manually, I just need a review on how to enter the warranty items.  We are meeting this week on how to do this work.
01/22/22 – All equipment and warranties are entered and up to date.
05/25/22 – Ready to Archive.

Crime Lab – PM Schedules Read More »

800 – Access Control

PM: Matt Butz, Mike Barth
05/27/21 – Project created.

06/23/21 – Project kick off meeting attended by TEI, HCFD, DK and HCSO. DK has began moving the doors over to the Vax system. Project construction continues.

07/28/21 – DK states that the project is substantially complete. TEI and HCFD provide punchlist site visit. TEI issues punchlist. DK addressing punchlist items.

08/26/21 – Punchlist items are picked up. TEI receives O&M manuals for review. No punchlist or warranty in O&Ms. Upon receipt, TEI will forward to HCFD.

10/26/21 – O&M Manuals delivered to HCFD. Project is complete.

800 – Access Control Read More »

Animal Shelter – Roof Replacement

05/21/21 – Hamilton County requested SOSS for the roof replacement of two roofs with alternates.
06/03/21 – THP provided SOSS for roof replacement project.
06/15/21 – County approved SOSS.
08/02/21 – THP visited site to survey and document existing conditions.
08/16/21 – THP issued Opinion of Probable Costs to Hamilton County for project budget approval.
08/20/21 – THP issued progress drawings and project manual for Owner Review.
08/25/21 – THP visited site to review condition of exposed decking in office and verify conditions at Entry canopy.
09/01/21 – THP received and reviewed AIA contract documents for project manual.
09/02/21 – THP met Hamilton County at site to review drawings and confirm scope of work items and Alternates.
09/03/21 – THP finalized and issued documents for bid.
09/09/21 – THP received and replied to substitution request email from roofing supplier and updated specifications.
09/14/21 – THP led pre-bid meeting at Animal Shelter.
09/15/21 – THP developed pre-bid meeting notes and issued Addendum 01.
10/05/21 – Bid opening. Received bids from Ace Exteriors, Wm. Kramer & Son, and Imbus Roofing.
10/06/21 – THP had conversations with Ace Exteriors to qualify bid, discuss pricing for canopy replacement, and request references and manufacturer’s certifications.
10/08/21 – THP finalized letter to Hamilton County summarizing bid process and recommending award to Ace Exteriors, including Base Bid and Alternate 1 scopes of work.
10/08/21 – THP responded to email from Hamilton County summarizing reasons bids received for canopy exceeded original estimates.
10/18/21 – THP received and began review of roofing products received from contractor as substitutions due to material availability.
10/20/21 – THP had conversation with Contractor and emailed Hamilton County about status of registering Ace Exteriors as a vendor.
10/21/21 – THP received from Contractor and forwarded to Hamilton County completed Substitutions form missing from bid proposal.
10/28/21 – THP issued revised title sheet with wind load information for Office/Admin. and Cat House roofs and requested Contractor review with manufacturer the potential implications on warranty and adhesive requirements.
11/05/21 – THP had conversation with Hamilton County to discuss material substitutions proposed by Ace Exterior due to material availability and schedule issues.
11/05/21 – THP had conversations with Wm. Kramer & Son about material availability and confirmed they would not be able to provide the specified roof insulation and cover board by spring 2022.
11/05/21 – THP emailed Hamilton County recommendations to proceed with the project using the substitute materials proposed by Ace Exteriors.
11/10/21 – Hamilton County emailed contract to Ace Exteriors.
11/23/21 – Ace Exteriors emailed Hamilton County the signed contract, worker compensation certificate, and a project-specific certificate of liability insurance.
12/23/21 – Hamilton County emailed the signed contract and PO to Ace Exteriors and requested development of required preconstruction documents.
01/28/22 – THP emailed Contractor about status of materials order, development of required pre-construction documents, completion date, and additional details to be developed.
02/01/22 – THP emailed Contractor draft of revised roof plan and details showing contract scope and new details at interface between project scope and canopies to remain.
02/04/22 – THP finalized and issued revised documents for Permit and Construction.
02/10/22 – THP reviewed and returned product submittals for roofing materials.
03/08/22 – THP received and reviewed Contractor’s pricing and lead time information for aluminum v. galvanized edge metals.
03/10/22 – THP had conversation with County about approval of proposed metal substitution due to increased costs and lead time issues, and re-reviewed submittals for roof specialties.
04/05/22 – Preconstruction meeting.
04/12/22 – THP issued minutes from preconstruction meeting.
04/12/22 – THP reviewed submittals and requested revised insulation layout.
04/13/22 – THP had conversation with Contractor about discrepancy in slope of tapered insulation between documents and submitted revised insulation layout, and retuned submittal with exceptions noted.
04/13/22 – THP had conversation with Contractor about installation issues and additional cost of taller fascia that would be required with 1/4″ slope tapered insulation v. 1/8″ slope indicated in documents. Contractor to request updated/revised tapered layout to reflect the 1/8″ slope.
04/19/22 – THP received, reviewed, and returned re-revised insulation layout submittal.
04/22/22 – THP had conversations with Contractor and Hamilton County to discuss delayed start date due to weather and insulation slope issue, and emailed team about rescheduling first progress meeting.
05/02/22 – THP met project team at site for progress meeting and site visit to document progress.
05/02/22 – THP emailed Contractor a link to a shared folder containing original construction drawings.
05/02/22 – THP developed and issued minutes from progress meeting #1.
05/03/22 – THP issued field report 01 from 5/2 site visit.
05/03/22 – THP reviewed pencil copy of Contractor’s first application for payment and replied with comments.
05/03/22 – THP reviewed and approved notarized copy of Contractor’s first application for payment and forwarded to Hamilton County.
05/12/22 – THP met Contractor on site to review and document progress.
05/15/22 – THP issued field report 02 from 5/12 site visit.
05/16/22 – THP met project team at site for progress meeting and site visit to document progress.
05/20/22 – THP developed and issued minutes from progress meeting #2.
05/20/22 – THP issued field report 03 from 5/16 site visit.
05/24/22 – THP visited site to review and documented completed installation of EPDM.
05/26/22 – THP issued field report 04 from 5/24 site visit.
06/01/22 – THP reviewed Ace fascia and coping profiles submittals.
06/29/22 – Progress meeting and site visit scheduled to review installed drains and progress of edge metal installation.
07/22/022 – THP visited site to do final inspection of completed work and identify punchlist items.
07/25/22 – THP published field report and punch list for roof work from 7/22/22 visit.
08/09/22 – THP emailed Contactor about status of completing punchlist items.
08/09/22 – THP developed Change Order #1 for unused Cash Allowance and Unit Price credit and forwarded to Contractor for signature.
09/21/22 – Contractor emailed team about status of completing punchlist.
09/26/22 – THP emailed Contractor about acceptance of remaining two punchlist items, status of second application for payment, closeout documents, and approval of Change Order #1.
10/28/22 – THP visited site to confirm completion of punchlist items, and emailed Contractor about the status of closeout documents, approval of Change Order #1, and the application for payment #2 for substantial completion.
11/09/22 – THP replied to email from Contractor rejecting request for additional use of Cash Allowance.
11/18/22 – Contractor provided preliminary closeout documents for THP’s review.
11/21/22 – Change Order #1, a credit for unused Unit Price Repairs and Cash Allowance, was signed by Contractor and Hamilton County.
12/01/22 – THP reviewed Contractor’s preliminary closeout documents and replied with revisions to be made and additional documents to be provided.
12/07/22 – Contractor provided revised closeout documents for THP’s review.
12/12/22 – THP reviewed revised closeout documents and emailed Contractor to proceed with providing hard copies, including notarized legal documents and the project binder.
01/03/23 – THP reviewed Contractor’s hard copies of closeout documents and project binder and requested revised as-built drawings using permit set as basis for markups.
01/04/23 – THP received revised as-built drawings, emailed Hamilton County a link to a shared folder containing digital copies of all closeout documents, approved Contractor’s second and final application for payment, and delivered project binder.
02/23/23 – OK to Archive.

Animal Shelter – Roof Replacement Read More »

CH – B-95 Facilities Accounting Renovation

PM: Mike Murphy
05/25/21 SOSS Submitted to County
06/25/21 Meeting Scheduled for 7/13
07/13/21 Meeting occurred.
07/16/21 SP-1 and SP-2 sent to county with two option.
07/29/21 Meeting scheduled to review options.

08/26/21 Layout settled. Waiting pricing from furniture vendor.

10/13/21 – Site visit to confirm existing conditions with Champlin, Thermaltech and County.

10/19/21 – Final SD set and Estimate uploaded to Archibus.

12/14/21 – Signed SOSS received for DD thru CA.

02/24/24 – Permit applications

03/31/22 – Building permit picked up and delivered to County.

04/28/22 – No update.

05/26/22 – No update.

07/28/22 – Building and IBI inspection scheduled for 8/4.

08/25/22 – Final building and IBI inspections preformed.

CH – B-95 Facilities Accounting Renovation Read More »

Comm Center – Building Masterplan

05/22/21 – SOSS Submitted to County
06/02/21 – Received signed SOSS
08/09/21 – Meeting held with users to review scope.
08/26/21 – County said to let THP look at floor loading for this work. OK to get them involved now. Previous work created a lot of penetrations in the existing floor and new furniture was heavy. THP to review. New furniture should be less substantial than existing spaces.
10/28/21 – Keep masterplan work in place because this building will remain in the county portfolio for repurposed training facilities.
12/14/21 – No Update.
02/24/22 – Combined Estimate required. need to schedule a meeting to resolve scope overlap.
03/31/22 – SD plan of Combined 2022 estimates created. Meeting is needed to confirm final SD scope.
04/28/22 – We discussed the scope in the Admin Office spaces? Were the Radio Room involved? and we decided that we have not. Should we include Mission Critical involved in this report? Kitchen and Locker room are included.
05/26/22 – Finalizing estimate.
06/30/22 – Combined scope plans provided to TEI for estimate. Finalizing estimate
08/25/22 – SD set sent to HC. Plans need further broken down and resent.
09/29/22 – Site visit scheduled for 10/11.
10/27/22 – Scope refined after field visit. Owner Review Issuance scheduled for 11/11.
12/15/22 – Masterplan drawings need to be changed to reflect current project. waiting until bids are accepted to update according to which alternate is chosen.
01/26/23 – Updated plans will be completed by end of next week.
03/30/23 – Updated plans and estimate uploaded to Archibus.
04/27/23 – No Update.
05/25/23 – No Update.
07/27/23 – No Update.
08/31/23 – No Update.
09/28/23 – No Update.
12/07/23 – No Update.
02/29/24 – No Update.
03/28/24 – No Update.
04/25/24 – No Update.
05/30/24 – No Update.
06/27/24 – No Update.
08/29/24 – No Update.
09/26/24 – No Update.
10/31/24 – No Update.
06/26/25 – No Update but keep on list per HC.
03/26/26 – Leave on list.
07/30/26 – OK to Archive, RT

Comm Center – Building Masterplan Read More »

TPC – Commissioners Conference Room Upgrades

04/30/21 – SOSS Submitted to County
05/11/21 – Signed SOSS received.
06/23/21 – Meeting on site to review scope. Champlin finishes scope removed. Light fixture selection and photometrics to be done.
07/29/21 – Sconce selection is made. acoustical selection is not required. Researching main light fixtures.
08/11/21 – Provided cutsheets for suggested fixture replacements.
08/18/21 – County provided feedback on fixture selections.
10/27/21 – Draft Rendering/Photo provided to County. Fixture cuts provided to Thermaltech for photometric calculations.
12/14/21 – No Update.
01/26/22 – No Update.
02/24/22 – No Update.
03/31/22 – No Update.
04/28/22 – No Update.
05/26/22 – No Update. Ready to archive.

TPC – Commissioners Conference Room Upgrades Read More »

2022 Project Request Cost Estimates

04/21/21 – Cannon created post from Bert Watts email for 2022 Project Request.
05/27/21 – Bert sent the preliminary list out to the partners for SOSS authoring. Kickoff meeting next Tuesday with TEI, THP, and Champlin.
06/11/21 – Started research on 230 MEP upgrades including new above grade boiler and chiller room.
06/22/21 – Met at Comm Center to discuss project scopes for repurposing and academy rework.
06/25/21 – User meetings held to discuss the scope for most Champlin lead estimates.
07/28/21 – Work continues on the individual estimates. Some will be complete by July 31 and all will be complete by August 31. Cost, data and scope still coming in the CH controls, Mechanical Yard items which are the “biggies” for TTC. Champlin is making progress. Smaller estimates will be done by 7/31, the rest by 8/31.
08/20/21 – Champlin has provided almost all of the floor plans we need to complete estimates. TEI is currently putting together the cost and scope documents for the remaining estimates.
08/24/21 – Teleconference held on the 230 East 9th estimates between all partners to finalize the scope and estimating. TTC followed an update later that day with additional information after speaking with BW about the #2105 estimate.
08/26/21 – TEI – work continues and we plan on making the 8/31 completion date as discussed. Estimate and drawings are being uploaded daily.
10/28/21 – Project complete. A couple of final projects have been added and updated to the list.

2022 Project Request Cost Estimates Read More »

P&D – Restroom Renovation

PM: John Nester, Terry Cannon
04/21/21 – Nester requested SOSS for small restroom renovation, emailed next day.
05/26/21 – Kickoff meeting scheduled Friday at 2:00 pm on site.
06/11/21 – Sent preliminary layout with new fixtures located.
06/18/21 – Sent owner review set to John & Greg for review.
06/21/21 – Answered budget questions & Small Project bidding questions via email.
06/25/21 – Use as many BOLD participants as we can.
04/28/21 – Prebid held last week. Addendum #1 issued this week. Addendum #2 will be issued Friday with some cost savings ideas included. Bids are due August 5.
08/16/21 – Bids received and tabulated and sent to County for approval.
08/20/21 – Post Bid review with DK went well. County, TEI and DK working through contract documents.
09/30/21 – PO and Contract approved, all paperwork sent to DK for processing, and project information requested.
10/28/21 – Paperwork received from DK. PO and Contract are in place and the project is ready to go.
12/08/21 – Pre-const mtg scheduled on site but rescheduled to next week for availability.
12/13/21 – Pre-Const mtg schedule for Wednesday.  Submittals are returned.  Permit drawings will be hand delivery to DK at meeting.
01/21/22 – Tumlin has measured for toilet partitions and Debra is updating the project schedule. Permits are ready for this job. DK arranging for temporary toilets. We just need to get started.
02/24/22 – DK almost done. Rough-in work complete and passed plumbing inspection. Walls are being reconstructed, partitions installed and fixture to be hung next.
03/31/22 – Tumlin performing change order work for extending toilet partitions this week. DK performing punchlist work this week. Change Order 1 approved.
04/28/22 – The project is complete. Punchlist was distributed and completed including change order work. Some minor touchup may still need to be done. We can start closing out this project.
05/25/22 – Working on closeout with DK at this time. No additional paperwork has been received yet. Bill says they are close.
06/17/22 – Spoke to Bill & Donna at DK. They are working on getting closeout documents.
07/27/22 – Most of the closeout documents have arrived. I think JN reached out for a PW document.
08/24/22 – Reached to DK for more closeout docs. PW received so far.
09/25/22 – All closeout documents received. Project ready to close out.

P&D – Restroom Renovation Read More »

CH – Chiller & Boiler Room Control Updates

PM: Terry Cannon, Tony Matre
04/23/21 – Tony requested an SOSS for a chiller study on controls and operations.
05/26/21 – Discussed scope with Tony Matre today and he wants better control of the system and better maintenance.
06/25/21 – Based on recent conversations with everyone about upcoming projects, I have not submitted a separate SOSS for this work yet.
07/28/21 – SOSS approved. The study will begin next week.
08/18/21- TTC discussed similar scope with Ameresco and their findings on the Courthouse Chillers
08/24/21 – TTC met with Honeywell and discussed chiller, cooling tower, free cooling controls and programming and learned a lot about what has been changed in the last few years. Honeywell can meet with ThermalTech and the County late September given Randy current scheduled. TTC will advise Matt and Tony on this schedule.
09/27/21 – Reached out to Ameresco and discussed previous jobs with Garyne and Brad and get download on what they’ve done.
10/27/21 – Contacted Randy for pricing on recommissioning project and scope.
10/28/21 – Emailed and called Randy today for pricing for recommissioning today. Randy called back today and promised to give us his recommissioning cost by Nov 4, TTC to turn over to Matt and Tony immediately afterward.
12/13/21 – TTC scheduled the Chiller Recommissioning work with Randy and County for 12/27 at 9:00am on site.
12/30/21 – TTE collected and sent sequences to Honeywell for use on this project. Cc’ed the County.
01/22/22 – Honeywell working on new sequences and project schedule. TTC to check on VFD repairs.
02/24/22 – Honeywell started the fieldwork and deficiency report work last week and was down at the Courthouse collecting data.
03/31/22 – met Randy and corporate on-site. Getting deficiency report for next steps.
04/28/22 – Honeywell turned over all the existing points list and we have gone through it. We have not seen the due diligence report yet but Randy is working on it. I have stayed in touch with Randy weekly on this job. CH-3 will not be here unit August for installation. Comm is Bacent MSTP on the existing chillers.
05/25/22 – Randy is working up a new controller that will handle the sequences we need for this job and getting pricing, all hopefully, within his budget. And help promises to send an deficiency report to me via email.
06/30/22 – As soon as Randy is done with the Server Room, he will start the Chiller Room work.
07/27/22 – Randy is onsite now working on controls, he may get to some of the Chiller Room controls this week.
08/03/22 – Trane Chiller #3 ships 9/18/22, Tony wants chiller controls completed before then.
08/18/22 – Met with Dave Johnson on CH Boiler Room Controls today. We discussed his scope and schedule for integrating the boiler plant into two control scenarios. 1) Courthosue controls which will be minimal boiler operation and 2) CH & JC and what does that look like? Dave will update his controller for two scendarios and we will work in the HTX-5 operation with the Summer Reheat operation.
08/24/22 – Reached out to Randy for Chiller update and reminded him this work to be done before 9/18.
09/22/22 – Randy back on 9/21 but he spent that time on CH Server Room job. He is coming back next week.
08/24/22 – Randy will be back on 8/31 with a new controller board and continue to work on CH updates. He owes us a quote for a new controller to get the chiller RECX done before 9/19.
10/26/22 – Randy has made some progress. Honeywell will be back Monday. NO updates form TPC on CH boiler controls.
12/15/22 – Vendors have been contacted multiple times to complete this work but I have not gotten them on site to do this work yet. I will have to try harder this month.
01/24/23 – Randy promised he will be down to do the CH Controls work on Friday. Dave Johnson does not call me back.
02/21/23 – Honeywell on-site twice last month but the new controller is not installed yet. Met with DJ and he is working on new controls programming.
03/29/23 – Honeywell Randy to install new controller this week. Dave Johnson working with TTC.
03/30/23 – Randy confirmed this morning is installed and controls completed.
04/26/23 – Honeywell coming back May 5 to finish programming on the chiller plant.
05/21/23 – Checked in wtih Honeywell last week, no updates yet.
06/28/23 – Chiller and Cooling Tower controls are in place. Next step Boiler Controls.
07/26/23 – ThermalTech will check programming on Thursday when on the building BAS system. DJ having open heart surgery, his work may have to wait.
08/29/23 – Chiller controls in place. Boiler controls awaiting DJ recovery.
09/27/23 – No updates on this yet, will check in with DJ in October.
10/25/23 – TTC contacted DJ on health condition to see if he is ready to return to work yet, no answer yet.
12/06/23 – Chiller Controls are in. Dave Johnson said that he will call me back with a day to come down and do the boiler reprogramming so he is feeling better and back in business. We will get this on the schedule and get it done very soon. TTE reviewed the plan for having a Courthouse Mode and a Justice Center mode. DJ has to program some of this ahead of time.
01/31/24 – Randy Waddell to be onsite by this date for CH Chiller Controls. Trane sent all data he need for Chiller integration. Dave Johnson not answering phone calls about boiler controls.
02/23/24 – Randy Waddell was onsite this month installed controller for chillers. New wires ran to VFD, but no power is on new VFD’s yet. MCC update coming soon.
03/22/24 – Honeywell was onsite two days last week and pulled their controls back to the front end. four VFD’s powered up with controls. The Carrier chilled is not hooked up yet.
04/24/24 – Honeywell says they are done but the Carrier chiller is not hooked up to DDC nor can we see the KW on it. TTE to reach out to Don Webber. Randy Waddell has to come back to the building to work on Bacnet points, add the generator to the systems and the deficiency report items. Dave Johnson has suggested May 18 and 19th for his weekend work at the CH.
05/28/24 – Chiller work is complete, all chillers are on graphics.
06/26/24 – Honeywell has completed their work and the systems appear to be working. Dave Johnson is being scheduled for July.
07/24/24 – Chillers are complete and working well. Boilers are scheduled August 24,25th with Dave Johnson.
08/10/24 – Met Dave Johnson and Tyler Laws on site and reprogrammed the boilers. We got most of the reprogramming done on Saturday but we will have to come back on Sunday.
08/11/24 – Met Dave Johnson on site Sunday to wrap up the boiler programming updates. The boiler room was flooded due to the boilers being off and some of the recirculation pumps being off. Later we discovered a room upstairs flooded too, note to self turn off all pumps when the boilers are off. Programming complete with two operator settable modes and three working modes. (1) Courthouse, (2) JC Low Load March-November, and (3) JC High Load Dec-Feb.
09/24/24 – Dave J contacted multiple times this month for Summer Boiler troubleshooting and Modbus map for boiler controls to ALC to no affect.
10/30/24 – Dave Johnson coming back in November to finish up but boilers are running okay so far.
12/12/24 – Dave Johnson has not returned yet and I have not gotten a new commitment date from him.
01/28/25 – Talked to Dave last weekend and he is going to send some availability for February to finished the Summer Boiler work.
02/27/25 – Original proposal cancelled by Auditor. TPC sent new proposal for recommissioning and troubleshooting services. New proposal rejected due to wording. Tony requested new proposal.
03/25/25 – New proposal sent last week with updated language and 2025 rates including additional troubleshooting for the summer boiler. TPC also included sole source letter.
04/23/25 – PO sent to Dave Johnson for troubleshooting work and summer boiler integration.
05/28/25 – TTC trying to get summer boiler date from Dave Johnson. No luck on confirmed date of work yet.
06/25/25 – No commitment from Dave Johnson on summer boiler startup.
07/30/25 – No updates from Dave Johnson, spoke to Tony about Emcor proposal to take over boiler controls.
08/26/25 – Helped Tony get BBC in the vendor database, now we can schedule David through BBC.
09/24/25 – Sole source letter on BBC letterhead received. TTC requested schedule dates to troubleshoot summer boiler.
10/29/25 – Repeated attempt to schedule Dave Johnson back down for summer boiler startup were unsuccessful.
12/12/25 – No updates from Dave on performing the summer boiler work. Just Archive and put this job out of its misery.

CH – Chiller & Boiler Room Control Updates Read More »

250 WHT – Public Health Lobby Renovation (2nd Flr)

03/31/21 – SOSS approved. Kickoff meeting scheduled for 5/6.
04/29/21 – Kickoff meeting schedule for 5/6/21.

05/06/21 – Kickoff meeting held

05/17/21 – Field visit to verify existing conditions

06/04/21 – Progress set sent to Greg Varner for review

06/08/21 – Updates from Greg received

06/10/21 – Updated plan sent to Greg

06/22/21 – HC, PH, and ES decided to combine project scopes of 2nd floor lobby and 1st floor lobby into one bid.

06/23/21 – Updated plan sent to Greg.

07/09/21 – 95% review meeting to review scope and budget. Raised questions related to code requirements. required additional research.

07/29/21 – Meeting scheduled for Final Review Set.

08/10/21 – Project Issued

08/23/21 – Pre-bid Meeting Held

09/09/21 – Bid opening – Triton was apparent low bidder.

09/15/21 – Zoom meeting with Champlin, Thermaltech and Triton to vet the bid. Sent Letter of Recommendation to County.

10/28/21 – Ready to archive.

 

 

 

250 WHT – Public Health Lobby Renovation (2nd Flr) Read More »